Professional Documents
Culture Documents
Sao S 201008
Sao S 201008
net/publication/233087981
CITATIONS READS
9 20,595
3 authors, including:
All content following this page was uploaded by John Kyu Hwang on 25 February 2020.
This study presents the ways and means of detailed design and construction of an on-going 2,000,000 BBLS floating,
production, storage and off-loading (FPSO) unit installed in the near offshore area of Nigeria. First, we explain the overall
procedure of a hull of FPSO unit from detailed design to construction and lessons learned from the hull of FPSO, contributing
to successful design and construction of future FPSO units. Then, we describe some problems and their solutions of the
detailed design and construction of the hull of FPSO. Through this study, readers will be able to learn the detailed design
and construction of FPSO.
Downloaded By: [Roh, Myung-Il] At: 02:24 13 August 2010
Keywords: floating, production, storage and off-loading unit (FPSO); offshore production system; oil field development;
front end engineering design (FEED); design; construction
1. Overview of FPSO and oil field development 1.2. Introduction to the Nigeria field development
1.1. Introduction to FPSO project
FPSO, which stands for floating, production, storage and The Nigeria field is located in the offshore area called OPL
off-loading unit, is a floating vessel that is able to produce 246 of Nigeria, as shown in Figure 3. This oil field, which
crude oil and gas. It is made up of two parts: the topside was discovered in March 2000, is located 200 km from Port
and the hull. The topside, like chemical plants, produces Harcourt. The water depth where this oil field is located is
and off-loads crude oil and gas, and the hull, like a big 1275∼1470 m. The Nigeria field development project refers
tank, stores the produced oil. The FPSO unit produces and to the project that produces oil and gas in this field. The
processes crude oil and gas on the topside, and stores the Nigeria field development project consists of several major
stabilised oil in cargo tanks of the hull. The FPSO unit oil companies, namely Nigerian National Petroleum Com-
also off-loads the stabilised oil and gas to a shuttle tanker pany (NNPC), South Atlantic Petroleum, Nigerian Com-
through the oil export/metering pump (Mather 2000). How- pany (Sapetro), Brasilian Oil Company (Petrobras) and
ever, the FPSO alone cannot produce oil and gas in the oil Nigerian Subsidiary of Total (Tupni). The share of each
field. It requires many offshore production systems, such company for this project is 50%, 10%, 16% and 24%, re-
as the sub-sea production systems (SPS), umbilicals, flow spectively.
lines and risers (UFR), mooring lines, a shuttle tanker, an From the perspective of field development, this project
off-loading buoy etc., as shown in Figure 1. Thus, the de- is largely made up of the FPSO, SPS, UFR and offshore
sign and construction of an FPSO unit includes many other loading terminal (OLT), as shown in Figure 1.
offshore production systems (Shimamura 2002; Infield Co., The FPSO of this project is made by the consor-
Ltd. 2005a, 2005b; International Maritime Associates Inc. tium members. Hyundai Heavy Industries Co., Ltd. (HHI;
2005). http://www.hhi.co.kr) is charged with the hull, Technip Co.,
Figure 2 shows a typical layout of an FPSO unit. It Ltd. (http://www.technip.com) with the topside, Cameron
is subdivided into two parts: topside and hull. An FPSO with the SPS and Saibos with the UFR. The design and con-
unit has many subsystems, such as the flare tower, living struction of the FPSO was done by HHI, Hyundai Samho
quarters, lay-down area, mooring fairleads and a helicopter Heavy Industries Co., Ltd. (HSHI; http://www.hshi.co.kr)
deck. and Technip. The detailed design of the topside was done by
∗
Corresponding author. Email: miroh@ulsan.ac.kr
ISSN: 1744-5302 print / 1754-212X online
Copyright
C 2010 Taylor & Francis
DOI: 10.1080/17445300903169168
http://www.informaworld.com
94 J.-K. Hwang et al.
Downloaded By: [Roh, Myung-Il] At: 02:24 13 August 2010
Technip. The detailed design of the hull and the construc- 2.1. FPSO
tion of the topside were done by HHI and the construction FPSO of this project consists of mooring, riser structure,
of the hull was carried out by HSHI. The methods used to accommodation, process (oil, gas and water) facilities, gas
produce the detailed design and construction of the hull of and water injection facilities, flaring facilities, oil storage
the FPSO is studied to help future design and construction facilities, export facilities (pumping and metering), gas ex-
of the hull of FPSOs. port facilities and control systems, as shown in Figure 4.
