PROPOSED COMMERCIAL BUILDING TO BE

BUILT ON PLOT NO. 116, BLOCK ….., ALONG


KILEMBE ROAD, KASESE TOWN

BILLS OF QUANTITIES

CONSTRUCTION COST ESTIMATE

CLIENT:
MUNIHIZI KATEGA BONNY
+ 256 (0) 782 - 444104
P.O Box 430045, Kasese

PROJECT MANAGER

QUANTITY SURVEYOR & ELECTRO-MECHANICAL ENGINEERS


QUEST INTERNATIONAL LTD
(0)787-243-649
P.O Box 2330, Kampala-Uganda

APRIL, 2022
2 742061422.xlsx
Item Description Amount Amount
USHS USD

PROPOSED COMMERCIAL BUILDING TO BE BUILT ON PLOT NO. 116, ALONG


KILEMBE ROAD, KASESE TOWN

FOR

MUNIHIZI KATEGA BONNY


Bank of Uganda
BILL OF QUANTITIES Ex. Rate as of
4/21/2022
GENERAL SUMMARY
1USD = 3525UGX
See provision below
- BILL NO.1 - PRELIMINARIES

- BILL NO.2: BUILDING WORKS AND ASSOCIATED CIVILWORKS

LEVEL 2 - SUBSTRUCTURE AND GROUND FLOOR Err:509 Err:509

LEVEL 2 - FIRST FLOOR Err:509 Err:509

LEVEL 3 - SECOND FLOOR Err:509 Err:509

LEVEL 4 - ROOF TERRACE Err:509 Err:509

- BILL NO.3 - ELECTRICAL INSTALLATIONS PENDING

- BILL NO.4 - MECHANICAL INSTALLATIONS PENDING

- BILL NO.5 - EXTERNAL WORKS PENDING

SUB-TOTAL (1) Err:509 Err:509

ADD: PRELIMINARIES ( Say 5%) Err:509 Err:509

SUB-TOTAL (2) Err:509 Err:509

ADD: CONTINGENCY (10%) Err:509 Err:509

SUB-TOTAL (3) Err:509 Err:509

ADD: V.A.T (18%) Err:509 Err:509

TOTAL COST ESTIMATE Err:509 Err:509

GENERAL SUMMARY
BILL NO.1: PRELIMINARIES
Item Description Amount
(Ushs)

BILL NO. 1

PROPOSED CLASSROOM AND MULTIPURPOSE HALL BLOCK TO BE BUILT AT KISINGA


TOWN COUNCIL, KASESE DISTRICT
FOR
KAGANDO SCHOOL OF NURSING AND MIDWIFREY (KARUDEC)
PRELIMINARIES

A DEFINITIONS AND ABBREVIATIONS

The following terms, phrases and abbreviations shall be deemed to have the following meanings
wherever used in these bills of quantities or elsewhere in the contract documents.

PPDA' shall mean Public Procurement and Disposal of Public Assets.

Works' shall mean all or any portion of the work described in the contract documents, comprising the
rehabilitation of existing buildings and the construction of new ones, complete with
electrical/mechanical installations and associated external works and including materials/items,
whereever the same are being manufactured or prepared for use in executing the contract.

"Approved" or "approval" shall mean as approved by the Project Manager

as directed' shall mean as directed by the Project Manager

fix only' shall mean the fixing of materials and components obtained from sources as directed,
including for obtaining information from suppliers, assembing and/or carefully dismantling and
reassembling as necessary.

"B.S." shall mean the current British Standard Specification published by the British Standards
Institution, 2 Park Street, London W.1., England, UK.

"Kg" shall mean Kilogrammes.


"No" shall mean Number.
mm' shall mean millmitre
M' shall mean Metres.

"m2" or 'SM' shall mean Square Metres.

"m3"' or 'CM' shall mean Cubic Metres.

"Prs" shall mean pairs.

"Do" or "Ditto" shall mean the whole of the preceding description except as qualified in the description
in which it occurs. Where shown in brackets, it shall mean the whole of the preceding description
contained in brackets.

"M.S." shall mean measured separately.

"Fuel" shall mean electricity, oil and any other approved source of energy.

Exceptional Weather' shall refer to any state of the weather that could cause damage or interference
to the execution of the works, including heavy rains, excessive sunshine, sleet, gales, driving winds
and floods.

"VAT" shall mean Value Added Tax.

"Net Contract Price'' or "Net Tender Price" shall mean the Tender/Contract Price or any subsequent
adjustment thereto before the addition of VAT.

CARRIED TO COLLECTION

BILL NO. 1 - PRELIMINARIES


Item Description Amount
(Ushs)
A FORM OF CONTRACT

The form of contract and its General and Special conditions, shall be in the PPDA formats as provided
in this tender dossier.

METHODS OF MEASUREMENT

B The Bills of Quantities have been prepared in accordance with the principles of Standard Method of
Measurement (SMM) of Building and Associated Civil Works for Eastern Africa, Second Edition
published by the Architectural Association of Kenya (Chapter of Quantity Surveyors) June 2008

C PRICING

The contractor shall price out individually IN INDELIBLE INK, all items containing a monetary value in
the preliminaries and all other sections of the bills. In no cases will lump sums be allowed unless
otherwise stated. The contractor's pricing shall be deemed to include for all his obligations under the
contract. Congruous, any item not priced will be taken to have been allowed for in the prices inserted
against all other items in the bills.

D SITE VISITS

The works comprised in this contract are located in Kisinga, Kasese, off Fort Portal Mpondwe Road,
Kasese District. Contact info@karudec.ug for more details.

The Contractor is recommended to visit the site and shall be deemed to have acquainted himself
therewith as to the nature, position, means of access etc. No claim in this connection will be allowed,
including travel or other expenses incurred by the contractor in visiting the site or in preparing his
tender.

E SITE LEVELS AND DIMENSIONS

Before commencing on the works at the site, the contractor must arrange for and agree the existing
site levels with the Project Manager and similarly establish site benchmarks.

Figured dimensions shown on the Architect's issued drawings shall be the actual dimensions to be
used in the works. The contractor shall in a timely manner, check all dimensions and levels marked
on the issued drawings for consistency and completeness, before commencing on pertinent sections
of the works. In the event of any discrepancies or missing dimensions, he shall immediately notify the
Project Manager who shall direct appropriately, the contractor shall not scale off the drawings.

Quantities shown in the bills of quantities shall not be used for ordering materials. The contractor
shall in a timely manner make his own computations for this purpose from the issued drawings and
his site measurements. In the event of any discrepancies between his computations and the
quantities shown in the bills of quantities, he shall immediately notify the Project Manager who shall
direct appropriately.

F COST OF SECURITIES AND INSURANCE

Performance Guarantee (article 52 of the GCC and SCC)

Insurances (article 13 of the GCC and SCC)

Advance Payment Guarantee (article 52 of the GCC and SCC)

Retention (article 48 of the GCC and SCC)

CARRIED TO COLLECTION -

BILL NO. 1 - PRELIMINARIES


Item Description Amount
(Ushs)
MATERIALS, GOODS AND WORKMANSHIP TO CONFORM TO DESCRIPTION, TESTING,
A
INSPECTION AND SAMPLES
The contractor shall employ the best materials and workmanship available, which shall in any case
not be inferior to the technical specifications in this Volume of the tender dossier. He shall be entirely
responsible for obtaining all materials required for the works, whether local or imported.

The contractor shall in a timely manner and at his own cost furnish any required samples of materials
or workmanship or any required tests/results, as well as any samples and tests that may be called for
by the Project Manager for approval, including any further requests in case of disapproval.

Samples shall be deemed to include for their making with the specified materials under similar
conditions to the site, protection of approved samples and removal of samples when no longer
required by the Project Manager.

The contractor shall particularly allow for making all necessary concrete test cubes and for their
testing at an approved laboratory. One copy of the test cube results shall be forwarded directly to the
Project Manager by the laboratory officials. An accurate record of all test cubes taken and crushed
must be kept on site by the contractor, who shall only be reimbursed for successful tests upon
production of laboratory certificates. Provisional successful concrete test cubes No. 100 @
USHS..................................... (the contractor to insert rate and extend amount to next column)

The contractor shall particulary allow for making i) Conducting field density test using sand
replacement method at every 600mm compacted layer and ii) Conducting Dynamic Cone Penetration
(DCP) tests at every 600mm compacted layer.Provisional successful tests 50pts @
USHS..................................... (the contractor to insert rate and extend amount to next column)

The contractor shall particulary allow for making Plate bearing Tests .Provisional successful tests 10
pts @ USHS..................................... (the contractor to insert rate and extend amount to next column)

STATUTORY OBLIGATIONS, NOTICES, FEES/CHARGES, LOCAL REGULATIONS AND BYE-


B
LAWS

The contractor shall comply with all statutory obligations, local regulations/bye-laws, police regulations
and those of the various utilities authorities (electricity, telephone, water), including serving of notices
and payment of relevant fees.

The contractor shall allow for obtaining all necessary approvals from local authorities, including interim
ones during the progress of the works, occupation permits at practical completion and all other legally
demandable ones, including payment of respective fees, rates or taxes

C SITE SUPERVISION, ATTENDANCE AND MEETINGS

The contractor shall execute the works under the direction and to the satisfaction of the Project
Manager. The contractor shall be responsible for works carried out by his subcontractors and allow
for pertinent attendance.

The Clerk of Works shall have the Project Manager's specifically delegated authority regarding the
contractor's site operations and shall at all times have access to the contractor's yards, workshops
and other places where elements of the works are being prepared.

In addition to impromptu site visits, the Project Manager shall preside over regularly held site
meetings. The contractor shall allow for his contract, site and relevant subcontractor representatives
to attend all site meetings and provide fortnightly progress photos for each building unit.

CARRIED TO COLLECTION -

BILL NO. 1 - PRELIMINARIES


Item Description Amount
(Ushs)
A TRANSPORT TO AND FROM SITES

The contractor shall include in his prices for the transportation of materials, workmen, etc to and from
the sites, at such hours and routes as permitted by the Project Manager and the local authority.

B WORKING HOURS AND FAIR WAGES

The contractor and his sub-contractors shall pay to their employees rates and wages and observe
working hours and conditions of labour, which are not less favourable than the minimum rates, wages
and conditions provided by the Ministry of Labour of Uganda and/or stipulated in the Employment Act.
The relevant notice must be posted and kept posted up on the site, at a position where it can be
conviniently read by the employees concerned.

The contractor or any subcontractor called upon, shall furnish the Project Manager, with particulars of
the rates, wages and conditions of their employees engaged on the works. Should the Project
Manager establish proof of any claim alleging default in rates, wages and conditions by the contractor
and/or any subcontractor, the Project Manager may failing relevant payment by the party concerned,
pay the claim out of any monies due or to become due to the contractor under the contract.

C SECURITY OF THE WORKS, EMPLOYEES AND THE PUBLIC

The contractor shall be entirely responsible for security of the entire works at the sites, including his
stores, materials, plant, personnel, etc as well as those of all sub-contractors engaged in the works.
He shall provide all necessary watching, lighting and other precautions necessary to ensure protection
of all employees and the public. He shall also provide itendification cards with photographs to the
satisfaction of the Project Manager, to all employees on the sites including those of subcontractors
engaged.

D PROGRAMME OF WORKS

As required in the Special Conditions of Contract, the contractor shall submit a detailed programme of
works per site (including elements of the works to be carried out by sub-contractors). The chart shall
include the anticipated weekly labour strength required (divided by trade). The contractor shall allow
for such charts showing the programme of works or updates thereof per site, to be visibly displayed in
the relevant site meeting room.

At the end of each contract week, the contractor shall mark on the works programmes in a different
colour, the actual time taken to complete respective tasks, as well as the actual numbers employed
(divided by trade).

The contractor shall supply copies of the approved programmes of works as requested from time to
time, for use by the Contracting Authority, Supervisor, Supervisor's Representative and Project
Manager as the case may be.

CARRIED TO COLLECTION -

BILL NO. 1 - PRELIMINARIES


Item Description Amount
(Ushs)
A OVERTIME WORK

The contractor shall be responsible for any extra costs for overtime work he considers necessary for
completing the works within the contract period.

B WATER FOR THE WORKS

The contractor shall provide for sufficient clean and pure water for use in connection with the works at
the sites (including for subcontactors and the Project Manager) and pay all related costs and fees,
including installation of water meters, temporary storage tanks, pipes, tubing, etc.

C LIGHTING AND ELECTRICITY FOR THE WORKS

The contractor shall provide and be entirely responsible for all temporary lighting and electricity for
use in connection with the works at the sites (including for subcontactors and the Project Manager)
and pay all related costs and fees, including installation of electricity meters and distribution systems.
He shall also provide and be wholly reliant upon his own self generated electricity back-up supply in
case of mains interruptions.

D TEMPORARY WORKS AND BUILDINGS

The contractor shall allow for all necessary preparation of the sites prior to commencement of the
works, including site clearence, removal of rubbish and the building of temporary access roads, with
culverts, crossings or any other means of gaining access, for the delivery of materials, plant and
workmen, in positions as agreed with the Project Manager and local authority.

The contractor shall provide site hoarding with lockable gates at the sites, as directed and approved
by the Project Manager.

The contractor shall provide for the erection and dismantling of all scaffolding required at the sites for
the proper execution of the works.

The contractor shall provide temporary water tight lock-up storage sheds at the sites, for all goods and
materials for use in the works that are liable to suffer damage from exposure to direct sunlight or
exceptional weather.

The contractor shall provide and maintain offices, workers' mess rooms and other temporary building
spaces required for his use and that of subcontractors at the sites, suitably equipped with desks,
chairs, drawing boards, tables, benches, cooking facilities and any othe necessary furniture or
equipment. No labour force, with the exception of watchmen, shall be housed on the site.

A separate room of adequate size shall be provided at each of the sites for site meetings and
equipped with a table and chairs of sufficient size and numbers, as well as wall mounted pin boards.

CARRIED TO COLLECTION -

BILL NO. 1 - PRELIMINARIES


Item Description Amount
(Ushs)
A TEMPORARY WORKS AND BUILDINGS CONTINUED

The Contractor shall not have any responsibility relating to housing (living accommodation) for the
Clerks of Works.

Upon completion, the contractor shall remove and clear away all temporary access roads and
buildings, plant, rubbish and unused material and make good all affected areas to the satisfaction of
the Project Manager.

B COMMUNICATION

All communications from the Contracting Authority, Supervisor, Supervisor's representative or Project
Manager will be served to the contractor's Kampala offices or on site. The contractor shall in turn
provide for effective and efficient means of relaying relevant such communication from his Kampala
offices to the sites, including telephone, fax and e-mail facilities plus payment of all related costs.
These facilities will be made available for use by the Clerk of Works.

C HEALTH, SAFETY, SANITATION, HIV/AIDS AND GENDER

The contractor shall allow for the implementation of all health and safety regulations relevant to the
Uganda construction industry and provide for all conservancy charges.

The contractor shall provide separate and appropriate health, safety and sanitation facilities for use by
the Employer, Project Manager and his employees while at the sites, to the satisfaction of the Project
Manager and the Local Authorities, including for a first aid box, fire fighting equipment, clean hand-
wash/drinking water, soap and appropriate drainage/disposal.

Temporary latrines shall be located in positions agreed with the Project Manager. Their side, partition
walls and roofs shall be made of timber framed corrugated roofing sheets, with their floors made of
concrete, steel trowelled smooth to falls, to facilitate easy washing.

The contractor shall ensure daily cleaning of all temporary buildings and weekly spraying of
disinfection in latrines. He shall also provide for weekly removal from the sites of all rubbish and dirt,
to the satisfaction of the Project Manager and the local authority.

The Conctractor shall provide a qualified safety officer to deal with OHS, HIV/AIDS and Gender
Management and provide all necessary facilities including transport. HIV/AIDS and STD prevention
and counselling shall include information, education and counselling campaigns including regular
distribution of condoms. The Contractor shall provide, maintain and operate a first aid clinic or make
alternative arrangements with an existing facility to the approval of the Architect. The Contractor shall
also carry out Gender sensitisation and awareness raising meetings and workshops and provide
gender sensitive monitoring and reporting.

CARRIED TO COLLECTION -

BILL NO. 1 - PRELIMINARIES


Item Description Amount
(Ushs)

On completion of the works, any temporary drains shall be removed and affected areas made good,
with the whole area disinfected and left free of polution to the satisfaction of the Project Manager and
local authority

A Compliance with NEMA Regulations

The Contractor shall comply with all the regulations set out by the National Environmental
Management Authority (NEMA).

B SIGN BOARDS

The contractor shall provide and erect where directed and maintain during the whole period of the
works, an approved temporary TWO FACED signboard to the Architect's standard design and giving
the title of the Works, 3D artistic impression of the project and showing the names of the Employer,
Architect, Quantity Surveyor, Engineers and the Contractor with sufficient space to add the names of
the Nominated Sub-Contractors and suppliers. The lettering concerning the Architect, Quantity
Surveyor and the Engineer is not to be more than 75mm high. The signboards shall not be removed
earlier than 6 months after completion.

C SITE RECORDS

The contractor shall allow for the keeping of all records in relation to the works, including a daily
record of weather conditions, temperature, rainfall, authorised site visitors (including names,
signatures and dates of visits in a visitors' book), plant, workforce (divided by trade and total), etc.

D OPERATING AND MAINTENANCE MANNUAL

The contractor shall supply to the Project Manager 3 copies of "as built"
Drawing and/or operating and maintenance manuals on the dates as stated
in the Special Conditions of Contract.

E TRAINING

The contractor shall allow for all costs related to the training of any apprentices admitted on the works.

F TAXES

The contractor shall ensure that he has full knowledge of the relevant tax legislation and workings of
the Government of Uganda and provide for all necessary administrative and accounting costs in
connection with his filing and payment of taxes, including VAT. The contractor shall be entirely liable
for the payment of his taxes and no adjustments to the contract price or claims by the contractor will
be allowed in this respect. The right to deduct any input taxes and/or allowances in accordance with
the rules/regulations pertaining to VAT is to be incorporated in respective provisional sums, unit rates
and prices.

CARRIED TO COLLECTION -

BILL NO. 1 - PRELIMINARIES


Item Description Amount
(Ushs)

The contractor's provisional sums, unit rates and prices as shown in the bills of quantities shall be
exclusive of VAT, in order to properly build up his Net Tender Sum. The total VAT applicable to the
Net Tender Sum shall then be added on the main summary page and included in his tender offer.

A COPYRIGHT

The copyright of these tender documents is vested in the Quantity Suveryors . No alterations of
quantities or descriptions made by the contractor in submitting his tender will be allowed.
Furthermore, the contractor shall not reproduce the documents in whole or in part, without the
Quantity Surveyor's written permission.

B REMOVING RUBBISH AND CLEANING

The Contractor shall make good all defects and injuries to the work, clean
down external faces, wash off stains and faced work, clean off marks of
mortar and cement, flush out drain runs and leave all parts of the Works
clean, free from rubbish and waste materials and perfect on completion.

The Contractor shall clear and cart away all rubbish as it accumulates and
keep all Works in an orderly condition to the satisfaction of the Project Manager.

C SAMPLES

The Contractor shall furnish at the earliest possible opportunity and at his
own cost, any samples of materials or workmanship that may be called
for by the Project Manager and such samples when approved shall be
the minimum standard for the work to which they apply.

D PROPRIETARY MATERIALS

Where proprietary materials are specified hereafter the Contractor may


propose the use of materials of other manufacture but of equal quality for
approval by the Project Manager.

All materials and goods where specified to be obtained from a particular

manufacturer or supplier, are to be used or fixed strictly in accordance with


their instructions.

E OCCUPATION CERTIFICATE

At the completion of the contract, the Contractor shall apply for and obtain
the occupation certificate from the Local Authority and see that it is duly
completed and signed in accordance with the condition laid down by the
current Bye-Laws.

CARRIED TO COLLECTION -

BILL NO. 1 - PRELIMINARIES


Item Description Amount
(Ushs)

A OFFICES FOR THE CONSULTANTS

(i) The Contractor shall provide, erect and maintain where directed on site approved weatherproof
lockup office for the sole use of the Consultants and clerk of works with a floor area not less than 34
square meters. The office shall be constructed with concrete or wooded floor and the walls and
ceiling internally are to be lined with fibreboard. Glazed windows (with curtains or sunshades) shall be
provided of not less than 1 meter square area and the door shall have a strong lock or fastening. The
office shall be provided with artificial lighting and electric power. The Contractor shall allow for regular
cleaning of the office. The office is to be furnished with the following:-

(a) 1No. 20 Seater table, and 20 chairs.


(b) 2No. Pin Boards with a minimum space of 2.0 square metres each.
(c ) 1No. A0 Size drawing chest with four drawers.
(d) 1No. lockable study shelving/samples cabinet

(ii) The Contractor shall maintain a display of the Programme and Progress chart in the Project
Manager's offices, devised in such a way that the line programme is shown and progress can be
marked up as the work proceeds. The Contractor shall keep this chart up todate at all times.

(iii) The Contractor shall keep on the Site and maintain in good condition, one dumpy of quickest level
and levelling staff and one 30 meters steel/linen tape for the use of the Consultants. The Contractor
shall also provide stationery for use by the Consultants.

(iv) He shall provide, erect and maintain a lockup pedestral type water closet for the sole use of the
Consultants including making temporary connection to drain where applicable to the satisfaction of the
Government and medical officers of Health and shall provide the services of a cleaner and pay all
conservancy charges and keep both office and closet clean and in sanitary condition from the
commencement to the completion of the Works and dismantle and make good disturbed surfaces to
the satisfaction of the Architect on completion of the Works.

(v) The office and the closet shall be completed before the Contractor is permitted to commence the
Works.

The Contractor shall also supply and maintain the following for the full contract duration, with and
including all consumables and maintenance, to the Architect's:-

(a) 1No. Fully connected personal desktop computer with UPS and licensed software (Microsoft
Windows 7 professional version, Intel Pentium G2020 [2.9 GHz, 3M Cache],4GB, 1600 MHz DDR3 (2
Dimm slots), 500GB SATA expandable to 2 hard drives, 16x DVD+/-RW Drive, Intel H61 Express
Chipset, Intel Integrated Graphics & Sound Card, Integrated Realtek 10/100/1000,USB optical scroll 3
buttons Mouse & quitekey keyboard, 8 USB 2.0, (2 Front, 6 Rear), 1 Serial, 1 VGA, HDMI, RJ45, 2
line-in, 2Line-out, Bays, 2 Internal 3.5", 2 External 5.25", Internal Slots: 1 full height PCIe x 16, 3 full
height PCIe x 1) complete with keyboard, mouse, mouse pad, 10/100bps Ethernet Card, 19" LCD TFT
Flat panel screen and accessories as manufactured by Dell or equal approved. This is the minimum
to be provided and the Contractor is expected to supply the latest version of both the equipment and
software.

(b) 1No. Plain paper photocopier, desktop type with variable magnification that can take A3 full size
copies, minimum capacity 10 copies/minute, including 3kg toner and regular service by agent.

(c ) 1No. A3 colour printer

(d) Full time internet connection

(e) 1No. 14.1 mega pixel digital camera with minimum 30-bit colour depth and 2GB memory card as
manufactured by Sony or equal approved.
-
CARRIED TO COLLECTION

BILL NO. 1 - PRELIMINARIES


Item Description Amount
(Ushs)

(f) 1 No. one dumpy level or equivalent, 1 No. metric levelling staff and one 100-meter measuring
tape.

On completion of the project, all equipment will become the property of the Employer.

A CONTINGENCIES

Include the Provisional sum for contingencies to be expended in whole or See Summary
in part as directed by the Project Manager.

CARRIED TO COLLECTION NIL


Note:
The Contractor shall be deemed to have made allowance in his prices
or hereunder to cover his site and general overaheads and for giving
statutory notices and paying relevant fees. The list of items given
below is not exhausitive and is only intended to enable the tenderers
price the items seperately if they so consider .

COLLECTION

page 1/1

page 1/2

page 1/3

page 1/4

page 1/5 Err:509

page 1/6

page 1/7

page 1/8

page 1/9

page 1/10

TOTAL CARRIED TO GENERAL SUMMARY Err:509

BILL NO. 1 - PRELIMINARIES


BILL NO.2

BUILDING WORKS AND


ASSOCIATED CIVILWORKS
BILL NO.2: GROUND FLOOR
THE PROPOSED COMMERCIAL BUILDING TO
BE BUILT ON PLOT NO. 2969, BLOCK NO. 206,
MPERERWE, ALONG KAMPALA, GAYAZA
ROAD, KAMPALA DISTRICT

M/S CK & COMPANY LIMITED

MEASUREMENT SHEETS

BILL OF QUANTITIES

DECEMBER, 2022

17 742061422.xlsx
CLIENT: CK & COMPANY LTD DATE: 4/5/2024
THE PROPOSED COMMERCIAL BUILDING TO BE BUILT ON PLOT NO. 2969, BLOCK NO. 206,
PROJECT: MPERERWE, ALONG KAMPALA, GAYAZA ROAD, KAMPALA DISTRICT CALC BY: IB
MEASUREMENTS PURPOSE: ESTIMATES
NO. DESCRIPTION UNIT EQ. PRTS EQ. PRTS EQ. PRTS L W H/D/kg/m QTY

SUBSTRUCTURE

ELEMENT NO. 1

(ALL PROVISIONAL)

Excavating and filling

Site clearance

Clear site of all vegetation, any trees, swamp vegetation, and other
growth and dispose off site. M2
1 1 1 3847.24 1 1 3,847.24
3,847.24

Site preparation

Remove topsoil: average depth 150mm and dispose off site. M2


1 1 1 3847.24 1 1 3,847.24
3,847.24

Bulk excavation

Excavate to reduce levels and dipose off site. M3


Building area 1 1 0.5 823.67 1 6.54 2,693.81
Exit ramp/drive way 1 1 0.5 322.93 1 1.35 217.98
Entrance ramp/drive in 1 1 0.5 615.70 1 1.35 415.60
Area in front of the building towards the road 1 1 0.5 1044.85 1 1.70 888.12
Lower area; swampy 1 1 0.5 1078.47 1 2.00 1,078.47
5,293.98

Excavate trench for strip foundation not exceeding 1.50M deep


starting from the reduced level M3
TRENCHES ALL
All measured with planswift 1 1 1 47.30 0.90 1.50 63.86
63.86

Ditto over 1.5M but not exceeding 3.0M deep ditto M3


TRENCHES ALL
All measured with planswift 1 1 1 47.30 0.90 0.50 21.29
21.29

Ditto pit for column bases not exceeding 1.5M deep ditto M3
F1 1 1 2 3.00 3.00 1.50 27.00
F2 1 1 8 4.00 4.00 1.50 192.00
F3 1 1 5 5.00 5.00 1.50 187.50
15 406.50

Ditto over 1.5M but not exceeding 3.0M deep ditto M3


F1 1 1 2 3.00 3.00 1.30 23.40
F2 1 1 8 4.00 4.00 1.30 166.40
F3 1 1 5 5.00 5.00 1.30 162.50
15 352.30

Ditto trenches to receive retaining wall foundations not exceeding


1.5M deep M3
Along G/L H (2'-5) 1 1 1 20.53 2.57 1.50 78.99
Along G/L 6 (A-H) 1 1 1 32.60 2.57 1.50 125.43
Along G/L 1 (A-F) 1 1 1 28.93 2.57 1.50 111.31
3 315.73

Ditto over 1.5M but not exceeding 3.0M deep ditto M3


Along G/L H (2'-5) 1 1 1 20.53 2.57 1.30 68.46
Along G/L 6 (A-H) 1 1 1 32.60 2.57 1.30 108.70
Along G/L 1 (A-F) 1 1 1 28.93 2.57 1.30 96.47
3 273.63

Excavate pit for lift shaft not exceeding 1.50M deep starting from
the reduced level. M3
1 1 1 6.49 5.05 1.50 49.16
49.16

Ditto over 1.5M but not exceeding 3.0M deep ditto M3


1 1 1 6.49 5.05 0.50 16.39
16.39

Extra over excavation for breaking up rock M3


149.88

Return, fill in and ram well selected material around


foundations M3
Excavations all combined 1 1 1 1,498.84 1.00 1.00 1,498.84
Adjustment
Less: structures
BILL NO. 3: FRAME
CLIENT: CK & COMPANY LTD DATE: 4/5/2024
THE PROPOSED COMMERCIAL BUILDING TO BE BUILT ON PLOT NO. 2969, BLOCK NO. 206,
PROJECT: MPERERWE, ALONG KAMPALA, GAYAZA ROAD, KAMPALA DISTRICT CALC BY: IB
Concrete blinding to column bases -1 1 1 271.00 1.00 0.05 (13.55)
Concrete blinding to lift shaft base -1 1 1 49.16 1.00 0.08 (3.69)
concrete blinding to retaining wall base -1 1 1 210.48 1.00 0.08 (15.79)
column bases -1 1 1 145.90 1.00 1.00 (145.90)
lift shaft base -1 1 1 16.39 1.00 1.00 (16.39)
retaining wall base -1 1 1 105.24 1.00 1.00 (105.24)
retaining wall -1 1 1 285.78 1.00 0.30 (85.73)
Columns -1 1 1 9.54 1.00 1.00 (9.54)
strip foundations -1 1 1 12.77 1.00 1.00 (12.77)
plinth walls -1 1 1 134.58 0.30 1.00 (40.37)
1,049.87

Remove surplus excavated materials from site M3


Concrete blinding to column bases 1 1 1 271.00 1.00 0.05 13.55
Concrete blinding to lift shaft base 1 1 1 49.16 1.00 0.08 3.69
concrete blinding to retaining wall base 1 1 1 210.48 1.00 0.08 15.79
column bases 1 1 1 145.90 1.00 1.00 145.90
lift shaft base 1 1 1 16.39 1.00 1.00 16.39
retaining wall base 1 1 1 105.24 1.00 1.00 105.24
retaining wall 1 1 1 285.78 1.00 0.30 85.73
Columns 1 1 1 9.54 1.00 1.00 9.54
strip foundations 1 1 1 12.77 1.00 1.00 12.77
plinth walls 1 1 1 134.58 0.30 1.00 40.37
448.97

Planking and Strutting

Allow for provision and subsequent removal of planking and


strutting to uphold and maintain the faces and excavations Item
1.00

Disposal of Water

Allow for keeping the whole of the excavations free from water and
silt and mud by pumping, bailing or otherwise Item
1.00

Keep excavations free from spring or running water from the site by
pumping; class of the pump to the discretion of the contractor. Hrs 1 1 8 45.00 1.00 1.00 360.00
360.00

Anti-Termite Treatment

Provide and apply an approved toxic chemical solution; applied at M2


All bottoms measured together; area considered includes slab and
splash apron area
Building foot print including the splash aprons; Measured with
planswift 1 1 1 823.67 1.00 1.00 823.67
Sides of excavated area
Sides; retaining walls 1 2 1 33.00 1.00 2.50 165.00
Sides; retaining walls 1 2 1 33.00 1.00 1.83 120.78
Sides; retaining walls 1 2 0.5 33.00 1.00 6.42 211.86
Front; retaining walls 1 1 1 33.00 1.00 10.74 354.42

Sides of pits
F1 1 4 2 3.00 1.00 1.50 36.00
F2 1 4 8 4.00 1.00 1.50 192.00
F3 1 4 5 5.00 1.00 1.50 150.00

Sides of trenches
TRENCHES ALL
All measured with planswift 1 2 1 47.30 1.00 1.50 141.90

Ddt: Sides of trenches


Intersection between the pits and trenches -1 1 26 0.60 0.80 1.00 (12.48)

Sides of retaining wall base


Along G/L H (2'-5) 1 2 1 20.53 2.57 2.80 294.89
Along G/L 6 (A-H) 1 2 1 32.60 2.57 2.80 468.27
Along G/L 1 (A-F) 1 2 1 28.93 2.57 2.80 415.55
3,361.86

Surface Treatments
Buhamizo Isaac:
Compaction of excavated reduced levels, including scarifying for a Omitted item
depth of 150mm, breaking down oversize material, adding suitable
material where necessary and compacting to 95% Mod AASHTO
density
Building area only
823.67

