File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No.

3921291)

Note No. #1

The old Note File of M/s.Sun Technologies consisting of n.f para Nos. 1 to 109 is
attached at pg Nos. 1 to 25 for reference. All the future correspondence is made
through e-office.

Further to the above, the consolidated location-wise calculation sheet of facilitation


charges at Rs. 0.20 / unit from the month of Feb-20 to July-2021 is attached at pg
Nos. 26 to 41. .

The raised respective invoices by Finance Wing towards facilitation charges from
Feb-20 to July-21 are attached at pg Nos.42 to 52.

Further, the JMR's and Invoices for the months of Aug-21 & Sep-21 were received
from M/s.Sun Technologies, duly signed by both power producer and beneficiary.
The received JMR’s / Invoices are placed at pg Nos.53 to 54 , 55 to 109 and 110 to
162.

In view of the above, the consolidated location-wise facilitation charges at Rs. 0.20/-
per unit is calculated and the summarized statement is placed at pg Nos.163 to 169.

The details are summarized as below:

Facilitation Charges amount


@ Rs.0.20/- per unit
Sl JMR’S of the Total Units Remarks
No. month Generated
1 Aug-21 63496 Rs.12,699.2/- JMR’s received on
07.10.2021
2 Sep-21 69605 Rs.13,921/- JMR’s received on
29.10.2021

Further, the Finance Wing is requested for examination of above received JMR’s /
Invoices and Summarized statement so as to raise the demand notice / invoice for
collecting the facilitation charges from M/s.Sun Technologies.

Hence this is submitted for perusal and approval / further Orders.

22/11/2021 5:16 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #2

submitted for preparation of Demand Notice

23/11/2021 11:16 AM

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 3921292)

CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #3

23/11/2021 1:46 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #4

As per the forwarding of soft copy of note file and hard copy of invoices & JMR's
the Pre- Audit CA has furnished the observation report with penalty calculation.
(The copy of report placed at pg No. 170 to 171 ).

Further, as proposed in the Note#01 for summarising the total units generated
for August 21 billed in September 21 and September 21 billed in October 21 and
proposing for issue of Facilitation Charges by attaching the JMR's and month wise
invoices, the JMR's and invoices are verified and found correct.

Hence, month wise Facilatation Charges Tax Invoices are issued and attached to
the file pg. No. 172 to 174 ). The details are summarised below:
Total FC
S. NO. Billed for the month Inv. No Date
Units @ .20 PU

1 August-21 billed in September-21 63496 12,699.20 SR/1604 30.11.21

2 September-21 billed in October-21 69605 13,921.00 SR/1605 30.11.21

Penalty for delayed submission of


3 233.00 SR/1606 30.11.21
JMR's & Invoices

Furhter, it is also submit that, the BG submitted vide Para No. 46, for PSD for
Rs.2,10,000/- was expired by 18.11.2021. As per the earlier communication, the
supplier has to submit auto renewable BG for 25 Years. Hence, it is requested to
obtained extended BG for Rs.2,10,000/-.

Further, it is aslo submit that, the M/s Sun Technologies, has not transfering the
Facilation Charges invoices issued in August 21 for the months December 2020
billed in January 2021 to July 21 billed in August 21 (for Rs.1,20,200/-) and
currently issued invoices value for Rs.26,853/-. Hence, it may issue reminders to
the supplier for making payment and delay may propose for penalty @18% p.a.

Submitted for further orders/approval please

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 3921293)

07/12/2021 11:53 AM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #5

09/12/2021 1:05 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #6

09/12/2021 2:20 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #7

Approved

10/12/2021 12:10 PM
NEELAM JANAIAH
(VICE CHAIRMAN & MANAGING DIRECTOR- TSREDCO)

Note No. #8

10/12/2021 12:55 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #9

send the invoices by reminding the old payments

10/12/2021 2:48 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 3921294)

Note No. #10

In continuation to the above, On verification of JMR’s and Invoices ,the Finance wing
has raised the tax invoices towards the Facilitation charges for the month of Aug and
Sep-21 and the same was communicated to M/s.Sun Technologies through Email.

In continuation to the above, the JMR's and Invoices for the month of Oct-21 were
received from M/s.Sun Technologies duly signed by both power producer and
beneficiary.The received JMR's/Invoices are placed at pg.no 175 to 228

In view of above, the consolidated location-wise Facilitation charges at Rs.0.20/-


per unit is calculated and the summarized statement is placed at Pg.no.229 to
231.

The details of F.C are tabulated below:

Facilitation charges
JMR's of Total Units
Sl.no amount @ Rs.0.2/- Remarks
the Month Generated
per unit

JMR’s received on
1 Oct-21 75075 Rs.15015/-
06.12.2021

Hence the above is submitted for approval/further Orders.

14/12/2021 5:42 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #11

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 3921295)

submitted for approval

15/12/2021 2:35 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #12

15/12/2021 4:01 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #13

As per the forwarding of soft copy of note file and hard copy of invoices & JMR's
the Pre- Audit CA has furnished the observation report with penalty calculation.
(The copy of report placed at pg No. 232-234 ).

Further, as proposed in the Note#10 by summarising the total units generated for
October-21 billed in November-21 and proposing for issue of Facilitation Charges by
attaching the JMR's, the Tax Invoice raised against to the M/s Sun Technologies, vide
SR/1742, Dated:28.12.2021, for Rs.15,015/- and late submission penalty raised vide
SR/1743, Dt:28.12.2021 for Rs.155/-. (Page No. 235 to 236)

Furhter, it is also submit that, the BG submitted vide Para No. 46, for PSD for
Rs.2,10,000/- was expired by 18.11.2021. As per the earlier communication, the
supplier has to submit auto renewable BG for 25 Years. Hence, it is requested to
obtained extended BG for Rs.2,10,000/-.