The overall functions and specific characteristics of each
component are as follows:
2. Elements of the field development project
The field development project is made up of FPSO, SPS, r Total production capacity (total fluids): 200,000 bar-
UFR and OLT, as shown in Figure 4. More details of each rel/day.
element are presented here. r Stabilised oil (Figure 4a): maximum 185,000 barrel/day.
r Produced gas (Figure 4b): 530 million standard cubic r 24 oil producer wells.
feet per day (Mscfd). r 3 gas injection wells.
r Injected gas (Figure 4c): 215 Mscfd at 400 bar. r 21 water injection wells.
r Export gas (Figure 4d): 320 Mscfd at 193 bar.
r Fuel gas: 25 Mscfd.
r Injected water (Figure 4e): 420,000 barrel water per day 2.3. Umbilicals, flow lines and risers
(bwpd) at 200 bar. Umbilicals, flow lines and risers (UFR) are the specific
r Produced water: 150,000 bwpd.
facilities that transfer the produced crude oil from SPS
r Crude storage (Figure 4b): 2,000,000 barrel (BBLS).
to the topside of FPSO, which is equipped with process
r Spread mooring (Figure 4f): 4 × 3 lines.
systems, as shown in Figure 4h (International Maritime
Associates Inc. 2005). In this project, components of UFR
are as follows:
2.2. Sub-sea production systems
Sub-sea production systems (SPS) are the sub-sea systems r Four production flow loops and risers (Figure 4b): Pro-
that were drilled by the fixed platform or the drill ship and duction lines for the crude oil from oil producer wells.
from which oil and gas were extracted, as shown in Figure r One gas injection line and risers (Figure 4c): Gas injec-
4g. SPS are also called wellheads or X-mas trees. In this tion line for compensating for the pressure of oil pro-
project, SPS consist of 48 wells, as shown below. ducer wells after producing the crude oil.
96 J.-K. Hwang et al.
Downloaded By: [Roh, Myung-Il] At: 02:24 13 August 2010
r Four water injection lines and risers (Figure 4e): Water shuttle tanker through the export and metering pump in the
injection lines for compensating for the pressure of oil topside, flow lines and off-loading buoy, as shown in Figure
producer wells after producing the crude oil. 4m (International Maritime Associates Inc. 2005).
r Four production umbilicals (Figure 4i): Specific lines for
installing cables to supply electric power for SPS.
r Four injection umbilicals (Figure 4i): Specific lines for
installing cables to supply electric power for gas and
water injection facilities. 3. Detailed design procedure and main activities of
r One export gas pipeline (Figure 4d): Specific line for the hull of FPSO
transferring gas to Amenam AMP2 Platform (Figure 3.1. Procedure of the FPSO field development
4j). In general, the crude oil of oil producer wells is
In order to develop the field, an exploration and feasibility
separated into oil, gas and water through the high- and
study must first be performed. Then, based on the result of
lower-pressure separators. That is, after the stabilised oil
the study, front-end engineering design (FEED) of FPSO is
is stored in cargo tanks of the hull of the FPSO (Figure
commenced if the economic value of the field development
4k), the stabilised oil is off-loaded to a shuttle tanker
is positive, taking the circumstances of offshore market into
(Figure 4l) through the oil export/metering pump and
account. In case of the Nigeria field development, FEED
the dehydrated gas is used for gas injection wells and
was performed by Doris Engineering Co., Ltd. (www.doris-
main turbine generator through the dehydration and ex-
engineering.com) in a 10∼12-month period. After FEED,
port compressor. Then, the remaining gas is transferred
the detailed design of the topside of FPSO was performed by
to Amenam AMP2 Platform. This line is used for this
Technip and the detailed design of the hull was performed
purpose.