Earth filling

BILL NO. 3: FRAME


CLIENT: CK & COMPANY LTD DATE: 4/5/2024
THE PROPOSED COMMERCIAL BUILDING TO BE BUILT ON PLOT NO. 2969, BLOCK NO. 206,
PROJECT: MPERERWE, ALONG KAMPALA, GAYAZA ROAD, KAMPALA DISTRICT CALC BY: IB

Imported selected murram filling on formation deposited in 150mm


thick layers and compacted with a 5-tonne roller to 98% MDD to
receive hardcore filling as described (measured separately).
Lower area; swampy 1 1 0.5 1078.47 1 2.00 1,078.47
1,078.47

Murram Filling to raise levels

Imported selected murram filling on formation deposited in 150mm


thick layers and compacted with a 5-tonne roller to 98% MDD to
receive hardcore filling as described (measured separately). M3
Within the building areas
Measured with planswift 1 1 1 761.20 1.00 0.40 304.48
304.48

Hardcore Filling

Hardcore comprising hard clean stone, laterite or broken


concrete to pass a 75mm ring, deposited in layers and
consolidated by ramming

Depositing and compacting in layers maximum 150 mm thick;


levelling; 200mm average thickness; blinding with 50mm thick sand
to receive polythene sheet (measured separately) M2
Within the building areas
Measured with planswift 1 1 1 761.20 1.00 1.00 761.20
761.20

generally; depositing and compacting in layers maximum 150 mm


thick; levelling; blinding with 50mm thick sand to receive polythene
sheet (measured separately) M3
Within the building areas
Measured with planswift 1 1 1 1078.47 1 0.90 970.62
970.62

French drains

GeoTextile Membrane; Non-Woven Fleece Fabric as per the


structural engineer's instructions
Around drain pipes M2
Measured with planswift 1 1 1 344.00 1 1.00 344.00
344.00

20mm thick angular crushed clear stone ASTM number 57


compacted with 5tonne roller to the back of retaining wall all to the
satisfaction and approval of the structural engineer. M3
Across 1 1 2 51.00 0.30 0.30 9.18
Connecting drains 1 1 11 22.00 0.30 0.30 21.78
30.96

110mm diameter PVC heavy gauge perforated pipes (6mm thick)


PN10 complete with bends, exit points at every 15000mm centres
with Tee outlets of approximately 3000mm long; and all
accessories at the foot of retaining wall
Across 1 1 2 51.00 1.00 1.00 102.00
Connecting drains 1 1 11 22.00 1.00 1.00 242.00
344.00

The prices for the following concrete are to include for


filling into formwork, well vibrating and packing around
rod reinforcement (formwork and reinforcement
measured separately)

Plain Insitu concrete grade 15 in:-

50 mm thick blinding under the column bases M2


F1 1 1 2 3.00 3.00 1.00 18.00
F2 1 1 8 4.00 4.00 1.00 128.00
F3 1 1 5 5.00 5.00 1.00 125.00
15 271.00

BILL NO. 3: FRAME


CLIENT: CK & COMPANY LTD DATE: 4/5/2024
THE PROPOSED COMMERCIAL BUILDING TO BE BUILT ON PLOT NO. 2969, BLOCK NO. 206,
PROJECT: MPERERWE, ALONG KAMPALA, GAYAZA ROAD, KAMPALA DISTRICT CALC BY: IB

75mm thick blinding under the retaining wall base M2


Along G/L H (2'-5) 1 1 1 20.53 2.57 1.00 52.66
Along G/L 6 (A-H) 1 1 1 32.60 2.57 1.00 83.62
Along G/L 1 (A-F) 1 1 1 28.93 2.57 1.00 74.21
210.48

Ditto under the lift shaft base M2


1 1 1 6.49 5.05 1.50 49.16
49.16

Plain Insitu concrete grade 20 in:-

Strip foundation M3
All 1 1 1 47.30 0.90 0.30 12.77
12.77

Reinforced Insitu concrete grade 30 in:-

Column bases M3
Step 1
F1 1 1 2 3.00 3.00 0.40 7.20
F2 1 1 8 4.00 4.00 0.40 51.20
F3 1 1 5 5.00 5.00 0.40 50.00
Step 2
F1 1 1 2 2.50 2.50 0.40 5.00
F2 1 1 8 2.50 2.50 0.40 20.00
F3 1 1 5 2.50 2.50 0.40 12.50
15 145.90

Columns M3
C1 1 1 9 0.40 0.40 2.25 3.24
C2 1 1 3 0.40 0.60 2.25 1.62
C3 1 1 3 0.40 0.60 2.25 1.62
C4 1 1 3 0.40 0.60 2.25 1.62
C5 1 1 2 0.40 0.60 2.25 1.08
C6 1 1 1 0.40 0.40 2.25 0.36
21 9.54

Lift shaft base M3


LF1 1 1 1 6.49 5.05 0.50 16.39
16.39

M2
Along G/L H (2'-5) 1 1 1 20.53 2.57 0.50 26.33
Along G/L 6 (A-H) 1 1 1 32.60 2.57 0.50 41.81
Along G/L 1 (A-F) 1 1 1 28.93 2.57 0.50 37.10
105.24

300 mm thick retaining walls M2


Sides; retaining walls 1 2 1 33.00 1.00 2.50 165.00
Sides; retaining walls 1 2 1 33.00 1.00 1.83 120.78
Sides; retaining walls 1 2 0.5 33.00 1.00 6.42 211.86
Front; retaining walls 1 1 1 33.00 1.00 10.74 354.42
852.06

200mm thick lift shaft walls M3


1 1 2 2.45 1.00 1.50 7.35
1 1 2 2.05 1.00 1.50 6.15
13.50

Ground beam M3
G/L A(2-5) 1 1 1 18.30 0.20 0.30 1.10
G/L B(2-3) 1 1 1 5.50 0.20 0.30 0.33
G/L B'(2-3) 1 1 1 4.80 0.20 0.30 0.29
G/L C(2-3) 1 1 1 5.50 0.20 0.30 0.33
G/L E(1-2) 1 1 1 3.09 0.20 0.30 0.19
G/L 2(A-E) 1 1 1 19.42 0.20 0.30 1.17
G/L 5(A-G) 1 1 1 31.20 0.20 0.30 1.87
G/L 3(A-C) 1 1 1 8.32 0.20 0.30 0.50
96.13 5.77

L Staircase starter beams M2


Staircase 02 as per the Architectural drawings
1 1 1 2.52 0.60 0.35 0.53
0.53

Insitu concrete grade 30 in:-

150 mm thick floor slab; reinforced with T8 spaced at 200mm c/c


and mechanically floated M2
Dispatch area 1 1 1 96.26 1.00 1.00 96.26
Main Area/storage 1 1 1 630.90 1.00 1.00 630.90
Main Area/storage 1 1 1 56.96 1.00 1.00 56.96
784.12

Reinforcement
BILL NO. 3: FRAME
CLIENT: CK & COMPANY LTD DATE: 4/5/2024
THE PROPOSED COMMERCIAL BUILDING TO BE BUILT ON PLOT NO. 2969, BLOCK NO. 206,
PROJECT: MPERERWE, ALONG KAMPALA, GAYAZA ROAD, KAMPALA DISTRICT CALC BY: IB
High tensile steel bar reinforcement to BS 4449 as described;
including all bends, hooks, tying wire, distance blocks,
spacers and the like

Assorted bars up to H32 Kg


Column bases 1 1 150 145.90 1.00 1.00 21,885.00
Columns 1 1 150 9.54 1.00 1.00 1,431.00
Lift shaft base 1 1 150 16.39 1.00 1.00 2,458.09
- 1 1 150 105.24 1.00 1.00 15,786.29
300 mm thick retaining walls 1 1 150 852.06 0.30 1.00 38,342.70
200mm thick lift shaft walls 1 1 150 13.50 0.20 1.00 405.00
Staircase starter beams 1 1 150 0.53 1.00 1.00 79.22
Ground beam 1 1 150 96.13 0.20 0.30 865.17
81,252.47

Fabric mesh reinforcement to B.S. 4483

Reference A142; mesh size 200mm x 200mm; weighing


3.92kg/sq.m with minimum 300mm end and side laps M²
Dispatch area 1 1 1 96.26 1.00 1.00 96.26
Main Area/storage 1 1 1 630.90 1.00 1.00 630.90
Main Area/storage 1 1 1 56.96 1.00 1.00 56.96
784.12

Sawn formwork as described to:-

Sides of column bases M2


Step 1
F1 1 4 2 3.00 1.00 0.40 9.60
F2 1 4 8 4.00 1.00 0.40 51.20
F3 1 4 5 5.00 1.00 0.40 40.00
Step 2
F1 1 4 2 2.50 1.00 0.40 8.00
F2 1 4 8 2.50 1.00 0.40 32.00
F3 1 4 5 2.50 1.00 0.40 20.00
30 160.80

Sides of columns M2
C1 1 2 9 0.80 1.00 2.25 32.40
C2 1 2 3 1.00 1.00 2.25 13.50
C3 1 2 3 1.00 1.00 2.25 13.50
C4 1 2 3 1.00 1.00 2.25 13.50
C5 1 2 2 1.00 1.00 2.25 9.00
C6 1 2 1 0.80 1.00 2.25 3.60
21 85.50

Sides of ground beam M2


G/L A(2-5) 1 1 2 18.30 1.00 0.30 10.98
G/L B(2-3) 1 1 2 5.50 1.00 0.30 3.30
G/L B'(2-3) 1 1 2 4.80 1.00 0.30 2.88
G/L C(2-3) 1 1 2 5.50 1.00 0.30 3.30
G/L E(1-2) 1 1 2 3.09 1.00 0.30 1.85
G/L 2(A-E) 1 1 2 19.42 1.00 0.30 11.65
G/L 5(A-G) 1 1 2 31.20 1.00 0.30 18.72
G/L 3(A-C) 1 1 2 8.32 1.00 0.30 4.99
57.68

Sides of lift shaft base M3


LF1 1 1 2 11.54 1.00 0.50 11.54
11.54

Sides of the retaining wall base M2


Along G/L H (2'-5) 1 1 2 20.53 1.00 0.50 20.53
Along G/L 6 (A-H) 1 1 2 32.60 1.00 0.50 32.60
Along G/L 1 (A-F) 1 1 2 28.93 1.00 0.50 28.93
Ends 1 1 2 2.57 1.00 0.50 2.57
84.63

Sides of retaining walls M2


Sides; retaining walls 2 2 1 33.00 1.00 2.50 330.00
Sides; retaining walls 2 2 1 33.00 1.00 1.83 241.56
Sides; retaining walls 2 2 0.5 33.00 1.00 6.42 423.72
Front; retaining walls 2 1 1 33.00 1.00 10.74 708.84
1,704.12

Sides of lift shaft walls M3


1 2 2 2.45 1.00 1.50 14.70
1 2 2 2.05 1.00 1.50 12.30
27.00

Staircase starter beams M3


1 1 2 2.52 0.35 1.00 1.76
1.76

Edge of slab 150mm high M


Dispatch area 1 1 1 108.70 1.00 1.00 108.70
Main Area/storage 1 1 1 36.20 1.00 1.00 36.20
BILL NO. 3: FRAME
CLIENT: CK & COMPANY LTD DATE: 4/5/2024
THE PROPOSED COMMERCIAL BUILDING TO BE BUILT ON PLOT NO. 2969, BLOCK NO. 206,
PROJECT: MPERERWE, ALONG KAMPALA, GAYAZA ROAD, KAMPALA DISTRICT CALC BY: IB
Main Area/storage 1 1 1 26.50 1.00 1.00 26.50
171.40

Solid concrete blocks with minimum compressive strength


3.6N/mm2; bedded and jointed in cement mortar (1:4);
reinforced with 40mm wide x 1.6mm thick galvanised mild
steel straps built into every second course and laped 300mm
at joints and intersections and carried at least 115mm into
abutting walls in:

300mm thick Plinth Wall M2


G/L A(2-5) 1 1 2 18.30 1.00 0.70 25.62
G/L B(2-3) 1 1 2 5.50 1.00 0.70 7.70
G/L B'(2-3) 1 1 2 4.80 1.00 0.70 6.72
G/L C(2-3) 1 1 2 5.50 1.00 0.70 7.70
G/L E(1-2) 1 1 2 3.09 1.00 0.70 4.33
G/L 2(A-E) 1 1 2 19.42 1.00 0.70 27.19
G/L 5(A-G) 1 1 2 31.20 1.00 0.70 43.68
G/L 3(A-C) 1 1 2 8.32 1.00 0.70 11.65
134.58

Wall ties (Provisional)

20 SWG Hoop iron wall ties 25 x 1500mm long cast into concrete
columns one end and the other and built in blockwall joints. No.
C1 1 1 26 1.00 1.00 1.00 26.00
26 26.00

BILL NO. 3: FRAME


CLIENT: CK & COMPANY LTD DATE: 4/5/2024
THE PROPOSED COMMERCIAL BUILDING TO BE BUILT ON PLOT NO. 2969, BLOCK NO. 206,
PROJECT: MPERERWE, ALONG KAMPALA, GAYAZA ROAD, KAMPALA DISTRICT CALC BY: IB

Damp Proof Membrane

1000 Gauge polythene oversite damp proof membrane; laid on


blinded hardcore bed with 200mm end and side laps M2
784.12

Water proofing; tanking

4mm thick APP - modified bitumen torch - on vertical


membrane on concrete retaining wall or any other approved
tanking layed as recommended by the manufacturer
Behind the retaining walls
Sides; retaining walls 1 2 1 33.00 1.00 2.50 165.00
Sides; retaining walls 1 2 1 33.00 1.00 1.83 120.78
Sides; retaining walls 1 2 0.5 33.00 1.00 5.42 178.86
Front; retaining walls 1 1 1 33.00 1.00 9.74 321.42
To retaining wall base/foot
Along G/L H (2'-5) 1 1 1 20.53 2.17 1.00 44.45
Along G/L 6 (A-H) 1 1 1 32.60 2.17 1.00 70.58
Along G/L 1 (A-F) 1 1 1 28.93 2.17 1.00 62.63
963.72

20mm thick angular crushed clear stone ASTM number 57


compacted with 5tonne roller to the back of retaining wall all to the
satisfaction and approval of the structural engineer.
Sides; retaining walls 1 2 1 33.00 0.45 2.50 74.25
Sides; retaining walls 1 2 1 33.00 0.45 1.83 54.35
Sides; retaining walls 1 2 0.5 33.00 0.45 5.42 80.49
Front; retaining walls 1 1 1 33.00 0.45 9.74 144.64
353.73

110mm diameter PVC heavy gauge perforated pipes (6mm thick)


PN10 complete with bends, exit points at every 15000mm centres
with Tee outlets of approximately 3000mm long; and all
accessories at the foot of retaining wall
Sides; retaining walls 1 2 1 33.00 1.00 1.00 66.00
Sides; retaining walls 1 2 1 33.00 1.00 1.00 66.00
Sides; retaining walls 1 2 0.5 33.00 1.00 1.00 33.00
Front; retaining walls 1 1 1 33.00 1.00 1.00 33.00
198.00

Solid burnt clay brickwork in cement and sand (1:3)


mortar minimum strength 3.5N/mm

Underground water tanks 100mm thick skin wall


963.72

Cement and sand (1:4) rendering with approved water proof


additive to:
Plinth Walls M2
Plinth walls 1 1 1 75.00 1.00 1.65 123.75
80.49

Prepare and apply three coats of bituminous


oil paint on:-

Rendered plinth wall M2

80.49

BILL NO. 3: FRAME


BILL NO. 3: LOWER GROUND FLOOR

CLIENT: CK & COMPANY LTD DATE: 4/5/2024


THE PROPOSED COMMERCIAL BUILDING TO BE BUILT ON PLOT NO. 2969, BLOCK NO. 206,
PROJECT: MPERERWE, ALONG KAMPALA, GAYAZA ROAD, KAMPALA DISTRICT CALC BY: IB
MEASUREMENTS PURPOSE: ESTIMATES
NO. DESCRIPTION UNIT EQ. PRTS EQ. PRTS EQ. PRTS L W H/D/kg/m QTY

LOWER GROUND

SUPERSTRUCTURE

The prices for the following concrete are to include for


filling into formwork, well vibrating and packing around
rod reinforcement (formwork and reinforcement
measured separately)

Reinforced concrete grade 30 in:-

A Columns M3
Columns M3
C1 1 1 9 0.40 0.40 6.65 9.58
C2 1 1 3 0.40 0.60 6.65 4.79
C3 1 1 3 0.40 0.60 6.65 4.79
C4 1 1 3 0.40 0.60 6.65 4.79
C5 1 1 2 0.40 0.60 6.65 3.19
C6 1 1 1 0.40 0.40 6.65 1.06
21 28.20

B Beams M3
G/L E(1-2) & F(1-2) 1 1 2 3.14 0.40 0.55 1.38
G/L G(1-2) 1 1 1 1.10 0.40 0.55 0.24
G/L A(1-4) 1 1 1 12.45 0.40 0.55 2.74
G/L B,C,D,E,F(2-3) 1 1 5 5.50 0.40 0.55 6.05
G/L G(2-3) 1 1 1 5.60 0.40 0.55 1.23
G/L G(3-5) 1 1 1 11.55 0.40 0.55 2.54
G/L C(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L D(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L E(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L F(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L G(3-4) 1 1 1 5.65 0.40 0.55 1.24
G/L G(4-5) 1 1 1 5.60 0.40 0.55 1.23

G/L A2-B2, A3-B3, A3'-B3', A4-B4 1 1 4 2.32 0.40 0.55 2.04


G/L B2-C2 & B3-C3 1 1 2 5.60 0.40 0.55 2.46
G/L B5-C5 1 1 1 5.50 0.40 0.55 1.21
G/L 2,3 & 5 (C-D) 1 1 3 5.60 0.40 0.55 3.70
G/L 2,3,& 5(D-E) 1 1 3 5.60 0.40 0.55 3.70
G/L 1,2,3 & 5 (E-F) 1 1 4 5.60 0.40 0.55 4.93
G/L F1-G1 1 1 1 2.75 0.40 0.55 0.61

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

G/L 2,3 & 5 (F-G) 1 1 3 5.59 0.40 0.55 3.69


49.06

Intermediate beam (provisonal)


Intermediate beam (provisonal) 1 1 1 103.80 0.30 0.30 9.34
9.34

Upstand beam and moulding as per the Architects details.


Beam moulding 1 1 1 110.80 0.17 1.00 18.84
18.84

F Staircase M3
Staircase 02 as per the Architectural drawings
Waists x 4 No. 1 1 4 3.73 1.20 0.20 3.58
Steps x 44 No. 1 0.5 44 0.30 0.16 1.20 1.24
4.82

F Staircase landing beams; add to main beams M3


Staircase 02 as per the Architectural drawings
4 Landings 1 1 4 2.52 0.20 0.20 0.40
0.40

G 250mm thick suspended roof slab M2


Panel; G/L B&G (2-5) 1 1 1 18.45 30.39 1.00 560.70
Panel; G/L A&B (3-4) 1 1 1 6.40 2.72 1.00 17.41
Panel; G/L F&G (1-2) 1 1 1 3.54 6.39 1.00 22.62
Ddt: Around the lift shaft area -1 1 1 8.55 1.00 1.00 (8.55)
Add; beam tops /areas without slabs
G/L A (2-3) 1 1 1 6.00 0.40 1.00 2.40
G/L A1-B1 1 1 1 2.75 0.40 1.00 1.10
G/L E1-F1 1 1 1 6.00 0.40 1.00 2.40
G/L E(1-2) 1 1 1 3.54 0.40 1.00 1.42
599.49

J 200mm thick staircase landing M2


Staircase 02 as per the Architectural drawings
Landing 01 x 4 1 1 4 2.52 1.60 1.00 16.10
16.10

K 200mm thick lift shaft walls M2


1 1 2 2.45 1.00 6.90 33.81
1 1 2 2.05 1.00 6.90 28.29
Less: Lift door "unamed" -1 1 1 1.22 1.00 2.10 (2.56)
59.54

Reinforcements

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Columns 1 1 150 28.20 1.00 1.00 4,229.40
Beams 1 1 150 49.47 1.00 1.00 7,419.85
Intermediate beams 1 1 150 9.34 1.00 1.00 1,401.30
Upstands and mouldings 1 1 150 18.84 1.00 1.00 2,825.40
Suspended slabs 1 1 150 599.49 0.25 1.00 22,480.88
Staircase 1 1 150 4.82 1.00 1.00 723.06
Staircase landings 1 1 150 16.10 0.20 1.00 482.88
Lift shaft walls 1 1 150 59.54 0.20 1.00 1,786.14
41,348.91

Sawn formwork to:-

B Sides of columns M2
C1 1 2 9 0.80 1.00 6.65 95.76
C2 1 2 3 1.00 1.00 6.65 39.90
C3 1 2 3 1.00 1.00 6.65 39.90
C4 1 2 3 1.00 1.00 6.65 39.90
C5 1 2 2 1.00 1.00 6.65 26.60
C6 1 2 1 0.80 1.00 6.65 10.64
21 252.70

D Sides and soffites of beams M2


G/L E(1-2) & F(1-2) 1 1 2 3.14 1.50 1.00 9.42
G/L G(1-2) 1 1 1 1.10 1.50 1.00 1.65
G/L A(1-4) 1 1 1 12.45 1.50 1.00 18.67
G/L B,C,D,E,F(2-3) 1 1 5 5.50 1.50 1.00 41.25
G/L G(2-3) 1 1 1 5.60 1.50 1.00 8.40
G/L G(3-5) 1 1 1 11.55 1.50 1.00 17.33
G/L C(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L D(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L E(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L F(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L G(3-4) 1 1 1 5.65 1.50 1.00 8.48
G/L G(4-5) 1 1 1 5.60 1.50 1.00 8.40

G/L A2-B2, A3-B3, A3'-B3', A4-B4 1 1 4 2.32 1.50 1.00 13.92


G/L B2-C2 & B3-C3 1 1 2 5.60 1.50 1.00 16.80
G/L B5-C5 1 1 1 5.50 1.50 1.00 8.25
G/L 2,3 & 5 (C-D) 1 1 3 5.60 1.50 1.00 25.20
G/L 2,3,& 5(D-E) 1 1 3 5.60 1.50 1.00 25.20
G/L 1,2,3 & 5 (E-F) 1 1 4 5.60 1.50 1.00 33.60
G/L F1-G1 1 1 1 2.75 1.50 1.00 4.13
G/L 2,3 & 5 (F-G) 1 1 3 5.59 1.50 1.00 25.13
38 334.52

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

Intermediate beam (provisonal)


Intermediate beam (provisonal) 1 1 1 103.80 0.90 1.00 93.42
93.42

Sides and soffites of upstand beams and mouldings


Beam moulding- Upper 1 1 1 110.80 1.30 1.00 144.04
Beam moulding - Lower 1 1 1 111.80 0.35 1.00 39.13
183.17

Extra over formwork for forming rebates over 50mm but not
exceeding 100mm wide.
Beam moulding - Upper 1 1 1 110.80 1.30 1.00 144.04
Beam moulding - Lower 1 1 1 111.80 0.35 1.00 39.13
183.17

J Soffite of Suspended roof slab M2


Panel 01; G/L A & B (3-4) 1 1 1 5.65 2.32 1.00 13.11

Panel 02: G/L A&B(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 03: G/L A&B(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 04: G/L B&C(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 05: G/L B&C(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 05: G/L C&D(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 06: G/L C&D(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 07: G/L D&E(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 08: G/L D&E(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 11: G/L F&G(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 12: G/L F&G(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 13: Area around the lift shaft 1 1 1 11.25 1.00 1.00 11.25
507.36

L Staircase landing beams M2


Staircase 02 as per the Architectural drawings
4 Landings 1 2 4 2.52 0.20 1.00 4.02
4.02

M Sloping soffites of staircase M2


Staircase 02 as per the Architectural drawings
Waists x 4 No. 1 1 4 3.73 1.20 1.00 17.88
17.88

N Staircase Landing soffites M2


.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

Staircase 02 as per the Architectural drawings


Landing 01 x 4 1 1 4 2.52 1.40 1.00 14.08
14.08

O Risers 150mm high M


Staircase 02 as per the Architectural drawings
Steps x 44 1 1 44 1.20 1.00 1.00 52.80
52.80

P Staircase stringer cut to profiles of treads and risers


average 300mm wide M
Staircase 02 as per the Architectural drawings
Waists x 4 No. 1 2 4 3.73 1.00 1.00 29.81
29.81

Q Edge of slab 250mm high M


Panel; G/L B&G (2-5) 1 1 2 21.99 1.00 1.00 43.98
Panel; G/L A&B (3-4) 1 1 2 33.10 1.00 1.00 66.20

G/L A (2-3) 1 1 2 6.00 1.00 1.00 12.00


G/L A1-B1 1 1 2 2.75 1.00 1.00 5.50
G/L E1-F1 1 1 2 6.00 1.00 1.00 12.00
G/L E(1-2) 1 1 2 3.54 1.00 1.00 7.08
146.76

T Ditto staircase ditto M


Staircase 02 as per the Architectural drawings
Landing 01 x 4 1 2 4 4.12 1.00 1.00 32.96
32.96

Sides of lift shaft walls


1 2 2 2.45 1.00 6.90 67.62
1 2 2 2.05 1.00 6.90 56.58
Less: Lift door "unamed" -1 2 1 1.22 1.00 2.10 (5.12)
119.08

ELEMENT NO. 4

EXTERNAL WALLS

Solid concrete blockwall in cement mortar (1:4)


minimum strength 3.5N/mm reinforced with 40mm wide
x 1.5mm thick galvanised mild steel straps and 25mm
x 2mm galvanised mild steel ties cast in columns with
150mm embedded into masonary in horizontal alternate
courses in:-

A 300mm thick wall M2

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

G/L A(2-5) 1 1 1 18.40 1.00 6.10 112.24


G/L A2-E2 1 1 1 20.72 1.00 6.10 126.39
G/L E(1-2) 1 1 1 3.19 1.00 6.10 19.46
G/L A5-G5 1 1 1 32.50 1.00 6.10 198.25
Deductions
Windows
W15b; louvered windows -1 1 7 3.70 1.00 1.54 (39.89)
W09; glazed windows -1 1 2 1.57 1.00 0.80 (2.50)
W10; glazed windows -1 1 4 1.57 1.00 2.20 (13.77)

Doors
Openings -1 1 1 4.00 1.00 5.25 (21.00)
D9 -1 1 2 0.90 1.00 2.10 (3.78)
Db-17 -1 1 1 3.75 1.00 5.25 (19.69)
355.71

Reinforced concrete grade 25 in:-


A Lintels M2
Windows
W15b; louvered windows 1 1 7 4.00 0.20 0.25 1.40
W09; glazed windows 1 1 2 1.87 0.20 0.25 0.19
W10; glazed windows 1 1 4 1.87 0.20 0.25 0.37

Doors
Openings 1 1 1 4.30 0.20 0.25 0.22
D9 1 1 2 1.20 0.20 0.25 0.12
Db-17 1 1 1 4.05 0.20 0.25 0.20
2.50

Sawn formwork to:-

A Sides and soffites of lintels M2


Windows
W15b; louvered windows 1 1 7 4.00 0.70 1.00 19.60
W09; glazed windows 1 1 2 1.87 0.70 1.00 2.61
W10; glazed windows 1 1 4 1.87 0.70 1.00 5.22

Doors
Openings 1 1 1 4.30 0.70 1.00 3.01
D9 1 1 2 1.20 0.70 1.00 1.68
Db-17 1 1 1 4.05 0.70 1.00 2.83
34.96

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Lintels 1 1 150 2.50 1.00 1.00 374.55
374.55

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

Anti- Moisture Penetration Course in plain insitu concrete


grade 20 receive damp proof course( measured separately)

300mm wide x 75mm thick M


G/L A(2-5) 1 1 1 18.40 1.00 1.00 18.40
G/L A2-E2 1 1 1 20.72 1.00 1.00 20.72
G/L E(1-2) 1 1 1 3.19 1.00 1.00 3.19
G/L A5-G5 1 1 1 32.50 1.00 1.00 32.50
Deductions
Doors
Openings -1 1 1 4.00 1.00 1.00 (4.00)
D9 -1 1 2 0.90 1.00 1.00 (1.80)
Db-17 -1 1 1 3.75 1.00 1.00 (3.75)
65.26

Hessian based bituminous damp proof course to


B.S. 743 Type 5A bedded in cement mortar (1:4)
on concrete bed with 150mm end laps and full
width at passings and angles

Under 300mm thick walls


G/L A(2-5) 1 1 1 18.40 1.00 1.00 18.40
G/L A2-E2 1 1 1 20.72 1.00 1.00 20.72
G/L E(1-2) 1 1 1 3.19 1.00 1.00 3.19
G/L A5-G5 1 1 1 32.50 1.00 1.00 32.50
Deductions
Doors
Openings -1 1 1 4.00 1.00 1.00 (4.00)
D9 -1 1 2 0.90 1.00 1.00 (1.80)
Db-17 -1 1 1 3.75 1.00 1.00 (3.75)
65.26

ELEMENT NO. 5

INTERNAL WALLS

Solid concrete blockwall in cement mortar (1:4)


minimum strength 3.5N/mm reinforced with 40mm wide
x 1.5mm thick galvanised mild steel straps and 25mm
x 2mm galvanised mild steel ties cast in columns with
150mm embedded into masonary in horizontal alternate
courses in:-

A 200mm wall M2
ALONG X-X
G/L B(1-4) 1 1 1 12.00 1.00 6.10 73.20
G/L C(1-3) 1 1 1 6.00 1.00 6.10 36.60
G/L B'(1-3) 1 1 1 5.80 1.00 6.65 38.57
.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

DUCT WALLS/FR 1 1 1 0.94 1.00 6.65 6.25


DUCT - DRAINAGE 1 1 2 0.70 1.00 6.65 9.31
ALONG Y-Y
G/L A3-B3 1 1 2 2.52 1.00 6.10 30.74
G/L B3-C3 1 1 1 5.80 1.00 6.10 35.38
ELECTRICAL DUCT 1 1 1 2.40 1.00 6.65 15.96
DRAINAGE DUCT 1 1 1 1.80 1.00 6.65 11.97

Deductions
Doors
Db-17 -1 1 1 3.75 1.00 5.25 (19.69)
Db-11 -1 1 1 1.00 1.00 2.65 (2.65)
Db-13 -1 1 1 1.60 1.00 2.65 (4.24)
Db-15 -1 1 1 0.70 1.00 2.65 (1.85)
229.55

B 150mm ditto M2
ALONG X-X
MALE TOILETS ENTRANCE WALL WITH 2 DOORS 1 1 1 2.30 1.00 6.65 15.30
FEMALE TOILETS ENTRANCE WALL WITH 3 DOORS 1 1 1 3.45 1.00 6.65 22.94
ALONG Y-Y
PARTITIONS - ALL X5 1 1 5 1.20 1.00 6.65 39.90
URINAL PARTITIONS 1 1 2 0.50 1.00 6.65 6.65
DUCT WALLS 1 1 2 0.70 1.00 6.65 9.31
Deductions
Doors
Db-15 -1 1 1 0.70 1.00 2.65 (1.85)
Db-12 -1 1 5 0.80 1.00 2.10 (8.40)
83.84

Reinforced concrete grade 25 in:-


A Lintels M2
Doors - 200mm thick walls
Db-17 1 1 1 4.75 0.20 0.25 0.24
Db-11 1 1 1 1.30 0.20 0.25 0.07
Db-13 1 1 1 1.90 0.20 0.25 0.10
Db-15 1 1 2 1.00 0.20 0.25 0.10

Doors - 150mm thick walls


Db-12 1 1 5 1.10 0.15 0.25 0.21
0.70

Sawn formwork to:-

A Sides and soffites of lintels M2


Doors - 200mm thick walls
Db-17 1 1 1 4.75 0.70 1.00 3.32
Db-11 1 1 1 1.30 0.70 1.00 0.91

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

Db-13 1 1 1 1.90 0.70 1.00 1.33


Db-15 1 1 2 1.00 0.70 1.00 1.40

Doors - 150mm thick walls


Db-12 1 1 5 1.10 0.65 1.00 3.58
10.54

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Lintels 1 1 120 0.70 1.00 1.00 84.45
84.45

Anti- Moisture Penetration Course in plain insitu concrete


grade 20 receive damp proof course( measured separately)

200mm wide x 75mm thick M


ALONG X-X
G/L B(1-4) 1 1 1 12.00 1.00 1.00 12.00
G/L C(1-3) 1 1 1 6.00 1.00 1.00 6.00
G/L B'(1-3) 1 1 1 5.80 1.00 1.00 5.80
DUCT WALLS/FR 1 1 1 0.94 1.00 1.00 0.94
DUCT - DRAINAGE 1 1 2 0.70 1.00 1.00 1.40
ALONG Y-Y
G/L A3-B3 1 1 2 2.52 1.00 1.00 5.04
G/L B3-C3 1 1 1 5.80 1.00 1.00 5.80
ELECTRICAL DUCT 1 1 1 2.40 1.00 1.00 2.40
DRAINAGE DUCT 1 1 1 1.80 1.00 1.00 1.80

Deductions
Doors
Db-17 -1 1 1 3.75 1.00 1.00 (3.75)
Db-11 -1 1 1 1.00 1.00 1.00 (1.00)
Db-13 -1 1 1 1.60 1.00 1.00 (1.60)
Db-15 -1 1 1 0.70 1.00 1.00 (0.70)
34.13

Hessian based bituminous damp proof course to


B.S. 743 Type 5A bedded in cement mortar (1:4)
on concrete bed with 150mm end laps and full
width at passings and angles

Under 200mm thick walls


ALONG X-X
G/L B(1-4) 1 1 1 12.00 1.00 1.00 12.00
G/L C(1-3) 1 1 1 6.00 1.00 1.00 6.00
G/L B'(1-3) 1 1 1 5.80 1.00 1.00 5.80
DUCT WALLS/FR 1 1 1 0.94 1.00 1.00 0.94
DUCT - DRAINAGE 1 1 2 0.70 1.00 1.00 1.40
.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

ALONG Y-Y
G/L A3-B3 1 1 2 2.52 1.00 1.00 5.04
G/L B3-C3 1 1 1 5.80 1.00 1.00 5.80
ELECTRICAL DUCT 1 1 1 2.40 1.00 1.00 2.40
DRAINAGE DUCT 1 1 1 1.80 1.00 1.00 1.80

Deductions
Doors
Db-17 -1 1 1 3.75 1.00 1.00 (3.75)
Db-11 -1 1 1 1.00 1.00 1.00 (1.00)
Db-13 -1 1 1 1.60 1.00 1.00 (1.60)
Db-15 -1 1 1 0.70 1.00 1.00 (0.70)
34.13

Anti- Moisture Penetration Course in plain insitu concrete


grade 20 receive damp proof course( measured separately)

150mm wide x 75mm thick M


ALONG X-X
MALE TOILETS ENTRANCE WALL WITH 2 DOORS 1 1 1 2.30 1.00 1.00 2.30
FEMALE TOILETS ENTRANCE WALL WITH 3 DOORS 1 1 1 3.45 1.00 1.00 3.45
ALONG Y-Y
PARTITIONS - ALL X5 1 1 5 1.20 1.00 1.00 6.00
URINAL PARTITIONS 1 1 2 0.50 1.00 1.00 1.00
DUCT 1 1 2 0.70 1.00 1.00 1.40
Deductions
Doors
Db-12 -1 1 5 0.80 1.00 1.00 (4.00)
10.15

Hessian based bituminous damp proof course to


B.S. 743 Type 5A bedded in cement mortar (1:4)
on concrete bed with 150mm end laps and full
width at passings and angles

Under 150mm thick walls


ALONG X-X
MALE TOILETS ENTRANCE WALL WITH 2 DOORS 1 1 1 2.30 1.00 1.00 2.30
FEMALE TOILETS ENTRANCE WALL WITH 3 DOORS 1 1 1 3.45 1.00 1.00 3.45
ALONG Y-Y
PARTITIONS - ALL X5 1 1 5 1.20 1.00 1.00 6.00
URINAL PARTITIONS 1 1 2 0.50 1.00 1.00 1.00
DUCT 1 1 2 0.70 1.00 1.00 1.40
Deductions
Doors
Db-12 -1 1 5 0.80 1.00 1.00 (4.00)
10.15

ELEMENT NO. 6
.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

WINDOWS, SCREENS AND LIGHTS

Anodized Aluminum casement windows. The color shall be to


client's approval; all additional costs are deemed included.