Further, as communicated vide Para No. 04, the Facilitation Charges are not
transferring by the power producer (M/s Sun Technologies,) against the invoices
raised from August 2021. (for a total of Rs.1,47,053/- and current month for
Rs.15,170/-). Hence, it may issue reminders to the supplier for making payment
and delay may propose for penalty @18% p.a.

Submitted for further orders/approval please.

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 3921296)

31/12/2021 5:11 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #14

It is requested to PD solar may take necessary action for realization of pending


facilitation charges and renewal of expired BG

03/01/2022 4:03 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #15

For necessary action as suggested by F & A

04/01/2022 2:52 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #16

put up a letter to pfor realization of pending dues and renewal of BG


04/01/2022 5:17 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #17

Further In continuation to the above, the letter is addressed to M/s.Sun Technologies


wherein seeking for submission of renewed BG towards the facilitation charges as
the BG has expired on 18.11.2021.And also insisted the M/s.Sun Technologies for
regular payments towards facilitation charges to TSREDCO without any delay. The
Draft letter is attached at Draft section for perusal.

Further, Nov-21 month consumption reading reports/JMR and invoices were received

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 3921297)

from M/s.Sun Technologies, duly signed by the power producer and beneficiary. The
received JMR’s /Invoices are attached at Pg.no. 237 to 238 and 239 to 290

In view of above, the consolidated location wise facilitation charges at Rs.0.20/- per
unit is calculated and the summarized statement is attached at Pg.no.291 to 293

The details are summarized as below:

Facilitation charges amount


@ Rs.0.2/- per unit
Sl.no JMR’S of the Total units Remarks
month Generated
1 Nov-21 58424 Rs.11,684.80/- JMR’s received on
11.01.2022

Further, the Finance Wing is requested for examination of above received JMR’s /
Invoices and summarized statement so as to raise the demand notice / invoice for
collecting the facilitation charges from M/s.Sun Technologies.

Hence the above is submitted for approval / further Orders.

21/01/2022 1:30 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #18

submitted for approval


21/01/2022 4:37 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #19

27/01/2022 12:54 PM
MARAGANI LAXMINARAYANA
(MANAGER (F&A) - TSREDCO)

Note No. #20

27/01/2022 3:02 PM

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 3921298)

AMANAGANTI SATYANARAYANA REDDY


(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #21

As per the forwarding of soft copy of note file and hard copy of invoices & JMR's
the Pre- Audit CA has furnished the observation report with penalty calculation.
(The copy of report placed at pg. No. 294-295 ).

Further, as proposed in the Note#17 by summarizing the total units generated for
November-21 and proposing for issue of Facilitation Charges by attaching the JMR's,
the Tax Invoice raised against to the M/s Sun Technologies, vide SR/2238,
Dated:01.02.2022, for Rs.11,685/- and late submission penalty raised vide SR/2239,
Dt:01.02.2022 for Rs.155/-.(Page No. 297 to 298)

Further, as mentioned in Note#04 & 13, No payment received from M/s. Sun
Technologies towards Facilitation Charges and Penalty charges from August 2021 to
October 2021 for amount Rs.1,62,405/-(Pg. No.296).Hence, it may issue reminders
to the supplier for making payment and delay may propose for penalty @18%
p.a. It also requested to forward the Invoices raised for the November -2021
billed units.

Submitted for further orders/approval please.

09/02/2022 2:40 PM
RACHAKONDA VAMSHI KRUSHNA
(JUNIOR MANAGER- F&A- TSREDCO)

Note No. #22

Submitted for approval of Note # 21 and for approval of draft letter for
communicating the renewal of BG and for transfer of Facilitation charges to
TSREDCO account.

09/02/2022 2:51 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #23

In view of the above necessary action may be initiated against M/s.Sun


Technologies, if the Power Producer failed to make the payment of Facilitation
Charges and submission of renewed BG

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 3921299)

09/02/2022 5:21 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #24

10/02/2022 5:40 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #25

Approved

11/02/2022 2:41 PM
NEELAM JANAIAH
(VICE CHAIRMAN & MANAGING DIRECTOR- TSREDCO)

Note No. #26

11/02/2022 4:00 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #27

11/02/2022 5:42 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #28

In continuation to the above, the 1 No Tax invoice towards the facilitation charges for
the month of Nov-21 was raised by the finance wing so as to receive the payments to
TSREDCO. The same was communicated to M/s.Sun Technologies through E-mail.

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
10)

Further, for the month of Dec-21 month consumption reading reports/JMR and
invoices were received from M/s.Sun Technologies, duly signed by the power
producer and beneficiary and the same is attached at page No.299 to 346 for kind
perusal.

In context to the above, it is observed that 3 No’s JMR’s that pertains to Metpally I
and II and Jagital Bus Depots were not received. And the same was intimated to
Power producer and it is came to known that the assignee Technical person who
departs for billing is has been affected by Covid detected. And hence power producer
submitted that the total Generated Units will going to submit in as bi monthly JMR in
the next month.

And the consolidated location wise facilitation charges at Rs.0.20/- per unit is
calculated and the summarized statement is attached at pg.no.347 to 349.

The details are summarized as below:

Facilitation charges amount


@ Rs.0.2/- per unit
Sl.no JMR’S of the Total units Remarks
month Generated
JMR’s Inward Dt
1 Dec-21 59669 Rs. 11933.80/- 05.02.2022

Further, the finance wing is requested for examination of JMR’s, Invoices and
Summarized statement to raise the demand notice/ invoice for collecting the
facilitation charges from M/s.Sun Technologies.