by HHI in a 12∼14-month period. Then, the construc-
tion and installation of the topside was performed by HHI
2.4. Offshore loading terminal and the construction of the hull was performed by HSHI.
Offshore loading terminal (OLT) is the specific facility that Figure 5 shows the overall procedure of the FPSO field
transfers the stabilised oil in cargo tanks of the hull to the development of this study (Barltrop 1998a, 1998b).
Ships and Offshore Structures 97
3.2. Detailed design procedure of the P&ID of Specifications on client’s requirements are largely di-
FPSO and main activities vided into the project and the company specifications. These
Figure 6 shows the detailed design procedure of the hull were incorporated in the P&ID after a technical review.
of FPSO and the main activities of the detailed design. Moreover, among the client’s requirements, if specific re-
As shown in Figure 6, the core of the detailed design is quirements are not acceptable in the technical or commer-
Downloaded By: [Roh, Myung-Il] At: 02:24 13 August 2010
preparing the pipe and instrumentation diagram (P&ID) cial view, clarification works have been performed using
for each system or facility of the hull. More details about the specifications deviation.
preparing P&ID at this stage are as follows:
2. FEED clarification
Figure 6. Detailed design procedure for P&ID of the hull of an FPSO unit in this study.
98 J.-K. Hwang et al.
Figure 7. Detailed design procedure for the hull of FPSO in this study.
Ships and Offshore Structures 99
Figure 10. Concept and FEM model for riser and umbilical installation aids supports.
Downloaded By: [Roh, Myung-Il] At: 02:24 13 August 2010
– Bow
– Side
– Stern
– Riser protector
– Mooring off-take protector
– Caisson/supply vessel berthing area
r Fire
– Riser support
– Topside module support
Figure 12. Bracket toe of a crane pedestal.
r Explosion
was negative, then the total pressure at that point was set to
zero. – Deck/living quarter
– Topside module support
r Fatigue analysis for the longitudinal hull
Downloaded By: [Roh, Myung-Il] At: 02:24 13 August 2010
r Drop object
– Phase 1: Hold FE model analysis
– Phase 2: Hydrodynamic and hold FE model analysis – Lay-down module/deck
– Refined: Longitudinal, bracket toe and heel etc. – Living quarter
– Phase 2: Hydrodynamic and hold FE model analysis The category definitions should be clarified in ac-
– Hold FE modelling cordance with the latest Bureau Veritas classification of
– Screening (the pre-step for the fatigue analysis to de- ships (BV rules; NR497, dated May 2006) and hull gen-
termine the area that experienced the highest stress eral specification. There are three kinds of categories as
from the same type of load component): Stringer con- follows:
nection, web connection, hopper corner etc. r Special category
– Refined: Transverse, shear lug and cutout etc. r First category
r Fatigue analysis of appurtenance and helicopter deck r Second category
support
The special category and hot spot stress areas should
– Phase 3: Full ship model analysis receive complete joint penetration (CJP) welds according
– Hydrodynamic analysis to American Welding Society (AWS) requirement and CJP
– Screening: Crane pedestal foundation connection, aft welds should be applied for the fatigue-concerned areas and
and fwd end of riser and umbilical support etc. high-tension areas also, but it is not mandatory for the first
– Refined: Topside support, pipe rack support, flare category and high stress concentration areas.
tower foundation, riser and umbilical support, hull
side caisson and support, mooring equipment foun-
3.3.3. Detailed structure drawings
dations etc.
