Professional Documents
Culture Documents
Report Progress 28 Agustus 2023
Report Progress 28 Agustus 2023
To day : Monday
To date : 28-Aug-23
1 OVERALL SCHEDULE : REPORT MOSQUE
Contract Duration : 97 HK
Start : 30-Jun-23
Finish : 5-Oct-23
Achievement Progress
Cumulative Plan : 80.73%
Progress Today : 0.10%
Cumulatif Actual : 96.62%
Deviation : 15.89% AHEAD
Contract Duration : 97 HK
Start : 30-Jun-23
Finish : 5-Oct-23
Achievement Progress
Cumulative Plan : 36.36%
Progress To day : 0.60%
Cumulatif Actual : 75.07%
Deviation : 38.71% AHEAD
Contract Duration : 97 HK
Start : 30-Jun-23
Finish : 5-Oct-23
Achievement Progress
Cumulative Plan : 36.86%
Progress To day : 3.24%
Cumulatif Actual : 79.98%
Deviation : 43.12% AHEAD
Achievement Progress
Cumulative Plan : 100.00%
Progress To day :
Cumulatif Actual : 96.38%
Deviation : -3.62% BEHIND
Contract Duration : 31 HK
Start : 7-Aug-23
Finish : 7-Sep-23
Achievement Progress
Cumulative Plan : 65.00%
Progress To day :
Cumulatif Actual : 50.00%
Deviation : -15.00% BEHIND
Contract Duration : 0 HK
Start :
Finish :
Achievement Progress
Cumulative Plan :
Progress To day :
Cumulatif Actual :
Deviation :
Achievement Progress
Cumulative Plan : 0.00%
Progress To day :
Cumulatif Actual : 0.00%
Deviation : 0.00% On Schedule