22/02/2022 4:35 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #29

submitted for approval


22/02/2022 5:40 PM

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
11)

CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #30

23/02/2022 3:49 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #31

23/02/2022 3:58 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #32

As per the forwarding of soft copy of note file and hard copy of invoices & JMR's
the Pre- Audit CA has furnished the observation report:

1)Facilitation charges raised from Dec-2020 to Nov-2021 total amount


Rs.1,74,245/- still not received.

2)the applicable provisions of PPA for non payment with advisable methods
clearly state in Pre audit CA report.(Report attached @ CF No.350-351)

In view of the above, it is requested to take necessary action as advised.

Further, as proposed in the Note#28 by summarizing the total units generated for
December-21 and proposing for issue of Facilitation Charges by attaching the JMR's,
the Tax Invoice raised against to the M/s Sun Technologies, vide SR/2579,
Dated:28.02.2022, for Rs.11,934/- and late submission penalty raised vide SR/2580,
Dt:28.02.2022 for Rs.123/-.( CF No. 352 and CF No.353)

Submitted for further orders/approval please.

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
12)

03/03/2022 5:05 PM
RACHAKONDA VAMSHI KRUSHNA
(JUNIOR MANAGER- F&A- TSREDCO)

Note No. #33

As advised by the Pre-Audit CA, the observations report may be verified and
necessary action may be initiated against to the supplier for collection of
Facilitation charges.

Submitted for further

04/03/2022 1:51 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #34

Submitted for approval of invoice and further orders on note # 33 please

04/03/2022 6:11 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #35

05/03/2022 1:03 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #36

Approved

05/03/2022 4:25 PM
NEELAM JANAIAH
(VICE CHAIRMAN & MANAGING DIRECTOR- TSREDCO)

Note No. #37

05/03/2022 4:50 PM
GUTTA SATYA VARA PRASAD

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
13)

(GENERAL MANAGER)

Note No. #38

05/03/2022 5:22 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #39

In continuation to the above, the 2 No Tax invoices towards F.C and its penalty
for the month of Dec-21 was raised by the finance wing so as to receive the
payments to TSREDCO. The same was communicated to M/s.Sun Technologies
through E-mail.

Further, an email was received from M/s.Sun Technologies wherein informed that,
the payments towards the invoices against solar power Generation at ZWS
Karimnagar with aggregate capacity of 98Kw were not receiving from TSRTC,
Karimnagar since last 3 Months.The received Email copy is placed at pg.no.354

Hence in view of above, the draft letter is prepared while addressing to ZWS
Karimnagar,TSRTC, by duly provided with suggestions and also recommended
TSRTC to submit the clarification to TSREDCO as early so as to take further
necessary action.The Draft letter was attached at Draft section for kind perusal.

The above is submitted for approval/further orders.

08/03/2022 4:54 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #40

submitted for drafapproval


10/03/2022 3:54 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #41

10/03/2022 5:15 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
14)

Note No. #42

Approved.

11/03/2022 2:16 PM
NEELAM JANAIAH
(VICE CHAIRMAN & MANAGING DIRECTOR- TSREDCO)

Note No. #43

11/03/2022 2:19 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #44

11/03/2022 3:13 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #45

In continuation to the above, a remainder letter has been prepared while addressing
to M/s.Sun Technologies, wherein reminded to submit the auto renewable BG /
Validity Extended BG towards the Facilitation charges. The Draft remainder Letter is
placed at draft section for kind perusal.

Further, for the month of Jan-22, the consumption reading reports/JMR and their
respective invoices were received from M/s.Sun Technologies, duly signed by the
power producer and beneficiary and the same is attached at page.no.355 to 402, for
kind perusal.

In context to the above, it is observed that 2 No’s JMR’s that pertains to Manthani I
and II with PCR No’s 171352 and 171350 were not received.

Further, the consolidated location wise facilitation charges at Rs.0.20/- per unit is
calculated and the summarized statement is attached at pg.no.403 to 405.

The details are summarized as below:

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
15)

Facilitation
charges @ Rs.0.2/- per
Sl.no JMR’S of Total units unit Remarks
the month Generated
JMR’s received on
1 Jan-22 76,647 Rs. 15,329.40/- 11.03.2022

Further, the finance wing is requested for examination of JMR’s, Invoices and
Summarized statement to raise the demand notice/ invoice for collecting the
facilitation charges from M/s.Sun Technologies.

Hence the above is placed for Approval / Further Orders.

16/03/2022 4:29 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #46

submitted for approval


19/03/2022 10:55 AM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #47

19/03/2022 6:45 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #48

22/03/2022 12:19 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #49

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
16)

As per the forwarding of soft copy of note file and hard copy of invoices & JMR's
the Pre- Audit CA has furnished the observation report:

1)Facilitation charges raised from Dec-2020 to Dec-2021 total amount


Rs.1,86,302/- still not received.( Report attached @ CF No.406-407 )

Further, as proposed in the Note#45 by summarizing the total units generated for
January-2022 and proposing for issue of Facilitation Charges by attaching the JMR's,
the Tax Invoice raised against to the M/s Sun Technologies, vide SR/2687,
Dated:24.03.2022, for Rs.15,329/- towards Facilitation charges(CF No.408) and
SR/2688, Dated:24.03.2022, for Rs.181/- towards late Payment surcharge.

( CF No.409)

Submitted for further orders/approval please.