Provide and fix purpose-made anodized aluminum windows


and window frames complete with 5mm thick translucent
glass and single glazing, glazing beads, wash leather strips,
sealing, burglar proofing, fly mesh, all ironmongery and
accessories; fixing to blockwork or concrete; all as per
Architect's drawings; Drawing No. NA(22)02-9/10; in:

The contractor is expected to prepare and submit shop


drawings for approval prior to fabrication and erection of the
windows and screens

A Glazed window and window frames size: 1565 mm wide x 800 mm


high; complete with 2 window panes size 600mm wide x 600mm
high; overall window type [Wb-09] No 2.00

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

B Glazed window and window frames size: 1565 mm wide x 2200


mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [Wb-10] No 4.00

B Glazed window and window frames size: 1565 mm wide x 1500


mm high; complete with 4 window panes size 600mm wide x
600mm high; overall window type [unamed but above Wb-10] No 4.00

B Louvered window and window frames size: 3700 mm wide x 1540


mm high; overall window type [Wb-15] No 7.00

Reinforced Insitu concrete grade 25 in:-

Moulded concrete window Sill; Section size 350 x 85 x 50mm;


weathered and throated; all as per Architect's details
Glazed window and window frames size: 1565 mm wide x 800 mm
high; complete with 2 window panes size 600mm wide x 600mm
high; overall window type [Wb-09] 1 1 2 1.87 1.00 1.00 3.73
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [Wb-10] 1 1 4 1.87 1.00 1.00 7.46
Glazed window and window frames size: 1565 mm wide x 1500
mm high; complete with 4 window panes size 600mm wide x
600mm high; overall window type [unamed but above Wb-10] 1 1 4 1.87 1.00 1.00 7.46
Louvered window and window frames size: 3700 mm wide x 1540
mm high; overall window type [Wb-15] 1 1 7 4.00 1.00 1.00 28.00
46.65

Window boards

Natural Stone Granite Window Board; size 150mm wide x 20mm


thick thick; all edges well finished with a coved mould; all as per
Architect's details
Glazed window and window frames size: 1565 mm wide x 800 mm
high; complete with 2 window panes size 600mm wide x 600mm
high; overall window type [Wb-09] 1 1 2 1.57 1.00 1.00 3.13
Glazed window and window frames size: 1565 mm wide x 2000
mm high; complete with 6 window panes size 600mm wide x
600mm high; overall window type [Wb-10] 1 1 4 1.57 1.00 1.00 6.26
Glazed window and window frames size: 1565 mm wide x 1500
mm high; complete with 4 window panes size 600mm wide x
600mm high; overall window type [unamed but above Wb-10] 1 1 4 1.57 1.00 1.00 6.26
Louvered window and window frames size: 3700 mm wide x 1540
mm high; overall window type [Wb-15] 1 1 7 3.70 1.00 1.00 25.90
41.55

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

BILL NO. 3

ELEMENT NO. 7

DOORS, SHUTTERS AND HATCHES

Timber doors

The following in wrot hardwood to architect's satisfaction:-

Approved hardwood flush doors

A 45mm thick solid core timber flush door shutter size 800mm wide x
2100 mm high complete with a mahogany veneer; to Architect's
detail; door type [Db-12] No
1 1 5 1.00 1.00 1.00 5.00
5.00

Approved hardwood panelled doors;

A 45mm thick solid panelled door shutter size 1000mm wide x


2100mm high complete with 2 No. vision panels size 200mm wide
x 1000mm high; to Architect's detail; door type [Db-11] No
1 1 1 1.00 1.00 1.00 1.00
1.00

Door frames and finishings in in wrot hardwood

C 250mm x 50mm rebated frame M


Db-12 1 1 5 5.00 1.00 1.00 25.00
Db-11 1 1 1 6.30 1.00 1.00 6.30
31.30

C Ditto transomes M
Db-11 1 1 1 1.00 1.00 1.00 1.00
1.00

D 40mm x 20mm Splayed architrave or qudrant beads where


applicable. M
Db-12 1 2 5 5.00 1.00 1.00 50.00
Db-11 1 2 1 6.30 1.00 1.00 12.60
62.60

D 20mm x 20mm moulded glazing beads. M


Db-11 1 2 1 3.10 1.00 1.00 6.20
Db-11 - Vision panels 1 2 2 2.40 1.00 1.00 9.60

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

15.80

Ironmongery to architect's approval and sartisfaction

E 100mm Pressed steel butt hinges Pr


1 1 5 1.50 1.00 1.00 7.50
Db-11 1 1 1 1.50 1.00 1.00 1.50
9.00

F 25mm diameter rubber door stop plugged to wall/floor No


1 1 14 1.00 1.00 1.00 14.00
14.00

H 3 - Lever motrice lock complete with approved door handles No


Db-11 1 1 1 1.00 1.00 1.00 1.00
1.00

H Commercial privacy Lock complete with occupancy indicator Oil


rubbed bronze and Lock restroom hardware brass door handles No
Db-12 1 1 5 1.00 1.00 1.00 5.00
5.00

I Coat hooks No
1 1 5 1.00 1.00 1.00 5.00
5.00

J Door closer No
1 1 3 1.00 1.00 1.00 3.00
3.00

K Mild steel aldrop bolt complete with all the necessary accessories
No
1 2 3 1.00 1.00 1.00 6.00
6.00

L Stainless Steel Push plate size 300mm x 100mm No


1 2 5 1.00 1.00 1.00 10.00
1 2 1 1.00 1.00 1.00 2.00
12.00

M Stainless Steel kick plate size 800mm wide x 150mm high x 3mm
thick No
1 2 5 1.00 1.00 1.00 10.00
10.00

M Stainless Steel kick plate size 1000mm wide x 150mm high x 3mm
thick No
.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

1 2 1 1.00 1.00 1.00 2.00


2.00

O Symbol (Male) No
1 1 1 1.00 1.00 1.00 1.00
1.00

B Symbol (Female) No
1 1 1 1.00 1.00 1.00 1.00
1.00

Glazing

5mm thick clear sheet glass fixed to hardwood frames with


glazing beads (measured seperately)
Db-11 - Vent 1 1 1 1.00 0.55 1.00 0.55
Db-11 - Vision panel 1 1 2 1.00 0.20 1.00 0.40
0.95

Steel Casement roller shutters; galvanised steel

C Galvanised steel casement roll up shutter door set; size 3700mm


wide x 2400mm high x 2mm thick overall with 3700mm x 300mm
high shutter cover on top complete with frame, fixing lugs, locking
device, surface treatment and protection; as per the Architect'
details and approved shop drawings; door type [Db-17]
No 2.00

Steel casement doors; mild steel

Supply and Fix the following purpose made mild steel door
and door frames; all members in 3mm thick steel sections
complete with mild steel frame, hinges, fixing lugs, locking
device and a single coat of red oxide primer, all fixed as per
Architect's details and satisfaction

D Louvered door set; size 700 mm wide x 2650 mm high; door type
[Db-15] No 3.00

D Louvered door set; size 1600 mm wide x 2650 mm high; complete


with 2 louvered door shutters; door type [Db-13] No 1.00

Anodised aluminium doors

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

Supply and fix purpose-made anodised aluminium casement


doors and frames; complete with 6mm thick translucent glass
and single glazing, ironmongery, fixing lugs, all accessories
and one coat of red oxide primer before delivery; fixing to
blockwork or concrete; all as per Architect's drawings;
Drawing No. NA(22)02-9/10; in:

Door set; size 900 mm wide x 2100 mm high; complete with 2 No.
light panes size 800 mm wide x 850 mm high with 6mm thick
frosted glass, 3 lever motrice lock; all as per the Architect's details;
door type [Db-09] 2.00

Prepare and apply undercoat and three coats of gloss oil paint
on:-

I General surfaces of metal M2


Louvered door set; size 700 mm wide x 2650 mm high; door type
[Db-15] 1 2 3 0.70 1.00 2.65 11.13
Louvered door set; size 1600 mm wide x 2650 mm high; complete
with 2 louvered door shutters; door type [Db-13] 1 2 1 1.60 1.00 2.65 8.48
19.61

J General surfaces of wood M2


Wood frames; girth exceeding 300mm wide; 350mm wide
250mm x 50mm rebated frame 1 1 1 31.30 0.35 1.00 10.96
Ditto transomes 1 1 1 1.00 0.60 1.00 0.60
Door shutters; Db-12 1 2 5 0.85 2.15 1.00 18.28
Door shutters; Db-11 1 2 1 1.05 2.15 1.00 4.52
34.35

K Wood surfaces not exceeding 100mm girth M


40mm x 20mm Splayed architrave or qudrant beads where
applicable. 1 1 1 62.60 1.00 1.00 62.60
20mm x 20mm moulded glazing beads 1 1 1 15.80 1.00 1.00 15.80
78.40

ELEMENT NO. 8

INTERNAL FINISHES

Floor screed; Cement and sand (1:4); wood floated finish to


receive floor tiles m/s:

A Floors M2
Washrooms - Female 1 1 1 11.58 1.00 1.00 11.58

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

Washrooms - Male 1 1 1 12.46 1.00 1.00 12.46


Washrooms lobby - Female 1 1 1 3.60 1.00 1.00 3.60
Washrooms lobby - Male 1 1 1 2.40 1.00 1.00 2.40

Staircase area 1 1 1 14.59 1.00 1.00 14.59


Lobby to staircase 1 1 1 14.59 1.00 1.00 14.59
Add: Door ways
Db-12 1 1 1 0.80 0.15 1.00 0.12
Db-09 1 1 2 0.90 0.30 1.00 0.54
Db-11 1 1 1 1.00 0.20 1.00 0.20
Db-17 1 1 1 3.75 0.20 1.00 0.75
OPENING 1 1 1 4.00 0.30 1.00 1.20
62.03

WATERPROOFING TO TOILETS and OTHER WET AREAS

Pure crystalline water proofing treatment in two coats using


"Vandex Super" manufactured by M/s. Vandex East Africa Limited
or approved equivalent to vertical and horizontal surfaces, with
proper gradient including surface preparation and applying slurry
coat of Vandex Super mixed with a cement sand mortar 1:3,
cleaning , pre-watering and then applying two coats of Vandex
Super (each coat approx. 0.75 kg per Sm) mixed to a slurry
consistency, curing, protecting the completed work by hessian
cloth, providing bonding keys for each coat, fillets, testing for water
tightness complete all as per manufacturer's specifications,
drawings and as directed by the Project Manager on:

To wet areas
Washrooms - Female 1 1 1 11.58 1.00 1.00 11.58
Washrooms - Male 1 1 1 12.46 1.00 1.00 12.46
Washrooms lobby - Female 1 1 1 3.60 1.00 1.00 3.60
Washrooms lobby - Male 1 1 1 2.40 1.00 1.00 2.40
Db-12 1 1 1 0.80 0.15 1.00 0.12
Db-09 1 1 2 0.90 0.30 1.00 0.54
30.70

D Staircase landing M2
Staircase 02 as per the Architectural drawings
Landing 01 x 4 1 1 4 2.52 1.40 1.00 14.08
14.08

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

F 300mm wide Staircase treads M


Staircase 02 as per the Architectural drawings
Steps x 44 1 1 44 1.20 1.00 1.00 52.80
52.80

G 150mm wide Staircase risers M


Staircase 02 as per the Architectural drawings
Steps x 44 1 1 44 1.20 1.00 1.00 52.80
52.80

H Edges of 200mm thick staircase landing M


Staircase 02 as per the Architectural drawings
Landing 01 x 4 1 2 4 4.12 1.00 1.00 32.96
32.96

I Staircase stringer cut to profiles of treads and risers average


300mm wide M
Staircase 02 as per the Architectural drawings
Waists x 4 No. 1 2 4 3.73 1.00 1.00 29.81
29.81

J 20mm thick 100mm high skirting with rounded top edge and
slight cove at bottom M
Washrooms - Female 1 1 1 17.20 1.00 1.00 17.20
Washrooms - Male 1 1 1 19.18 1.00 1.00 19.18
Washrooms lobby - Female 1 1 1 13.20 1.00 1.00 13.20
Washrooms lobby - Male 1 1 1 8.80 1.00 1.00 8.80

Staircase area 1 1 1 16.63 1.00 1.00 16.63


Lobby to staircase 1 1 1 16.63 1.00 1.00 16.63

Deduct the doors


Db-12 -1 5 1 0.80 0.15 1.00 (0.60)
Db-09 -1 1 2 0.90 0.30 1.00 (0.54)
Db-11 -1 2 1 1.00 0.20 1.00 (0.40)
Db-17 -1 1 1 3.75 0.20 1.00 (0.75)
OPENING -1 1 1 4.00 0.30 1.00 (1.20)
88.15

Supply and Fix approved Class 4: moderate to Heavy Traffic;


porcelain tiles; non-slip; laid in an approved pattern; bedded
in approved adhesive cement and pointed with an approved
tile grout

K Floors M2 62.03

L Staircase landings M2 14.08


.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

N 300mm wide Staircase treads complete with non slip inserts M 52.80

O 150mm wide Staircase risers M 52.80

A Edges of 200mm thick staircase landing M 32.96

B Staircase stringer cut to profiles of treads and risers average


300mm wide M 29.81

C 20mm thick 100mm high skirting with rounded top edge and
slight cove at bottom M 88.15

Industrial Epoxy floor paint (Production area)

Prepare floor surface to receive floor epoxy paint; apply sika-


floor heavy duty industrial anti-acid epoxy floor paint (Sika
heavy duty that can withstand constant traffic, mechanical
wear, corrosive liquids, and high temperatures to:
Floors
STORAGE 1 1 1 538.61 1.00 1.00 538.61
DISPATCH AREA 1 1 1 96.80 1.00 1.00 96.80
EXTERNAL AREA 1 1 1 56.67 1.00 1.00 56.67
692.08

Skirting
Storage area 1 1 1 108.93 1.00 1.00 108.93
Deduct the doors
Db-17 -1 1 2 3.75 1.00 1.00 (7.50)
Db-15 to duct -1 1 1 0.70 1.00 1.00 (0.70)
Db-13 to duct -1 1 1 1.60 1.00 1.00 (1.60)
Lift -1 1 1 2.40 1.00 1.00 (2.40)
FHR -1 1 1 0.94 1.00 1.00 (0.94)

Dispatch area 1 1 1 23.90 1.00 1.00 23.90


Deduct the doors
Db-17 -1 1 1 3.75 1.00 1.00 (3.75)
Db-09 -1 1 2 0.90 1.00 1.00 (1.80)
114.14

Two coat lime plaster (1:2:9) to:-

F Concrete block Walls M2


Washrooms - Female 1 1 1 17.20 1.00 6.65 114.38
Washrooms - Male 1 1 1 19.18 1.00 6.65 127.55
Washrooms lobby - Female 1 1 1 13.20 1.00 6.65 87.78
Washrooms lobby - Male 1 1 1 8.80 1.00 6.65 58.52
.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

Staircase area 1 1 1 16.63 1.00 6.65 110.59


Lobby to staircase 1 1 1 16.63 1.00 6.65 110.59

Deduct the doors


Db-12 -1 2 1 0.80 1.00 2.10 (3.36)
Db-09 -1 1 2 0.90 1.00 2.10 (3.78)
Db-11 -1 2 1 1.00 1.00 2.65 (5.30)
Db-17 -1 1 1 3.75 1.00 5.25 (19.69)
OPENING -1 1 1 4.00 1.00 5.25 (21.00)

Storage area 1 1 1 108.93 1.00 6.65 724.38


Deduct the doors
Db-17 -1 1 2 3.75 1.00 5.25 (39.38)
Db-15 to duct -1 1 1 0.70 1.00 2.65 (1.85)
Db-13 to duct -1 1 1 1.60 1.00 2.65 (4.24)
Lift -1 1 1 2.40 1.00 2.10 (5.04)

Inside ducts
Duct 01 1 1 2 2.30 1.00 6.90 31.74
Db-15 to duct -1 1 1 0.70 1.00 2.65 (1.85)

Duct 02 1 1 2 2.54 1.00 6.90 35.05


Db-15 to duct -1 1 1 1.60 1.00 2.65 (4.24)

Duct 02 1 1 2 1.74 1.00 6.90 24.01


Db-15 to duct -1 1 1 0.94 1.00 6.90 (6.49)

Duct 01 1 1 2 1.30 1.00 6.90 17.94


Db-15 to duct -1 1 1 0.70 1.00 2.65 (1.85)

Less: tiled area -1 1 1 1.00 1.00 1.00 -1

Windows
W15b; louvered windows -1 1 7 3.70 1.00 1.54 (39.89)
W09; glazed windows -1 1 2 1.57 1.00 0.80 (2.50)
W10; glazed windows -1 1 4 1.57 1.00 2.20 (13.77)
1,267.30

G Concrete surfaces M2
Sides of columns
C1 1 2 9 0.80 1.00 6.65 95.76
C2 1 2 3 1.00 1.00 6.65 39.90
C3 1 2 3 1.00 1.00 6.65 39.90
C4 1 2 3 1.00 1.00 6.65 39.90
C5 1 2 2 1.00 1.00 6.65 26.60
C6 1 2 1 0.80 1.00 6.65 10.64
252.70
.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

I Ditto staircase landing M2


Staircase 02 as per the Architectural drawings
Landing 01 x 4 1 1 4 2.52 1.40 1.00 14.08
14.08

J Slopping soffites of stair case M2


Staircase 02 as per the Architectural drawings
Waists x 4 No. 1 1 4 3.73 1.20 1.00 17.88
17.88

L Ceiling soffites of the slab above M2


Panel 01; G/L A & B (3-4) 1 1 1 5.65 2.32 1.00 13.11

Panel 02: G/L A&B(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 03: G/L A&B(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 04: G/L B&C(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 05: G/L B&C(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 05: G/L C&D(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 06: G/L C&D(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 07: G/L D&E(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 08: G/L D&E(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 09: G/L E&F(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 10: G/L E&F(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 11: G/L F&G(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 12: G/L F&G(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 13: Area around the lift shaft 1 1 1 5.60 11.65 1.00 65.24
657.95

Cement and sand mortar (1:4) backing


A 25mm thick rendered backing to receive white glazed
tiles (measured separately) M2
Washrooms - Female 1 1 1 17.20 1.00 2.10 36.12
Washrooms - Male 1 1 1 19.18 1.00 2.10 40.28
Washrooms lobby - Female 1 1 1 13.20 1.00 2.10 27.72
Washrooms lobby - Male 1 1 1 8.80 1.00 2.10 18.48

Deduct the doors


Db-12 -1 2 5 0.80 1.00 2.10 (16.80)
105.80

Glazed Wall Tiles


.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

B 200mm x 300mm x 6mm approved glazed ceramic wall


tiles in approved colour fixed to rendered backing (measured
separately) with anapproved adhesive and joints pointed in
white cement M2
Washrooms - Female 1 1 1 17.20 1.00 2.10 36.12
Washrooms - Male 1 1 1 19.18 1.00 2.10 40.28
Washrooms lobby - Female 1 1 1 13.20 1.00 2.10 27.72
Washrooms lobby - Male 1 1 1 8.80 1.00 2.10 18.48

Deduct the doors


Db-12 -1 2 5 0.80 1.00 2.10 (16.80)
105.80

B Edge trim; plastic; quarter round; setting at edges of wall tile finish M
Washrooms - Female 1 1 1 17.20 1.00 1.00 17.20
Washrooms - Male 1 1 1 19.18 1.00 1.00 19.18
Washrooms lobby - Female 1 1 1 13.20 1.00 1.00 13.20
Washrooms lobby - Male 1 1 1 8.80 1.00 1.00 8.80

Deduct the doors


Db-12 1 2 5 1.00 1.00 2.10 21.00
79.38

Moulded Ceiling cornice as per Architect's detail


Storage area 1 1 1 108.93 1.00 1.00 108.93
Dispatch area 1 1 1 23.90 1.00 1.00 23.90
132.83

Mild Steel balustrades to Architect's details

Horizontal or raking balustrade; 900mm high comprising of;


50mx3mm thick CHS handrail; 4 No. 25x2mm thick CHS
intermediate horizontal rails; 2/50x6mm thick MS flat balusters,
mild steel base plates; all rawl bolted into concrete; including
primer, spray painting wth three coats gloss oil paint and
decorations to approval.

Staircase 02 as per the Architectural drawings


Waists x 4 No. 1 2 4 3.73 1.00 1.00 29.81
Landings x 4 1 1 4 0.20 1.00 1.00 0.80
End of landing 1 1 1 1.40 1.00 1.00 1.40
32.01

Hand rails fixed to walls as per the Architect's details


Waists x 4 No. 1 2 4 3.73 1.00 1.00 29.81
Half landings 1 1 2 2.52 1.00 1.00 5.03
34.84

.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

Glass railing; 900mm high comprising of: 12mm thick tempered


(toughed) laminated glass fixed to and including: 50mm diameter
chrome plated stainless steel hand rails and and vertical balusters
spaced at 900mm centres; all chrome plated stainless brackets;
fixed to walls and staircase steel frame.

Prepare and apply three coats of silk vinyl painting on:-

F Walls M2
Washrooms - Female 1 1 1 17.20 1.00 6.65 114.38
Washrooms - Male 1 1 1 19.18 1.00 6.65 127.55
Washrooms lobby - Female 1 1 1 13.20 1.00 6.65 87.78
Washrooms lobby - Male 1 1 1 8.80 1.00 6.65 58.52

Staircase area 1 1 1 16.63 1.00 6.65 110.59


Lobby to staircase 1 1 1 16.63 1.00 6.65 110.59

Deduct the doors


Db-12 -1 2 1 0.80 1.00 2.10 (3.36)
Db-09 -1 1 2 0.90 1.00 2.10 (3.78)
Db-11 -1 2 1 1.00 1.00 2.65 (5.30)
Db-17 -1 1 1 3.75 1.00 5.25 (19.69)
OPENING -1 1 1 4.00 1.00 5.25 (21.00)

Storage area 1 1 1 108.93 1.00 6.65 724.38


Deduct the doors
Db-17 -1 1 2 3.75 1.00 5.25 (39.38)
Db-15 to duct -1 1 1 0.70 1.00 2.65 (1.85)
Db-13 to duct -1 1 1 1.60 1.00 2.65 (4.24)
Lift -1 1 1 2.40 1.00 2.10 (5.04)

Inside ducts
Duct 01 1 1 2 2.30 1.00 6.90 31.74
Db-15 to duct -1 1 1 0.70 1.00 2.65 (1.85)

Duct 02 1 1 2 2.54 1.00 6.90 35.05


Db-15 to duct -1 1 1 1.60 1.00 2.65 (4.24)

Duct 02 1 1 2 1.74 1.00 6.90 24.01


Db-15 to duct -1 1 1 0.94 1.00 6.90 (6.49)

Duct 01 1 1 2 1.30 1.00 6.90 17.94


Db-15 to duct -1 1 1 0.70 1.00 2.65 (1.85)

Less: tiled area -1 1 1 1.00 1.00 1.00 (1.00)

W15b; louvered windows -1 1 7 3.70 1.00 1.54 (39.89)


.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

W09; glazed windows -1 1 2 1.57 1.00 0.80 (2.50)


W10; glazed windows -1 1 4 1.57 1.00 2.20 (13.77)
1,267.30

A Concrete surfaces M2
Sides of columns
C1 1 2 9 0.80 1.00 6.65 95.76
C2 1 2 3 1.00 1.00 6.65 39.90
C3 1 2 3 1.00 1.00 6.65 39.90
C4 1 2 3 1.00 1.00 6.65 39.90
C5 1 2 2 1.00 1.00 6.65 26.60
C6 1 2 1 0.80 1.00 6.65 10.64
252.70

Prepare and apply three coats of matt emulsion painting on:-

D Ditto staircase landing M2


Staircase 02 as per the Architectural drawings
Landing 01 x 4 1 1 4 2.52 1.40 1.00 14.08
14.08

E Slopping soffites of stair case M2


Staircase 02 as per the Architectural drawings
Waists x 4 No. 1 1 4 3.73 1.20 1.00 17.88
17.88

G Ditto soffites of slab M2


Panel 01; G/L A & B (3-4) 1 1 1 5.65 2.32 1.00 13.11

Panel 02: G/L A&B(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 03: G/L A&B(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 04: G/L B&C(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 05: G/L B&C(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 05: G/L C&D(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 06: G/L C&D(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 07: G/L D&E(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 08: G/L D&E(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 09: G/L E&F(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 10: G/L E&F(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 11: G/L F&G(2-3) 1 1 1 5.60 5.60 1.00 31.36


Panel 12: G/L F&G(3-5) 1 1 1 5.60 11.65 1.00 65.24

Panel 13: Area around the lift shaft 1 1 1 5.60 11.65 1.00 65.24
.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

657.95

Prepare and apply three coats of gloss oil paint on:-

H Metal balustrade and handrails (both sides) M2


Staircase 02 as per the Architectural drawings
Waists x 4 No. 2 2 4 3.73 1.00 0.90 53.65
Landings x 4 2 1 4 0.20 1.00 0.90 1.44
End of landing 2 1 1 1.40 1.00 0.90 2.52

Waists x 4 No. 2 2 4 3.73 1.00 0.25 14.90


Half landings 2 1 2 2.52 1.00 0.25 2.52
75.03

Wall Guards

Providing and fixing 75 x 75 x 2 mm thick acrylic corner guards


(AC) of 1500 mm high as detailed in Architectural Drawing the
exposed masonry corners as specified and directed including
painting with reflective paint.
1 1 8 1.00 1.00 1.00 8.00
8.00

ELEMENT NO. 9

EXTERNAL FINISHINGS

Cement and sand (1:4) rendering to:-

E Walls M2
G/L A(2-5) 1 1 1 18.40 1.00 6.90 126.96
G/L A2-E2 1 1 1 20.72 1.00 6.90 142.97
G/L E(1-2) 1 1 1 3.19 1.00 6.90 22.01
G/L A5-G5 1 1 1 32.50 1.00 6.90 224.25
Deductions
Windows
W15b; louvered windows -1 1 7 3.70 1.00 1.54 (39.89)
W09; glazed windows -1 1 2 1.57 1.00 0.80 (2.50)
W10; glazed windows -1 1 4 1.57 1.00 2.20 (13.77)

Doors
Openings -1 1 1 4.00 1.00 5.25 (21.00)
D9 -1 1 2 0.90 1.00 2.10 (3.78)
Db-17 -1 1 1 3.75 1.00 5.25 (19.69)
415.56

F Concrete surfaces; retaining walls. M2


Sides; retaining walls 1 2 1 33.00 1.00 2.50 165.00
.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
BILL NO. 3: LOWER GROUND FLOOR

Sides; retaining walls 1 2 1 33.00 1.00 1.83 120.78


Sides; retaining walls 1 2 0.5 33.00 1.00 6.42 211.86
497.64

Prepare and apply three coats of weatherguard paint


on:-

H Rendered walls M2
G/L A(2-5) 1 1 1 18.40 1.00 6.90 126.96
G/L A2-E2 1 1 1 20.72 1.00 6.90 142.97
G/L E(1-2) 1 1 1 3.19 1.00 6.90 22.01
G/L A5-G5 1 1 1 32.50 1.00 6.90 224.25
Deductions
Windows
W15b; louvered windows -1 1 7 3.70 1.00 1.54 (39.89)
W09; glazed windows -1 1 2 1.57 1.00 0.80 (2.50)
W10; glazed windows -1 1 4 1.57 1.00 2.20 (13.77)

Doors
Openings -1 1 1 4.00 1.00 5.25 (21.00)
D9 -1 1 2 0.90 1.00 2.10 (3.78)
Db-17 -1 1 1 3.75 1.00 5.25 (19.69)
415.56

1.5mm thick layer of textured decorative paint finishes


I Concrete surfaces/retaining walls M2
Sides; retaining walls 1 2 1 33.00 1.00 2.50 165.00
Sides; retaining walls 1 2 1 33.00 1.00 1.83 120.78
Sides; retaining walls 1 2 0.5 33.00 1.00 6.42 211.86
497.64

