Professional Documents
Culture Documents
Schedule Q
Schedule Q
3000848438 (M-IK)
SCHEDULE Q
QUALITY REQUIREMENTS
TABLE OF CONTENTS
1. General
3. Documentation Requirements
4. Management Responsibility
5. Resource Management
Q-i
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
SCHEDULE Q
QUALITY REQUIREMENTS
1. GENERAL
1.1 Unless otherwise defined in this Contract or below, capitalized terms used
in this Schedule “Q” shall have the respective meaning specified in the
2015 version of ISO 9001 (Quality Management Systems – Requirements).
In addition, the following terms shall have the respective meanings
ascribed below, which, in this Contract, are in addition to and not in
substitution of the defined terms specified in Schedule “A”:
“Agreed Completion Date” or “ACD” means the date which the violation
notification will be closed upon completion of the required corrective and
preventive actions for the reported violation fully.
“Inspection and Test Plan” or “ITP” means a document based on the detailed
manufacturing, fabrication and construction program which identifies each
process description, sets out the related sequence of activities to be
inspected, examined and tested and lists the relevant approved procedures for
a particular material, component, assembly, or, in some cases, type of work. It
shall include identification of requirements for documents, acceptance criteria
Q-1
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
1.3 CONTRACTOR shall manage, inspect, test and accept all parts of the
WORK, to ensure conformance with all standards, specifications and
drawings applicable to the WORK.
Q-2
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
1.10 In the event CONTRACTOR does not fulfil quality requirements of this
Contract, SAUDI ARAMCO may perform CONTRACTOR’s WORK in
accordance with Schedule “A”.
CONTRACTOR shall, and shall ensure that all of its Subcontractors, including its
Vendors, plan and implement a Quality Management System (QMS) for this
Contract in accordance with:
3. DOCUMENTATION REQUIREMENTS
3.1 CONTRACTOR shall plan, organize, control and execute all WORK in
accordance with the SAUDI ARAMCO approved CONTRACTOR Quality
Manual, PQP, ITP’s, work instructions and quality procedures.
CONTRACTOR’s PQP shall ensure that quality Personnel, resources
(facilities, Tools and Equipment), processes and activities, including those
of Subcontractors and Vendors are planned, coordinated, and effectively
completed in strict compliance with Contract requirements.
Q-4
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
3.2.3 The CONTRACTOR PQP shall identify and adopt specific Vendor
material preservation quality procedures, work instructions and
recommendations as minimum quality requirements for each
commodity, material type and equipment, to ensure Vendor
warranties are maintained and delivered to SAUDI ARAMCO. If
SAUDI ARAMCO preservation requirements exceed manufacturer
requirements, then SAUDI ARAMCO requirements shall also be
specified and adopted by CONTRACTOR, to the extent allowed
under Vendor warranties.
Q-5
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
3.3 CONTRACTOR shall timely revise the PQP and related quality documents
as needed to cover the Scope of Work and reflect any significant changes
identified by CONTRACTOR or SAUDI ARAMCO.
4. MANAGEMENT RESPONSIBILITY
4.2 CONTRACTOR Top Management shall review the project specific QMS
every six (6) calendar months to ensure that the system is suitable,
adequate and effective. Top Management reviews shall address the items
listed in Paragraphs 7.1.1 and 7.4 of this Schedule “Q”. Top Management
reviews shall be scheduled events, included in the quality audit schedule
approved by the Company Representative, as provided in Paragraph 7.3.2
of this Schedule “Q”.
4.3 Within two (2) calendar weeks of the scheduled review date,
CONTRACTOR shall report in writing to the Company Representative on
results and recommended actions from Top Management Review.
Changes to the QMS that result from CONTRACTOR Top Management
reviews shall be incorporated in the PQP, with Approval of the Company
Representative.