24/03/2022 3:57 PM
RACHAKONDA VAMSHI KRUSHNA
(JUNIOR MANAGER- F&A- TSREDCO)

Note No. #50

Further, as proposed in the Note No. 45, the draft reminder letter for renewal of BG and
instructions for payment of FC & intimation for regular submission of bills may be approved.
25/03/2022 1:06 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #51

25/03/2022 5:49 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #52

27/03/2022 8:00 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
17)

Note No. #53

Approved.

28/03/2022 12:57 PM
NEELAM JANAIAH
(VICE CHAIRMAN & MANAGING DIRECTOR- TSREDCO)

Note No. #54

28/03/2022 1:23 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #55

28/03/2022 4:21 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #56

In continuation to the above, the 2 No’s Tax invoices towards the facilitation charges
for the month of Jan-22 was raised by the finance wing is been communicated to
M/s.Sun Technologies through E-mail so as to receive the payments to TSREDCO.

Further, a reminder mail was sent to M/s.Sun Technologies, wherein reminded to


submit the auto renewable BG / Validity Extended BG towards the Facilitation
charges.

Further, for the month of Feb-22, Mar-22 and Apr-22 the monthly consumption
reading reports/JMR were received from M/s.Sun Technologies, duly signed by the
power producer and beneficiary and the same is attached at page No 410 to 461,
462 to 462, 463 to 517, 518 to 518 , 519 to 565 and 566 to 570 for kind perusal.

Further, the consolidated location wise facilitation charges at Rs.0.20/- per unit is
calculated and the summarized statement is attached at pg.no.571 to 572, 573 to
574 and 575 to 576 for perusal.

The details are summarized as below:

Facilitation charges amount

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
18)

@ Rs.0.2/- per unit


Sl.no JMR’S of the Total units Remarks
month Generated
JMR’s Inward Dt
1 Feb-22 48777 Rs. 9755.4/-
23.03.2022
JMR’s inward
2 Mar-22 55990 Rs.11,198/-
Dt.01.06.2022
JMR’s inward
3 Apr-22 66376 Rs.13,275.20/-
Dt.01.06.2022

To the above summarized statement the following observations are made:

1. 1 No JMR of Korutla Bus Station not received during Feb-22.


2. 01No’s JMR’s Karimnagar bus depot is not received for the month of Mar-22 @
sl.no.14
3. 01No’s JMR’s Metpally bus depot is not received for the month of Apr-22 , @
sl.no-15 .

Further, the finance wing is requested for examination of JMR’s, Invoices and
Summarized statement so as to raise the demand notice/ invoice towards FC
charges in order for collecting the facilitation charges from M/s.Sun Technologies.

Hence, the above is submitted for approval or further orders.

20/06/2022 4:44 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #57

submitted for approval


21/06/2022 12:25 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #58

21/06/2022 12:38 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #59

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
19)

21/06/2022 1:08 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #60

The file is forwarded to Pre Audit CA for verification and Observations report.

21/06/2022 3:45 PM
RACHAKONDA VAMSHI KRUSHNA
(JUNIOR MANAGER- F&A- TSREDCO)

Note No. #61

We have verified documents submitted for raising invoice for facilitation charges. Our Opinion and
Report with observations and comments are sent by EMail vide Ref: KRA/PA/2022-23/038, dated:
25/06/2022 to Finance Section.

25/06/2022 1:03 PM
KRAJU AND ASSOCIATES
(AUDITOR-TSREDCO)

Note No. #62

As per the forwarding of file to Pre Audit CA, the Pre Audit CA has furnished the observation
report with certain remarks :( Page No.577-578)

1) The Invoices raised towards Facilitation charges (December-2020 to January-2022) not yet
received from M/s. Sun Technologies.

2)Non Payment of FC is in the violation of PPA, the same may be intimated to power
producer and write a letter to power purchaser to hold the payments made to power producer
till the FC are received by TSREDCO.

Further, as per the information provided at Note#56, by summarizing the total units generated
for the month of February-2022,March-2022 and April-2022 and proposing for issue of
Facilitation Charges by attaching the JMR's, the Tax Invoice raised against to the M/s Sun
Technologies along with late payment surcharge for delay in submission of JMR's. (Tax
Invoices attached @580-583)

S.No Month Units Amount Tally Ref Remarks

1 February-2022 48,777 9,755/- SR/677,Dt:09.06.2022

2 March-2022 55,990 11,198/- SR/678,Dt:09.06.2022

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
20)

3 April-2022 66,376 13,275/- SR/679,Dt:09.06.2022

4 Penalty 408/- SR/680,Dt:09.06.2022

Submitted for further orders/approval please

30/06/2022 11:53 AM
RACHAKONDA VAMSHI KRUSHNA
(JUNIOR MANAGER- F&A- TSREDCO)

Note No. #63

30/06/2022 12:15 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #64

30/06/2022 1:05 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #65

30/06/2022 3:55 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #66

Approved.

30/06/2022 5:47 PM
NEELAM JANAIAH
(VICE CHAIRMAN & MANAGING DIRECTOR- TSREDCO)

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
21)

Note No. #67

30/06/2022 5:47 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #68

01/07/2022 10:38 AM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #69

In continuation to the above, it is to submit that, vide Note # 53 and 58 in old note file,
the facilitation charges for an amount of Rs.1,03,370 for the period of May-2019 to
Dec-2020 (against generation up to Nov-20) was deducted from CFA amount that
was released to M/s Sun Technologies for 22 No’s of solar plant installations.