Retaining wall coping


Precast concrete grade 25, finished fair on all exposed
surfaces including bedding and jointing in cement sand (1:3)
mortar

B 300mm x 75 mm average thick twice weathered and throated


coping to wall top; 600mm long pre-cast concrete units. M
Sides; retaining walls 1 1 1 33.65 1.00 1.00 33.65
Sides; retaining walls 1 1 1 33.65 1.00 1.00 33.65
67.30

J Supply and fix 50mm diameter x 6mm thick CHS mild steel handrail
plugged with 25mm x 4mm thick mild steel support fixed into
concrete retaining wall; all painting and decorations M
Sides; retaining walls 1 1 1 33.65 1.00 1.00 33.65
Sides; retaining walls 1 1 1 33.65 1.00 1.00 33.65
67.30
.............................................
............................................. .............................................
PROJECT MANAGER
CONTRACTOR'S REPRESENTATIVE PROJECT Q.S
CLIENT: CK COMPANY DATE: 4/5/2024
PROJECT: PROPOSED OFFICE BLOCK CALC BY: IB
LEVEL GROUND FLOOR
MEASUREMENTS PURPOSE: ESTIMATES
NO. DESCRIPTION UNIT EQ. PRTS EQ. PRTS EQ. PRTS L W H/D/kg/m QTY

UPPER GROUND FLOOR

SUPERSTRUCTURE

RC in grade 25 to columns M3

C1 9 1 1 0.40 0.40 3.65 5.26


C2 3 1 1 0.40 0.60 3.65 2.63
C3 3 1 1 0.40 0.60 3.65 2.63
C4 3 1 1 0.40 0.60 3.65 2.63
C5 2 1 1 0.40 0.60 3.65 1.75
C6 1 1 1 0.35 0.35 3.65 0.45
15.34

RC in grade 25 to beams M3
G/L E(1-2) & F(1-2) 1 1 2 3.14 0.40 0.55 1.38
G/L G(1-2) 1 1 1 1.10 0.40 0.55 0.24
G/L A(1-4) 1 1 1 12.45 0.40 0.55 2.74
G/L B,C,D,E,F(2-3) 1 1 5 5.50 0.40 0.55 6.05
G/L G(2-3) 1 1 1 5.60 0.40 0.55 1.23
G/L G(3-5) 1 1 1 11.55 0.40 0.55 2.54
G/L C(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L D(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L E(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L F(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L G(3-4) 1 1 1 5.65 0.40 0.55 1.24
G/L G(4-5) 1 1 1 5.60 0.40 0.55 1.23

G/L A2-B2, A3-B3, A3'-B3', A4-B4 1 1 4 2.32 0.40 0.55 2.04


G/L B2-C2 & B3-C3 1 1 2 5.60 0.40 0.55 2.46
G/L B5-C5 1 1 1 5.50 0.40 0.55 1.21
G/L 2,3 & 5 (C-D) 1 1 3 5.60 0.40 0.55 3.70
G/L 2,3,& 5(D-E) 1 1 3 5.60 0.40 0.55 3.70
G/L 1,2,3 & 5 (E-F) 1 1 4 5.60 0.40 0.55 4.93
G/L F1-G1 1 1 1 2.75 0.40 0.55 0.61
G/L 2,3 & 5 (F-G) 1 1 3 5.59 0.40 0.55 3.69
49.06

RC in grade 25 to the staircase M3


Staircase 01
Steps 1 26 1/2 0.30 0.15 1.50 0.44
Waist 1 1 2 4.36 1.50 0.20 2.62

Staircase 02
Steps 1 26 1/2 0.30 0.15 1.20 0.35
Waist 1 1 2 4.36 1.20 0.20 2.09
5.50
200mm thick to staircase landing M2
Staircase 01
Landing 1 1 1 3.29 1.70 1.00 2.80
Staircase 02
Landing 1 1 1 2.52 1.60 1.00 2.01
4.81

Landing beams M2
Staircase 01
Landing beams 1 1 1 3.89 0.20 0.20 0.08
Staircase 02
Landing beams 1 1 1 3.12 0.20 0.20 0.06
0.14

RC in grade 25 to the lift walls 20mm thick M2


2 1 1 2.45 1.00 3.90 19.11
2 1 1 2.05 1.00 3.90 15.99
Less opening -1 1 1 1.22 1.00 2.10 -2.56
32.54

250mm thick solid slab in RC grade 25 M2


Panel; G/L B&G (2-5) 1 1 1 18.45 30.39 1.00 560.70
Panel; G/L A&B (3-4) 1 1 1 6.45 2.72 1.00 17.54
Panel; G/L F&G (1-2) 1 1 1 3.54 6.75 1.00 23.90
Ddt: Around the lift shaft area -1 1 1 2.45 2.45 1.00 -6.00

Add; beam tops /areas without slabs


G/L A (2-3) 1 1 1 6.00 0.40 1.00 2.40
G/L A1-B1 1 1 1 2.75 0.40 1.00 1.10
G/L E1-F1 1 1 1 6.00 0.40 1.00 2.40
G/L E(1-2) 1 1 1 3.54 0.40 1.00 1.42
603.45

Reinforcements

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Columns 1 1 150 15.34 1.00 1.00 2,300.87
RC in grade 25 to beams 1 1 150 49.06 1.00 1.00 7,359.49
RC in grade 25 to the staircase 1 1 150 5.50 1.00 1.00 824.84
200mm thick to staircase landing 1 1 150 4.81 1.00 1.00 721.28
Landing beams 1 1 150 0.14 1.00 1.00 21.03
RC in grade 25 to the lift walls 20mm thick 1 1 150 32.54 0.20 1.00 976.14
250mm thick solid slab in RC grade 25 1 1 150 603.45 0.25 1.00 22,629.30
34,832.95
Sawn form work to;

Sides of columns M2

C1 9 1 2 0.80 1.00 3.65 52.56


C2 3 1 2 1.00 1.00 3.65 21.90
C3 3 1 2 1.00 1.00 3.65 21.90
C4 3 1 2 1.00 1.00 3.65 21.90
C5 2 1 2 1.00 1.00 3.65 14.60
C6 1 1 2 0.70 1.00 3.65 5.11
137.97

Sides and soffits of beams M2


G/L E(1-2) & F(1-2) 1 1 2 3.14 1.50 1.00 9.42
G/L G(1-2) 1 1 1 1.10 1.50 1.00 1.65
G/L A(1-4) 1 1 1 12.45 1.50 1.00 18.67
G/L B,C,D,E,F(2-3) 1 1 5 5.50 1.50 1.00 41.25
G/L G(2-3) 1 1 1 5.60 1.50 1.00 8.40
G/L G(3-5) 1 1 1 11.55 1.50 1.00 17.33
G/L C(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L D(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L E(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L F(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L G(3-4) 1 1 1 5.65 1.50 1.00 8.48
G/L G(4-5) 1 1 1 5.60 1.50 1.00 8.40

G/L A2-B2, A3-B3, A3'-B3', A4-B4 1 1 4 2.32 1.50 1.00 13.92


G/L B2-C2 & B3-C3 1 1 2 5.60 1.50 1.00 16.80
G/L B5-C5 1 1 1 5.50 1.50 1.00 8.25
G/L 2,3 & 5 (C-D) 1 1 3 5.60 1.50 1.00 25.20
G/L 2,3,& 5(D-E) 1 1 3 5.60 1.50 1.00 25.20
G/L 1,2,3 & 5 (E-F) 1 1 4 5.60 1.50 1.00 33.60
G/L F1-G1 1 1 1 2.75 1.50 1.00 4.13
G/L 2,3 & 5 (F-G) 1 1 3 5.59 1.50 1.00 25.13
334.52

Soffits of the slab 250mm thick M2


4 1 1 5.60 5.60 1.00 125.44
1 1 1 5.59 5.60 1.00 31.28
4 1 1 11.65 5.60 1.00 260.96
1 1 1 11.65 5.59 1.00 65.07
1 1 1 2.50 2.40 1.00 6.00
1 1 1 3.00 2.40 1.00 7.20
1 1 1 1.30 2.40 1.00 3.12
1 1 1 4.20 3.20 1.00 13.44
512.50

soffits of stiracse case landing M2


Staircase 01
Landing 1 1 1 3.29 1.50 1.00 2.47
Staircase 02
Landing 1 1 1 2.52 1.40 1.00 1.76
4.23

Sides and soffits of staircase landing beams M2


Staircase 01
Sides and soffits of staircase landing beams 1 1 1 3.89 0.60 1.00 1.17
Staircase 02
Sides and soffits of staircase landing beams 1 1 1 3.12 0.60 1.00 0.94
2.10

Slopping sofffits of staircase M2


Staircase 01
Waist 1 1 2 4.36 1.50 1.00 13.08

Staircase 02
Waist 1 1 2 4.36 1.20 1.00 10.46
23.55

Risers; 150mm wide


Staircase 01
Steps 1 26 1 1.50 1.00 1.00 19.50

Staircase 02
Steps 1 26 1 1.20 1.00 1.00 15.60
35.10

Sides of the lift walls M2


1 2 2 2.45 1.00 3.90 38.22
1 2 2 2.05 1.00 3.90 31.98
Less: Lift door "unamed" -1 2 1 1.22 1.00 2.10 -5.12
65.08

Edges of the slab 250mm wide M


Panel; G/L B&G (2-5) 1 1 2 21.99 1.00 1.00 43.98
Panel; G/L A&B (3-4) 1 1 2 33.10 1.00 1.00 66.20

G/L A (2-3) 1 1 2 6.00 1.00 1.00 12.00


G/L A1-B1 1 1 2 2.75 1.00 1.00 5.50
G/L E1-F1 1 1 2 6.00 1.00 1.00 12.00
G/L E(1-2) 1 1 2 3.54 1.00 1.00 7.08
146.76
Edges of the staircase landing 200mm wide M
Staircase 01; girth computed 1 1 1 6.98 1.00 1.00 6.98
Staircase 02; ditto 1 1 1 5.72 1.00 1.00 5.72
12.70

open springer of stairacse; 350mm high max M


Staircase 01
Waist 1 2 2 4.36 1.00 1.00 17.44

Staircase 02
Waist 1 2 2 4.36 1.00 1.00 17.44
34.88

ELEMENT NO. 2

BILL NO.2

ELEMENT NO. 4

EXTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties
set in horizontal alternate courses:

A 300mm thick M2

1 1 1 6.60 1.00 3.10 20.46


1 1 2 2.72 1.00 3.10 16.83
1 1 1 11.80 1.00 3.10 36.58
2 1 1 27.74 1.00 3.10 171.96
1 1 2 2.95 1.00 3.10 18.29
1 1 1 3.49 1.00 3.10 10.82
2 1 1 18.40 1.00 3.10 114.08
Deductions
Openings at the entrance/front -3 1 1 3.70 1.00 3.10 -34.41
Openings at the entrance/sides -1 1 1 1.44 1.00 3.10 -4.46
Openings -1 1 1 3.40 1.00 2.65 -9.01

Wg-05 1600x2200 -1 1 2 1.60 1.00 2.65 -8.48


Wg-07 1565x2200 -1 1 1 1.57 1.00 2.20 -3.44
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -4 1 1 1.57 1.00 2.20 -13.77
Wg-7 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89

Type 4 (ext) 1600x2650 -1 1 1 1.60 1.00 2.65 -4.24


Type 4 (ext) 1600x2650 -1 1 1 1.60 1.00 2.65 -4.24
Type 6 (ext) 1500x2650 -1 1 1 1.50 1.00 2.20 -3.30
Type 13 (ext) 1600x2650 -1 1 1 1.60 1.00 2.65 -4.24
244.33

Reinforced Insitu concrete grade 25 in:-


Moulded concrete window Sill; Section size 250 x 85 x 50mm;
C M
weathered and throated; all as per Architect's details

Wg-05 1600x2200 2 1 1 1.90 1.00 1.00 3.80


Wg-07 1565x2200 1 1 1 1.87 1.00 1.00 1.87
Wg-10 1565x2200 2 1 1 1.87 1.00 1.00 3.73
Wg-10 1565x2200 2 1 1 1.87 1.00 1.00 3.73
Wg-10 1565x2200 2 1 1 1.87 1.00 1.00 3.73
Wg-10 1565x2200 2 1 1 1.87 1.00 1.00 3.73
Wg-10 1565x2200 2 1 1 1.87 1.00 1.00 3.73
Wg-10 1565x2200 2 1 1 1.87 1.00 1.00 3.73
Wg-10 1565x2200 2 1 1 1.87 1.00 1.00 3.73
Wg-10 1565x2200 4 1 1 1.87 1.00 1.00 7.46
Wg-7 1565x2200 2 1 1 1.87 1.00 1.00 3.73
42.96

Reinforced concrete grade 25 in:-


A Lintels M2
Windows
Wg-05 1600x2200 2 1 1 1.90 0.30 0.30 0.34
Wg-07 1565x2200 1 1 1 1.87 0.30 0.30 0.17
Wg-10 1565x2200 2 1 1 1.87 0.30 0.30 0.34
Wg-10 1565x2200 2 1 1 1.87 0.30 0.30 0.34
Wg-10 1565x2200 2 1 1 1.87 0.30 0.30 0.34
Wg-10 1565x2200 2 1 1 1.87 0.30 0.30 0.34
Wg-10 1565x2200 2 1 1 1.87 0.30 0.30 0.34
Wg-10 1565x2200 2 1 1 1.87 0.30 0.30 0.34
Wg-10 1565x2200 2 1 1 1.87 0.30 0.30 0.34
Wg-10 1565x2200 4 1 1 1.87 0.30 0.30 0.67
Wg-7 1565x2200 2 1 1 1.87 0.30 0.30 0.34
Doors
Type 4 (ext) 1600x2650 1 1 1 1.90 0.30 0.30 0.17
Type 4 (ext) 1600x2650 1 1 1 1.90 0.30 0.30 0.17
Type 6 (ext) 1500x2650 1 1 1 1.80 0.30 0.30 0.16
Type 13 (ext) 1600x2650 1 1 1 1.90 0.30 0.30 0.17

Openings

Less openings at the veradanh 3 1 1 4.70 0.30 0.50 2.11


1 1 1 1.74 0.30 0.30 0.16
6.81

Sawn formwork to:-

Windows
Wg-05 1600x2650 2 1 1 1.90 0.90 1.00 3.42
Wg-07 1565x2200 1 1 1 1.87 0.90 1.00 1.68
Wg-10 1565x2200 2 1 1 1.87 0.90 1.00 3.36
Wg-10 1565x2200 2 1 1 1.87 0.90 1.00 3.36
Wg-10 1565x2200 2 1 1 1.87 0.90 1.00 3.36
Wg-10 1565x2200 2 1 1 1.87 0.90 1.00 3.36
Wg-10 1565x2200 2 1 1 1.87 0.90 1.00 3.36
Wg-10 1565x2200 2 1 1 1.87 0.90 1.00 3.36
Wg-10 1565x2200 2 1 1 1.87 0.90 1.00 3.36
Wg-10 1565x2200 4 1 1 1.87 0.90 1.00 6.71
Wg-7 1565x2200 2 1 1 1.87 0.90 1.00 3.36
Doors
Type 4 (ext) 1600x2650 1 1 1 1.90 0.90 1.00 1.71
Type 4 (ext) 1600x2650 1 1 1 1.90 0.90 1.00 1.71
Type 6 (ext) 1500x2650 1 1 1 1.80 0.90 1.00 1.62
Type 13 (ext) 1600x2650 1 1 1 1.90 0.90 1.00 1.71

Openings

Less openings at the veradanh 3 1 1 4.70 1.30 1.00 18.33


1 1 1 1.74 0.90 1.00 1.57
65.31
High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Lintels 1 1 150 6.81 1.00 1.00 1,022.02
1,022.02

BILL NO.2

ELEMENT NO. 5

INTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties
set in horizontal alternate courses:

A 300mm thick walls M2


G/L E2-F'2 1 1 1 5.82 1.00 3.10 18.04
Deductions ; doors
Dg-01 1 1 2 1.65 1.00 2.65 8.75
26.79

A 200mm thick Wall M2

G/L E2-F'2 1 1 1 8.87 1.00 3.10 27.50


G/L F3-F'3 1 1 1 2.36 1.00 3.65 8.61
G/L C(1-3') 1 1 1 9.71 1.00 3.65 35.44
Toilet partition (main) 1 1 1 8.55 1.00 3.65 31.21
G/L B(1-3') & Toilet partition (main) 1 1 1 8.55 1.00 3.10 26.51
Partitions - Toilets FF 1 1 1 3.60 1.00 3.65 13.14
Partitions - Toilets M 1 1 1 2.80 1.00 3.65 10.22
Partitions - Toilets FF 1 1 1 1.80 1.00 3.65 6.57
Duct close to spirit shop 1 1 1 2.00 1.00 3.65 7.30
Duct close to spirit shop 1 1 2 0.50 1.00 3.65 3.65

Ddt opening
Type 03 1800x2650; Dg-03 -1 1 1 1.80 1.00 2.65 -4.77
Type 16 500x2650 Dg-16 -1 1 2 0.50 1.00 2.65 -2.65

Type 12 800x2100; Dg-12 -1 1 5 0.80 1.00 2.10 -8.40


Type 15 700x2650; Dg-15 -1 1 2 0.70 1.00 2.65 -3.71
150.61

A 150mm thick walls M2


Toilet partitions 1 1 3 1.80 1.00 3.65 19.71
Duct in the toilet 1 1 1 1.50 1.00 3.65 5.48
Urinal partitions 1 1 3 0.50 1.00 3.65 5.48
Toilet entrance walls 1 1 2 1.65 1.00 3.65 12.05
Toilet entrance walls 1 1 2 1.25 1.00 3.65 9.13
Partition between the hallway and toilets 1 1 1 9.32 1.00 3.65 34.02
Deductions ; doors
Type 15 700x2650; Dg-15 -1 1 1 0.70 1.00 2.65 -1.85
Openings to the toilets -1 1 2 0.90 1.00 2.65 -4.77
Dg-11 -1 1 3 1.00 1.00 2.65 -7.95
71.27

C Drywall, aluminum partitioning 3650mm high M2


G/L E(1-4) 1 1 1 11.84 1.00 3.65 43.22
Paritition (Meeting room & IT server room) 1 1 1 9.71 1.00 3.65 35.44
Paritition (Offices/Sales/Offices) 1 1 2 5.84 1.00 3.65 42.63
Paritition (Spirits shop/Office) 1 1 1 5.34 1.00 3.65 19.49
Paritition (Hallway/Meeting/IT) 1 1 1 11.04 1.00 3.65 40.30
G/L B4-F'4 1 1 1 26.84 1.00 3.65 97.97
Paritition (Reception/lobby) 1 1 1 6.21 1.00 3.65 22.67
Deductions ; doors
Dg-02; -1 1 1 2.70 1.00 2.40 -6.48
Dg-05; -1 1 1 1.50 1.00 2.40 -3.60
Dg-10; -1 1 5 1.00 1.00 2.65 -13.25
Dg-11; -1 1 1 1.00 1.00 2.65 -2.65
275.73

Reinforced concrete grade 25 in:-


A Lintels M
1800x2650; Dg-03 1 1 1 2.10 0.30 0.30 0.19
500x2650 Dg-16 1 1 2 1.80 0.30 0.30 0.32

800x2100; Dg-12 1 1 5 1.10 0.30 0.30 0.50


700x2650; Dg-15 1 1 2 1.00 0.30 0.30 0.18

Deductions ; doors
700x2650; Dg-15 1 1 1 1.00 0.20 0.30 0.06
Openings to the toilets 1 1 2 1.20 0.20 0.30 0.14
Dg-11 1 1 3 1.30 0.20 0.30 0.23

Deductions ; doors
Dg-02; 1 1 1 3.30 0.15 0.30 0.15
Dg-05; 1 1 1 1.80 0.15 0.30 0.08
Dg-10; 1 1 5 1.30 0.15 0.30 0.29
Dg-11; 1 1 1 1.30 0.15 0.30 0.06
2.21

Sawn formwork to:-


Sides and soffites of lintels
1800x2650; Dg-03 1 1 1 2.10 0.90 1.00 1.89
500x2650 Dg-16 1 1 2 1.80 0.90 1.00 3.24

800x2100; Dg-12 1 1 5 1.10 0.90 1.00 4.95


700x2650; Dg-15 1 1 2 1.00 0.90 1.00 1.80

Deductions ; doors
700x2650; Dg-15 1 1 1 1.00 0.80 1.00 0.80
Openings to the toilets 1 1 2 1.20 0.80 1.00 1.92
Dg-11 1 1 3 1.30 0.80 1.00 3.12

Deductions ; doors
Dg-02; 1 1 1 3.30 0.75 1.00 2.47
Dg-05; 1 1 1 1.80 0.75 1.00 1.35
Dg-10; 1 1 5 1.30 0.75 1.00 4.88
Dg-11; 1 1 1 1.30 0.75 1.00 0.98
27.40

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Deductions ; doors 1 1 150 2.21 1.00 1.00 330.97
330.97

ELEMENT NO. 5
INTERNAL WALING

BILL NO.2

ELEMENT NO. 6

WINDOWS, SCREENS AND LIGHTS

Anodized Aluminum casement windows. The color shall be to


client's approval; all additional costs are deemed included.

Provide and fix purpose-made anodized aluminum windows


and window frames complete with 5mm thick translucent
glass and single glazing, glazing beads, wash leather strips,
sealing, burglar proofing, fly mesh, all ironmongery and
accessories; fixing to blockwork or concrete; all as per
Architect's drawings; Drawing No. NA(22)02-9/10; in:

The contractor is expected to prepare and submit shop


drawings for approval prior to fabrication and erection of the
windows and screens
A Glazed window and window frames size: 1600 mm wide x 2650
mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [Wg-05] No 2.00

B Glazed window and window frames size: 1565 mm wide x 2200


mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [Wg-07] No 3.00

B Glazed window and window frames size: 1565 mm wide x 2200


mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [Wg-10] No 18.00

Reinforced Insitu concrete grade 25 in:-

Moulded concrete window Sill; Section size 350 x 85 x 50mm;


weathered and throated; all as per Architect's details
Glazed window and window frames size: 1600 mm wide x 2650
mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [Wg-05] 1 1 2 1.90 1.00 1.00 3.80
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [Wg-07] 1 1 3 1.87 1.00 1.00 5.60
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [Wg-10] 1 1 18 1.87 1.00 1.00 33.57
42.97

Window boards

Natural Stone Granite Window Board; size 150mm wide x 20mm


thick thick; all edges well finished with a coved mould; all as per
Architect's details
Glazed window and window frames size: 1600 mm wide x 2650
mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [Wg-05] 1 1 2 1.60 1.00 1.00 3.20
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [Wg-07] 1 1 3 1.57 1.00 1.00 4.71
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [Wg-10] 1 1 18 1.57 1.00 1.00 28.26
36.17

BILL NO.2
ELEMENT NO. 7

DOORS

DOORS, SHUTTERS AND HATCHES

Timber doors

The following in wrot hardwood to architect's satisfaction:-

Approved hardwood flush doors

A 45mm thick solid core timber flush door shutter size 800mm wide x
2100 mm high complete with a mahogany veneer; to Architect's
detail; door type [Dg-12] No
1 1 5 1.00 1.00 1.00 5.00
5.00

Approved hardwood panelled doors;

A 45mm thick solid panelled door shutter size 1000mm wide x


2100mm high complete with 2 No. vision panels size 200mm wide
x 1000mm high; to Architect's detail; door type [Dg-11] No
1 1 4 1.00 1.00 1.00 4.00
4.00

Door frames and finishings in in wrot hardwood

C 250mm x 50mm rebated frame M


Db-12 1 1 5 5.00 1.00 1.00 25.00
Db-11 1 1 4 6.30 1.00 1.00 25.20
Opening to toilet 1 1 2 6.20 1.00 1.00 12.40
62.60

C Ditto transomes M
Db-11 1 1 4 1.00 1.00 1.00 4.00
Opening to toilet 1 1 2 0.90 1.00 1.00 1.80
5.80

D 40mm x 20mm Splayed architrave or qudrant beads where


applicable. M
Db-12 1 2 5 5.00 1.00 1.00 50.00
Db-11 1 2 4 6.30 1.00 1.00 50.40
Opening to toilet 1 2 2 6.20 1.00 1.00 24.80
125.20
D 20mm x 20mm moulded glazing beads. M
Db-11 1 2 4 3.10 1.00 1.00 24.80
Db-11 - Vision panels 2 2 4 2.40 1.00 1.00 38.40
Opening to toilet 1 2 2 2.00 1.00 1.00 8.00
71.20

Ironmongery to architect's approval and sartisfaction

E 100mm Pressed steel butt hinges Pr


1 1 5 1.50 1.00 1.00 7.50
Db-11 1 1 4 1.50 1.00 1.00 6.00
13.50

F 25mm diameter rubber door stop plugged to wall/floor No


1 1 31 1.00 1.00 1.00 31.00
31.00

H 3 - Lever motrice lock complete with approved door handles No


Db-11 1 1 4 1.00 1.00 1.00 4.00
4.00

H Commercial privacy Lock complete with occupancy indicator Oil


rubbed bronze and Lock restroom hardware brass door handles No
Db-12 1 1 5 1.00 1.00 1.00 5.00
5.00

I Coat hooks No
1 1 5 1.00 1.00 1.00 5.00
5.00

J Door closer No
1 1 14 1.00 1.00 1.00 14.00
14.00

K Mild steel aldrop bolt complete with all the necessary accessories No
1 1 5 1.00 1.00 1.00 5.00
5.00

L Stainless Steel Push plate size 300mm x 100mm No


1 2 5 1.00 1.00 1.00 10.00
1 2 4 1.00 1.00 1.00 8.00
18.00

M Stainless Steel kick plate size 800mm wide x 150mm high x 3mm
thick No
1 2 5 1.00 1.00 1.00 10.00
10.00

M Stainless Steel kick plate size 1000mm wide x 150mm high x 3mm
thick No
1 2 4 1.00 1.00 1.00 8.00
8.00

O Symbol (Male) No
1 1 1 1.00 1.00 1.00 1.00
1.00

B Symbol (Female) No
1 1 1 1.00 1.00 1.00 1.00
1.00

B Sign - Base is 5mm thick Acrylic plate PU Coated with Silver Pan-
tone PU color
Content - Logo & Artwork to be in Plotter cut High Grade Vinyl .
Vinyl to match approved pan-tone (Blue 2935C) and Black color
Bubble free Glossy Lacquer Coating to be done after Vinyl Pasting.
Size : 300 MM X 75 MM
Location : Room Doors
Sided – Single sided
Fixing - Fixing of Sign with Reverse Screws

No
1 1 15 1.00 1.00 1.00 15.00
15.00

Glazing

5mm thick clear sheet glass fixed to hardwood frames with


glazing beads (measured seperately)
Db-11 - Vent 1 1 4 1.00 0.55 1.00 2.20
Db-11 - Vision panel 1 2 4 1.00 0.20 1.00 1.60
3.80

Steel casement doors; mild steel

Supply and Fix the following purpose made mild steel door
and door frames; all members in 3mm thick steel sections
complete with mild steel frame, hinges, fixing lugs, locking
device and a single coat of red oxide primer, all fixed as per
Architect's details and satisfaction

D Louvered door set; size 1600 mm wide x 2650 mm high; complete


with 2 louvered door shutters; door type [Dg-13]
No 1.00
D Louvered door set; size 700 mm wide x 2650 mm high; door type
[Dg-15]
No 3.00

D Louvered door set; size 500mm wide x 2650 mm high; complete


with 1 louvered door shutters; door type [Dg-16]
No 2.00

Anodised aluminium doors

Supply and fix purpose-made anodised aluminium casement


doors and frames; complete with 6mm thick translucent glass
and single glazing, ironmongery, fixing lugs, all accessories
and one coat of red oxide primer before delivery; fixing to
blockwork or concrete; all as per Architect's drawings;
Drawing No. NA(22)02-9/10; in:

Folding door set; size 1600 mm wide x 2650 mm high; complete as


per the Architect's details; door type [Db-01] 2.00

Sliding door set; size 2700 mm wide x 2400 mm high; complete as


per the Architect's details; door type [Db-02] 1.00

Door set; size 1800 mm wide x 2650 mm high; complete as per the
Architect's details; door type [Db-03] 1.00

Door set; size 1600mm wide x 2650 mm high; complete as per the
Architect's details; door type [Db-04] 2.00

Door set; size 1500mm wide x 2650 mm high; complete with 6mm
thick frosted glass; as per the Architect's details; door type [Db-05]
1.00

Door set; size 1500mm wide x 2650 mm high; complete as per the
Architect's details; door type [Db-06] 1.00

Door set; size 100mm wide x 2650 mm high; complete as per the
Architect's details; door type [Db-10] 5.00
Prepare and apply undercoat and three coats of gloss oil paint
on:-

I General surfaces of metal M2


Louvered door set; size 1600 mm wide x 2650 mm high; complete
with 2 louvered door shutters; door type [Dg-13] 1 2 1 1.60 1.00 2.65 8.48
Louvered door set; size 700 mm wide x 2650 mm high; door type
[Dg-15] 1 2 3 0.70 1.00 2.65 11.13
Louvered door set; size 500mm wide x 2650 mm high; complete
with 1 louvered door shutters; door type [Dg-16] 1 2 2 0.50 1.00 2.65 5.30
24.91

J General surfaces of wood M2


Wood frames; girth exceeding 300mm wide; 350mm wide
250mm x 50mm rebated frame 1 1 1 62.60 0.35 1.00 21.91
Ditto transomes 1 1 1 5.80 0.60 1.00 3.48
Door shutters; Db-12 1 2 5 0.85 2.15 1.00 18.28
Door shutters; Db-11 1 2 4 1.05 2.15 1.00 18.06
61.72

K Wood surfaces not exceeding 100mm girth M


40mm x 20mm Splayed architrave or qudrant beads where
applicable. 1 1 1 125.20 1.00 1.00 125.20
20mm x 20mm moulded glazing beads 1 1 1 71.20 1.00 1.00 71.20
196.40

ELEMENT NO. 7
DOORS 2/7/2

BILL NO.2

ELEMENT NO. 8

INTERNAL FINISHINGS

Floor screed; Cement and sand (1:4); wood floated finish:

A 40mm thick; to receive procelain floor tiles (measured separately) M2


Verandah
Verandah 1 1 1 17.80 2.65 1.00 47.17
Entrance points 1 1 3 4.00 0.30 1.00 3.60
Entrance points 1 1 1 1.74 0.30 1.00 0.52
Duct doors/telecoms 1 1 1 1.60 0.30 1.00 0.48
Lobby entrance 1 1 1 3.70 0.30 1.00 1.11
Dg-04 1 1 2 1.60 0.30 1.00 0.96
Reception
Reception 1 1 1 5.95 6.34 1.00 37.66

Entrance lobby
Entrance lobby; measurements include areas beneath the
partitions 1 1 1 6.02 8.87 1.00 53.35
Add: Dg-4 door way 1 1 1 1.60 0.20 1.00 0.32

Spirits store
Spirits store 1 1 1 5.84 8.87 1.00 51.80
Add: duct door Dg-16 1 1 1 0.50 0.20 1.00 0.10
Less: duct -1 1 1 0.93 0.50 1.00 -0.46
Add: Dg-4 door way 1 1 1 1.60 0.20 1.00 0.32

Staircase/lift lobby area


Staircase/lift lobby area 1 1 1 3.29 8.87 1.00 29.18
Add: Dg-3 door way 1 1 1 1.80 0.20 1.00 0.36

Meeting room/office/hall-way/IT serverroom/


Meeting room/office/hall-way/IT serverroom/ 1 1 1 17.80 11.17 1.00 198.74
Add: duct door Dg-16 1 1 1 0.50 0.20 1.00 0.10

Dining/Hallway
Dining/Hallway 1 1 1 9.11 6.80 1.00 61.91
Less: wall portion enroaching -1 1 1 1.15 0.20 1.00 -0.23
Add: Dg-11 1 1 2 1.00 0.20 1.00 0.40
Add: Dg-6 1 1 1 1.50 0.20 1.00 0.30