5. RESOURCE MANAGEMENT
5.5 If the WORK includes welding and Non-Destructive Testing (NDT) and
exceeds five hundred (500) groove -or butt- weld joints, CONTRACTOR
shall deploy a SAUDI ARAMCO Approved NDT Coordinator at least thirty
(30) calendar days prior to the start of Work Site welding. The NDT
Coordinator’s principal duties and responsibilities shall be the
administration and coordination of Work Site NDT Service Providers and
activities. When planned and approved by SAUDI ARAMCO, this
individual may perform other quality functions on the project, provided
those functions do not interfere with the coordination of NDT activities.
5.8 CONTRACTOR Quality Personnel shall have well defined roles and
responsibilities, including sufficient authority and organizational freedom to
identify Nonconformities, Defects, and quality problems, report and
escalate nonconformities, and initiate corrective actions. During all
phases of the WORK, CONTRACTOR Quality Personnel shall functionally
report to the CONTRACTOR QA Manager or QC Manager.
5.9 Within thirty (30) calendar days of SAUDI ARAMCO’s issuance of the
Notice to Proceed, CONTRACTOR shall submit to the Company
Representative a roster of all CONTRACTOR Quality Personnel, sorted by
discipline and position, including personnel identified to be:
Q-8
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
5.11 CONTRACTOR planned and actual staffing levels shall comply with this
Contract. Any proposed reduction from the required levels shall be
approved in advance, in writing by the Company Representative.
5.12 CONTRACTOR shall anticipate, plan and make all changes required due
to vacations, illness, temporary assignments, emergency leave,
resignations or other reasons as necessary to maintain required coverage
of CONTRACTOR Quality Personnel. CONTRACTOR shall notify the
Company Representative of all planned quality personnel changes at least
thirty (30) calendar days in advance. CONTRACTOR shall notify in writing
the Company Representative of unplanned personnel absences and
changes within twenty-four (24) hours. CONTRACTOR shall deploy
SAUDI ARAMCO Approved replacement quality Personnel within seven
(7) calendar days of each unplanned absence.
Q-9
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
Q-11
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
6.3.2 All Third-Party and NDT original reports shall include the printed
names, identification numbers, credential numbers, calendar
date(s) and handwritten, wet ink signatures for all Third-Party and
NDT personnel directly involved in the reported inspection,
testing, review and interpretation WORK.
6.3.3 All Third-Party and NDT original reports shall be legible, uniquely
identified, registered, controlled and traceable to the specific
scope of WORK inspected, tested and reported. All original
reports shall be cross-indexed and traceable to the
CONTRACTOR, Third-Party or NDT personnel involved in the
reported activities.
7.1 General
Q-16
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
7.6 Waivers
Q-18
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
Q-21
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
7.7.6 Attachments
END OF SCHEDULE Q
Q-22
NS
SCHEDULE Q REQUISITION NO. 3000848438 (M-IK)
Q-23
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
ATTACHMENT I TO SCHEDULE Q
(a) Internationally recognized university issued four (4) or five (5) year
Bachelor degree in an engineering discipline, or equivalent.
Q-I-1
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
(b) Five (5) or more years of direct work experience in supervision and
auditing of capital projects quality; ISO 9001 QMS requirements,
activities and resources in the engineering discipline(s) and
Contract scope of WORK to be audited.
(d) Participated in four (4) or more capital project internal audits during
the past three (3) years; with a minimum of sixteen (16) days of
auditor-auditee contact within the period.
Q-I-2
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
Q-I-3
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
– or –
High school diploma with twelve (12) or more years of direct work
experience in supervision of capital projects quality, ISO 9001 QMS
requirements, activities and resources for procurement of services,
materials and equipment.
Q-I-5
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
Q-I-6
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
B31.4 & B31.8; NACE SPs, API 620, API 650 and AWS
D1.1.
Q-I-7
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
Q-I-8
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
Q-I-9
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
3. CONSTRUCTION PHASE
3.1 QC Manager:
– or –
High school diploma and twelve (12) or more years of direct work
experience as a QC Manager or QC Supervisor of capital projects
construction & Pre-Commissioning quality, ISO 9001 QMS
requirements, activities and resources (i.e., supervising a minimum
of ten (10) quality Personnel).
(b) Five (5) or more years direct work experience in managing quality
of capital projects construction related to the Contract scope of
WORK (e.g., industrial oil and gas production or petrochemical
projects).
Q-I-10
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
3.2 QC Supervisor:
– or –
High school diploma with twelve (12) or more years of direct work
experience in inspection of capital projects quality, ISO 9001 QMS
requirements, activities and resources for construction & Pre-
Commissioning of materials and equipment.
(a) High school diploma with ten (10) or more years of direct work
experience in a specific inspection discipline, performing QC
inspection and testing of industrial project materials, equipment,
systems and facilities under construction and pre-commissioning.
Q-I-11
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
3.4 QC Inspectors:
(a) High school diploma with six (6) or more years of direct work
experience, in the specific engineering discipline(s), performing QC
inspection and testing of industrial project materials, equipment,
systems and facilities under construction and Pre-Commissioning.
– or –
– or –
Citizen of Saudi Arabia with a high school diploma and three (3) or
more years of direct work experience in a specific inspection
discipline, performing QC inspection and testing of industrial project
materials, equipment, systems and facilities under construction and
Pre-Commissioning.
Q-I-14
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
Q-I-15
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
Q-I-18
NS
SCHEDULE Q ATTACHMENT I REQUISITION NO. 3000848438 (M-IK)
Q-I-20
NS
SCHEDULE Q ATTACHMENT II REQUISITION NO. 3000848438 (M-IK)
ATTACHMENT II TO SCHEDULE Q
1.0 CONTRACTOR and Contract WORK shall comply with all applicable SAUDI
ARAMCO Mandatory Engineering Requirements (MSAER’s) as defined under
SAEP-301; Material System Specifications (SAMSS), Engineering Standards
(SAES), Engineering Procedures (SAEP) and Standard Drawings (SASD); and
other SAUDI ARAMCO instructions, procedures, standards and specifications
including, but not limited to the following documents with quality requirements:
Q-II-2
NS
SCHEDULE Q ATTACHMENT II REQUISITION NO. 3000848438 (M-IK)
Q-II-2
NS
SCHEDULE Q ATTACHMENT II REQUISITION NO. 3000848438 (M-IK)
Q-II-2
NS
SCHEDULE Q ATTACHMENT III REQUISITION NO. 3000848438 (M-IK)
1. PROCUREMENT PROCESS
1.1 Requisitions
Q-III-1
NS
SCHEDULE Q ATTACHMENT III REQUISITION NO. 3000848438 (M-IK)
2. PROCUREMENT INFORMATION
2.1 CONTRACTOR technical and quality Personnel shall review and ensure
the quality of all CONTRACTOR requisitions and PO’s prior to submission
to SAUDI ARAMCO for review, including all technical and quality
requirements specified in this Contract.
2.2 CONTRACTOR shall review Vendor suborders to ensure that all relevant
SAUDI ARAMCO technical and quality requirements are passed on to
subsuppliers.
Q-III-2
NS
SCHEDULE Q ATTACHMENT III REQUISITION NO. 3000848438 (M-IK)
2.5 For critical risk PO’s, CONTRACTOR shall conduct focused technical and
quality assessments at thirty percent (30%), sixty percent (60%) and
ninety percent (90%) of the manufacturing completion schedule. For high
risk PO’s, CONTRACTOR shall conduct assessments at sixty percent
(60%) and ninety percent (90%) completion. For medium risk PO’s,
CONTRACTOR shall conduct assessments at ninety percent (90%)
completion. For bulk Materials, CONTRACTOR focus assessments shall
be completed prior to shipment of the first batch.
Q-III-3
NS
SCHEDULE Q ATTACHMENT III REQUISITION NO. 3000848438 (M-IK)
2.9 SAUDI ARAMCO shall have access to all CONTRACTOR Purchase Order
inspection reports and files. CONTRACTOR shall include a clause in all
Purchase Orders that SAUDI ARAMCO (or SAUDI ARAMCO’s designee)
has the right to access manufacturer facilities and suborder locations.
Q-III-4
NS
SCHEDULE Q ATTACHMENT III REQUISITION NO. 3000848438 (M-IK)
3.8 CONTRACTOR shall review and direct revisions to Vendor ITP’s for
compliance with applicable SAUDI ARAMCO quality requirements. Each
Vendor ITP shall identify the assigned Inspection Level and detail all
witness, hold and certification review points as specified in SAUDI
ARAMCO standards and Forms SA-175 per SAEP-1151 requirements.
3.9 CONTRACTOR shall prepare and submit a Special Form SA-175 for
Approval by the Company Representative:
3.10 As a minimum, each Vendor ITP shall include the following information:
Q-III-6
NS
SCHEDULE Q ATTACHMENT III REQUISITION NO. 3000848438 (M-IK)
3.11 CONTRACTOR shall submit for SAUDI ARAMCO review and Approval all
Vendor, manufacturer and subsupplier Special Process procedures for
refractory, welding, welding repair, heat treatment and Positive Material
Identification (PMI, alloy verification) as applicable to the WORK, thirty
(30) or more calendar days prior to the start of the specific work activity.
3.12 Vendor, manufacturer and subsupplier personnel for PMI and welding
shall be evaluated and qualified as specified in Attachment I of this
Schedule “Q”. CONTRACTOR shall review and approve personnel
qualifications prior to the start of manufacturing.
3.13.4 SAUDI ARAMCO reserves the right to evaluate and reject any NDT
personnel and procedures at any stage of the project.
Q-III-8
NS
SCHEDULE Q ATTACHMENT III REQUISITION NO. 3000848438 (M-IK)
(a) Narrative details about the plant visit and inspection activities
performed.
(b) The Form SA-175 and ITP specified inspection and test activities
(review, witness and hold points) covered during the plant visit.
(c) Brief narrative and photographs covering material fabrication,
manufacturing and completion status.
(d) A punchlist of outstanding corrective action and work items (when
applicable).
Q-III-10
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
ATTACHMENT IV TO SCHEDULE Q
1.1 Unless submitted with the PQP in accordance with Paragraph 3.2 of this
Schedule “Q”, one (1) calendar month prior to the start of the applicable
WORK, CONTRACTOR shall submit for SAUDI ARAMCO review and
Approval a detailed ITP along with related QA procedures, QC
procedures, QC forms and work instructions for all construction
processes, Pre-Commissioning and related quality activities to be
executed by the CONTRACTOR, Subcontractors, Third-Parties,
Inspection and Testing Agencies and NDT Service Providers.
CONTRACTOR shall review and adopt quality requirements from all
applicable SAUDI ARAMCO standards and procedures in each ITP, QAP
and QCP. Each ITP shall detail all review, witness, and hold points for
SAUDI ARAMCO, CONTRACTOR and subcontractors as specified in this
Contract. Each ITP shall also include the methods, extent and timing for
examinations, measurements and tests.
1.3 CONTRACTOR shall schedule, plan and manage critical and high risk
construction and Pre-Commissioning quality activities under the Special
Process requirements of Paragraphs 2.1 and 3.1.2 of this Attachment IV.
CONTRACTOR shall issue and implement Method Statements, Special
Work Procedures and Special Personnel Qualification Procedures that
specify the resources, knowledge, experience level, and methods needed
to prevent issues, minimize rework and lower the risk of failures. Senior-
grade inspectors as defined in Attachment I of this Schedule “Q” shall be
planned and deployed for the control of critical and high risk activities.
CONTRACTOR method statements and work procedures for critical and
Q-IV-1
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
high risk quality activities shall be reviewed and approved by the SAUDI
ARAMCO.
1.7 CONTRACTOR adoption and use of SAUDI ARAMCO SATIPs and SAICs
shall not release CONTRACTOR from any obligations under SAUDI
ARAMCO SAEP-301 standards and this Contract.
Q-IV-2
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
Of Personnel
Qualification
Qualification
Procedure
Procedure
Risk Level
Statement
Personnel
(Note 3)
(Note 2)
(Note 3)
(Note 3)
(Note 4)
Method
Work
General Processes
Design Office - Engineering Change Control H A A N N
Q-IV-3
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
Of Personnel
Qualification
Qualification
Procedure
Procedure
Risk Level
Statement
Personnel
(Note 3)
(Note 2)
(Note 3)
(Note 3)
(Note 4)
Method
Work
Special Process (SP) Name
Cleaning of Pipelines H A A N N
Refractory Installation H A A N N
Q-IV-4
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
3.1 CONTRACTOR shall plan, initiate and document the following quality
meetings with SAUDI ARAMCO, CONTRACTOR and other concerned
parties as required for the WORK under this Contract:
Q-IV-5
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
3.6 CONTRACTOR shall receive, review with evidence of review and accept
or reject all quality records, inspection and testing performed by
CONTRACTOR, Vendors, manufacturers, subsuppliers, Third-Parties,
Inspection and Testing Agencies and NDT Service Providers for the
WORK. Quality records and evidence shall be organized, maintained
current and available at CONTRACTOR’s Job Site office for SAUDI
ARAMCO review. Delivery of CONTRACTOR quality records and
evidence to SAUDI ARAMCO shall be in accordance with the PQP, SAEP-
122 and this Contract.
3.9 CONTRACTOR shall witness all NDT Service Provider activities using (a)
Welding & NDT Level II QC Inspectors or (b) NDT Level III quality
Personnel; certified, evaluated and approved by SAUDI ARAMCO in
accordance with SAEP-1142 and Attachment I of this Schedule “Q”.
CONTRACTOR Level III quality Personnel shall review and approve all
NDT results and reports.
3.10 CONTRACTOR shall plan and maintain all necessary resources (e.g.,
Computer Systems, Software, etc.) for NDT quality Personnel review and
analysis of NDT Service Provider NDT reports, results and data from AUT,
such as Time of Flight Diffraction (ToFD) and Phased Array UT (PAUT).
CONTRACTOR shall ensure all NDT Level II and Level III personnel
assigned to the related WORK have been trained by the test equipment
manufacturers or manufacturer authorized representatives.
Q-IV-6
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
3.12 NDT reports of Manual UT (MUT), Magnetic Particle Testing (MT) and
Liquid Penetrant Testing (PT) shall be prepared and signed on the Job
Site, at the time tests are conducted and prior to any repairs, if required. If
required repairs are completed and concurrently retested, NDT reports
shall accurately reflect initial test results, the rejection, and results of
retesting following required repairs.
3.13 SAUDI ARAMCO reserves the right to review, assess and audit NDT
results at any time and frequency deemed necessary. SAUDI ARAMCO
NDT activities and related actions shall not release CONTRACTOR from
any NDT and test interpretation obligations and quality requirements
contained in this Contract.
Q-IV-7
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
3.14 SAUDI ARAMCO reserves the right to conduct SAUDI ARAMCO NDT
Cross-Checks (i.e., retesting), at SAUDI ARAMCO’s expense, of any
welds subjected to NDT by CONTRACTOR. NDT Cross-Checks will be
planned and initiated based on results from SAUDI ARAMCO NDT
Assessments. SAUDI ARAMCO NDT Cross-Checks shall use the same
NDT method(s) applied by the CONTRACTOR. SAUDI ARAMCO
Inspection Department representative shall determine the required scope,
schedule and rate of SAUDI ARAMCO NDT Cross-Checks.
3.15 Substandard welds that are rejected due to NDT Assessment or NDT
Cross-Check results shall be repaired in accordance with governing codes
and standards, inspected and retested using the same NDT methods.
Additional testing for penalty or tracer NDT may be required as directed by
SAEP-1160 and this Contract.
Q-IV-8
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
and tracking of welded joints and related weld inspection and testing
activities shall be in accordance with SAEP-1160.
6. PRESERVATION
Q-IV-9
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
6.7 CONTRACTOR preservation data, backlog and Failure Rate (PFR) shall
be collected, analyzed and reported to SAUDI ARAMCO in accordance
with SAEP-385 and Paragraph 7.7 of this Schedule “Q”.
7.1 CONTRACTOR shall include in PQP and implement quality procedures for
the control and accuracy of construction and Pre-Commissioning
inspection, measuring and testing equipment. Specific CONTRACTOR
Tools and Equipment shall be identified to make and perform inspections,
measurements and tests in the field with instructions for their use,
calibration and storage. The CONTRACTOR shall identify, maintain,
control, adjust, and calibrate all Tools and Equipment; gauges, instruments
and other measuring and testing devices used for controlling quality.
Q-IV-10
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
7.4 CONTRACTOR shall review, investigate and document the validity of prior
inspection and test results when inspection, measuring and test Tools and
Equipment are found to be out of calibration. A copy of the
CONTRACTOR report shall be submitted to SAUDI ARAMCO for review.
8. RADIATION SAFETY
8.2 CONTRACTOR shall timely plan and deploy at least one SAUDI ARAMCO
approved employee having documented work experience in radiation
safety and the safe application of Industrial Radiography. Working with
the NDT Service Provider(s) RSO(s), the employee(s) shall plan and
implement a program of Radiation Safety audits, reviews, evaluations and
monitoring of Job Site radiographic technicians. CONTRACTOR’s
employee(s) may be the NDT Coordinator, Safety Supervisor(s), or other
qualified individual(s) having direct field responsibilities for the project.
8.3 When CONTRACTOR NDT activities involve six (6) or more NDT
Radiography (RT) crews concurrently working on the same project Job
Site, CONTRACTOR shall provide a “Site in Charge” NDT technician to
ensure the safe utilization and storage of radiation sources. The “Site in
Charge” may be a CONTRACTOR direct-hire employee or a NDT Service
Provider employee. The “Site in Charge” NDT technician shall be a Senior
Industrial Radiographer, certified, evaluated and qualified to SAEP-1142
Q-IV-11
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
8.5 CONTRACTOR shall plan and establish a work permit system that
requires effective advance notification of where and when radiography will
be conducted on the project. Advance notification shall be timely
communicated and posted at sufficient locations necessary for
CONTRACTOR and SAUDI ARAMCO Job Site personnel are fully aware
of planned and ongoing radiography.
8.6 CONTRACTOR shall plan and direct NDT Service Providers to conduct
regular Job Site safety audits of NDT activities and technicians utilizing
radiation sources. NDT Service Provider personnel conducting safety
audits shall be currently qualified and licensed as Radiation Safety
Officers (RSO) under SAEP-1141 and the King Abdulaziz City for Atomic
and Renewable Energy (K.A.CARE). Frequency of safety audits shall be
sufficient to ensure that every NDT technician involved in radiography on
the Job Site is evaluated at least once per month for the duration of the
project. All safety audits shall be documented, with records maintained by
CONTRACTOR and made available upon demand by SAUDI ARAMCO.
Q-IV-12
NS
SCHEDULE Q ATTACHMENT IV REQUISITION NO. 3000848438 (M-IK)
Q-IV-13
NS
SCHEDULE Q ATTACHMENT V REQUISITION NO. 3000848438 (M-IK)
Q-V-1
NS
SCHEDULE Q ATTACHMENT V REQUISITION NO. 3000848438 (M-IK)
Q-V-2
NS
SCHEDULE Q ATTACHMENT V REQUISITION NO. 3000848438 (M-IK)
Q-V-3
NS