Further, it is to submit that, M/s Sun Technologies has installed SPV plants at 26
Locations whereas due to non submission of JMR’s and Invoices for 2 No’s of sites
i.e (1) TSRTC Bus Station, B.Y.Nagar, Sirisilla, Rajanna Sirisilla and (2) TSRTC Bus
Station, Vemulawada, Rajanna Sirisilla , the CFA amount of Rs.1,65,000/- was kept
pending for unbilled services.

However, Since Feb-21, the JMR’s and Invoices were receiving from supplier for
above said 2 No’s sites and accordingly the Facilitation charges were calculated for
every month.

Further, it is to submit that, TSREDCO is not receiving the facilitation charges @ 0.20
paisa since Jan-2021 (Generation for the period of Dec-20) till Apr-22 from M/s Sun
Technologies.

The total receivable facilitation charges are:

Bills /JMR's issued Total Facilitation Penalty


Name of the
Sl.no for Solar Generation Billed Charges Amount Amount in
Firm
for the month of Units @ 0.20 paisa Rs.
1 M/s Sun Dec-20 55690 11,138

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
22)

2 Jan-21 58037 11,607


3 Feb-21 70787 14,157
4 Mar-21 88557 17,711
5 Apr-21 77325 15,465
6 May-21 104343 20,868
7 Jun-21 63,322 12,666
8 Jul-21 68,267 13,654 182
9 Aug-21 63,496 12,699 233
Technologies
10 Sep-21 69,605 13,921
11 Oct-21 75075 15,051
12 Nov-21 58,424 11,685
13 Dec-21 59,669 11,934
14 Jan-22 76,647 15,329
15 Feb-22 48,777 9,755
16 Mar-22 55,990 11,198
17 Apr-22 66,376 13,275 408
Total Amount 2,32,113 823

Hence in view of above context, it is proposed to set-off the TSREDCO withhold


pending CFA amount of Rs.1,65,000/- for 2 No’s of sites against the receivable
facilitation charges from the M/s Sun Technologies to TSREDCO.

The details are as below:

Capacity CFA Amount with Facilitation charges to be


Name of the
Sl.no executed in hold with received from Dec-20 to Apr-
Firm
KW TSREDCO 22 including penalty charges
M/s.Sun
1 716 Kw 1,65,000 2,32,936
Technologies

Further, the finance wing is requested to impose the interest on delayed payments of
Facilitation charges from the M/s.Sun Technologies as per the PPA clause.

Further, M/s.Sun Technologies has submitted the renewed Bank Guarantee bearing
B.G.No.0505522BG0002633 / Dt.30.09.2022, for a BG Value of Rs.2,10,000/. The
received BG is attached at Pg.no.584 to 590.

The above submitted BG shall remain in force until 29.09.2023, and TSREDCO shall
be entitled to claim this Guarantee till 29.09.2024.

In this context, the above BG is hereby transmitted to finance wing with a request to
verify genuineness of above said BG and to preserve the BG in their safe Guard
custody, thereby returning the old BG to M/s.Sun Technologies.

Hence in view of above, The letter adrressing to M/s.Sun Technologies is prepared

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
23)

regarding return of the lapsed original Bank Guarantee. The letter is attached in draft
section vide DFA/586910 for kind perusal.

Hence the above is submitted for approval/further orders

12/10/2022 2:45 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #70

submitted for approval


12/10/2022 6:03 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #71

12/10/2022 7:09 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #72

13/10/2022 11:07 AM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #73

the file is forwarded for verification and observations report

13/10/2022 11:47 AM
RACHAKONDA VAMSHI KRUSHNA
(JUNIOR MANAGER GR.I- F&A- TSREDCO)

Note No. #74

We have verified documents submitted for recovery of facilitation charges. Our


Opinion and Report with observations and comments vide KRA/PA/2022-23/091,
dated: 14/10/2022 are attached herewith (refer Pag. No. 591-592). And also
forwarded to F & A Email.

14/10/2022 7:49 PM

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
24)

KRAJU AND ASSOCIATES


(AUDITOR-TSREDCO)

Note No. #75

As per the forwarding of file, The Pre Audit CA has furnished the observation report with
observations and suggestions :( Page No.591-592)

As per the observations & suggestions of Pre-Audit CA, it is stated that:

i. The total amount to be receivable from M/s. Sun Technologies towards Facilitation
charges & penalty for the period .i.e. December-2020 to April-2022 for Rs.2,36,448/-.
ii. It is also requested to obtain the statement of billed units with invoices for power bills
from the supplier for the period Feb-2022 to September-2022 for Raising Invoice
towards Facilitation charges.
iii. It is requested to incorporate the reasons for Non payment of Facilitation charges by
supplier for levying of late payment surcharge on the supplier as per the terms and
conditions of PPA Agreement.
iv. As advised by of Pre Audit CA, it is requested to inform to the supplier for
recovery of Facilitation charges and penalty amounts withhold from the
subsequent amounts due to the supplier from TSREDCO without any further
notices.
v. Non Payment of FC is in the violation of PPA, the same may be intimated to power
producer and write a letter to power purchaser to hold the payments made to power
producer till the FC are received by TSREDCO.

Further, as mentioned in Note # 69 Para No.08, it is not a renewed Bank Guarantee (BG), it is
a fresh Bank Guarantee (BG), hence the Original BG may be forwarded to F&A for obtaining
genuineness and preserving with F&A.

Hence, the lapsed BG may be returned, since the supplier the has submitted fresh BG. The
DFA/586910 may be approved.

Submitted for further orders/approval please

17/10/2022 3:01 PM
RACHAKONDA VAMSHI KRUSHNA
(JUNIOR MANAGER GR.I- F&A- TSREDCO)

Note No. #76

18/10/2022 12:17 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
25)

Note No. #77

18/10/2022 1:45 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #78

Note No. 75 may pls be approved to take further necessary action by the solar
section.