Hallway extension towards the balcony 1 1 1 2.72 3.10 1.00 8.42


Add: Dg-11 to staircase 02 1 1 2 1.00 0.20 1.00 0.40

Staircase-02 lobby
Staircase-02 lobby 1 1 1 4.20 2.52 1.00 10.58

Toilets/entrance lobby
Toilets/entrance lobby 1 2 2 1.60 1.10 1.00 7.04
Openings to toilets 1 2 1 1.00 0.15 1.00 0.30

Female toilet/lobby
Female toilet/lobby 1 1 1 3.60 6.55 1.00 23.58
Less: lobby area already measured -1 1 1 1.25 1.75 1.00 -2.19
Add; door ways Dg-12 1 1 3 0.80 0.20 1.00 0.48

Female Toilets /3
Female Toilets /3 1 1 2 1.80 1.00 1.00 3.60
Female Toilets /3 1 1 1 1.50 1.15 1.00 1.72
Add; door ways Dg-15 1 1 1 0.70 0.20 1.00 0.14

Male toilet/lobby
Male toilet/lobby 1 1 1 2.80 6.55 1.00 18.34
Less; urinal partition walls -1 1 3 0.50 0.15 1.00 -0.22
Less: lobby area already measured -1 1 1 1.25 1.75 1.00 -2.19
Add; door ways Dg-12 1 1 1 0.80 0.20 1.00 0.16
Add; door ways Dg-15 1 1 2 0.70 0.20 1.00 0.28

Toilets and duct


Toilets and duct 1 1 2 1.80 1.00 1.00 3.60
Toilets and duct 1 1 1 1.80 0.60 1.00 1.08
562.82

40mm thick; to receive quarry floor tiles (measured separately)

Balcony
Balcony 1 1 1 6.00 2.72 1.00 16.29

16.29
D Ditto; on staircase landings ditto M2
Staircase 01
Landing 1 1 1 3.29 1.50 1.00 2.47
Staircase 02
Landing 1 1 1 2.52 1.40 1.00 1.76
4.23

E Ditto; on treads 300mm wide ditto M


Staircase 01
Steps 1 26 1 1.50 1.00 1.00 19.50

Staircase 02
Steps 1 26 1 1.20 1.00 1.00 15.60
35.10

F Ditto; to risers 150 mm high ditto M


Staircase 01
Steps 1 26 1 1.50 1.00 1.00 19.50

Staircase 02
Steps 1 26 1 1.20 1.00 1.00 15.60
35.10

G Ditto; to stringer 375mm wide (maximum) M


Staircase 01
Waist 1 2 2 4.36 1.00 1.00 17.44

Staircase 02
Waist 1 2 2 4.36 1.00 1.00 17.44
34.88

H Skirting; edge of landings M


Staircase 01
Landings 1 1 1 3.29 1.00 1.00 3.29
Landings 1 1 2 1.50 1.00 1.00 3.00
Staircase 02
Landings 1 1 1 2.52 1.00 1.00 2.52
Landings 1 1 2 1.20 1.00 1.00 2.40
11.21

J Ditto; to receive skirting; 100mm high ditto M


Verandah 1 1 2 20.45 1.00 1.00 40.90
Entrance points/openings -1 1 3 4.00 1.00 1.00 -12.00
Entrance points/openings -1 1 1 1.74 1.00 1.00 -1.74
Duct doors/telecoms -1 1 1 1.60 1.00 1.00 -1.60
Lobby entrance/opening -1 1 1 3.70 1.00 1.00 -3.70
Dg-04 -1 1 2 1.60 1.00 1.00 -3.20
Opening/edges 1 2 8 0.30 1.00 1.00 4.80

Reception
Reception 1 1 1 6.21 1.00 1.00 6.21
Reception 1 1 1 6.02 1.00 1.00 6.02
Less: Dg-1 -1 1 2 1.60 1.00 1.00 -3.20

Entrance lobby
Entrance lobby; measurements include areas beneath the
partitions 1 1 2 6.02 1.00 1.00 12.03
Entrance lobby; measurements include areas beneath the
partitions 1 1 2 2.66 1.00 1.00 5.32
Less: Dg-3 door way -1 1 1 1.80 1.00 1.00 -1.80
Less: Dg-1 1 1 2 1.60 1.00 1.00 3.20
Lobby entrance/opening -1 1 1 3.70 1.00 1.00 -3.70

Spirits store
Spirits store 1 1 1 6.34 1.00 1.00 6.34
Spirits store 1 1 1 8.87 1.00 1.00 8.87
Less; Duct door Dg-16 -1 1 1 0.50 1.00 1.00 -0.50
Less; Dg-04 -1 1 1 1.60 1.00 1.00 -1.60

Staircase/lift lobby area


Staircase/lift lobby area 1 1 2 3.29 1.00 1.00 6.58
Staircase/lift lobby area 1 1 2 8.87 1.00 1.00 17.74
Less: Dg-3 door way -1 1 1 1.80 1.00 1.00 -1.80
Less: Lift door -1 1 1 1.20 1.00 1.00 -1.20
Add: FHR area/sides -1 1 2 0.60 1.00 1.00 -1.20

Meeting room/office/hall-way/IT serverroom/


Meeting room/office/hall-way/IT serverroom/ 1 1 2 11.17 1.00 1.00 22.34
Meeting room/office/hall-way/IT serverroom/ 1 1 1 9.84 1.00 1.00 9.84
Add: duct area 1 1 1 0.70 1.00 1.00 0.70
Less: Dg-3 door way -1 1 1 1.80 1.00 1.00 -1.80

Dining/Hallway
Dining/Hallway 1 1 2 6.80 1.00 1.00 13.60
Dining 1 1 1 5.97 1.00 1.00 5.97
Less: Dg-6 -1 1 1 1.50 1.00 1.00 -1.50
Less: Dg-11 -1 1 2 1.00 1.00 1.00 -2.00

Hallway extension towards the balcony 1 1 2 2.72 1.00 1.00 5.43


Hallway extension towards the balcony 1 1 1 3.10 1.00 1.00 3.10
Less: Dg-11 -1 1 1 1.00 1.00 1.00 -1.00

Staircase-02 lobby
Staircase-02 lobby 1 1 2 4.20 1.00 1.00 8.40
Staircase-02 lobby 1 1 1 2.52 1.00 1.00 2.52
Less: Dg-11 -1 1 1 1.00 1.00 1.00 -1.00

Toilets/entrance lobby
Toilets/entrance lobby 1 2 2 1.60 1.00 1.00 6.40
Toilets/entrance lobby 1 2 2 1.10 1.00 1.00 4.40
Openings to toilets -1 2 1 1.00 1.00 1.00 -2.00
Less: Dg-11 -1 1 2 1.00 1.00 1.00 -2.00

Female toilet/lobby
Female toilet/lobby 1 1 0 3.60 1.00 1.00 0.00
Female toilet/lobby 1 1 0 6.55 1.00 1.00 0.00
Openings to toilets -1 1 0 1.00 1.00 1.00 0.00
Dg-12 -1 1 0 0.80 1.00 1.00 0.00

Female Toilets /3
Female Toilets /3 1 1 0 1.80 1.00 1.00 0.00
Female Toilets /3 1 1 0 1.00 1.00 1.00 0.00
Dg-12 -1 1 0 0.80 1.00 1.00 0.00

Female Toilets /3 1 1 0 1.50 1.00 1.00 0.00


Female Toilets /3 1 1 0 1.15 1.00 1.00 0.00
Dg-12 -1 1 0 0.80 1.00 1.00 0.00
Add; door ways Dg-15 -1 1 0 0.70 1.00 1.00 0.00

Male toilet/lobby
Male toilet/lobby 1 1 0 2.80 1.00 1.00 0.00
Male toilet/lobby 1 1 0 6.55 1.00 1.00 0.00
Openings to toilets -1 1 0 1.00 1.00 1.00 0.00
Dg-12 -1 1 0 0.80 1.00 1.00 0.00

Add; urinal partition walls 1 2 0 0.68 1.00 1.00 0.00


Add; door ways Dg-15 -1 1 0 0.70 1.00 1.00 0.00

Toilets and duct


Toilets and duct 1 2 0 1.80 1.00 1.00 0.00
Toilets and duct 1 2 0 1.00 1.00 1.00 0.00
Toilets and duct 1 1 0 1.80 1.00 1.00 0.00
Toilets and duct 1 1 0 0.60 1.00 1.00 0.00
Add; door ways Dg-15 -1 1 0 0.70 1.00 1.00 0.00
Dg-12 -1 1 0 0.80 1.00 1.00 0.00

To receive quarry tiles


Balcony
Balcony 1 1 1 6.00 1.00 1.00 6.00
Balcony 1 1 1 2.72 1.00 1.00 2.72
Dg-06 -1 1 1 1.50 1.00 1.00 -1.50
159.38

Supply and Fix approved ceramic tiles; non-slip; laid in an


approved pattern; bedded in approved adhesive cement and
pointed with an approved tile grout

M Size 450 x 450 x 10 mm thick to floors M2


1 1 1 562.82 1.00 1.00 562.82
562.82

D Ditto; on staircase landings ditto M2


Staircase 01 & 02 1 1 1 4.23 1.00 1.00 4.23

4.23

E Ditto; on treads 275mm wide ditto M


Staircase 01 & 02 1 1 35.10 1.00 1.00 1.00 35.10

35.10

F Ditto; to risers 150 mm high ditto M


Staircase 01 & 02 1 1 35.10 1.00 1.00 1.00 35.10

35.10

G Ditto; to stringer 375mm wide (maximum) M


Staircase 01 & 02 1 1 34.88 1.00 1.00 1.00 34.88

34.88

H Edge of staircase landing; 200mm wide M


Staircase 01 & 02 1 1 2 4.80 1.00 1.00 9.60

9.60

J Ditto; to receive skirting; 100mm high ditto M


1 1 1 152.16 1.00 1.00 152.16
152.16

Quarry tiles

150x150x6mm thick tiles


1 1 1 16.29 1.00 1.00 16.29
16.29

J Ditto; to receive skirting; 100mm high ditto M


1 1 1 7.22 1.00 1.00 7.22
7.22

WATERPROOFING TO TOILETS and OTHER WET AREAS

Pure crystalline water proofing treatment in two coats using


"Vandex Super" manufactured by M/s. Vandex East Africa Limited
or approved equivalent to vertical and horizontal surfaces, with
proper gradient including surface preparation and applying slurry
coat of Vandex Super mixed with a cement sand mortar 1:3,
cleaning , pre-watering and then applying two coats of Vandex
Super (each coat approx. 0.75 kg per Sm) mixed to a slurry
consistency, curing, protecting the completed work by hessian
cloth, providing bonding keys for each coat, fillets, testing for water
tightness complete all as per manufacturer's specifications,
drawings and as directed by the Project Manager on:

To wet areas
48.39

WALL FINISHES

Wall Tile backing

Screed backing to wall; Cement and sand (1:4); wood floated


finish:
C 12mm thick; to receive ceramic wall tiles (measured separately) M2
Wall tiles

Female toilet/lobby
Female toilet/lobby 1 1 2 3.60 1.00 2.10 15.12
Female toilet/lobby 1 1 2 6.55 1.00 2.10 27.51
Openings to toilets -1 1 1 1.00 1.00 2.10 -2.10
Dg-12 -1 1 3 0.80 1.00 2.10 -5.04

Female Toilets /3
Female Toilets /3 1 1 2 1.80 1.00 2.10 7.56
Female Toilets /3 1 1 2 1.00 1.00 2.10 4.20
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36

Female Toilets /3 1 1 2 1.50 1.00 2.10 6.30


Female Toilets /3 1 1 2 1.15 1.00 2.10 4.83
Dg-12 -1 1 1 0.80 1.00 2.10 -1.68
Add; door ways Dg-15 -1 1 1 0.70 1.00 2.10 -1.47

Male toilet/lobby
Male toilet/lobby 1 1 2 2.80 1.00 2.10 11.76
Male toilet/lobby 1 1 2 6.55 1.00 2.10 27.51
Openings to toilets -1 1 1 1.00 1.00 2.10 -2.10
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36

Add; urinal partition walls 1 2 3 0.65 1.00 2.10 8.19


Add; door ways Dg-15 -1 1 2 0.70 1.00 2.10 -2.94

Toilets and duct


Toilets and duct 1 2 2 1.80 1.00 2.10 15.12
Toilets and duct 1 2 2 1.00 1.00 2.10 8.40
Toilets and duct 1 1 2 1.80 1.00 2.10 7.56
Toilets and duct 1 1 2 0.60 1.00 2.10 2.52
Add; door ways Dg-15 -1 1 2 0.70 1.00 2.10 -2.94
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36
Deductions
Generally deduct the windows for the washrooms
Wg-10 -1 1 2 1.57 1.00 1.20 -3.76
114.47

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm


second coat of cement and lime putty (1:10); steel trowelled
to:

D Walls M2
Verandah 1 1 2 20.45 1.00 3.65 149.29
Entrance points/openings -1 1 3 4.00 1.00 3.10 -37.20
Entrance points/openings -1 1 3 1.74 1.00 3.10 -16.18
Duct doors/telecoms; Dg-13 -1 1 1 1.60 1.00 2.65 -4.24
Lobby entrance/opening -1 1 1 3.70 1.00 3.65 -13.51
Dg-04 -1 1 2 1.60 1.00 2.65 -8.48
Add: Reveals and jambs
Doors and openings
Entrance points/openings 1 1 3 10.20 0.30 1.00 9.18
Entrance points/openings 1 1 3 7.94 0.30 1.00 7.15
Duct doors/telecoms; Dg-13 1 1 1 6.90 0.30 1.00 2.07
Lobby entrance/opening 1 1 1 11.00 0.30 1.00 3.30
Dg-04 1 1 2 6.90 0.30 1.00 4.14
Windows
Wg-05 1 1 2 6.90 0.30 1.00 4.14

Reception
Reception 1 1 1 6.21 1.00 3.65 22.67
Reception 1 1 1 6.02 1.00 3.65 21.97
Less: Dg-1 -1 1 2 1.60 1.00 2.65 -8.48
Add: Reveals and jambs
Doors and openings
Less: Dg-1 1 1 2 1.60 0.20 1.00 0.64

Entrance lobby
Entrance lobby; measurements include areas beneath the
partitions 1 1 2 6.02 1.00 3.65 43.91
Entrance lobby; measurements include areas beneath the
partitions 1 1 2 2.66 1.00 3.65 19.42
Dg-3 door way -1 1 1 1.80 1.00 2.65 -4.77
Dg-1 1 1 2 1.60 1.00 2.65 8.48
Lobby entrance/opening -1 1 1 3.70 1.00 3.10 -11.47
Add: Reveals and jambs
Doors and openings
Dg-3 door way 1 1 1 1.80 0.20 1.00 0.36
Dg-1 1 1 2 1.60 0.30 1.00 0.96
Lobby entrance/opening 1 1 1 3.70 0.30 1.00 1.11
Spirits store
Spirits store 1 1 1 6.34 1.00 3.65 23.14
Spirits store 1 1 1 8.87 1.00 3.65 32.38
Less; Duct door Dg-16 -1 1 1 0.50 1.00 2.65 -1.33
Less; Dg-04 -1 1 1 1.60 1.00 2.65 -4.24
Less; Wg-10 -1 1 2 1.57 1.00 2.20 -6.89
Less; Wg-07 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
Doors and openings
Duct door Dg-16 1 1 1 0.50 0.20 1.00 0.10
Dg-04 1 1 1 11.00 0.30 1.00 3.30
Wg-10 1 1 2 7.53 0.30 1.00 4.52
Wg-07 1 1 1 7.53 0.30 1.00 2.26

Staircase/lift lobby area


Staircase/lift lobby area 1 1 2 3.29 1.00 3.65 24.02
Staircase/lift lobby area 1 1 2 8.87 1.00 3.65 64.75
Less: Dg-3 door way -1 1 1 1.80 1.00 2.65 -4.77
Less: Lift door -1 1 1 1.20 1.00 2.10 -2.52
Add: FHR area/sides -1 1 2 0.60 1.00 2.65 -3.18
Wg-10 1 1 2 1.57 1.00 2.20 6.89
Add: Reveals and jambs
Doors and openings
Less: Dg-3 door way 1 1 1 1.80 0.20 1.00 0.36
Less: Lift door 1 1 1 1.20 0.20 1.00 0.24
Wg-10 1 1 2 7.53 0.30 1.00 4.52

Meeting room/office/hall-way/IT serverroom


Meeting room/office/hall-way/IT serverroom 1 1 2 11.17 1.00 3.65 81.54
Meeting room/office/hall-way/IT serverroom 1 1 1 9.84 1.00 3.65 35.90
Dg-15 1 1 1 0.70 1.00 2.65 1.85
Less: Dg-3 door way -1 1 1 1.80 1.00 2.65 -4.77
Wg-10 -1 1 8 1.57 1.00 2.20 -27.54
Add: Reveals and jambs
Doors and openings
Dg-15 1 1 1 0.70 0.20 1.00 0.14
Less: Dg-3 door way 1 1 1 1.80 0.20 1.00 0.36
Wg-10 1 1 8 7.53 0.30 1.00 18.07

Dining/Hallway
Dining/Hallway 1 1 2 6.80 1.00 3.65 49.64
Dining 1 1 1 5.97 1.00 3.65 21.77
Less: Dg-6 -1 1 1 1.50 1.00 2.65 -3.97
Less: Dg-11 -1 1 2 1.00 1.00 2.65 -5.30
Wg-10 -1 1 2 1.57 1.00 2.20 -6.89
Add: Reveals and jambs
Doors and openings
Less: Dg-6 1 1 1 6.80 0.30 1.00 2.04
Less: Dg-11 1 1 2 6.30 0.30 1.00 3.78
Wg-10 1 1 2 7.53 0.30 1.00 4.52

Hallway extension towards the balcony


Hallway extension towards the balcony 1 1 2 2.72 1.00 3.65 19.82
Hallway extension towards the balcony 1 1 1 3.10 1.00 3.65 11.32
Less: Dg-11 -1 1 1 1.00 1.00 2.65 -2.65
Wg-10 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
Doors and openings
Less: Dg-11 1 1 1 10.40 0.30 1.00 3.12
Wg-10 1 1 1 7.30 0.30 1.00 2.19

Staircase-02 lobby
Staircase-02 lobby 1 1 2 4.20 1.00 3.65 30.66
Staircase-02 lobby 1 1 1 2.52 1.00 3.65 9.20
Less: Dg-11 -1 1 1 1.00 1.00 2.65 -2.65
Wg-10 -1 1 3 1.57 1.00 2.20 -10.33
Add: Reveals and jambs
Doors and openings
Less: Dg-11 1 1 1 6.30 0.30 1.00 1.89
Wg-10 1 1 3 7.53 0.30 1.00 6.78

Toilets/entrance lobby
Toilets/entrance lobby 1 2 2 1.60 1.00 3.65 23.36
Toilets/entrance lobby 1 2 2 1.10 1.00 3.65 16.06
Openings to toilets -1 2 1 1.00 1.00 2.65 -5.30
Less: Dg-11 -1 1 2 1.00 1.00 2.65 -5.30
Add: Reveals and jambs
Doors and openings
Openings to toilets 1 2 1 6.30 0.15 1.00 1.89
Less: Dg-11 (alreadly considered)

Female toilet/lobby
Toilets/entrance lobby (to receive Two coats of “Plascon Hygienic
Coating” paint finishes over the appropriate undercoat
Female toilet/lobby 1 1 2 3.60 1.00 3.65 26.28
Female toilet/lobby 1 1 2 6.55 1.00 3.65 47.82
Openings to toilets -1 1 1 1.00 1.00 2.65 -2.65
Dg-12 -1 1 3 0.80 1.00 2.10 -5.04
Add: Reveals and jambs
Doors and openings
Openings to toilets (already considered)
Dg-12 1 1 3 5.00 0.20 1.00 3.00

Female Toilets /3
Female Toilets /3 1 1 2 1.80 1.00 3.65 13.14
Female Toilets /3 1 1 2 1.00 1.00 3.65 7.30
Dg-12 -1 1 2 0.80 1.00 2.65 -4.24
Wg-10 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
Doors and openings
Dg-12 1 1 2 6.10 0.20 1.00 2.44
Wg-10 1 1 1 7.53 0.30 1.00 2.26

Female Toilets /3
Female Toilets /3 1 1 2 1.50 1.00 3.65 10.95
Female Toilets /3 1 1 2 1.15 1.00 3.65 8.40
Dg-12 -1 1 1 0.80 1.00 2.10 -1.68
Add; door ways Dg-15 -1 1 1 0.70 1.00 2.65 -1.85

Add: Reveals and jambs


Doors and openings
Dg-12 1 1 1 5.00 0.20 1.00 1.00
Add; door ways Dg-15 1 1 1 6.00 0.15 1.00 0.90

Male toilet/lobby
Male toilet/lobby 1 1 2 2.80 1.00 3.65 20.44
Male toilet/lobby 1 1 2 6.55 1.00 3.65 47.82
Openings to toilets -1 1 1 1.00 1.00 2.65 -2.65
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36
Add; urinal partition walls 1 2 3 0.65 1.00 3.65 14.24
Add; door ways Dg-15 -1 1 2 0.70 1.00 2.65 -3.71
Add: Reveals and jambs
Doors and openings
Dg-12 1 1 2 0.80 0.20 1.00 0.32
Add; door ways Dg-15 1 1 2 0.70 0.20 1.00 0.28
Openings to toilets (already considered)

Toilets and duct


Toilets and duct 1 2 2 1.80 1.00 3.65 26.28
Toilets and duct 1 2 2 1.00 1.00 3.65 14.60
Toilets and duct 1 1 2 1.80 1.00 3.65 13.14
Toilets and duct 1 1 2 0.60 1.00 3.65 4.38
Add; door ways Dg-15 -1 1 2 0.70 1.00 2.65 -3.71
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36
Wg-10 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
Doors and openings
Add; door ways Dg-15 1 1 2 6.00 0.20 1.00 2.40
Dg-12 1 1 2 5.00 0.20 1.00 2.00
Wg-10 1 1 1 7.53 0.30 1.00 2.26

To receive quarry tiles


Balcony
Balcony 1 1 1 6.00 1.00 3.65 21.90
Balcony 1 1 1 2.72 1.00 3.65 9.93
Dg-06 -1 1 1 1.50 1.00 2.65 -3.97
Add: Reveals and jambs
Doors and openings
Dg-06 (already considered)

Less tiled area in the toilets -1 1 1 114.47 1.00 1.00 -114.47

Lift shall walls/internally 1 1 4 2.05 1.00 3.90 31.98


Less: Lift door "unamed" -1 1 1 1.22 1.00 2.10 -2.56

777.59

Concrete surfaces (exposed beam and column surfaces) M2 472.49

Supply and fix approved glazed ceramic wall tiles; 300mm x


200mm x 6mm thick; approved colour; bedding and jointing
on screed (measured separately) with approved water proof
adhesive; flush pointing in approved coloured grout to:

M2 114.47

SUNDRIES

Accessories

G Edge trim; plastic; quarter round; setting at edges of wall tile finish M
Wall tiles

Female toilet/lobby
Female toilet/lobby 1 1 2 3.60 1.00 1.00 7.20
Female toilet/lobby 1 1 2 6.55 1.00 1.00 13.10
Openings to toilets 1 2 1 1.00 1.00 2.10 4.20
Dg-12 1 2 3 1.00 1.00 2.10 12.60

Female Toilets /3
Female Toilets /3 1 1 2 1.80 1.00 2.10 7.56
Female Toilets /3 1 2 2 1.00 1.00 2.10 8.40
Dg-12 1 2 2 1.00 1.00 2.10 8.40

Female Toilets /3 1 1 2 1.50 1.00 2.10 6.30


Female Toilets /3 1 1 2 1.15 1.00 2.10 4.83
Dg-12 1 2 1 1.00 1.00 2.10 4.20
Add; door ways Dg-15 1 2 1 1.00 1.00 2.10 4.20

Male toilet/lobby
Male toilet/lobby 1 1 2 2.80 1.00 2.10 11.76
Male toilet/lobby 1 1 2 6.55 1.00 2.10 27.51
Openings to toilets 1 2 1 1.00 1.00 2.10 4.20
Dg-12 1 2 2 1.00 1.00 2.10 8.40

Add; urinal partition walls 1 2 3 0.65 1.00 2.10 8.19


Add; door ways Dg-15 1 2 2 0.70 1.00 1.00 2.80

Toilets and duct


Toilets and duct 1 2 2 1.80 1.00 2.10 15.12
Toilets and duct 1 2 2 1.00 1.00 2.10 8.40
Toilets and duct 1 1 2 1.80 1.00 2.10 7.56
Toilets and duct 1 1 2 0.60 1.00 2.10 2.52
Add; door ways Dg-15 1 2 2 1.00 1.00 2.10 8.40
Dg-12 1 2 2 1.00 1.00 2.10 8.40

Deductions
Generally deduct the windows for the washrooms
Wg-10 1 1 2 3.97 1.00 1.00 7.94
202.19

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm


second coat of cement and lime putty (1:10); steel trowelled
to:

G Concrete ceiling soffites. M2


1 1 1 512.50 1.00 1.00 512.50
512.50

H Staircase landing soffites M2 4.23

J Sloping staircase sofffites M2 23.55

K Moulded Ceiling cornice as per Architect's detail M


Verandah 1 1 2 20.45 1.00 1.00 40.90

Reception 1 1 1 6.21 1.00 1.00 6.21


Reception 1 1 1 6.02 1.00 1.00 6.02

Entrance lobby
Entrance lobby; measurements include areas beneath the
partitions 1 1 2 6.02 1.00 1.00 12.03
Entrance lobby; measurements include areas beneath the
partitions 1 1 2 2.66 1.00 1.00 5.32

Spirits store
Spirits store 1 1 1 6.34 1.00 1.00 6.34
Spirits store 1 1 1 8.87 1.00 1.00 8.87

Staircase/lift lobby area


Staircase/lift lobby area 1 1 2 3.29 1.00 1.00 6.58
Staircase/lift lobby area 1 1 2 8.87 1.00 1.00 17.74

Meeting room/office/hall-way/IT serverroom


Meeting room/office/hall-way/IT serverroom/ 1 1 2 11.17 1.00 1.00 22.34
Meeting room/office/hall-way/IT serverroom/ 1 1 1 9.84 1.00 1.00 9.84
Add: duct area 1 1 1 0.70 1.00 1.00 0.70

Dining/Hallway
Dining/Hallway 1 1 2 6.80 1.00 1.00 13.60
Dining 1 1 1 5.97 1.00 1.00 5.97

Hallway extension towards the balcony 1 1 2 2.72 1.00 1.00 5.43


Hallway extension towards the balcony 1 1 1 3.10 1.00 1.00 3.10

Staircase-02 lobby
Staircase-02 lobby 1 1 2 4.20 1.00 1.00 8.40
Staircase-02 lobby 1 1 1 2.52 1.00 1.00 2.52

Toilets/entrance lobby
Toilets/entrance lobby 1 2 2 1.60 1.00 1.00 6.40
Toilets/entrance lobby 1 2 2 1.10 1.00 1.00 4.40

Female toilet/lobby
Female toilet/lobby 1 1 2 3.60 1.00 1.00 7.20
Female toilet/lobby 1 1 2 6.55 1.00 1.00 13.10

Female Toilets /3
Female Toilets /3 1 1 2 1.80 1.00 1.00 3.60
Female Toilets /3 1 1 2 1.00 1.00 1.00 2.00

Female Toilets /3 1 1 2 1.50 1.00 1.00 3.00


Female Toilets /3 1 1 2 1.15 1.00 1.00 2.30

Male toilet/lobby
Male toilet/lobby 1 1 2 2.80 1.00 1.00 5.60
Male toilet/lobby 1 1 2 6.55 1.00 1.00 13.10
Add; urinal partition walls 1 2 3 0.65 1.00 1.00 3.90

Toilets and duct


Toilets and duct 1 2 2 1.80 1.00 1.00 7.20
Toilets and duct 1 2 2 1.00 1.00 1.00 4.00
Toilets and duct 1 1 2 1.80 1.00 1.00 3.60
Toilets and duct 1 1 2 0.60 1.00 1.00 1.20

To receive quarry tiles


Balcony
Balcony 1 1 1 6.00 1.00 1.00 6.00
Balcony 1 1 1 2.72 1.00 1.00 2.72
271.22

Mild steel Staircase balustrade; welded construction; shop


primed with red oxide

A Horizontal or raking balustrade; 900mm high comprising of;


50mx3mm thick CHS handrail; 4 No. 25x2mm thick CHS
intermediate horizontal rails; 2/50x6mm thick MS flat balusters,
mild steel base plates; all rawl bolted into concrete; including
primer, spray painting wth three coats gloss oil paint and
decorations to approval.
M
Staircase 01
Waist 1 1 2 4.36 1.00 1.00 8.72
Void 1 1 1 1.70 1.00 1.00 1.70
Void 1 1 1 0.20 1.00 1.00 0.20

Staircase 02
Waist 1 1 2 4.36 1.00 1.00 8.72
Void 1 1 1 1.40 1.00 1.00 1.40
Void 1 1 1 0.20 1.00 1.00 0.20
20.94

A Dado rails; Supply and fix 50mm diameter x 6mm thick CHS mild
steel handrail plugged with 25mm x 4mm thick mild steel support
fixed into wall; all painting and decorations M
Staircase 01
Waist 1 1 2 4.36 1.00 1.00 8.72
Landing 1 1 2 1.50 1.00 1.00 3.00
Landing 1 1 1 3.29 1.00 1.00 3.29

Staircase 02
Waist 1 1 2 4.36 1.00 1.00 8.72
Void 1 1 2 1.40 1.00 1.00 2.80
Void 1 1 1 2.52 1.00 1.00 2.52
29.05

Glass railing; 900mm high comprising of 12mm thick tempered


(toughed) laminated glass fixed to and including 50x50mm chrome
plated stainless steel handrails, bottom rails and vertical balusters
spaced at 900mm centres; all chrome plated stainless brackets; all
cast in concrete.
M
Balcony 1 1 1 6.20 1.00 1.00 6.20
Balcony 1 1 1 2.72 1.00 1.00 2.72
Front verandah 1 1 1 1.74 1.00 1.00 1.74
10.66

Prepare and apply one undercoat and two finishing coats of


matt emulsion paint in accordance with manufacturer's
instructions to:

B Concrete ceiling soffites. M2 512.50

C Staircase landing soffites M2 4.23

D Sloping staircase sofffites M2 23.55

E Moulded Ceiling cornice as per Architect's detail M 271.22

Prepare and apply one undercoat and two finishing coats of


silk vinyl paint in accordance with manufacturer's instructions
to:
Plastered walls 1 1 1 437.27 1.00 1.00 437.27
437.27

Prepare and apply one undercoat and two finishing coats of


hygienic coating paint in accordance with the manufacturer's
instructions to:
Toilets/entrance lobby 1 1 2 3.60 1.00 3.65 26.28
Toilets/entrance lobby 1 1 2 6.55 1.00 3.65 47.82
Openings to toilets -1 1 1 1.00 1.00 2.65 -2.65
Dg-12 -1 1 3 0.80 1.00 2.10 -5.04
Add: Reveals and jambs
Doors and openings \
Openings to toilets (already considered)
Dg-12 1 1 3 5.00 0.20 1.00 3.00

Female Toilets /3
Female Toilets /3 1 1 2 1.80 1.00 3.65 13.14
Female Toilets /3 1 1 2 1.00 1.00 3.65 7.30
Dg-12 -1 1 2 0.80 1.00 2.65 -4.24
Wg-10 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
Doors and openings
Dg-12 1 1 2 6.10 0.20 1.00 2.44
Wg-10 1 1 1 7.53 0.30 1.00 2.26

Female Toilets /3
Female Toilets /3 1 1 2 1.50 1.00 3.65 10.95
Female Toilets /3 1 1 2 1.15 1.00 3.65 8.40
Dg-12 -1 1 1 0.80 1.00 2.10 -1.68
Add; door ways Dg-15 -1 1 1 0.70 1.00 2.65 -1.85

Add: Reveals and jambs


Doors and openings
Dg-12 1 1 1 5.00 0.20 1.00 1.00
Add; door ways Dg-15 1 1 1 6.00 0.15 1.00 0.90

Male toilet/lobby
Male toilet/lobby 1 1 2 2.80 1.00 3.65 20.44
Male toilet/lobby 1 1 2 6.55 1.00 3.65 47.82
Openings to toilets -1 1 1 1.00 1.00 2.65 -2.65
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36
Add; urinal partition walls 1 2 3 0.65 1.00 3.65 14.24
Add; door ways Dg-15 -1 1 2 0.70 1.00 2.65 -3.71
Add: Reveals and jambs
Doors and openings
Dg-12 1 1 2 0.80 0.20 1.00 0.32
Add; door ways Dg-15 1 1 2 0.70 0.20 1.00 0.28
Openings to toilets (already considered)

Toilets and duct


Toilets and duct 1 2 2 1.80 1.00 3.65 26.28
Toilets and duct 1 2 2 1.00 1.00 3.65 14.60
Toilets and duct 1 1 2 1.80 1.00 3.65 13.14
Toilets and duct 1 1 2 0.60 1.00 3.65 4.38
Add; door ways Dg-15 -1 1 2 0.70 1.00 2.65 -3.71
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36
Wg-10 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
Doors and openings
Add; door ways Dg-15 1 1 2 6.00 0.20 1.00 2.40
Dg-12 1 1 2 5.00 0.20 1.00 2.00
Wg-10 1 1 1 7.53 0.30 1.00 2.26
Less:
tiled area -1 1 1 114.47 1.00 1.00 -114.47
M2 118.01
Prepare and apply one undercoat and two finishing coats of
eggshell enamel paint in accordance with the manufacturer's
instructions to:
Balcony
Balcony 1 1 1 6.00 1.00 3.65 21.90
Balcony 1 1 1 2.72 1.00 3.65 9.93
Dg-06 -1 1 1 1.50 1.00 2.65 -3.97
27.85

Prepare and apply 1.5mm thick layer of textured decorative


paint finishes to the plastered wall.
Verandah 1 1 2 20.45 1.00 3.65 149.29
Entrance points/openings -1 1 3 4.00 1.00 3.10 -37.20
Entrance points/openings -1 1 3 1.74 1.00 3.10 -16.18
Duct doors/telecoms; Dg-13 -1 1 1 1.60 1.00 2.65 -4.24
Lobby entrance/opening -1 1 1 3.70 1.00 3.65 -13.51
Dg-04 -1 1 2 1.60 1.00 2.65 -8.48
Add: Reveals and jambs
Doors and openings
Entrance points/openings 1 1 3 10.20 0.30 1.00 9.18
Entrance points/openings 1 1 3 7.94 0.30 1.00 7.15
Duct doors/telecoms; Dg-13 1 1 1 6.90 0.30 1.00 2.07
Lobby entrance/opening 1 1 1 11.00 0.30 1.00 3.30
Dg-04 1 1 2 6.90 0.30 1.00 4.14
Windows
Wg-05 1 1 2 6.90 0.30 1.00 4.14

Reception
Reception 1 1 1 6.21 1.00 3.65 22.67
Reception 1 1 1 6.02 1.00 3.65 21.97
Less: Dg-1 -1 1 2 1.60 1.00 2.65 -8.48
Add: Reveals and jambs
Doors and openings
Less: Dg-1 1 1 2 1.60 0.20 1.00 0.64

Entrance lobby
Entrance lobby; measurements include areas beneath the
partitions 1 1 2 6.02 1.00 3.65 43.91
Entrance lobby; measurements include areas beneath the
partitions 1 1 2 2.66 1.00 3.65 19.42
Dg-3 door way -1 1 1 1.80 1.00 2.65 -4.77
Dg-1 1 1 2 1.60 1.00 2.65 8.48
Lobby entrance/opening -1 1 1 3.70 1.00 3.10 -11.47
Add: Reveals and jambs
Doors and openings
Dg-3 door way 1 1 1 1.80 0.20 1.00 0.36
Dg-1 1 1 2 1.60 0.30 1.00 0.96
Lobby entrance/opening 1 1 1 3.70 0.30 1.00 1.11
H Plastered walls and concrete surfaces. M2 194.45
Prepare and apply one undercoat and two finishing coats of
gloss oil paint in accordance with manufacturer's instructions
to:

J General surfaces of metal (measured flat both sides) M2


Balustrades
Staircase 01
Waist 1 2 2 4.36 1.00 0.90 15.70
Void 1 2 1 1.70 1.00 0.90 3.06
Void 1 2 1 0.20 1.00 0.90 0.36

Staircase 02
Waist 1 2 2 4.36 1.00 0.90 15.70
Void 1 2 1 1.40 1.00 0.90 2.52
Void 1 2 1 0.20 1.00 0.90 0.36
Dado rails; M
Staircase 01
Waist 1 2 2 4.36 1.00 0.30 5.23
Landing 1 2 2 1.50 1.00 0.30 1.80
Landing 1 2 1 3.29 1.00 0.30 1.97

Staircase 02
Waist 1 2 2 4.36 1.00 0.30 5.23
Void 1 2 2 1.40 1.00 0.30 1.68
Void 1 2 1 2.52 1.00 0.30 1.51
M2 55.12

ELEMENT NO. 8
INTERNAL FINISHINGS

BILL NO.2

ELEMENT NO. 9

EXTERNAL FINISHINGS

Roof drainage

Fulbora; 150mm diameter; stainless steel; complete with a clamp


ring and grating; including taking around the opening and making
good to distrubed concrete and finished surfaces; as per the
Architect's detail.
1 1 1 1.00 1.00 1.00 1.00
1.00
Piepwork measured elsewhere in plumbing installations

APP - Modified Bitumen


4mm thick APP modified bituminous water
proofing membrane reinforced with polyester with
50mm side and 75mm end laps, fully bonded and torch
applied in accordance with manufacturers
instructions; to

16.29

100mm high x 10mm thick skirting

1 1 2 8.72 1.00 1.00 17.43


17.43

Supply and Fix 600 x 600 x 10mm Thick approved Quarry floor tiles
in approved water adhesive, pointed with approved tri poly fortified
grout and admix grout to :
16.29

100mm high x 10mm thick skirting


1 1 1 17.43 1.00 1.00 17.43
17.43
20mm thick rendering in cement and Sand (1:4) mortar; as per
Architect's details; on:

A Walls and concrete surfaces M2

1 1 1 6.60 1.00 3.90 25.74


1 1 2 2.72 1.00 3.90 21.18
1 1 1 11.80 1.00 3.90 46.02
2 1 1 27.74 1.00 3.90 216.33
1 1 2 2.65 1.00 3.90 20.67
1 1 1 3.49 1.00 3.90 13.61
1 1 1 3.49 1.00 3.90 13.61
2 1 1 18.60 1.00 3.90 145.08
2 1 1 0.84 1.00 3.90 6.55
1 1 1 17.40 1.00 3.90 67.86

Less openings at the veradanh -3 1 1 3.70 1.00 3.10 -34.41


-1 1 1 1.44 1.00 3.10 -4.46

Wg-05 1600x2200 -1 1 2 1.60 1.00 2.65 -8.48


Wg-07 1565x2200 -1 1 1 1.57 1.00 2.20 -3.44
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89
Wg-10 1565x2200 -4 1 1 1.57 1.00 2.20 -13.77
Wg-7 1565x2200 -2 1 1 1.57 1.00 2.20 -6.89

Type 4 (ext) 1600x2650 -1 1 1 1.60 1.00 2.65 -4.24


Type 4 (ext) 1600x2650 -1 1 1 1.60 1.00 2.65 -4.24
Type 6 (ext) 1500x2650 -1 1 1 1.50 1.00 2.20 -3.30

Add: beams over verandahs and balcony


Balcony area/sides 1 1 2 6.30 1.00 0.80 10.08
Balcony area/sides 1 1 2 2.72 1.00 0.80 4.35
Balcony area/soffites 1 1 1 6.30 0.40 1.00 2.52
Balcony area/soffites 1 1 1 2.72 0.40 1.00 1.09

Lift shall walls 1 1 4 2.45 1.00 3.90 38.22


Less: Lift door "unamed" -1 1 1 1.22 1.00 2.10 -2.56
498.91
Prepare and apply Plascon Architexture Grafiato coating in
accordance with manufacturer's instructions to:

C Rendered surfaces M2 498.91


ELEMENT NO. 9
EXTERNAL FINISHINGS

BILL NO.2

ELEMENT NO. 10

FITTINGS

A Alow a provisional sum of Ushs. 15,000,000 for fittings 14,124,000.00

Washroom wash basin worktop 1 1 2 2.00 1.00 850000.00 3,400,000.00


Janitor store 1 1 2 2.40 1.00 1200000.00 5,760,000.00
Dining worktop with one sink 1 1 1 5.84 1.00 850000.00 4,964,000.00
CLIENT: CK COMPANY DATE: 4/5/2024
PROJECT: PROPOSED OFFICE BLOCK CALC BY: IB
LEVEL GROUND FLOOR
MEASUREMENTS PURPOSE: ESTIMATES
NO. DESCRIPTION UNIT EQ. PRTS EQ. PRTS EQ. PRTS L W H/D/kg/m QTY

FIRST FLOOR

SUPERSTRUCTURE

RC in grade 25 to columns M3
C1 9 1 1 0.40 0.40 3.65 5.26
C2 3 1 1 0.40 0.60 3.65 2.63
C3 3 1 1 0.40 0.60 3.65 2.63
C4 3 1 1 0.40 0.60 3.65 2.63
C5 2 1 1 0.40 0.60 3.65 1.75
C6 1 1 1 0.35 0.35 3.65 0.45
15.34

RC in grade 25 to beams M3
G/L E(1-2) & F(1-2) 1 1 2 3.14 0.40 0.55 1.38
G/L G(1-2) 1 1 1 1.10 0.40 0.55 0.24
G/L A(1-4) 1 1 1 12.45 0.40 0.55 2.74
G/L B,C,D,E,F(2-3) 1 1 5 5.50 0.40 0.55 6.05
G/L G(2-3) 1 1 1 5.60 0.40 0.55 1.23
G/L B(3-5) 1 1 1 11.55 0.40 0.55 2.54
G/L C(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L D(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L E(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L F(3-5) 1 1 1 11.45 0.40 0.55 2.52
G/L G(3-4) 1 1 1 5.65 0.40 0.55 1.24
G/L G(4-5) 1 1 1 5.60 0.40 0.55 1.23

further depth to 1200mm


G/L B,C,D,E(2-3) 1 1 4 5.50 0.40 0.40 3.52
G/L B(3-5) 1 1 1 11.55 0.40 0.40 1.85
G/L C(3-5) 1 1 1 11.45 0.40 0.40 1.83
G/L D(3-5) 1 1 1 11.45 0.40 0.40 1.83
G/L E(3-5) 1 1 1 11.45 0.40 0.40 1.83

G/L B4 - G4 1 1 1 27.99 0.40 0.40 4.48

G/L A2-B2, A3-B3, A3'-B3', A4-B4 1 1 4 2.32 0.40 0.55 2.04


G/L B2-C2 & B3-C3 1 1 2 5.60 0.40 0.55 2.46
G/L B5-C5 1 1 1 5.50 0.40 0.55 1.21
G/L 2,3 & 5 (C-D) 1 1 3 5.60 0.40 0.55 3.70
G/L 2,3,& 5(D-E) 1 1 3 5.60 0.40 0.55 3.70
G/L 1,2,3 & 5 (E-F) 1 1 4 5.60 0.40 0.55 4.93
G/L F1-G1 1 1 1 2.75 0.40 0.55 0.61
G/L 2,3 & 5 (F-G) 1 1 3 5.59 0.40 0.55 3.69
64.40
Upstand beam and moulding as per the Architects details.
Beam moulding 1 1 1 110.80 0.17 1.00 18.84
Beam moulding 1 1 1 110.80 0.11 1.00 11.63
30.47

RC in grade 25 to the staircase M3


Staircase 01
Steps 1 26 1/2 0.30 0.15 1.50 0.44
Waist 1 1 2 4.36 1.50 0.20 2.62

Staircase 02
Steps 0 26 1/2 0.30 0.15 1.20 0.00
Waist 0 1 2 4.36 1.20 0.20 0.00
3.05

200mm thick to staircase landing M2


Staircase 01
Landing 1 1 1 3.29 1.70 1.00 2.80
Staircase 02
Landing 0 1 1 2.52 1.60 1.00 0.00
2.80

Landing beams M2
Staircase 01
Landing beams 1 1 1 3.89 0.20 0.20 0.08
Staircase 02
Landing beams 0 1 1 3.12 0.20 0.20 0.00
0.08

RC in grade 25 to the lift walls 20mm thick M2


2 1 1 2.45 1.00 3.90 19.11
2 1 1 2.05 1.00 3.90 15.99
Less opening -1 1 1 1.22 1.00 2.10 -2.56
32.54

250mm thick solid slab in RC grade 25 M2


Panel; G/L B&G (2-5) 1 1 1 18.45 30.39 1.00 560.70
Panel; G/L A&B (3-4) 1 1 1 6.45 2.72 1.00 17.54
Panel; G/L F&G (1-2) 1 1 1 3.54 6.75 1.00 23.90
Ddt: Around the lift shaft area -1 1 1 2.45 2.45 1.00 -6.00

Add; beam tops /areas without slabs


G/L A (2-3) 1 1 1 6.00 0.40 1.00 2.40
G/L A1-B1 1 1 1 2.75 0.40 1.00 1.10
G/L E1-F1 1 1 1 6.00 0.40 1.00 2.40
G/L E(1-2) 1 1 1 3.54 0.40 1.00 1.42
603.45

Reinforcements

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Columns 1 1 150 15.34 1.00 1.00 2,300.87
RC in grade 25 to beams 1 1 150 64.40 1.00 1.00 9,660.74
Upstand beam and moulding as per the Architects details. 1 1 150 30.47 1.00 1.00 4,570.50
RC in grade 25 to the staircase 1 1 150 3.05 1.00 1.00 458.24
200mm thick to staircase landing 1 1 150 2.80 1.00 1.00 419.48
Landing beams 1 1 150 0.08 1.00 1.00 11.67
RC in grade 25 to the lift walls 20mm thick 1 1 150 32.54 0.20 1.00 976.14
250mm thick solid slab in RC grade 25 1 1 150 603.45 0.25 1.00 22,629.30
41,026.93

Sawn form work to;

Sides of columns M2

C1 9 1 2 0.80 1.00 3.65 52.56


C2 3 1 2 1.00 1.00 3.65 21.90
C3 3 1 2 1.00 1.00 3.65 21.90
C4 3 1 2 1.00 1.00 3.65 21.90
C5 2 1 2 1.00 1.00 3.65 14.60
C6 1 1 2 0.70 1.00 3.65 5.11
137.97

Sides and soffits of beams M2


G/L E(1-2) & F(1-2) 1 1 2 3.14 1.50 1.00 9.42
G/L G(1-2) 1 1 1 1.10 1.50 1.00 1.65
G/L A(1-4) 1 1 1 12.45 1.50 1.00 18.67
G/L B,C,D,E,F(2-3) 1 1 5 5.50 1.50 1.00 41.25
G/L G(2-3) 1 1 1 5.60 1.50 1.00 8.40
G/L G(3-5) 1 1 1 11.55 1.50 1.00 17.33
G/L C(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L D(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L E(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L F(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L G(3-4) 1 1 1 5.65 1.50 1.00 8.48
G/L G(4-5) 1 1 1 5.60 1.50 1.00 8.40

further depth to 1200mm


G/L B,C,D,E(2-3) 1 2 4 5.50 0.40 1.00 17.60
G/L B(3-5) 1 2 1 11.55 0.40 1.00 9.24
G/L C(3-5) 1 2 1 11.45 0.40 1.00 9.16
G/L D(3-5) 1 2 1 11.45 0.40 1.00 9.16
G/L E(3-5) 1 2 1 11.45 0.40 1.00 9.16

G/L B4 - G4 1 2 1 27.99 0.40 1.00 22.39

G/L A2-B2, A3-B3, A3'-B3', A4-B4 1 1 4 2.32 1.50 1.00 13.92


G/L B2-C2 & B3-C3 1 1 2 5.60 1.50 1.00 16.80
G/L B5-C5 1 1 1 5.50 1.50 1.00 8.25
G/L 2,3 & 5 (C-D) 1 1 3 5.60 1.50 1.00 25.20
G/L 2,3,& 5(D-E) 1 1 3 5.60 1.50 1.00 25.20
G/L 1,2,3 & 5 (E-F) 1 1 4 5.60 1.50 1.00 33.60
G/L F1-G1 1 1 1 2.75 1.50 1.00 4.13
G/L 2,3 & 5 (F-G) 1 1 3 5.59 1.50 1.00 25.13
411.23

Sides and soffits of staircase landing beams M2


Staircase 01
Sides and soffits of staircase landing beams 1 1 1 3.89 0.60 1.00 1.17
Staircase 02
Sides and soffits of staircase landing beams 0 1 1 3.12 0.60 1.00 0.00
1.17
Sides of upstand beams and mouldings
Beam moulding 1 1 1 110.80 1.30 1.00 144.04
Beam moulding 1 1 1 110.80 0.70 1.00 77.56
221.60

Extra over formwork to parapet walls for forming grooves,


chamfers, rebates, chases and mouldings.
221.60
Soffits of the slab 250mm thick M2
4 1 1 5.60 5.60 1.00 125.44
1 1 1 5.59 5.60 1.00 31.28
4 1 1 11.65 5.60 1.00 260.96
1 1 1 11.65 5.59 1.00 65.07
1 1 1 2.50 2.40 1.00 6.00
1 1 1 3.00 2.40 1.00 7.20
1 1 1 1.30 2.40 1.00 3.12
1 1 1 4.20 3.20 1.00 13.44
512.50

soffits of stiracse case landing M2


Staircase 01
Landing 1 1 1 3.29 1.50 1.00 2.47
Staircase 02
Landing 0 1 1 2.52 1.40 1.00 0.00
2.47

Slopping sofffits of staircase M2


Staircase 01
Waist 1 1 2 4.36 1.50 1.00 13.08

Staircase 02
Waist 0 1 2 4.36 1.20 1.00 0.00
13.08

Risers; 150mm wide


Staircase 01
Steps 1 26 1 1.50 1.00 1.00 19.50
Staircase 02
Steps 0 26 1 1.20 1.00 1.00 0.00
19.50

Sides of the lift walls M2


1 2 2 2.45 1.00 3.90 38.22
1 2 2 2.05 1.00 3.90 31.98
Less: Lift door "unamed" -1 2 1 1.22 1.00 2.10 -5.12
65.08
Edges of the slab 250mm wide M
Panel; G/L B&G (2-5) 1 1 2 21.99 1.00 1.00 43.98
Panel; G/L A&B (3-4) 1 1 2 33.10 1.00 1.00 66.20
G/L A (2-3) 1 1 2 6.00 1.00 1.00 12.00
G/L A1-B1 1 1 2 2.75 1.00 1.00 5.50
G/L E1-F1 1 1 2 6.00 1.00 1.00 12.00
G/L E(1-2) 1 1 2 3.54 1.00 1.00 7.08
146.76

Edges of the staircase landing 200mm wide M


Staircase 01; girth computed 1 1 1 6.98 1.00 1.00 6.98
Staircase 02; ditto 0 1 1 5.72 1.00 1.00 0.00
6.98
open springer of stairacse; 350mm high max M
Staircase 01
Waist 1 2 2 4.36 1.00 1.00 17.44
17.44

ELEMENT NO. 2

BILL NO.2

ELEMENT NO. 4

EXTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties
set in horizontal alternate courses:

A 300mm thick M2
G/L G(2-5) 1 1 1 18.40 1.00 3.10 57.04
Walls at telecom duct towards the lift shaft 1 1 2 0.84 1.00 3.10 5.21
G/L G(2-5) 1 1 1 30.09 1.00 3.10 93.28
G/L G(2-5) 1 1 1 6.30 1.00 3.10 19.53
G/L G(2-5) 1 1 1 12.40 1.00 3.10 38.44
G/L G(2-5) 1 1 2 2.42 1.00 3.10 14.97
G/L G(2-5) 1 1 1 18.00 1.00 3.10 55.79
G/L G(2-5) 1 1 1 3.59 1.00 3.10 11.13
G/L G(2-5) 1 1 1 9.15 1.00 3.10 28.35
G/L G(2-5) 1 1 1 2.65 1.00 3.10 8.21
G/L G(2-5) 1 1 1 17.80 1.00 3.10 55.18

Deductions
Openings and doors
Verandah openings/front -1 1 3 3.70 1.00 3.10 -34.41
Verandah openings/sides -1 1 1 1.44 1.00 3.10 -4.46
D1-13 -1 1 1 1.60 1.00 2.65 -4.24
D1-04 -1 1 2 1.60 1.00 2.65 -8.48

Windows
W1-06 -1 1 2 1.60 1.00 2.20 -7.04
W1-05 -1 1 2 1.60 1.00 2.65 -8.48
W1-07 -1 1 3 1.57 1.00 2.20 -10.33
W1-10 -1 1 19 1.57 1.00 2.20 -65.42
244.28
Reinforced Insitu concrete grade 25 in:-
Moulded concrete window Sill; Section size 250 x 85 x 50mm;
C M
weathered and throated; all as per Architect's details
Openings and doors
D1-13 1 1 1.90 1.00 1.00 0.00
D1-04 1 2 1.90 1.00 1.00 0.00

Windows
W1-06 1 1 2 1.90 1.00 1.00 3.80
W1-05 1 1 2 1.90 1.00 1.00 3.80
W1-07 1 1 3 1.87 1.00 1.00 5.60
W1-10 1 1 19 1.87 1.00 1.00 35.44
48.63

Reinforced concrete grade 25 in:-


A Lintels M2
Over openings and doors
Openings and doors
D1-13 1 1 1 1.90 0.30 0.30 0.17
D1-04 1 1 2 1.90 0.30 0.30 0.34

Windows
W1-06 1 1 2 1.90 0.30 0.30 0.34
W1-05 1 1 2 1.90 0.30 0.30 0.34
W1-07 1 1 3 1.87 0.30 0.30 0.50
W1-10 1 1 19 1.87 0.30 0.30 3.19
4.89

Sawn formwork to:-

Sides and soffites of lintels


Over openings and doors
Openings and doors
D1-13 1 1 1 2.20 0.90 1.00 1.98
D1-04 1 1 2 0.30 0.90 1.00 0.54

Windows
W1-06 1 1 2 2.20 0.90 1.00 3.96
W1-05 1 1 2 2.17 0.90 1.00 3.90
W1-07 1 1 3 2.17 0.90 1.00 5.85
W1-10 1 1 19 0.30 0.90 1.00 5.13
21.35
High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Lintels 1 1 150 4.89 1.00 1.00 733.46
733.46

BILL NO.2

ELEMENT NO. 5

INTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties
set in horizontal alternate courses:

A 200mm thick Wall M2

G/L E2-F'2 1 1 1 8.85 1.00 3.10 27.43


Partition between the office/Female toilets 1 1 1 9.71 1.00 3.65 35.44
Partition the FF toilets and Male toilets 1 1 1 8.55 1.00 3.65 31.21
G/L B(1-3) 1 1 1 8.55 1.00 3.65 31.21
Partition between the washrooms and the hallway 1 1 1 1.77 1.00 3.65 6.44
Partition between the GM office / hallway 1 1 1 5.32 1.00 3.65 19.42
Duct walls 1 1 1 2.00 1.00 3.65 7.30
Duct walls 1 1 2 0.50 1.00 3.65 3.65

Deductions; doors
D1-03 -1 1 1 1.80 1.00 2.65 -4.77
D1-16 -1 1 2 0.50 1.00 2.65 -2.65
154.68

A 150mm thick walls M2


Partition wall between CEO office and washrooms 1 1 1 5.97 1.00 3.65 21.79
Partition wall between CEO office and washrooms 1 1 1 0.79 1.00 3.65 2.87

Partitions - Toilets FF 1 1 1 3.60 1.00 3.65 13.14


Partitions - Toilets M 1 1 1 2.80 1.00 3.65 10.22
Toilet partitions 1 1 4 1.80 1.00 3.65 26.28
Duct in the toilet 1 1 1 1.50 1.00 3.65 5.48
Urinal partitions 1 1 3 0.50 1.00 3.65 5.48
Toilet entrance walls 1 1 2 1.65 1.00 3.65 12.05
Toilet entrance walls 1 1 2 1.25 1.00 3.65 9.13
Partition between the hallway and toilets 1 1 1 9.32 1.00 3.65 34.02
Deductions ; doors
700x2650; D1-15 -1 1 1 0.70 1.00 2.65 -1.85
Openings to the toilets -1 1 2 0.90 1.00 2.65 -4.77
D1-11 -1 1 3 1.00 1.00 2.65 -7.95
800x2100; D1-12 -1 1 5 0.80 1.00 2.10 -8.40
125.86

C Drywall, aluminum partitioning 3650mm high M2


Meeting/hallway 1 1 1 9.84 1.00 3.65 35.90
Hallway/Director's office 1 1 1 8.60 1.00 3.65 31.37
Meeting room/office admin 1 1 1 9.71 1.00 3.65 35.44
GM office/cashier 1 1 1 5.84 1.00 3.65 21.32
Cashier/archives 1 1 1 5.84 1.00 3.65 21.32
lobby/director/CEO 1 1 2 6.95 1.00 3.65 50.74
Hallway/Meetingroom/accounts 1 1 1 11.17 1.00 3.65 40.75
Hallway/archives/GM 1 1 1 17.80 1.00 3.65 64.97

Deductions ; doors
D1-10; -1 1 8 1.00 1.00 2.65 -21.20
280.60

Reinforced concrete grade 25 in:-


A Lintels M
Deductions; doors
D1-03 1 1 1 1.80 0.30 0.30 0.16
D1-16 1 1 2 0.50 0.30 0.30 0.09
Deductions ; doors
700x2650; D1-15 1 1 1 0.70 0.20 0.30 0.04
Openings to the toilets 1 1 2 0.90 0.20 0.30 0.11
D1-11 1 1 3 1.00 0.20 0.30 0.18
800x2100; D1-12 1 1 5 0.80 0.20 0.30 0.24
Deductions ; doors
D1-10; 1 1 8 1.00 0.15 0.30 0.36
1.18

Sawn formwork to:-

Sides and soffites of lintels


Deductions; doors
D1-03 1 1 1 1.80 0.90 1.00 1.62
D1-16 1 1 2 0.50 0.90 1.00 0.90
Deductions ; doors
700x2650; D1-15 1 1 1 0.70 0.80 1.00 0.56
Openings to the toilets 1 1 2 0.90 0.80 1.00 1.44
D1-11 1 1 3 1.00 0.80 1.00 2.40
800x2100; D1-12 1 1 5 0.80 0.80 1.00 3.20
Deductions ; doors
D1-10; 1 1 8 1.00 0.75 1.00 6.00
16.12

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Deductions ; doors 1 1 150 1.18 1.00 1.00 177.30
177.30

ELEMENT NO. 5
INTERNAL WALING

BILL NO.2

ELEMENT NO. 6

WINDOWS, SCREENS AND LIGHTS

Anodized Aluminum casement windows. The color shall be to


client's approval; all additional costs are deemed included.

Provide and fix purpose-made anodized aluminum windows


and window frames complete with 5mm thick translucent
glass and single glazing, glazing beads, wash leather strips,
sealing, burglar proofing, fly mesh, all ironmongery and
accessories; fixing to blockwork or concrete; all as per
Architect's drawings; Drawing No. NA(22)02-9/10; in:

The contractor is expected to prepare and submit shop


drawings for approval prior to fabrication and erection of the
windows and screens

A Glazed window and window frames size: 1600 mm wide x 2650


mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [W1-05] No 2.00

A Glazed window and window frames size: 1600 mm wide x 2200


mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [W1-06] No 2.00

B Glazed window and window frames size: 1565 mm wide x 2200


mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [W1-07] No 3.00
B Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [W1-10] No 19.00

Reinforced Insitu concrete grade 25 in:-

Moulded concrete window Sill; Section size 350 x 85 x 50mm;


weathered and throated; all as per Architect's details
Glazed window and window frames size: 1600 mm wide x 2650
mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [W1-05] 1 1 2 1.90 1.00 1.00 3.80
Glazed window and window frames size: 1600 mm wide x 2200
mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [W1-06] 1 1 2 1.90 1.00 1.00 3.80
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [W1-07] 1 1 3 1.87 1.00 1.00 5.60
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [W1-10] 1 1 19 1.87 1.00 1.00 35.44
48.63

Window boards

Natural Stone Granite Window Board; size 150mm wide x 20mm


thick thick; all edges well finished with a coved mould; all as per
Architect's details
Glazed window and window frames size: 1600 mm wide x 2650
mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [W1-05] 1 1 2 1.60 1.00 1.00 3.20
Glazed window and window frames size: 1600 mm wide x 2650
mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [W1-05] 1 1 2 1.60 1.00 1.00 3.20
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [W1-07] 1 1 3 1.57 1.00 1.00 4.71
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [W1-10] 1 1 19 1.57 1.00 1.00 29.83
40.94

BILL NO.2

ELEMENT NO. 7

DOORS
DOORS, SHUTTERS AND HATCHES

TIMBER DOORS

The following in wrot hardwood to architect's satisfaction:-

Approved hardwood flush doors

A 45mm thick solid core timber flush door shutter size 800mm wide x
2100 mm high complete with a mahogany veneer; to Architect's
detail; door type [Dg-12] No
1 1 5 1.00 1.00 1.00 5.00
5.00

Approved hardwood panelled doors;

A 45mm thick solid panelled door shutter size 1000mm wide x


2100mm high complete with 2 No. vision panels size 200mm wide
x 1000mm high; to Architect's detail; door type [Dg-11] No
1 1 3 1.00 1.00 1.00 3.00
3.00

Door frames and finishings in in wrot hardwood

C 250mm x 50mm rebated frame M


Db-12 1 1 5 5.00 1.00 1.00 25.00
Db-11 1 1 3 6.30 1.00 1.00 18.90
Opening to toilet 1 1 2 6.20 1.00 1.00 12.40
56.30

C Ditto transomes M
Db-11 1 1 3 1.00 1.00 1.00 3.00
Opening to toilet 1 1 2 0.90 1.00 1.00 1.80
4.80

D 40mm x 20mm Splayed architrave or qudrant beads where


applicable. M
Db-12 1 2 5 5.00 1.00 1.00 50.00
Db-11 1 2 3 6.30 1.00 1.00 37.80
Opening to toilet 1 2 2 6.20 1.00 1.00 24.80
112.60

D 20mm x 20mm moulded glazing beads. M


Db-11 1 2 3 3.10 1.00 1.00 18.60
Db-11 - Vision panels 2 2 3 2.40 1.00 1.00 28.80
Opening to toilet 1 2 2 2.00 1.00 1.00 8.00
55.40

Ironmongery to architect's approval and sartisfaction

E 100mm Pressed steel butt hinges Pr


1 1 5 1.50 1.00 1.00 7.50
Db-11 1 1 3 1.50 1.00 1.00 4.50
12.00

F 25mm diameter rubber door stop plugged to wall/floor No


1 1 30 1.00 1.00 1.00 30.00
30.00

H 3 - Lever motrice lock complete with approved door handles No


Db-11 1 1 3 1.00 1.00 1.00 3.00
3.00

H Commercial privacy Lock complete with occupancy indicator Oil


rubbed bronze and Lock restroom hardware brass door handles No
Db-12 1 1 5 1.00 1.00 1.00 5.00
5.00

I Coat hooks No
1 1 5 1.00 1.00 1.00 5.00
5.00

J Door closer No
1 1 10 1.00 1.00 1.00 10.00
10.00

K Mild steel aldrop bolt complete with all the necessary accessories No
1 1 5 1.00 1.00 1.00 5.00
5.00

L Stainless Steel Push plate size 300mm x 100mm No


1 2 5 1.00 1.00 1.00 10.00
1 2 3 1.00 1.00 1.00 6.00
16.00

M Stainless Steel kick plate size 800mm wide x 150mm high x 3mm
thick No
1 2 5 1.00 1.00 1.00 10.00
10.00

M Stainless Steel kick plate size 1000mm wide x 150mm high x 3mm
thick No
1 2 3 1.00 1.00 1.00 6.00
6.00

O Symbol (Male) No
1 1 1 1.00 1.00 1.00 1.00
1.00

B Symbol (Female) No
1 1 1 1.00 1.00 1.00 1.00
1.00

B Sign - Base is 5mm thick Acrylic plate PU Coated with Silver Pan-
tone PU color
Content - Logo & Artwork to be in Plotter cut High Grade Vinyl .
Vinyl to match approved pan-tone (Blue 2935C) and Black color
Bubble free Glossy Lacquer Coating to be done after Vinyl Pasting.
Size : 300 MM X 75 MM
Location : Room Doors
Sided – Single sided
Fixing - Fixing of Sign with Reverse Screws

No
1 1 10 1.00 1.00 1.00 10.00
10.00

Glazing

5mm thick clear sheet glass fixed to hardwood frames with


glazing beads (measured seperately)
Db-11 - Vent 1 1 3 1.00 0.55 1.00 1.65
Db-11 - Vision panel 1 2 3 1.00 0.20 1.00 1.20
2.85

Steel casement doors; mild steel

Supply and Fix the following purpose made mild steel door
and door frames; all members in 3mm thick steel sections
complete with mild steel frame, hinges, fixing lugs, locking
device and a single coat of red oxide primer, all fixed as per
Architect's details and satisfaction

D Louvered door set; size 1600 mm wide x 2650 mm high; complete


with 2 louvered door shutters; door type [D1-13]
No 1.00

D Louvered door set; size 700 mm wide x 2650 mm high; door type
[D1-15] No 3.00
D Louvered door set; size 500mm wide x 2650 mm high; complete
with 1 louvered door shutters; door type [D1-16] No 2.00

Anodised aluminium doors

Supply and fix purpose-made anodised aluminium casement


doors and frames; complete with 6mm thick translucent glass
and single glazing, ironmongery, fixing lugs, all accessories
and one coat of red oxide primer before delivery; fixing to
blockwork or concrete; all as per Architect's drawings;
Drawing No. NA(22)02-9/10; in:

Door set; size 1800 mm wide x 2650 mm high; complete as per the
Architect's details; door type [D1-03] 1.00

Door set; size 1600mm wide x 2650 mm high; complete as per the
Architect's details; door type [D1-04] 2.00

Door set; size 1000mm wide x 2650 mm high; complete as per the
Architect's details; door type [D1-10] 8.00

Prepare and apply undercoat and three coats of gloss oil paint
on:-

I General surfaces of metal M2


Louvered door set; size 1600 mm wide x 2650 mm high; complete
with 2 louvered door shutters; door type [D1-13] 1 2 1 1.60 1.00 2.65 8.48
Louvered door set; size 700 mm wide x 2650 mm high; door type
[D1-15] 1 2 3 0.70 1.00 2.65 11.13
Louvered door set; size 500mm wide x 2650 mm high; complete
with 1 louvered door shutters; door type [D1-16] 1 2 2 0.50 1.00 2.65 5.30
24.91

J General surfaces of wood M2


Wood frames; girth exceeding 300mm wide; 350mm wide
250mm x 50mm rebated frame 1 1 1 56.30 0.35 1.00 19.71
Ditto transomes 1 1 1 4.80 0.60 1.00 2.88
Door shutters; Db-12 1 2 5 0.85 2.15 1.00 18.28
Door shutters; Db-11 1 2 3 1.05 2.15 1.00 13.54
54.41

K Wood surfaces not exceeding 100mm girth M


40mm x 20mm Splayed architrave or qudrant beads where
applicable. 1 1 1 112.60 1.00 1.00 112.60
20mm x 20mm moulded glazing beads 1 1 1 55.40 1.00 1.00 55.40
168.00
BILL NO.2

ELEMENT NO. 8

INTERNAL FINISHINGS

Floor screed; Cement and sand (1:4); wood floated finish:

A 40mm thick; to receive procelain floor tiles (measured separately) M2


Verandah
Verandah 1 1 1 17.80 2.65 1.00 47.17
Entrance points 1 1 3 4.00 0.30 1.00 3.60
Entrance points 1 1 1 1.74 0.30 1.00 0.52
Duct doors/telecoms 1 1 1 1.60 0.30 1.00 0.48
D1-04 1 1 2 1.60 0.30 1.00 0.96

Lobby/office-director/office -CEO
Office part 1 1 1 1 17.80 6.93 1.00 123.35
Duct; recess towards the washrooms/CEO office -1 1 1 0.94 0.65 1.00 -0.61
Office part 2 1 1 1 11.84 1.93 1.00 22.78
D1-13 1 1 1 1.80 0.20 1.00 0.36

Staircase 01 area
Staircase 1 1 1 4.15 3.29 1.00 13.65
Staircase 1 1 1 1.00 0.65 1.00 0.65

Washroom for the CEO


Washroom 1 1 1 5.11 1.77 1.00 9.01
Ddt: duct area -1 1 1 0.93 0.65 1.00 -0.60
Add recess towards CEO's office 1 1 1 0.79 0.65 1.00 0.51
D1-11 1 1 1 1.00 0.15 1.00 0.15
D1-16 1 1 1 0.50 0.15 1.00 0.08

Meeting/finance
Meeting/finance 1 1 1 11.84 11.17 1.00 132.14

GM/Archives/Cashier
GM/Archives/Cashier 1 1 1 17.81 5.97 1.00 106.21
Ddt: duct area -1 1 1 0.93 0.65 1.00 -0.60

Hallway towards staircase 02


Hallway towards staircase 02 1 1 1 9.52 3.14 1.00 29.88
Less; wall -1 1 1 1.00 2.00 1.00 -2.00
D1-11 1 1 3 1.00 0.15 1.00 0.45

Staircase 02 area
Staircase 1 1 1 4.15 2.52 1.00 10.44
Lobbies to the toilets (Female and male)
Lobbies to the toilets (Female and male) 1 1 2 1.60 1.10 1.00 3.52
Openings 1 1 2 1.00 0.15 1.00 0.30

Washroom ; female
Washroom ; female 1 1 1 6.60 3.60 1.00 23.76
Ddt: lobbies to the toilet -1 1 1 1.25 1.75 1.00 -2.19
D1-12 1 1 3 0.80 0.15 1.00 0.36

Washroom ; male
Washroom ; male 1 1 1 6.60 2.80 1.00 18.48
Ddt: lobbies to the toilet -1 1 1 1.25 1.75 1.00 -2.19
D1-12 1 1 2 0.80 0.15 1.00 0.24
D1-15 1 1 2 0.70 0.15 1.00 0.21
Urinal partitions -1 1 3 0.50 0.15 1.00 -0.22

Toilets; Female and make


Toilets; Female and make 1 1 4 1.80 1.00 1.00 7.20

Toilet with a duct


Toilet with a duct 1 1 1 1.50 1.20 1.00 1.80
D1-15 1 1 1 0.70 0.15 1.00 0.11

Utility
Utility 1 1 1 1.80 0.90 1.00 1.62
551.57

D Ditto; on staircase landings ditto M2


Staircase 01
Landing 1 1 1 3.29 1.50 1.00 2.47
Staircase 02
Landing 0 1 1 2.52 1.40 1.00 0.00
2.47

E Ditto; on treads 300mm wide ditto M


Staircase 01
Steps 1 26 1 1.50 1.00 1.00 19.50

Staircase 02
Steps 0 26 1 1.20 1.00 1.00 0.00
19.50

F Ditto; to risers 150 mm high ditto M


Staircase 01
Steps 1 26 1 1.50 1.00 1.00 19.50

Staircase 02
Steps 0 26 1 1.20 1.00 1.00 0.00
19.50

G Ditto; to stringer 375mm wide (maximum) M


Staircase 01
Waist 1 2 2 4.36 1.00 1.00 17.44

Staircase 02
Waist 0 2 2 4.36 1.00 1.00 0.00
17.44

H Skirting; edge of landings M


Staircase 01
Landings 1 1 1 3.29 1.00 1.00 3.29
Landings 1 1 2 1.50 1.00 1.00 3.00
Staircase 02
Landings 0 1 1 2.52 1.00 1.00 0.00
Landings 0 1 2 1.20 1.00 1.00 0.00
6.29

J Ditto; to receive skirting; 100mm high ditto M


Verandah
Verandah 1 1 2 17.80 1.00 1.00 35.60
Verandah 1 1 2 2.65 1.00 1.00 5.30
Entrance points -1 1 3 4.00 1.00 1.00 -12.00
Entrance points -1 1 1 1.74 1.00 1.00 -1.74
Duct doors/telecoms -1 1 1 1.60 1.00 1.00 -1.60
D1-04 -1 1 2 1.60 1.00 1.00 -3.20

Lobby/office-director/office -CEO
Office part 1 1 1 1 17.80 1.00 1.00 17.80
Office part 1 1 1 2 8.86 1.00 1.00 17.71
Office part 1 1 1 1 5.97 1.00 1.00 5.97
Washroom/hallway 1 1 1 1.77 1.00 1.00 1.77
D1-11 -1 1 1 1.00 1.00 1.00 -1.00
D1-04 -1 1 2 1.60 1.00 1.00 -3.20
D1-13 -1 1 1 1.80 1.00 1.00 -1.80

Staircase 01 area
Staircase 1 1 2 4.15 1.00 1.00 8.30
Staircase 1 1 1 3.29 1.00 1.00 3.29
Staircase 1 1 2 0.65 1.00 1.00 1.30
Duct: lift door -1 1 1 1.22 1.00 1.00 -1.22

Washroom for the CEO


Washroom 1 0 2 5.11 1.00 1.00 0.00
Washroom 1 0 2 1.77 1.00 1.00 0.00
Add recess towards CEO's office 1 0 2 0.79 1.00 1.00 0.00
D1-11 1 0 1 1.00 1.00 1.00 0.00
D1-16 1 0 1 0.50 1.00 1.00 0.00

Meeting/finance
Meeting/finance 1 1 1 11.84 1.00 1.00 11.84

GM/Archives/Cashier
GM/Archives/Cashier 1 1 1 17.81 1.00 1.00 17.81
GM/Archives/Cashier 1 1 2 5.97 1.00 1.00 11.93
D1-16 -1 1 1 0.50 1.00 1.00 -0.50

Hallway towards staircase 02


Hallway towards staircase 02 1 1 1 9.52 1.00 1.00 9.52
Hallway towards staircase 02 1 1 2 3.14 1.00 1.00 6.28
Hallway towards staircase 02 1 1 1 2.42 1.00 1.00 2.42
D1-11 -1 1 3 1.00 1.00 1.00 -3.00
Openings -1 1 1 2.00 1.00 1.00 -2.00

Staircase 02 area
Staircase 1 1 2 4.15 1.00 1.00 8.30
Staircase 1 1 1 2.52 1.00 1.00 2.52
D1-11 -1 1 1 1.00 1.00 1.00 -1.00
cornice 1 0 2 4.45 1.00 1.00 0.00
cornice 1 0 1 2.52 1.00 1.00 0.00

Lobbies to the toilets (Female and male)


Lobbies to the toilets (Female and male) 1 2 2 1.60 1.00 1.00 6.40
Lobbies to the toilets (Female and male) 1 2 2 1.10 1.00 1.00 4.40
Openings -1 1 2 1.00 1.00 1.00 -2.00
D1-11 -1 1 2 1.00 1.00 1.00 -2.00

Washroom ; female
Washroom ; female 1 0 2 6.60 1.00 1.00 0.00
Washroom ; female 1 0 2 3.60 1.00 1.00 0.00
Openings -1 0 1 1.00 1.00 1.00 0.00
D1-12 -1 0 3 0.80 1.00 1.00 0.00

Washroom ; male
Washroom ; male 1 1 2 6.60 1.00 0.00 0.00
Washroom ; male 1 1 2 2.80 1.00 0.00 0.00
Openings -1 0 1 1.00 1.00 0.00 0.00
D1-12 -1 1 2 0.80 1.00 0.00 0.00
D1-15 -1 1 2 0.70 1.00 0.00 0.00
Urinal partitions 1 2 3 0.68 1.00 0.00 0.00

Toilets; Female and make


Toilets; Female and make 1 2 4 1.80 1.00 0.00 0.00
Toilets; Female and make 1 2 4 1.00 1.00 0.00 0.00
D1-12 -1 1 2 0.80 1.00 0.00 0.00

Toilet with a duct


Toilet with a duct 1 1 2 1.50 1.00 0.00 0.00
Toilet with a duct 1 1 2 1.20 1.00 0.00 0.00
D1-15 -1 1 1 0.70 1.00 0.00 0.00

Utility
Utility 1 1 2 1.80 1.00 0.00 0.00
Utility 1 1 2 0.90 1.00 0.00 0.00
D1-15 -1 1 2 0.70 1.00 0.00 0.00
142.17

Supply and Fix approved ceramic tiles; non-slip; laid in an


approved pattern; bedded in approved adhesive cement and
pointed with an approved tile grout

M Size 450 x 450 x 10 mm thick to floors M2


1 1 1 551.57 1.00 1.00 551.57
551.57

D Ditto; on staircase landings ditto M2


Staircase 01 & 02 1 1 1 2.47 1.00 1.00 2.47

2.47

E Ditto; on treads 275mm wide ditto M


Staircase 01 & 02 1 1 19.50 1.00 1.00 1.00 19.50

19.50

F Ditto; to risers 150 mm high ditto M


Staircase 01 & 02 1 1 19.50 1.00 1.00 1.00 19.50

19.50

G Ditto; to stringer 375mm wide (maximum) M


Staircase 01 & 02 1 1 17.44 1.00 1.00 1.00 17.44

17.44

H Edge of staircase landing; 200mm wide M


Staircase 01 & 02 1 1 2 4.80 1.00 1.00 9.60

9.60

J Ditto; to receive skirting; 100mm high ditto M


1 1 1 142.17 1.00 1.00 142.17
142.17

WATERPROOFING TO TOILETS and OTHER WET AREAS

Pure crystalline water proofing treatment in two coats using


"Vandex Super" manufactured by M/s. Vandex East Africa Limited
or approved equivalent to vertical and horizontal surfaces, with
proper gradient including surface preparation and applying slurry
coat of Vandex Super mixed with a cement sand mortar 1:3,
cleaning , pre-watering and then applying two coats of Vandex
Super (each coat approx. 0.75 kg per Sm) mixed to a slurry
consistency, curing, protecting the completed work by hessian
cloth, providing bonding keys for each coat, fillets, testing for water
tightness complete all as per manufacturer's specifications,
drawings and as directed by the Project Manager on:

To wet areas
51.37

WALL FINISHES

Wall Tile backing

Screed backing to wall; Cement and sand (1:4); wood floated


finish:
C 12mm thick; to receive ceramic wall tiles (measured separately) M2
Wall tiles
Female toilet/lobby
Female toilet/lobby 1 1 2 3.60 1.00 2.10 15.12
Female toilet/lobby 1 1 2 6.60 1.00 2.10 27.72
Openings to toilets -1 1 1 1.00 1.00 2.10 -2.10
D1-12 -1 1 3 0.80 1.00 2.10 -5.04

Female Toilets /3
Female Toilets /3 1 1 2 1.80 1.00 2.10 7.56
Female Toilets /3 1 1 2 1.00 1.00 2.10 4.20
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36

Female Toilets /3 1 1 2 1.50 1.00 2.10 6.30


Female Toilets /3 1 1 2 1.15 1.00 2.10 4.83
D1-12 -1 1 1 0.80 1.00 2.10 -1.68
Add; door ways D1-15 -1 1 1 0.70 1.00 2.10 -1.47

Male toilet/lobby
Male toilet/lobby 1 1 2 2.80 1.00 2.10 11.76
Male toilet/lobby 1 1 2 6.60 1.00 2.10 27.72
Openings to toilets -1 1 1 1.00 1.00 2.10 -2.10
D1-12 -1 1 2 0.80 1.00 2.10 -3.36

Add; urinal partition walls 1 2 3 0.65 1.00 2.10 8.19


Add; door ways D1-15 -1 1 2 0.70 1.00 2.10 -2.94

Toilets and duct


Toilets and duct 1 2 2 1.80 1.00 2.10 15.12
Toilets and duct 1 2 2 1.00 1.00 2.10 8.40
Toilets and duct 1 1 2 1.80 1.00 2.10 7.56
Toilets and duct 1 1 2 0.60 1.00 2.10 2.52
Add; door ways D1-15 -1 1 2 0.70 1.00 2.10 -2.94
D1-12 -1 1 2 0.80 1.00 2.10 -3.36

Deductions
Generally deduct the windows for the washrooms
W1-10 -1 1 2 1.57 1.00 1.20 -3.76
114.89

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm


second coat of cement and lime putty (1:10); steel trowelled
to:

D Walls M2
Verandah
Verandah 1 1 2 17.80 1.00 3.65 129.94
Verandah 1 1 2 2.65 1.00 3.65 19.35
Entrance points -1 1 3 4.00 1.00 3.10 -37.20
Entrance points -1 1 1 1.74 1.00 3.10 -5.39
Duct doors/telecoms -1 1 1 1.60 1.00 2.65 -4.24
D1-04 -1 1 2 1.60 1.00 2.65 -8.48
W1-06 -1 1 2 1.60 1.00 2.20 -7.04
W1-05 -1 1 2 1.60 1.00 2.65 -8.48
Add: Reveals and jambs
Entrance points 1 1 3 10.20 0.30 1.00 9.18
Entrance points 1 1 1 7.94 0.30 1.00 2.38
Duct doors/telecoms 1 1 1 6.90 0.30 1.00 2.07
D1-04 1 1 2 6.90 0.30 1.00 4.14
W1-06 1 1 2 7.60 0.30 1.00 4.56
W1-05 1 1 2 8.50 0.30 1.00 5.10

Lobby/office-director/office -CEO
Office part 1 1 1 1 17.80 1.00 3.65 64.97
Office part 1 1 1 2 8.86 1.00 3.65 64.64
Office part 1 1 1 1 5.97 1.00 3.65 21.77
Washroom/hallway 1 1 1 1.77 1.00 3.65 6.44
D1-11 -1 1 1 1.00 1.00 2.65 -2.65
D1-04 -1 1 2 1.60 1.00 2.65 -8.48
D1-13 -1 1 1 1.80 1.00 2.65 -4.77
W1-07 -1 1 1 1.57 1.00 2.20 -3.44
W1-10 -1 1 2 1.57 1.00 2.20 -6.89
Add: Reveals and jambs
D1-11 -1 1 1 6.90 0.15 1.00 -1.04
D1-04 -1 1 2 7.10 0.30 1.00 -4.26
D1-13 -1 1 1 5.97 0.20 1.00 -1.19
W1-07 -1 1 1 7.53 0.30 1.00 -2.26
W1-10 -1 1 2 7.53 0.30 1.00 -4.52

Staircase 01 area
Staircase 1 1 2 8.88 1.00 3.65 64.82
Staircase 1 1 1 3.29 1.00 3.65 12.01
Staircase 1 1 2 0.65 1.00 3.65 4.75
Duct: lift door -1 1 1 1.22 1.00 2.10 -2.56
D1-13 -1 1 1 1.60 1.00 2.65 -4.24
W1-07 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
Duct: lift door 1 1 1 5.42 0.20 1.00 1.08
D1-13 1 1 1 6.90 0.20 1.00 1.38
W1-07 1 1 1 7.53 0.30 1.00 2.26

Washroom for the CEO


Washroom 1 1 2 5.11 1.00 3.65 37.27
Washroom 1 1 2 1.77 1.00 3.65 12.88
Add recess towards CEO's office 1 1 2 0.79 1.00 3.65 5.73
D1-11 -1 1 1 1.00 1.00 2.65 -2.65
D1-16 -1 1 1 0.50 1.00 2.65 -1.33
W1-10 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
D1-11 1 1 1 6.30 0.15 1.00 0.95
D1-16 1 1 1 5.80 0.15 1.00 0.87
W1-10 1 1 1 7.53 0.30 1.00 2.26

Meeting/finance
Meeting/finance 1 1 1 11.84 1.00 3.65 43.20
W1-10 1 1 3 1.57 1.00 2.20 10.33
Add: Reveals and jambs
W1-10 1 1 3 7.53 0.30 1.00 6.78

GM/Archives/Cashier
GM/Archives/Cashier 1 1 1 17.81 1.00 3.65 64.99
GM/Archives/Cashier 1 1 2 5.97 1.00 3.65 43.54
D1-16 -1 1 1 0.50 1.00 2.65 -1.33
W1-10 -1 1 7 1.57 1.00 2.20 -24.10
Add: Reveals and jambs
W1-10 1 1 7 7.53 0.30 1.00 15.81
Hallway towards staircase 02
Hallway towards staircase 02 1 1 1 9.52 1.00 3.65 34.73
Hallway towards staircase 02 1 1 2 3.14 1.00 3.65 22.92
Hallway towards staircase 02 1 1 1 2.42 1.00 3.65 8.81
D1-11 -1 1 3 1.00 1.00 2.65 -7.95
W1-10 -1 1 1 1.57 1.00 2.20 -3.44
Openings -1 1 1 2.00 1.00 3.65 -7.30

Add: Reveals and jambs


D1-11 1 1 3 6.30 0.15 1.00 2.84
W1-10 1 1 1 7.53 0.30 1.00 2.26

Staircase 02 area
Staircase 1 1 2 8.55 1.00 3.65 62.42
Staircase 1 1 2 2.52 1.00 3.65 18.36
W1-10 -1 1 3 1.57 1.00 2.20 -10.33
D1-11 -1 1 1 1.00 1.00 2.65 -2.65
Add: Reveals and jambs
W1-10 1 1 1 7.53 0.30 1.00 2.26

Toilets/entrance lobby
Toilets/entrance lobby 1 2 2 1.60 1.00 3.65 23.36
Toilets/entrance lobby 1 2 2 1.10 1.00 3.65 16.06
Openings to toilets -1 2 1 1.00 1.00 2.65 -5.30
Less: Dg-11 -1 1 2 1.00 1.00 2.65 -5.30
Add: Reveals and jambs
Doors and openings
Openings to toilets 1 2 1 6.30 0.15 1.00 1.89
Less: Dg-11 (alreadly considered)

Female toilet/lobby
Toilets/entrance lobby (to receive Two coats of “Plascon Hygienic
Coating” paint finishes over the appropriate undercoat
Female toilet/lobby 1 1 2 3.60 1.00 3.65 26.28
Female toilet/lobby 1 1 2 6.55 1.00 3.65 47.82
Openings to toilets -1 1 1 1.00 1.00 2.65 -2.65
Dg-12 -1 1 3 0.80 1.00 2.10 -5.04
Add: Reveals and jambs
Doors and openings
Openings to toilets (already considered)
Dg-12 1 1 3 5.00 0.20 1.00 3.00

Female Toilets /3
Female Toilets /3 1 1 2 1.80 1.00 3.65 13.14
Female Toilets /3 1 1 2 1.00 1.00 3.65 7.30
Dg-12 -1 1 2 0.80 1.00 2.65 -4.24
Wg-10 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
Doors and openings
Dg-12 1 1 2 6.10 0.20 1.00 2.44
Wg-10 1 1 1 7.53 0.30 1.00 2.26

Female Toilets /3
Female Toilets /3 1 1 2 1.50 1.00 3.65 10.95
Female Toilets /3 1 1 2 1.15 1.00 3.65 8.40
Dg-12 -1 1 1 0.80 1.00 2.10 -1.68
Add; door ways Dg-15 -1 1 1 0.70 1.00 2.65 -1.85

Add: Reveals and jambs


Doors and openings
Dg-12 1 1 1 5.00 0.20 1.00 1.00
Add; door ways Dg-15 1 1 1 6.00 0.15 1.00 0.90

Male toilet/lobby
Male toilet/lobby 1 1 2 2.80 1.00 3.65 20.44
Male toilet/lobby 1 1 2 6.55 1.00 3.65 47.82
Openings to toilets -1 1 1 1.00 1.00 2.65 -2.65
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36
Add; urinal partition walls 1 2 3 0.65 1.00 3.65 14.24
Add; door ways Dg-15 -1 1 2 0.70 1.00 2.65 -3.71
Add: Reveals and jambs
Doors and openings
Dg-12 1 1 2 0.80 0.20 1.00 0.32
Add; door ways Dg-15 1 1 2 0.70 0.20 1.00 0.28
Openings to toilets (already considered)

Toilets and duct


Toilets and duct 1 2 2 1.80 1.00 3.65 26.28
Toilets and duct 1 2 2 1.00 1.00 3.65 14.60
Toilets and duct 1 1 2 1.80 1.00 3.65 13.14
Toilets and duct 1 1 2 0.60 1.00 3.65 4.38
Add; door ways Dg-15 -1 1 2 0.70 1.00 2.65 -3.71
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36
Wg-10 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
Doors and openings
Add; door ways Dg-15 1 1 2 6.00 0.20 1.00 2.40
Dg-12 1 1 2 5.00 0.20 1.00 2.00
Wg-10 1 1 1 7.53 0.30 1.00 2.26

Less: Tiled area

Tiled area -1 1 1 114.89 1.00 1.00 -114.89


F Walls M2 783.26

E Concrete surfaces (exposed beam and column surfaces) M2 770.80


Supply and fix approved glazed ceramic wall tiles; 300mm x
200mm x 6mm thick; approved colour; bedding and jointing
on screed (measured separately) with approved water proof
adhesive; flush pointing in approved coloured grout to:

F Walls M2 114.89

SUNDRIES

Accessories

G Edge trim; plastic; quarter round; setting at edges of wall tile finish M
Wall tiles

Female toilet/lobby
Female toilet/lobby 1 1 2 3.60 1.00 1.00 7.20
Female toilet/lobby 1 1 2 6.55 1.00 1.00 13.10
Openings to toilets 1 2 1 1.00 1.00 2.10 4.20
Dg-12 1 2 3 1.00 1.00 2.10 12.60

Female Toilets /3
Female Toilets /3 1 1 2 1.80 1.00 2.10 7.56
Female Toilets /3 1 2 2 1.00 1.00 2.10 8.40
Dg-12 1 2 2 1.00 1.00 2.10 8.40

Female Toilets /3 1 1 2 1.50 1.00 2.10 6.30


Female Toilets /3 1 1 2 1.15 1.00 2.10 4.83
Dg-12 1 2 1 1.00 1.00 2.10 4.20
Add; door ways Dg-15 1 2 1 1.00 1.00 2.10 4.20

Male toilet/lobby
Male toilet/lobby 1 1 2 2.80 1.00 2.10 11.76
Male toilet/lobby 1 1 2 6.55 1.00 2.10 27.51
Openings to toilets 1 2 1 1.00 1.00 2.10 4.20
Dg-12 1 2 2 1.00 1.00 2.10 8.40

Add; urinal partition walls 1 2 3 0.65 1.00 2.10 8.19


Add; door ways Dg-15 1 2 2 0.70 1.00 1.00 2.80

Toilets and duct


Toilets and duct 1 2 2 1.80 1.00 2.10 15.12
Toilets and duct 1 2 2 1.00 1.00 2.10 8.40
Toilets and duct 1 1 2 1.80 1.00 2.10 7.56
Toilets and duct 1 1 2 0.60 1.00 2.10 2.52
Add; door ways Dg-15 1 2 2 1.00 1.00 2.10 8.40
Dg-12 1 2 2 1.00 1.00 2.10 8.40
Deductions
Generally deduct the windows for the washrooms
Wg-10 1 1 2 3.97 1.00 1.00 7.94
202.19

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm


second coat of cement and lime putty (1:10); steel trowelled
to:

G Concrete ceiling soffites. M2


1 1 1 512.50 1.00 1.00 512.50
512.50

H Staircase landing soffites M2 2.47

J Sloping staircase sofffites M2 13.08

K Moulded Ceiling cornice as per Architect's detail M


Verandah
Verandah 1 1 2 17.80 1.00 1.00 35.60
Verandah 1 1 2 2.65 1.00 1.00 5.30

Lobby/office-director/office -CEO
Office part 1 1 1 1 17.80 1.00 1.00 17.80
Office part 1 1 1 2 8.86 1.00 1.00 17.71
Office part 1 1 1 1 5.97 1.00 1.00 5.97
Washroom/hallway 1 1 1 1.77 1.00 1.00 1.77

Staircase 01 area
Staircase 1 1 2 8.88 1.00 1.00 17.76
Staircase 1 1 2 3.29 1.00 1.00 6.58
Staircase 1 1 2 0.65 1.00 1.00 1.30

Washroom for the CEO


Washroom 1 1 2 5.11 1.00 1.00 10.21
Washroom 1 1 2 1.77 1.00 1.00 3.53
Add recess towards CEO's office 1 1 2 0.79 1.00 1.00 1.57

Meeting/finance
Meeting/finance 1 1 1 11.84 1.00 1.00 11.84

GM/Archives/Cashier
GM/Archives/Cashier 1 1 1 17.81 1.00 1.00 17.81
GM/Archives/Cashier 1 1 2 5.97 1.00 1.00 11.93

Hallway towards staircase 02


Hallway towards staircase 02 1 1 1 9.52 1.00 1.00 9.52
Hallway towards staircase 02 1 1 2 3.14 1.00 1.00 6.28
Hallway towards staircase 02 1 1 1 2.42 1.00 1.00 2.42
Openings -1 1 1 2.00 1.00 1.00 -2.00

Staircase 02 area
Staircase 1 1 2 8.60 1.00 1.00 17.20
Staircase 1 1 2 2.52 1.00 1.00 5.03

Lobbies to the toilets (Female and male)


Lobbies to the toilets (Female and male) 1 2 2 1.60 1.00 1.00 6.40
Lobbies to the toilets (Female and male) 1 2 2 1.10 1.00 1.00 4.40

Washroom ; female
Washroom ; female 1 1 2 6.60 1.00 1.00 13.20
Washroom ; female 1 1 2 3.60 1.00 1.00 7.20

Washroom ; male
Washroom ; male 1 1 2 6.60 1.00 11.00 145.20
Washroom ; male 1 1 2 2.80 1.00 1.00 5.60
Urinal partitions 1 2 3 0.68 1.00 1.00 4.05

Toilets; Female and make


Toilets; Female and make 1 2 4 1.80 1.00 1.00 14.40
Toilets; Female and make 1 2 4 1.00 1.00 1.00 8.00

Toilet with a duct


Toilet with a duct 1 1 2 1.50 1.00 1.00 3.00
Toilet with a duct 1 1 2 1.20 1.00 1.00 2.40
Utility
Utility 1 1 2 1.80 1.00 1.00 3.60
Utility 1 1 2 0.90 1.00 1.00 1.80
424.35

Mild steel Staircase balustrade; welded construction; shop


primed with red oxide

A Horizontal or raking balustrade; 900mm high comprising of;


50mx3mm thick CHS handrail; 4 No. 25x2mm thick CHS
intermediate horizontal rails; 2/50x6mm thick MS flat balusters,
mild steel base plates; all rawl bolted into concrete; including
primer, spray painting wth three coats gloss oil paint and
decorations to approval.
M
Staircase 01
Waist 1 1 2 4.36 1.00 1.00 8.72
Void 1 1 1 1.70 1.00 1.00 1.70
Void 1 1 1 0.20 1.00 1.00 0.20

Staircase 02
Waist 0 1 2 4.36 1.00 1.00 0.00
Void 0 1 1 1.40 1.00 1.00 0.00
Void 0 1 1 0.20 1.00 1.00 0.00
10.62

A Dado rails; Supply and fix 50mm diameter x 6mm thick CHS mild
steel handrail plugged with 25mm x 4mm thick mild steel support
fixed into wall; all painting and decorations M
Staircase 01
Waist 1 1 2 4.36 1.00 1.00 8.72
Landing 1 1 2 1.50 1.00 1.00 3.00
Landing 1 1 1 3.29 1.00 1.00 3.29

Staircase 02
Waist 0 1 2 4.36 1.00 1.00 0.00
Void 0 1 2 1.40 1.00 1.00 0.00
Void 0 1 1 2.52 1.00 1.00 0.00
15.01

Glass railing; 900mm high comprising of 12mm thick tempered


(toughed) laminated glass fixed to and including 50x50mm chrome
plated stainless steel handrails, bottom rails and vertical balusters
spaced at 900mm centres; all chrome plated stainless brackets; all
cast in concrete.
M
Verandah 1 1 3 4.00 1.00 1.00 12.00
Verandah 1 1 1 1.44 1.00 1.00 1.44
13.44

