BALANCE WORK OF BGKA-NXN SEC. AS ON DATED 05.03.

2024
Balance Work status of Minor Bridges and LHS.
Coping block
Drop fixing,Inspection
Boulder
Description wall,apron,wearing steps,HFL DL
Wing wall backing,filter Assistance required
of works course, coping block marking,Bridge
media filling
& inspection steps Tablet,Wearing
course

Drop wall, inspection


Br.No-683 Completed. Balance Balance 12 labours for 3 days with concrete and shuttering work
steps

15 labours for 7days, with concrete and shuttering work. Hume


Br.No-684 completed. Balance Completed. Balance
pipe dia 900mm total 6 nos, JCB,
Br.No-685 Balance Balance Completed. Balance 5 labours for 3 days with concrete and shuttering work

30 labours for 7 days with concrete and shuttering work, 1 AJEX,


Br.No-686 Completed. Balance Completed. Balance
1 poclain with shuttering materials and coping blocks.

Br.No-687 Completed Balance Completed. Balance 8 labours for 4 days with concrete and shuttering work.

Br.No-688 Completed Balance Completed. Balance 10 labours for 4 days with concrete and shuttering work

30 labours for 7 days with concrete and shuttering work, 1 AJEX,


BGKA end- 2
1 poclain with shuttering materials and coping blocks. Boulder
Br.No-689 lift casting Balance Balance Balance
backfilling with Formation 100 mtrs with roller, dozer, ballasting
done.
and track linking.

30 labours for 7 days with concrete and shuttering work, 1 AJEX,


Br.No-690 Completed. Only drop wall made Done Balance
1 poclain with shuttering materials and coping blocks.

25 labours for 7 days with concrete and shuttering work, 1 AJEX,


Br.No-691 Balance Balance Balance Balance
with shuttering materials and coping blocks.
Br.No-692 Completed Only drop wall made Done Balance 8 labours for 4 days with concrete and shuttering work.
Both side 2nd
Br.No-693 Balance Done Balance 15 labours for 5 days with concrete and shuttering work.
footing done
45 labours for 10 days with concrete and shuttering work, 1
AJEX, 1 poclain with shuttering materials and coping blocks.
Br.No-695 Completed. Balance Balance Balance
Boulder backfilling with Formation 400 mtrs with roller, dozer,
ballasting and track linking. (24Hrs Work required)
Proposed side-
Completed.
20 labours for 7 days with concrete and shuttering work, 1 AJEX,
HB-55 Ext. side-One Balance Done Balance
with shuttering materials and coping blocks.
footing done at
nxn end.
Total labours rqeuired for Bridge work= 253 nos