6 Weeks Lookahead Plan(01/09/2023)

ID Task Name Duration Start Finish September October November December January
13/08 20/08 27/08 03/09 10/09 17/09 24/09 01/10 08/10 15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12
1 Long‐Distance Train Station Stuttgart Airport 335 days 12/09/2022 25/12/2023
30 Construction 335 days 12/09/2022 25/12/2023
31 Central Access (Area 1) 335 days 12/09/2022 25/12/2023
32 U‐10 82 days 01/09/2023 25/12/2023
33 A.U10.005 Cellular Room 66 days 01/09/2023 01/12/2023
34 Sanitary 13 days 01/09/2023 19/09/2023
36 Marking in walls/Ceilings 2 days 06/09/2023 07/09/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
37 cutting & chasing 3 days 08/09/2023 12/09/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
38 Installation of drain pipes 3 days 13/09/2023 15/09/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
39 Connection with ULKG 2 days 18/09/2023 19/09/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
40 Cable Support Structures 19 days 04/09/2023 28/09/2023
41 Storage of material 3 days 04/09/2023 06/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
42 Installation of support structures 3 days 07/09/2023 11/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
43 straight line section installation 3 days 12/09/2023 14/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
44 Fittings installation 2 days 15/09/2023 18/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
45 Ancillary products/accessories installation 3 days 19/09/2023 21/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
46 Grounding 2 days 22/09/2023 25/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
47 Placement of cables on cable trays/ducts 3 days 26/09/2023 28/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
48 Cooling System 58 days 13/09/2023 01/12/2023
49 Installation of chill/hot water hangers & supports 5 days 13/09/2023 19/09/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
50 Installation of chilled /hot water pip 10 days 20/09/2023 03/10/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
51 Set mounting rings for Pipes 5 days 04/10/2023 10/10/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
52 Cleaning of pipework surfaces 5 days 11/10/2023 17/10/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
60 Ventilation (Smoke Extraction System) 46 days 13/09/2023 15/11/2023
61 Installation of Supply/Return air pipes hangers & suppo9 days 13/09/2023 25/09/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
62 Installation of Supply/Return air pipe 15 days 26/09/2023 16/10/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
67 A.U10.006 Floor 79 days 06/09/2023 25/12/2023
68 Sanitary 15 days 06/09/2023 26/09/2023
69 Marking in walls 5 days 06/09/2023 12/09/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
70 Cutting & chasing 5 days 13/09/2023 19/09/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
71 Installation of drain pipes 5 days 20/09/2023 26/09/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
72 Cable Support Structures 47 days 07/09/2023 10/11/2023
73 Installation of support structures 7 days 07/09/2023 15/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
74 straight line section installation 16 days 18/09/2023 09/10/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
75 Fittings installation 7 days 10/10/2023 18/10/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
79 Cooling System 74 days 13/09/2023 25/12/2023
80 Installation of chill/hot water hangers & supports 15 days 13/09/2023 24/10/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
88 Ventilation (Smoke Extraction System) 66 days 13/09/2023 13/12/2023
89 Installation of Supply/Return air pipes hangers & suppo5 days 13/09/2023 19/09/2023 Plumber Assistant -1,Plumber-1,Plumbing Supervisor -1
95 A.U10.S08 MS/Entrance 14 days 07/09/2023 26/09/2023
96 Cable Support Structures 14 days 07/09/2023 26/09/2023
97 Installation of support structures 3 days 07/09/2023 11/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
98 Straight line section installation 4 days 12/09/2023 15/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
99 Fittings installation 2 days 18/09/2023 19/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
100 Ancillary products/accessories installation 2 days 20/09/2023 21/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
101 Grounding 1 day 22/09/2023 22/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
102 Placement of cables on cable trays/ducts 2 days 25/09/2023 26/09/2023 Electrical Superviser -1,Electrician -1,Electrician Helper -1
103 U‐4 302 days 12/09/2022 08/11/2023
104 A.U4.009 Smoke extraction room 302 days 12/09/2022 08/11/2023
105 Cooling System 41 days 13/09/2023 08/11/2023
106 Installation of chill/hot water hangers & supports 5 days 13/09/2023 19/09/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
107 Installation of chilled /hot water pipes 10 days 20/09/2023 03/10/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Long-Distance Train St
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: 25/06/2023
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
6 Weeks Lookahead Plan(01/09/2023)
ID Task Name Duration Start Finish September October November December January
13/08 20/08 27/08 03/09 10/09 17/09 24/09 01/10 08/10 15/10 22/10 29/10 05/11 12/11 19/11 26/11 03/12 10/12 17/12 24/12 31/12
108 Set mounting rings for Pipes 2 days 04/10/2023 05/10/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
109 Cleaning of pipework surfaces 2 days 06/10/2023 09/10/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
110 Application of internal acoustic insulation 3 days 10/10/2023 12/10/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
111 Ceiling & curing 2 days 13/10/2023 16/10/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
117 Ventilation (Smoke Extraction System) 36 days 13/09/2023 01/11/2023
118 Installation of Supply/Return air pipes hangers & suppo10 days 13/09/2023 26/09/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
119 Installation of Supply/Return air pipe 10 days 27/09/2023 10/10/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
120 set mounting rings 5 days 11/10/2023 17/10/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
124 Sanitary 8 days 06/09/2023 15/09/2023
125 Marking in walls 2 days 06/09/2023 07/09/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
126 Cutting & chasing 3 days 08/09/2023 12/09/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
127 Installation of drain pipes 3 days 13/09/2023 15/09/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
138 A.U4.010 Entry. Center 2 25 days 13/09/2023 17/10/2023
139 Ventilation (Smoke Extraction System) 25 days 13/09/2023 17/10/2023
140 Installation of Supply/Return air pipes hangers & suppo5 days 13/09/2023 19/09/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
141 Installation of Supply/Return air pipe 10 days 20/09/2023 03/10/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
142 Set mounting rings 3 days 04/10/2023 06/10/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
143 Ceiling & curing 3 days 09/10/2023 11/10/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2
144 Installation of Flow Controllers 2 days 12/10/2023 13/10/2023 Plumber Assistant -2,Plumber-2,Plumbing Supervisor -2

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Long-Distance Train St
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: 25/06/2023
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress