Step-by-Step existing process for installation of Rooftop Solar PV System under Net

Metering arrangement in DHBVN e-solar portal

Application for Approval for Signing of Net


Application for Metering
installation of installation of
installation of Agreement with
Rooft Solar Acknowledge Site Verification/ Rooftop Solar PV Installation of Submission of Commissioning
Rooftop Solar PV Nigam Work Completion
System PV ment for receipt T echnical System and Rooftop Solar PV safety certificate of Rooftop Solar
System in Report
System in MNRE of application Feasibility issuance of letter Installation of System by consumer PV System
DHBVN e-solar
PM Surya Ghar of approval Rooftop Solar PV
portal
Portal (LOA) System

• Applicant Shall tender • Applicant shall tender • Acknowledgement of • Site verification shall be • Approval shall be • Agreement shall be • After approval of • Applicant shall submit • For PV system upto 20 • Applicant may procured
an application in MNRE an application to SDO receipt of application carried out by SDO granted by XEN (OP) signed by consumer installation, consumer the “work completion kWp work completion the meter from
PM Surya Ghar Portal with a processing fees shall be given by (OP), within 3 working within 7 days from the and concerned SDO, shall install Rooftop report” along with report by empanelled empanelled firm, if
with DHBVN Electricity of Rs 1000/- for subdivision office to days from the receipt of date of system within 30 days from the Solar PV System from enclosures agency is suffice. meter is not available in
Account No. and seeking permission for consumer on same Application feasibiliy check by the date of (LOA) companies/firms • Annexure-VI) • For PV system above Nigam Store. Meter
Registered Mobile No. installation of Rooftop day. • System feasibility SDO • (Annexure-V) empanelled with 20kWp inspection shall comply the
• Applicant shall Solar PV System with • (Annexure-II) check shall be done • Annexure-IV) MNRE. report of Chief specifications issued by
download the PM MNRE National Portal within 15 days for • Installation of Solar Electrical Inspector Nigam.
Surya Ghar portal reference no. 5kWp above capacity Rooftop shall be done shall be required before • After submission of
reference no. of the • (Annexure-I) plant, however it shall in 180days from date of commissioning work completion report
application. be done within 10 days LOA. • (Annexure-VII) and safety certificate by
for plant having applicant,
capacity upto 5kWp commissioning of
• (Annexure-III) system shall be done
within 7 days by the
SDO.
• Joint Commissioning
Report of the RTS plant
will be uploaded by
SDO on DHBVN e-
solar portal and MNRE
portal.
• Annexure-VIII)