SAM REE DYEING (BD) LTD.

Ghorashal, Palash, Narsingdi-1613


Implementation Plan-Air Emission
Date: 02.01.2024
S/L Significant Aspects Objectives Targets Baseline Year Action Plan & Progress Time line Responsible Person Remarks
1. Schedule maintenance of AC to avoid leakage Continuous process Mr.Mozammel Hoq-DGM
To implement a (Maintanance),
proper control 2. To use R-410A refrigerant instead of R-22 2025
1 AIR EMISSION To minimize GHG 2023 Mehrab Mohsin Shohag-
process and reduce 3. To use wet scrubber for boiler and generator flue gas 2026 Manager (HR Admin &
GHG. Compliance)
4. To use dry scrubber for non-point source 2028

Prepared by Approved by
Md.Shoriful Islam Mehrab Mohsin Shohag
Executive-ECR and Compliance Manager-HR, Admin and Compliance