EXECUTIVE SUMMARY PROJECT

PT. BISSOT JAYA PRATAMA


BATU HIJAU COMBINATION OF CYCLE POWER PROJECT, BENETE BAY-BARAT SUMBAWA
NUSA TENGGARA BARAT

To day : Monday
To date : 28-Aug-23
1 OVERALL SCHEDULE : REPORT MOSQUE

Contract Duration : 97 HK
Start : 30-Jun-23
Finish : 5-Oct-23

Achievement Progress
Cumulative Plan : 80.73%
Progress Today : 0.10%
Cumulatif Actual : 96.62%
Deviation : 15.89% AHEAD

Next Action Material


- Finishing Lantai :
- Pengecatan Floor Coating :
- Elektrikal Fixture :
- Pekerjaan Bio Tank & Plumbing :
- Tandon Air :

2 OVERALL SCHEDULE : REPORT STAFF CANTEEN

Contract Duration : 97 HK
Start : 30-Jun-23
Finish : 5-Oct-23

Achievement Progress
Cumulative Plan : 36.36%
Progress To day : 0.60%
Cumulatif Actual : 75.07%
Deviation : 38.71% AHEAD

Next Action Material


- Finishing Lantai :
- Pengecatan Floor Coating :
- Elektrikal Fixture :
- Pekerjaan Bio Tank & Plumbing :
- Tandon Air :
3 OVERALL SCHEDULE : REPORT WORKER CANTEEN

Contract Duration : 97 HK
Start : 30-Jun-23
Finish : 5-Oct-23

Achievement Progress
Cumulative Plan : 36.86%
Progress To day : 3.24%
Cumulatif Actual : 79.98%
Deviation : 43.12% AHEAD

Next Action Material


- Finishing Lantai :
- Pengecatan Floor Coating :
- Elektrikal Fixture :
- Pekerjaan Bio Tank & Plumbing :
- Tandon Air :

4 OVERALL SCHEDULE : REPORT SITE OE

Contract Duration : 45159 HK


Start :
Finish : 21-Aug-23

Achievement Progress
Cumulative Plan : 100.00%
Progress To day :
Cumulatif Actual : 96.38%
Deviation : -3.62% BEHIND

Next Action Material


- Pekerjaan Plafon :
- Keramik Toilet :
- Keramik Ruang Doc Control :
- Fixture Toilet :
- Penangkal Petir :
- Instal water Pump :
- Elektrikal Fixture :
5 OVERALL SCHEDULE : REPORT DRAINASEE

Contract Duration : 31 HK
Start : 7-Aug-23
Finish : 7-Sep-23

Achievement Progress
Cumulative Plan : 65.00%
Progress To day :
Cumulatif Actual : 50.00%
Deviation : -15.00% BEHIND

Next Action Material


- Darinase Utama & Sekeliling Bangunan :
- Chamber Filtrasi :
- Shower Drain :
- Road Crossing ( Open Cut ) :

6 OVERALL SCHEDULE : REPORT CCR Plumbing

Contract Duration : 0 HK
Start :
Finish :

Achievement Progress
Cumulative Plan :
Progress To day :
Cumulatif Actual :
Deviation :

Next Action Material


- Pre Test Line : DOP 6" = 1 Ea
: DOP 4" = 10 Ea
: DOP 3" = 2 Ea
: DOP 2" = 16 Ea
: Lem Pipa PVC = 15 Ea
6 OVERALL SCHEDULE : REPORT CCR Administrasi & Central Control Building

Contract Duration : 186 HK


Start : 1-Sep-23
Finish : 5-Mar-24

Achievement Progress
Cumulative Plan : 0.00%
Progress To day :
Cumulatif Actual : 0.00%
Deviation : 0.00% On Schedule

Next Action Material


- Wall Finishing Basic Lavel : Hollow Block Lecon 60cm x 20cm x 15 cm = 57 M3
: MU.308 = 39 Zak
MANPOWER
- Mason Skill = 6 Person
- Helper = 12 Person
- Foreman = 1 Person