20/10/2022 12:21 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #79

Approved Note#78.

21/10/2022 5:09 PM
NEELAM JANAIAH
(VICE CHAIRMAN & MANAGING DIRECTOR- TSREDCO)

Note No. #80

22/10/2022 11:12 AM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #81

22/10/2022 11:54 AM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #82

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
26)

In continuation to the above, as per suggestions made at Note # 75, a letter was
prepared while addressing to M/s Sun Technologies, wherein requested to submit
the willingness towards recovery of FC charges from unsettled CFA amount. The
draft letter is placed at DFA/593757 for kind perusal.

Further, as per request made at Note # 75, the new submitted BG towards FC
Charges is physically transmitted to finance wing to verify the genuineness and to
preserve the BG in their safe custody.

22/10/2022 5:49 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #83

submitted for approval


25/10/2022 12:39 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #84

25/10/2022 1:07 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #85

As proposed in Note # 82, the draft letter DFA/593757, may be approved.

Submitted for approval please


25/10/2022 1:57 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #86

25/10/2022 2:44 PM

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
27)

MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #87

25/10/2022 3:35 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #88

APPROVED Note#87.

26/10/2022 3:36 PM
NEELAM JANAIAH
(VICE CHAIRMAN & MANAGING DIRECTOR- TSREDCO)

Note No. #89

26/10/2022 4:14 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #90

26/10/2022 4:54 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #91

Further, for the month of May-22, June-22, July-2022, Aug-22 and sep-22 the
monthly consumption reading reports/JMR were received from M/s.Sun
Technologies, duly signed by the power producer and beneficiary and the same is
attached at page No.593 to 594, 595 to 651, 652 to 653, 654 to 705, 706 to 707, 708
to 761, 762 to 763, 764 to 815, 816 to 817, 818 to 871 for kind perusal.

Further, the consolidated location wise facilitation charges at Rs.0.20/- per unit is

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
28)

calculated and the summarized statement is attached at pg.no.872 to 873, 874 to


875, 876 to 877, 878 to 879, 880 to 881.

The details are summarized as below:

Facilitation charges
amount @ Rs.0.2/- per unit
Sl.no JMR’S of the Total units Remarks
month Generated
JMR’s Inward Dt
1 May-22 72,378 14,476
30.08.2022
JMR’s Inward Dt
2 June-22 68,101 13,620
30.08.2022
JMR’s Inward Dt
3 July-22 69,706 13,941
24.08.2022
JMR’s Inward Dt
4 Aug-22 65,083 13,016
23.09.2022
JMR’s Inward
5 Sep-22 51,868 10,373.6
Dt .14.10.2022

Further, it is to submit that,

1) 03 No’s of JMR’s of Godavarikhani Bus station, Manthani Bus depot and Manthani
Bus station were not taken for the month of May-2022 and meanwhile it was billed
for 2 months in June-22.

2) 01 No JMR of Jagitial , Karimnagar for the month of Aug-22 was not taken and it
was billed for 2 months in sep-22.

Further, the finance wing is requested for examination of JMR’s, Invoices and
Summarized statement so as to raise the demand notice/ invoice towards FC
charges and collecting the facilitation charges from M/s.Sun Technologies.

Hence the above is submitted for approval.

28/10/2022 4:19 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #92

submitted for approval


28/10/2022 5:27 PM
CH.AMARENDER REDDY

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
29)

(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #93

As mentioned in note #82 para 2 the copy of acknowledgement for transmission


of physical BG to F&A section may please be attached for taking further
necessary action.

29/10/2022 1:29 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #94

attach and re submit


29/10/2022 2:17 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #95

In continuation to the above, the copy of acknowledgement for transmission of


physical BG to F & A section is herewith attched at pg.no 882 for information and
taking further necessary action.

01/11/2022 12:19 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #96

Re submitted for approval


01/11/2022 4:57 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #97

02/11/2022 11:06 AM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #98

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
30)

02/11/2022 11:35 AM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #99

the file is forwarded for verification and observation report

02/11/2022 4:29 PM
RACHAKONDA VAMSHI KRUSHNA
(JUNIOR MANAGER GR.I- F&A- TSREDCO)

Note No. #100

We have verified documents submitted for recovery of facilitation charges. Our


Opinion and Report with observations and comments vide KRA/PA/2022-23/101,
dated: 03/11/2022 are attached herewith (refer Pag. No. 883-884). And also
forwarded to F & A Email.

03/11/2022 8:31 PM
KRAJU AND ASSOCIATES
(AUDITOR-TSREDCO)

Note No. #101

As per the forwarding of file to Pre Audit CA, The Pre Audit CA has furnished the
observation report with certain remarks ( Page No.883-885). The observations are as follows

1. The Facilitation charges (December-2020 to April -2022) for an


amount Rs.2,36,448/- not yet received from M/s. Sun Technologies.

Non Payment of FC is in the violation of PPA, the same may be intimated to


power producer and write a letter to power purchaser to hold the payments
made to power producer till the FC are received by TSREDCO.

2. As per the PPA agreement (Ref. Para No. 7.7 of PPA page No. 22 of 49), late
payment surcharge @1.25% per month shall be paid by the Power Purchaser,
in case of delay in payment of any invoice towards supply of power. Hence,
due to delay in submission of invoices to TSREDCO, the penalty clause is
applied accordingly penalty is levied for Rs.960/-
3. It is advised to direct Power Producer to submit copy of Invoice raised in
favour of Power Purchaser, to TSREDCO simultaneously in order to raise the
invoice timely for facilitation charges by TSREDCO.

