Professional Documents
Culture Documents
Checklist Mini Roller
Checklist Mini Roller
Checklist Mini Roller
PROJECT :
Capacity :
Year -2023
Remarks:
Checked By :
Date :
ROHAN BUILDERS INDIA PVT. LTD.
Project-Uflex Limited
Capacity :
Extinguisher No:
Year -2023 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
9 Weight in Kgs
10 Access should be clear
Remarks:
Sign: Sign:
DERS INDIA PVT. LTD.
ect-Uflex Limited
Reamark
ROHAN BUILDER'S INDIA PVT .LTD
Project-
Capacity :
Location :
Remarks:
Date : Date:
Sign: Sign:
Project - Pragati, Mondelez Malanpur
Machine No:………………….
Date_____________
Sr.No:………………….
1 Vibration function
3 General Cleanliness
4 Steering/Braking/Handbrake/Lock
5 Hydraulics/Pipework/Controls/Decals
6 Gaues/Instrumentation
7 ROPS/FOPS/Bodywork
8 Battery levels/condition
9 Fluid levelsAll/Greasing
10 WaterTank levels
11
Competet Operators
12 Other