Professional Documents
Culture Documents
PROFESSIONAL PRACTICE - M3L3 - 22march24
PROFESSIONAL PRACTICE - M3L3 - 22march24
PRACTICE
Termination of contract
1. Defects liability period
2. Latent and patent defects
3. Liquidated and un-liquidated damages
4. Extension of time, delays and penalty
5. Non tendered items, extras, extra work,
additional works, variations, rate analysis
6. Architect’s role in certification of variations
Defects liability period (DLP)
“In case any structural defect or any other defect in workmanship, quality or provision of
services or any other obligations of the promoter as per the agreement for sale relating to
such development is brought to the notice of the promoter within a period of five years by
the allottee from the date of handing over possession, it shall be the duty of the promoter to
rectify such defects without further charge, within thirty days, and in the event of promoter’s
failure to rectify such defects within such time, the aggrieved allottees shall be entitled to
receive appropriate compensation in the manner as provided under this Act”.
Defects liability period (DLP)
Examples of defects as per The Haryana RERA Rules, 2017
actual physical damage/ defects to the designated load-bearing elements of the building
like faults, breakage or cracks which can affect the strength and stability of the
apartment or the building
Defect – something is not correct or the way one expects – abnormal, imperfect, lacking
Duty of Care – Universally accepted convention; to be good to others, not to cause harm or
loss
• Liquidated damages - Provision for the contractor to pay to the client if the contract is
breached.
• It’s a pre-agreed amount of money that is set out in advance in the contract, that fixes
the sum payable as damages if the contractor breaches the contract - typically by
failing to complete the construction works on time as set out in the contract.
• Liquidated damages are typically calculated on a daily or weekly basis.
• Unliquidated damages - amount which has not been agreed. The amount to be paid
as compensation and is determined after the breach occurs by a court.
Liquidated and un-liquidated damages
• Liquidated damages (or an agreed damages clause)- damage must either be proven or
admitted
• there is no need to prove the actual loss, because the clause stipulates a pre-
assessment or pre-estimation of damages
• Charges on daily basis – deterrent for contractor against delaying the work
Arbitration
• Saves cost
• Award is final
Arbitration
Process-
• Arbitration hearing
• To decide on cost of award & proportion with which parties have to bear
-To consolidate and amend the laws relating to the above fields
• decree
ARBITRATION UNDER IIA CONDITIONS OFCONTRACT
Sole arbitration by architect on excepted (excluded from arbitration) matter
Parties agree in the absence of mistakes or fraud
EXCEPTED MATTERS (condition no. 55)
· Drawings and specifications and their interpretations
· Architects' instructions regarding variations
· Contractors field organizations ,equipment, office accommodation, tools and
plants etc.
Arbitration &conciliation act of 1996
Extension of time
Within 28 days of decision, parties write to each other about areas of dispute
· In case the arbitration is in the middle of the ongoing work and when matter is
pending with arbitrator contractor to proceed with the work and owner to make
Un biased