4. Joint Meter reading and Invoices are not issued on monthly basis and reasons
for non-receipt of Joint Meter reading and Invoice are not stated.

a. May, 2022 of TSRTC Godavarikhani Bus station, Manthani Bus depot

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
31)

and Manthani Bus station are not received.

b. June, 2022 of TSRTC Metpally Bus Depot Jagitial is not received.

c. August, 2022 of TSRTC Jagitial, Karimnagar is not received.

5. However while rising of subsequent month bills the same was considered and
bills were raised.

6. It is advised to intimate the Power Producer to mention the PCR code in the
meter reading report and in the tax invoice, so as to facilitate easy identification
of location of Solar Power Plants.

In view of the above, it is requested to solar section to follow the suggestions made by Pre-
Audit CA and take necessary steps in realization of Facilitation charges and also requested to
intimate to the Power Producer to raise the bills infavour of Power Purchaser (TSRTC) on
monthly basis and to submit the bills to TSRTC as well as TSREDCO simultaneously for
timely accounting of revenue.

Further, as per the information provided at Note#91, by summarizing the total units generated
for the period May-2022 to September-2022 and proposing for issue of Facilitation Charges
by attaching the JMR's, the Tax Invoice raised against to the M/s Sun Technologies along
with late payment surcharge. (Tax Invoices attached @886-891).

S. No For the Months Billed FC Accounted


Units Rs.
1 May-2022 72,378 14,476/- SR/1883
2 June-2022 68,101 13,620/- SR/1884
3 July-2022 69,706 13,941/- SR/1885
4 August-2022 65,083 13,017/- SR/1886
5 September-2022 51,868 10,374/- SR/1887
Penalty 960/- SR/1888
Total Amount 66,388/-

In view of the above, it is requested to solar section to take necessary steps for realization of
total Facilitation charges due from M/s Sun Technologies for Rs.3,02,836/- (i.e. for
December-2020 to April-2022 for Rs.2,36,448/- and for May-22 to September-22 for
Rs.66,388/-).

Submitted for further orders please

09/11/2022 3:38 PM
RACHAKONDA VAMSHI KRUSHNA
(JUNIOR MANAGER GR.I- F&A- TSREDCO)

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
32)

Note No. #102

09/11/2022 4:07 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #103

10/11/2022 12:12 PM
MANGALI SATHAIAH
(MANAGER (F&A) - TSREDCO)

Note No. #104

Note No.101 may be approved

10/11/2022 4:44 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #105

Approved Note#104.

14/11/2022 1:07 PM
NEELAM JANAIAH
(VICE CHAIRMAN & MANAGING DIRECTOR- TSREDCO)

Note No. #106

14/11/2022 1:41 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #107

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
33)

14/11/2022 2:46 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #108

In continuation to the above, it is to submit that, for the month of Oct-22 the monthly
consumption reading reports/JMR were received from M/s.Sun Technologies,duly
signed by the power producer and beneficiary and the same is attached at page
No.892 to 944 for kind perusal.

Further, the consolidated location wise facilitation charges at Rs.0.20/- per unit are
calculated and the summarized statement is attached at pg.no. 945 to 946.
The details are summarized as below:

Facilitation charges
amount @ Rs.0.2/-
Sl.no JMR’S of Total units per unit Remarks
the month Generated
JMR’s
1 Oct-22 58,815 11,763 Inward Dt
18.11.2022

Further, the finance wing is requested for examination of JMR’s, Invoices and
Summarized statement so as to raise the demand notice/ invoice towards FC
charges and for collecting the facilitation charges from M/s. Sun Technologies.
Further, a letter received from M/s.Sun Technologies wherein informed that, M/s.Sun
Technologies is not receiving the monthly payments against the Solar power
generation bills dues of ZWS , Karimnagar, TSRTC. The letter attached at pg.no.947
to 948.
Hence in this regard, the letter is prepared and attached at draft section vide DFA/
622515 while addressing to TSRTC.
Hence the above (i) Oct-22 Fc calculation sheet (ii) Letter to karimnagar,TSRTC is
submitted for approval.

14/12/2022 1:50 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #109

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
34)

submitted for approval


15/12/2022 5:27 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #110

16/12/2022 12:12 PM
J . ANIL KUMAR
(MANAGER (F&A) - TSREDCO)

Note No. #111

16/12/2022 2:51 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #112

We have verified documents submitted for recovery of facilitation charges. Our


Opinion and Report with observations and comments vide KRA/PA/2022-23/120,
dated: 19/12/2022 are attached herewith (refer Pag. No. 949-950). And also
forwarded to F & A Email.

19/12/2022 10:56 AM
KRAJU AND ASSOCIATES
(AUDITOR-TSREDCO)

Note No. #113

19/12/2022 12:00 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Note No. #114

As per the forwarding of file to Pre Audit CA, The Pre Audit CA has furnished the
observation report with certain remarks ( Page No.949-950). The observations are as follows

1. The Facilitation charges (December-2020 to September -2022) for an amount


Rs.3,02,836/- (Ref:Note#101) not yet received from M/s. Sun Technologies.