Detailed structure drawings can be developed based on the
Most positions tried in previous lessons, were rein- hull key plan and key drawing of appurtenances. These
forced by thicker plates and soft shapes in prior. However, drawings have been separated according to the character-
several positions of the welding around the toes could not istic of the structures and updated with outfitting system.
meet the allowable stress level. Thus, the welding beads The convenience utilisation of the yard’s facilities and safe
were modified into soft type and counter grindings were working of fabrication and maintenance were considered
provided onto the plates, which were recommended by In- with reference to the category plan, arrangement of outfit-
ternational Institute of Welding (IIW). Some critical posi- ting on the hull deck, machinery arrangement for the ma-
tions (see Figure 12) were replaced with thicker plates even chinery space, block division, detailed assembly procedure
though above efforts. and so on.
102 J.-K. Hwang et al.
1. Block division
2. Detailed assembly procedures (See Figure 13)
3. Block fabrication drawings
4. Welding map
5. Non-destructive test plan
2. Activities related to L/Q blocks to the weight increase of topsides. In order to solve
these problems, the overall design on the hull has been
Activities related to the L/Q blocks are the tasks for verified, changed and compared with FEED. Also, many
living quarters, lay-down module, helicopter deck and so man-hours (M/Hs) were required in this project. Based
on. on this valuable experience, sufficient verification works
on initial FEED data are very important.
3. Activities related to hull appurtenances 2. If critical safety study such as HAZOP is performed at
Downloaded By: [Roh, Myung-Il] At: 02:24 13 August 2010
Figure 15. Launching and dock out of the hull of an FPSO unit.
mind those damages to the side shell and appurtenances the following results. First, the scheme of the FPSO field
should be avoided in case of dock out after floating. Es- development has been examined. Second, detailed design
pecially, if the wind speed is above 7 m/s, the launching procedures and activities of the hull of an FPSO unit have
should be stopped and postponed. Also, the weight con- been examined. Third, construction procedures and activi-
trol is very important because various systems of the ties of the hull have been examined. Finally, critical points
topside are installed after installing appurtenances on on interface work between systems and disciplines in the
the hull. hull construction have been examined. The above contents
8. After launching the hull of the FPSO, a problem is will be used as guidelines in order to reduce M/H and cost
generated due to minor movements of the hull while impacts on the design and construction of the hull of future
bolting work is being performed at the steel fender. In FPSO units.
order to solve this problem, the bracket type of the hull
has been changed from the recess pocket type to the
pivot-type bracket.
9. In erecting L/Q blocks, which is one of the main events, References
a crane with a safety working load of above 3000 ton Barltrop NDP. 1998a. Floating structures: a guide for design
and analysis – Vol 1. Herefordshire, UK: The Center for
should be arranged because the weight of L/Q blocks Marine and Petroleum Technology, Oilfield Publications
is over 2000 ton. Ltd.
10. When unit cabins are installed after installing the L/Q Barltrop NDP. 1998b. Floating structures: a guide for design
blocks, the telecom cable frequency test should be per- and analysis – Vol. 2. Herefordshire, UK: The Center for
formed in advance so as to prevent re-work because of Marine and Petroleum Technology, Oilfield Publications
Ltd.
insufficient compatibility on frequency. Infield Co., Ltd. 2005a. Global perspectives floating production
11. At the procurements stage, it is very important for raw market update. Houston, TX: Infield Co., Ltd.
materials to be ordered well in advance in order to Infield Co., Ltd. 2005b. Fixed platforms report market update.
avoid work delay. Houston, TX: Infield Co., Ltd.
International Maritime Associates Inc. 2005. Floating production
systems. Washington D.C.: IMA Inc.
6. Conclusions Mather A. 2000. Offshore engineering – an introduction. London:
Witherby & Co. Ltd.
Based on our valuable experience of the detailed design and Shimamura Y. 2002. FPSO/FSO: state of the art. J Mar Sci Tech-
construction of the hull of an FPSO unit, this study presents nol. 7(2):59–70.