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
35)

2. Non Payment of FC is in the violation of PPA, the same may be intimated to power
producer and write a letter to power purchaser to hold the payments made to power
producer till the FC are received by TSREDCO.
3. As per the PPA agreement (Ref. Para No. 7.7 of PPA page No. 22 of 49), late payment
surcharge @1.5% per month shall be paid by the Power Purchaser, in case of delay in
payment of any invoice towards supply of power.
4. It is advised to direct Power Producer to submit copy of Invoice raised in favor of
Power Purchaser, to TSREDCO simultaneously in order to raise the invoice timely for
facilitation charges by TSREDCO.
5. Joint Meter reading and Invoices for the month of October-2022 of TSRTC Manthani
depot-II, Peddapally, karimnagar(PCR Code:171922) are not received and reasons for
non-receipt of Joint Meter reading and Invoice are not stated.
6. It is advised to intimate the Power Producer to mention the PCR code in the meter
reading report and in the tax invoice, so as to facilitate easy identification of location
of Solar Power Plants.

In view of the above, it is requested to solar section to follow the suggestions made by Pre-
Audit CA and take necessary steps in realization of Facilitation charges and also requested to
intimate to the Power Producer to raise the bills in favor of Power Purchaser (TSRTC) on
monthly basis and to submit the bills to TSRTC as well as TSREDCO simultaneously for
timely accounting of revenue.
Further, as per the information provided at Note#108Note#108, by summarizing the total
units generated for the month of October-2022 and proposing for issue of Facilitation Charges
by attaching the JMR's, the Tax Invoice raised against to the M/s Sun Technologies.( Tax
Invoice attached @951 ).
S. No For the Month Billed units FC @0.20 per Unit Accounted
1 October-2022 58,815 11,763/- SR/2277

In view of the above, it is requested to solar section to take necessary steps for realization of
total Facilitation charges due from M/s Sun Technologies for Rs.3,02,836/- (i.e. for
December-2020 to September-2022) and Rs.11,763/- for the month of October-2022 .
Further, as proposed in Note # 108, the draft letter (DFA/622515) may be approved.
Submitted for further orders/approval please.

28/12/2022 5:02 PM
RACHAKONDA VAMSHI KRUSHNA
(JUNIOR MANAGER GR.I- F&A- TSREDCO)

Note No. #115

28/12/2022 5:05 PM
AMANAGANTI SATYANARAYANA REDDY
(ASSISTANT MANAGER- F&A - TSREDCO)

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
36)

Note No. #116

28/12/2022 5:16 PM
J . ANIL KUMAR
(MANAGER (F&A) - TSREDCO)

Note No. #117

Note No.1147 may be approved

29/12/2022 11:01 AM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #118

Approved Note#117.

29/12/2022 11:58 AM
NEELAM JANAIAH
(VICE CHAIRMAN & MANAGING DIRECTOR- TSREDCO)

Note No. #119

Note No. 117 Please be read as "Note No.114 may be approved"

By erroniously 7 added with 114

29/12/2022 12:09 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #120

29/12/2022 1:26 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #121

In contiuation to the above, vide dt.21.01.2023, a letter received from TSRTC


wherein requested to arrange for shifting of SPV plant from existing ZWS,

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
37)

Karimnagar to Bus Station Karimnagar and TRS/ Karimnagar.The received letter


copy is placed at page no.958 for kind perusal.

Hence in this regard, a letter is prepared vide DFA/648489 while addressing to


TSRTC wherein requested to submit the quotation for shifting of SPV plants from
ZWS karinnagar.

Hence the above is submitted for approval or further orders.

30/01/2023 1:29 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Note No. #122

submitted for approval


30/01/2023 6:04 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #123

31/01/2023 1:00 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Note No. #124

Approved Note#122.

31/01/2023 3:10 PM
NEELAM JANAIAH
(VICE CHAIRMAN & MANAGING DIRECTOR- TSREDCO)

Note No. #125

31/01/2023 3:19 PM
GUTTA SATYA VARA PRASAD
(GENERAL MANAGER)

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM
File No. REDCO-SE/RESC/SUNT/2/2021-SOLAR ENERGY SECTION-TSREDCO (Computer No. 392129
38)

Note No. #126

31/01/2023 5:01 PM
CH.AMARENDER REDDY
(PROJECT DIRECTOR - SOLAR ENERGY - TSREDCO)

Note No. #127

Further, for the month of Nov-22, Dec-22 and Jan-23, the monthly consumption
reading reports/JMR and invoices were received from M/s.Sun Technologies , duly
signed by the power producer and beneficiary and the same is attached at page
No.980 to 1026, 1027 to 1069, 1070 to 1117, 1118 to 1158, 1159 to 1165 for kind
perusal.

Further, the consolidated location wise facilitation charges at Rs.0.20/- per unit are
calculated and the summarized statement is attached at pg.no.1166 to 1167, 1168 to
1169 and 1170 to 1171.
The details are summarized as below:

Facilitation charges
amount @ Rs.0.2/- per
Sl.no JMR’S of Total units unit Remarks
the month Generated
JMR’s received Inward
1 Nov-22 55,820 Rs.11,164
Dt.07.02.2023
2 Dec-22 60,227 Rs.12,045 11.01.2023
3 Jan-23 57,617 Rs.11,523.4 25.02.2023

Further, it is to submit that, 03 No’s JMR’s i.e, Huzurabad Bus Station, Huzurabad
Bus Depot and Rajanna Sirisilla Bus Station were not received and the same was
submitted in the month of Dec-22 as a bimonthly readings.
Further, the finance wing is requested for examination of JMR’s, Invoices and
Summarized statement so as to raise the demand notice/ invoice towards FC
charges and for collecting the facilitation charges from M/s. Sun Technologies.
Hence the above is submitted for approval

16/03/2023 2:31 PM
MADHURI.BUNGA
(DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO)

Generated from eOffice by MADHURI.BUNGA, DEVELOPMENT OFFICER-SOLAR ENERGY - TSREDCO, TSREDCO on 20/03/23 12:33 AM