Prepare and apply one undercoat and two finishing coats of


matt emulsion paint in accordance with manufacturer's
instructions to:

B Concrete ceiling soffites. M2 512.50

C Staircase landing soffites M2 2.47

D Sloping staircase sofffites M2 13.08

E Moulded Ceiling cornice as per Architect's detail M 424.35

Prepare and apply one undercoat and two finishing coats of


silk vinyl paint in accordance with manufacturer's instructions
to:

Plastered walls 1 1 1 559.78 1.00 1.00 559.78


559.78

Prepare and apply one undercoat and two finishing coats of


hygienic coating paint in accordance with the manufacturer's
instructions to:
Female toilet/lobby 1 1 2 3.60 1.00 3.65 26.28
Female toilet/lobby 1 1 2 6.55 1.00 3.65 47.82
Openings to toilets -1 1 1 1.00 1.00 2.65 -2.65
Dg-12 -1 1 3 0.80 1.00 2.10 -5.04
Add: Reveals and jambs
Doors and openings
Openings to toilets (already considered)
Dg-12 1 1 3 5.00 0.20 1.00 3.00

Female Toilets /3
Female Toilets /3 1 1 2 1.80 1.00 3.65 13.14
Female Toilets /3 1 1 2 1.00 1.00 3.65 7.30
Dg-12 -1 1 2 0.80 1.00 2.65 -4.24
Wg-10 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
Doors and openings
Dg-12 1 1 2 6.10 0.20 1.00 2.44
Wg-10 1 1 1 7.53 0.30 1.00 2.26

Female Toilets /3
Female Toilets /3 1 1 2 1.50 1.00 3.65 10.95
Female Toilets /3 1 1 2 1.15 1.00 3.65 8.40
Dg-12 -1 1 1 0.80 1.00 2.10 -1.68
Add; door ways Dg-15 -1 1 1 0.70 1.00 2.65 -1.85

Add: Reveals and jambs


Doors and openings
Dg-12 1 1 1 5.00 0.20 1.00 1.00
Add; door ways Dg-15 1 1 1 6.00 0.15 1.00 0.90

Male toilet/lobby
Male toilet/lobby 1 1 2 2.80 1.00 3.65 20.44
Male toilet/lobby 1 1 2 6.55 1.00 3.65 47.82
Openings to toilets -1 1 1 1.00 1.00 2.65 -2.65
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36
Add; urinal partition walls 1 2 3 0.65 1.00 3.65 14.24
Add; door ways Dg-15 -1 1 2 0.70 1.00 2.65 -3.71
Add: Reveals and jambs
Doors and openings
Dg-12 1 1 2 0.80 0.20 1.00 0.32
Add; door ways Dg-15 1 1 2 0.70 0.20 1.00 0.28
Openings to toilets (already considered)

Toilets and duct


Toilets and duct 1 2 2 1.80 1.00 3.65 26.28
Toilets and duct 1 2 2 1.00 1.00 3.65 14.60
Toilets and duct 1 1 2 1.80 1.00 3.65 13.14
Toilets and duct 1 1 2 0.60 1.00 3.65 4.38
Add; door ways Dg-15 -1 1 2 0.70 1.00 2.65 -3.71
Dg-12 -1 1 2 0.80 1.00 2.10 -3.36
Wg-10 -1 1 1 1.57 1.00 2.20 -3.44
Add: Reveals and jambs
Doors and openings
Add; door ways Dg-15 1 1 2 6.00 0.20 1.00 2.40
Dg-12 1 1 2 5.00 0.20 1.00 2.00
Wg-10 1 1 1 7.53 0.30 1.00 2.26
Less:
tiled area -1 1 1 114.89 1.00 1.00 -114.89
117.59
Prepare and apply 1.5mm thick layer of textured decorative
paint finishes to the plastered wall.
Verandah
Verandah 1 1 2 17.80 1.00 3.65 129.94
Verandah 1 1 2 2.65 1.00 3.65 19.35
Entrance points -1 1 3 4.00 1.00 3.10 -37.20
Entrance points -1 1 1 1.74 1.00 3.10 -5.39
Duct doors/telecoms -1 1 1 1.60 1.00 2.65 -4.24
D1-04 -1 1 2 1.60 1.00 2.65 -8.48
W1-06 -1 1 2 1.60 1.00 2.20 -7.04
W1-05 -1 1 2 1.60 1.00 2.65 -8.48
Add: Reveals and jambs
Entrance points 1 1 3 10.20 0.30 1.00 9.18
Entrance points 1 1 1 7.94 0.30 1.00 2.38
Duct doors/telecoms 1 1 1 6.90 0.30 1.00 2.07
D1-04 1 1 2 6.90 0.30 1.00 4.14
W1-06 1 1 2 7.60 0.30 1.00 4.56
W1-05 1 1 2 8.50 0.30 1.00 5.10
105.88
Prepare and apply one undercoat and two finishing coats of
gloss oil paint in accordance with manufacturer's instructions
to:

J General surfaces of metal (measured flat both sides) M2


Balustrades
Staircase 01
Waist 1 2 2 4.36 1.00 0.90 15.70
Void 1 2 1 1.70 1.00 0.90 3.06
Void 1 2 1 0.20 1.00 0.90 0.36

Staircase 02
Waist 1 2 2 4.36 1.00 0.90 15.70
Void 1 2 1 1.40 1.00 0.90 2.52
Void 1 2 1 0.20 1.00 0.90 0.36
Dado rails; M
Staircase 01
Waist 1 2 2 4.36 1.00 0.30 5.23
Landing 1 2 2 1.50 1.00 0.30 1.80
Landing 1 2 1 3.29 1.00 0.30 1.97

Staircase 02
Waist 1 2 2 4.36 1.00 0.30 5.23
Void 1 2 2 1.40 1.00 0.30 1.68
Void 1 2 1 2.52 1.00 0.30 1.51
M2 55.12
ELEMENT NO. 8
INTERNAL FINISHINGS

BILL NO.2

ELEMENT NO. 9

EXTERNAL FINISHINGS

20mm thick rendering in Cement and Sand (1:4) mortar; as


per Architect's details; on:

A Walls and concrete surfaces M2


G/L G(2-5) 1 1 1 18.40 1.00 3.90 71.76
Walls at telecom duct towards the lift shaft 1 1 2 0.84 1.00 3.90 6.55
G/L G(2-5) 1 1 1 30.09 1.00 3.90 117.35
G/L G(2-5) 1 1 1 6.30 1.00 3.90 24.57
G/L G(2-5) 1 1 1 12.40 1.00 3.90 48.36
G/L G(2-5) 1 1 2 2.42 1.00 3.90 18.84
G/L G(2-5) 1 1 1 18.00 1.00 3.90 70.19
G/L G(2-5) 1 1 1 3.59 1.00 3.90 14.00
G/L G(2-5) 1 1 1 9.15 1.00 3.90 35.67
G/L G(2-5) 1 1 1 2.65 1.00 3.90 10.33
G/L G(2-5) 1 1 1 17.80 1.00 3.90 69.42

Deductions
Openings and doors
Verandah openings/front -1 1 3 3.70 1.00 3.10 -34.41
Verandah openings/sides -1 1 1 1.44 1.00 3.10 -4.46
D1-13 -1 1 1 1.60 1.00 2.65 -4.24
D1-04 -1 1 2 1.60 1.00 2.65 -8.48

Windows
W1-06 -1 1 2 1.60 1.00 2.20 -7.04
W1-05 -1 1 2 1.60 1.00 2.65 -8.48
W1-07 -1 1 3 1.57 1.00 2.20 -10.33
W1-10 -1 1 19 1.57 1.00 2.20 -65.42

Lift shall walls 1 1 4 2.45 1.00 3.90 38.22


Less: Lift door "unamed" -1 1 1 1.22 1.00 2.10 -2.56
379.84

Prepare and apply Plascon Architexture Grafiato coating in


accordance with manufacturer's instructions to:

379.84
ELEMENT NO. 9
EXTERNAL FINISHINGS

BILL NO.2

ELEMENT NO. 10

FITTINGS

A Alow a provisional sum of Ushs. 10,000,000 for fittings 9,160,000.00

Washroom wash basin worktop 1 1 2 2.00 1.00 850000.00 3,400,000.00


Janitor store 1 1 2 2.40 1.00 1200000.00 5,760,000.00
CLIENT: CK COMPANY DATE: 4/5/2024
PROJECT: PROPOSED OFFICE BLOCK CALC BY: IB
LEVEL GROUND FLOOR
MEASUREMENTS PURPOSE: ESTIMATES
NO. DESCRIPTION UNIT EQ. PRTS EQ. PRTS EQ. PRTS L W H/D/kg/m QTY

SECOND FLOOR

SUPERSTRUCTURE

RC in grade 25 to columns M3
C1 9 1 1 0.40 0.40 3.25 4.68
C2 3 1 1 0.40 0.60 3.25 2.34
C3 6 1 1 0.40 0.60 3.25 4.68
C5 3 1 1 0.40 0.60 3.25 2.34
C6 1 1 1 0.35 0.35 3.25 0.40
14.44

RC in grade 25 to beams M3
G/L E(1-2) & F(1-2) 1 1 2 3.14 0.40 0.55 1.38
G/L G(1-2) 1 1 1 1.10 0.40 0.55 0.24
G/L A(1-4) 1 1 1 12.45 0.40 0.55 2.74
G/L B,C,D,E,F(2-3) 1 1 5 5.50 0.40 0.55 6.05
G/L G(2-3) 1 1 1 5.60 0.40 0.55 1.23
G/L B(3-4) 1 1 1 5.45 0.40 0.55 1.20
G/L C(3-4) 1 1 1 5.45 0.40 0.55 1.20
G/L D(3-4) 1 1 1 5.45 0.40 0.55 1.20
G/L E(3-4) 1 1 1 11.45 0.40 0.55 2.52
G/L F(3-4) 1 1 1 11.45 0.40 0.55 2.52
G/L G(3-4) 1 1 1 5.65 0.40 0.55 1.24
G/L G(4-5) 1 1 1 5.60 0.40 0.55 1.23

G/L A2-B2, A3-B3, A3'-B3', A4-B4 1 1 4 2.32 0.40 0.55 2.04


G/L B2-C2 & B3-C3 1 1 2 5.60 0.40 0.55 2.46
G/L B4-C4 1 1 1 5.50 0.40 0.55 1.21
G/L 2,3 & 4 (C-D) 1 1 3 5.60 0.40 0.55 3.70
G/L 2,3,& 4(D-E) 1 1 3 5.60 0.40 0.55 3.70
G/L 1,2,3 & 5 (E-F) 1 1 4 5.60 0.40 0.55 4.93
G/L F1-G1 1 1 1 2.75 0.40 0.55 0.61
G/L 2,3 & 5 (F-G) 1 1 3 5.59 0.40 0.55 3.69
45.08
Upstand beam and moulding as per the Architects details.

RC in grade 25 to the staircase M3


Staircase 01/Architetcural
Steps 1 26 1/2 0.30 0.15 1.50 0.44
Waist 1 1 2 4.36 1.50 0.20 2.62
3.05

200mm thick to staircase landing M2


Staircase 01
Landing 1 1 1 3.29 1.70 1.00 2.80
2.80

Landing beams M2
Staircase 01
Landing beams 1 1 1 3.89 0.20 0.20 0.08
Staircase 02
Landing beams 1 1 0 3.12 0.20 0.20 0.00
0.08

RC in grade 25 to the lift walls 20mm thick M2


2 1 1 2.45 1.00 3.50 17.15
2 1 1 2.05 1.00 3.50 14.35
Less opening -1 1 1 1.22 1.00 2.10 - 2.56
28.94

250mm thick solid slab in RC grade 25 M2


Part 1; see planswift file 1 1 1 15.60 15.30 1.00 238.68
Part 2; see planswift file 1 1 1 6.00 2.40 1.00 14.40
Part 3; see planswift file 1 1 1 12.60 12.60 1.00 158.76
Part 4; see planswift file 1 1 1 12.60 6.50 1.00 81.90
Part 5; see planswift file 1 1 1 4.00 0.30 1.00 1.20
Deduct: Voids
Staircase 01 -1 1 1 4.95 3.20 1.00 - 15.84
Void verandah -1 1 1 16.65 1.45 1.00 - 24.14
Void/terrace -1 1 1 5.70 2.76 1.00 - 15.73
Lift shaft -1 1 1 2.05 2.05 1.00 - 4.20
435.02
Reinforcements

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Columns 1 1 150 14.44 1.00 1.00 2,165.72
RC in grade 25 to beams 1 1 150 45.08 1.00 1.00 6,762.20
Upstand beam and moulding as per the Architects details. 1 1 150 - 1.00 1.00 -
RC in grade 25 to the staircase 1 1 150 3.05 1.00 1.00 458.24
200mm thick to staircase landing 1 1 150 2.80 1.00 1.00 419.48
Landing beams 1 1 150 0.08 1.00 1.00 11.67
RC in grade 25 to the lift walls 20mm thick 1 1 150 28.94 0.20 1.00 868.14
250mm thick solid slab in RC grade 25 1 1 150 435.02 0.25 1.00 16,313.36
26,998.80

Sawn form work to;

Sides of columns M2
C1 9 1 2 0.80 1.00 3.25 46.80
C2 3 1 2 1.00 1.00 3.25 19.50
C3 6 1 2 1.00 1.00 3.25 39.00
C5 3 1 2 1.00 1.00 3.25 19.50
C6 1 1 2 0.70 1.00 3.25 4.55
129.35

Sides and soffits of beams M2


G/L E(1-2) & F(1-2) 1 1 2 3.14 1.50 1.00 9.42
G/L G(1-2) 1 1 1 1.10 1.50 1.00 1.65
G/L A(1-4) 1 1 1 12.45 1.50 1.00 18.67
G/L B,C,D,E,F(2-3) 1 1 5 5.50 1.50 1.00 41.25
G/L G(2-3) 1 1 1 5.60 1.50 1.00 8.40
G/L B(3-4) 1 1 1 5.45 1.50 1.00 8.18
G/L C(3-4) 1 1 1 5.45 1.50 1.00 8.18
G/L D(3-4) 1 1 1 5.45 1.50 1.00 8.18
G/L E(3-4) 1 1 1 11.45 1.50 1.00 17.17
G/L F(3-4) 1 1 1 11.45 1.50 1.00 17.17
G/L G(3-4) 1 1 1 5.65 1.50 1.00 8.48
G/L G(4-5) 1 1 1 5.60 1.50 1.00 8.40

G/L A2-B2, A3-B3, A3'-B3', A4-B4 1 1 4 2.32 1.50 1.00 13.92


G/L B2-C2 & B3-C3 1 1 2 5.60 1.50 1.00 16.80
G/L B4-C4 1 1 1 5.50 1.50 1.00 8.25
G/L 2,3 & 4 (C-D) 1 1 3 5.60 1.50 1.00 25.20
G/L 2,3,& 4(D-E) 1 1 3 5.60 1.50 1.00 25.20
G/L 1,2,3 & 5 (E-F) 1 1 4 5.60 1.50 1.00 33.60
G/L F1-G1 1 1 1 2.75 1.50 1.00 4.13
G/L 2,3 & 5 (F-G) 1 1 3 5.59 1.50 1.00 25.13
307.37

Sides of upstand beams and mouldings

Extra over formwork to parapet walls for forming grooves,


chamfers, rebates, chases and mouldings.

-
Sides and soffits of staircase landing beams M2
Staircase 01
Sides and soffits of staircase landing beams 1 1 1 3.89 0.20 0.20 0.08
Staircase 02
Sides and soffits of staircase landing beams 1 1 0 3.12 0.20 0.20 0.00
0.08

Soffits of the slab 250mm thick M2


Slab area 1 1 1 435.02 1.00 1.00 435.02
Les: beam soffites
G/L E(1-2) & F(1-2) -1 1 2 3.14 0.40 1.00 - 2.51
G/L G(1-2) -1 1 1 1.10 0.40 1.00 - 0.44
G/L A(1-4) -1 1 1 12.45 0.40 1.00 - 4.98
G/L B,C,D,E,F(2-3) -1 1 5 5.50 0.40 1.00 - 11.00
G/L G(2-3) -1 1 1 5.60 0.40 1.00 - 2.24
G/L B(3-4) -1 1 1 5.45 0.40 1.00 - 2.18
G/L C(3-4) -1 1 1 5.45 0.40 1.00 - 2.18
G/L D(3-4) -1 1 1 5.45 0.40 1.00 - 2.18
G/L E(3-4) -1 1 1 11.45 0.40 1.00 - 4.58
G/L F(3-4) -1 1 1 11.45 0.40 1.00 - 4.58
G/L G(3-4) -1 1 1 5.65 0.40 1.00 - 2.26
G/L G(4-5) -1 1 1 5.60 0.40 1.00 - 2.24

G/L A2-B2, A3-B3, A3'-B3', A4-B4 -1 1 4 2.32 0.40 1.00 - 3.71


G/L B2-C2 & B3-C3 -1 1 2 5.60 0.40 1.00 - 4.48
G/L B4-C4 -1 1 1 5.50 0.40 1.00 - 2.20
G/L 2,3 & 4 (C-D) -1 1 3 5.60 0.40 1.00 - 6.72
G/L 2,3,& 4(D-E) -1 1 3 5.60 0.40 1.00 - 6.72
G/L 1,2,3 & 5 (E-F) -1 1 4 5.60 0.40 1.00 - 8.96
G/L F1-G1 -1 1 1 2.75 0.40 1.00 - 1.10
G/L 2,3 & 5 (F-G) -1 1 3 5.59 0.40 1.00 - 6.70
353.06

soffits of stiracse case landing M2


Staircase 01
Landing 1 1 1 3.29 1.50 1.00 2.47
Staircase 02
Landing 0 1 1 2.52 1.40 1.00 -
2.47

Slopping sofffits of staircase M2


Staircase 01
Waist 1 1 2 4.36 1.50 1.00 13.08

13.08

Risers; 150mm wide


Staircase 01
Steps 1 26 1 1.50 1.00 1.00 19.50
19.50

Sides of the lift walls M2


1 2 2 2.45 1.00 3.90 38.22
1 2 2 2.05 1.00 3.90 31.98
Less: Lift door "unamed" -1 2 1 1.22 1.00 2.10 - 5.12
65.08

Edges of the slab 250mm wide M

Part 1; see planswift file 1 1 2 15.60 1.00 1.00 31.20


Part 2; see planswift file -1 1 2 6.00 1.00 1.00 - 12.00
Part 3; see planswift file 1 1 2 12.60 1.00 1.00 25.20
Part 4; see planswift file 1 1 2 12.60 1.00 1.00 25.20

Part 1; see planswift file 1 1 2 15.30 1.00 1.00 30.60


Less: 1 1 2 2.40 1.00 1.00 4.80
Part 4; see planswift file 1 1 2 6.50 1.00 1.00 13.00
Part 5; see planswift file 1 1 2 0.30 1.00 1.00 0.60

Deduct: Voids
Staircase 01 1 1 2 4.95 1.00 1.00 9.90
Void verandah 1 1 2 16.65 1.00 1.00 33.30
Void/terrace 1 1 2 5.70 1.00 1.00 11.40
Lift shaft 1 1 2 2.05 1.00 1.00 4.10

Deduct: Voids
Staircase 01 1 1 2 3.20 1.00 1.00 6.40
Void verandah 1 1 2 1.45 1.00 1.00 2.90
Void/terrace 1 1 2 2.76 1.00 1.00 5.52
Lift shaft 1 1 2 2.05 1.00 1.00 4.10
196.22
Edges of the staircase landing 200mm wide M
Staircase 01; girth computed 1 1 1 6.98 1.00 1.00 6.98
6.98

open springer of stairacse; 350mm high max M


Staircase 01
Waist 1 2 2 4.36 1.00 1.00 17.44
17.44

ELEMENT NO. 2

BILL NO.2

ELEMENT NO. 4

EXTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties
set in horizontal alternate courses:

A 300mm thick M2
G/L G(2-5) 1 1 2 17.80 1.00 2.70 96.12
Walls at telecom duct towards the lift shaft 1 1 2 0.84 1.00 2.70 4.54
Along side 1 1 1 1.45 1.00 2.70 3.92
Walls at telecom duct towards the lift shaft 1 1 1 2.36 1.00 2.70 6.37
Along G/L 5 1 1 1 13.63 1.00 2.70 36.79
Along G/L D1 1 1 1 9.70 1.00 2.70 26.18
Wall with exit door D2-07 1 1 1 2.82 1.00 2.70 7.60
Wall with exit door D2-07 1 1 1 3.70 1.00 2.70 9.98
Along G/L 2,B,4 1 1 3 12.10 1.00 2.70 98.01
Along G/L D 1 1 2 3.06 1.00 2.70 16.52
Along G/L 2' 1 1 1 11.28 1.00 2.70 30.44
Along G/L E 1 1 1 6.55 1.00 2.70 17.69
Along G/L 1 1 1 1 9.14 1.00 2.70 24.68

Deductions
Openings and doors
Verandah openings/front -1 1 3 3.70 1.00 2.70 - 29.97
Verandah openings/front -1 1 1 2.40 1.00 2.70 - 6.48
D2-08 -1 1 1 1.00 1.00 2.65 - 2.65
D2-07 -1 1 1 1.20 1.00 2.65 - 3.18
D2-03 -1 1 2 1.80 1.00 2.65 - 9.54
D2-06 -1 1 1 1.50 1.00 2.65 - 3.97
D2-14 -1 1 1 0.90 1.00 2.65 - 2.39
W2-05 -1 1 6 1.60 1.00 2.65 - 25.44
W2-11 -1 1 5 1.50 1.00 1.50 - 11.25
W2-03 -1 1 3 2.20 1.00 1.59 - 10.49
W2-14 -1 1 4 1.20 1.00 1.59 - 7.63
W2-02 -1 1 1 2.20 1.00 2.65 - 5.83
W2-10 -1 1 3 1.57 1.00 2.20 - 10.33
W2-08 -1 1 2 1.57 1.00 1.59 - 4.98
244.69

A 200mm thick
Wall along E2 to lift shaft 1 1 1 8.84 1.00 2.70 23.87
Ddt: D2-03 -1 1 1 1.80 1.00 2.65 - 4.77
19.10

Reinforced Insitu concrete grade 25 in:-


Moulded concrete window Sill; Section size 250 x 85 x 50mm;
C M
weathered and throated; all as per Architect's details
Windows
W2-05 1 1 6 1.90 1.00 1.00 11.40
W2-11 1 1 5 1.80 1.00 1.00 9.00
W2-03 1 1 3 2.50 1.00 1.00 7.50
W2-14 1 1 4 1.50 1.00 1.00 6.00
W2-02 1 1 1 2.50 1.00 1.00 2.50
W2-10 1 1 3 1.87 1.00 1.00 5.60
W2-08 1 1 2 1.87 1.00 1.00 3.73
45.72

Reinforced concrete grade 25 in:-


A Lintels M2
Verandah openings/front 1 1 3 4.70 0.30 0.30 1.27
Verandah openings/front 1 1 1 2.70 0.30 0.30 0.24
D2-08 1 1 1 1.30 0.30 0.30 0.12
D2-07 1 1 1 1.50 0.30 0.30 0.14
D2-03 1 1 2 2.10 0.30 0.30 0.38
D2-06 1 1 1 1.80 0.30 0.30 0.16
D2-14 1 1 1 1.20 0.30 0.30 0.11

W2-05 1 1 6 1.90 0.30 0.30 1.03


W2-11 1 1 5 1.80 0.30 0.30 0.81
W2-03 1 1 3 2.50 0.30 0.30 0.67
W2-14 1 1 4 1.50 0.30 0.30 0.54
W2-02 1 1 1 2.50 0.30 0.30 0.22
W2-10 1 1 3 1.87 0.30 0.30 0.50
W2-08 1 1 2 1.87 0.30 0.30 0.34
6.53
Sawn formwork to:-

Sides and soffites of lintels

Verandah openings/front 1 1 3 4.70 0.90 1.00 12.69


Verandah openings/front 1 1 1 2.70 0.90 1.00 2.43
D2-08 1 1 1 1.30 0.90 1.00 1.17
D2-07 1 1 1 1.50 0.90 1.00 1.35
D2-03 1 1 2 2.10 0.90 1.00 3.78
D2-06 1 1 1 1.80 0.90 1.00 1.62
D2-14 1 1 1 1.20 0.90 1.00 1.08

W2-05 1 1 6 1.90 0.90 1.00 10.26


W2-11 1 1 5 1.80 0.90 1.00 8.10
W2-03 1 1 3 2.50 0.90 1.00 6.75
W2-14 1 1 4 1.50 0.90 1.00 5.40
W2-02 1 1 1 2.50 0.90 1.00 2.25
W2-10 1 1 3 1.87 0.90 1.00 5.04
W2-08 1 1 2 1.87 0.90 1.00 3.36
65.27

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Lintels 1 1 150 6.53 1.00 1.00 979.09
979.09

BILL NO.2

ELEMENT NO. 5

INTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties
set in horizontal alternate courses:

A 200mm thick Wall M2


G/L D'3-E'3 & D4-E'4 1 1 2 12.08 1.00 3.25 78.52
Closet walls 1 1 1 0.60 1.00 3.25 1.95
G/L 3 & 3' (A-C) 1 1 2 5.80 1.00 3.25 37.70
L pantry 1 1 1 2.80 1.00 3.25 9.10
L pantry 1 1 1 2.80 1.00 3.25 9.10
Master/bathroom 1 1 1 5.80 1.00 3.25 18.83
Bedroom 1/Masterroom 1 1 1 5.80 1.00 3.25 18.83
Pantry towards the door 1 1 1 2.11 1.00 3.25 6.84
G/L D(2-3) 1 1 1 5.05 1.00 3.25 16.40
Master/lounge 1 1 1 5.80 1.00 3.25 18.85
Recess 1 1 1 0.45 1.00 3.25 1.46
Duct 1 1 1 0.70 1.00 3.25 2.28
Kitchen/shared bath 1 1 1 5.80 1.00 3.25 18.85
Bedroom/Bathroom 1 1 1 3.60 1.00 3.25 11.70
Bath/bedroom 1 1 1 1 2.84 1.00 3.25 9.23
Duct 1 1 1 2.80 1.00 3.25 9.10
Deductions
D3-12 -1 1 8 0.80 1.00 2.10 - 13.44
D3-11 -1 1 2 1.00 1.00 2.65 - 5.30
D3-05 -1 1 2 1.50 1.00 2.65 - 7.95
242.05

A 150mm thick walls M2


Masterbath/lobby both apartments 1 1 2 2.00 1.00 3.65 14.60
Masterbath/lobby both apartments 1 1 2 0.60 1.00 3.65 4.38
18.98

Reinforced concrete grade 25 in:-


A Lintels M
D3-12 1 1 8 1.10 0.20 0.30 0.53
D3-11 1 1 2 1.30 0.20 0.30 0.16
D3-05 1 1 2 1.80 0.20 0.30 0.22
0.90

Sawn formwork to:-

Sides and soffites of lintels


D3-12 1 1 8 1.10 0.80 1.00 7.04
D3-11 1 1 2 1.30 0.80 1.00 2.08
D3-05 1 1 2 1.80 0.80 1.00 2.88
12.00

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Master/bathroom 1 1 150 0.90 1.00 1.00 135.00
135.00

BILL NO.2

ELEMENT NO. 6

WINDOWS, SCREENS AND LIGHTS


Anodized Aluminum casement windows. The color shall be to
client's approval; all additional costs are deemed included.

Provide and fix purpose-made anodized aluminum windows


and window frames complete with 5mm thick translucent
glass and single glazing, glazing beads, wash leather strips,
sealing, burglar proofing, fly mesh, all ironmongery and
accessories; fixing to blockwork or concrete; all as per
Architect's drawings; Drawing No. NA(22)02-9/10; in:

The contractor is expected to prepare and submit shop


drawings for approval prior to fabrication and erection of the
windows and screens

A Glazed window and window frames size: 1600 mm wide x 2650


mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [W2-05] No 6.00
A Glazed window and window frames size: 1565 mm wide x 1590
mm high; overall window type [W2-08] No 2.00
B Glazed window and window frames size: 2200mm wide x 2650 mm
high; overall window type [W2-02] No 1.00
B Glazed window and window frames size: 2200mm wide x 1590 mm
high; overall window type [W2-03] No 3.00
B Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [W2-10] No 3.00
B Glazed window and window frames size: 1500 mm wide x 1500
mm high; complete with 4 window panes size 750mm wide x
750mm high; overall window type [W2-11] No 5.00
B Glazed window and window frames size: 1200 mm wide x 1590
mm high; overall window type [W2-14] No 4.00

Reinforced Insitu concrete grade 25 in:-

Moulded concrete window Sill; Section size 350 x 85 x 50mm;


weathered and throated; all as per Architect's details
Glazed window and window frames size: 1600 mm wide x 2650
mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [W2-05] 1 1 6 1.90 1.00 1.00 11.40
Glazed window and window frames size: 1565 mm wide x 1590
mm high; overall window type [W2-08] 1 1 2 1.87 1.00 1.00 3.73
Glazed window and window frames size: 2200mm wide x 2650 mm
high; overall window type [W2-02] 1 1 1 2.30 1.00 1.00 2.30
Glazed window and window frames size: 2200mm wide x 1590 mm
high; overall window type [W2-03] 1 1 3 2.50 1.00 1.00 7.50
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [W2-10] 1 1 3 1.87 1.00 1.00 5.60
Glazed window and window frames size: 1500 mm wide x 1500
mm high; complete with 4 window panes size 750mm wide x
750mm high; overall window type [W2-11] 1 1 5 1.80 1.00 1.00 9.00
Glazed window and window frames size: 1200 mm wide x 1590
mm high; overall window type [W2-14] 1 1 4 1.50 1.00 1.00 6.00
45.53

Window boards

Natural Stone Granite Window Board; size 150mm wide x 20mm


thick thick; all edges well finished with a coved mould; all as per
Architect's details

Glazed window and window frames size: 1600 mm wide x 2650


mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [W2-05] 1 1 6 1.60 1.00 1.00 9.60
Glazed window and window frames size: 1565 mm wide x 1590
mm high; overall window type [W2-08] 1 1 2 1.57 1.00 1.00 3.13
Glazed window and window frames size: 2200mm wide x 2650 mm
high; overall window type [W2-02] 1 1 1 2.00 1.00 1.00 2.00
Glazed window and window frames size: 2200mm wide x 1590 mm
high; overall window type [W2-03] 1 1 3 2.20 1.00 1.00 6.60
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [W2-10] 1 1 3 1.57 1.00 1.00 4.70
Glazed window and window frames size: 1500 mm wide x 1500
mm high; complete with 4 window panes size 750mm wide x
750mm high; overall window type [W2-11] 1 1 5 1.50 1.00 1.00 7.50
Glazed window and window frames size: 1200 mm wide x 1590
mm high; overall window type [W2-14] 1 1 4 1.20 1.00 1.00 4.80
38.33

BILL NO.2

ELEMENT NO. 7

DOORS

DOORS, SHUTTERS AND HATCHES

Timber doors

The following in wrot hardwood to architect's satisfaction:-


Approved hardwood flush doors

A 45mm thick solid core timber flush door shutter size 800mm wide x
2100 mm high complete with a mahogany veneer; to Architect's
detail; door type [Dg-12] No
1 1 8 1.00 1.00 1.00 8.00
8.00

Approved hardwood panelled doors;

A 45mm thick solid panelled door shutter size 1000mm wide x


2100mm high complete with 2 No. vision panels size 200mm wide
x 1000mm high; to Architect's detail; door type [Dg-11] No
1 1 2 1.00 1.00 1.00 2.00
2.00

Door frames and finishings in in wrot hardwood

C 250mm x 50mm rebated frame M


Db-12 1 1 8 5.00 1.00 1.00 40.00
Db-11 1 1 2 6.30 1.00 1.00 12.60
Opening to toilet 1 1 2 6.20 1.00 1.00 12.40
65.00

C Ditto transomes M
Db-11 1 1 2 1.00 1.00 1.00 2.00
Opening to toilet 1 1 2 0.90 1.00 1.00 1.80
3.80

D 40mm x 20mm Splayed architrave or qudrant beads where


applicable. M
Db-12 1 2 8 5.00 1.00 1.00 80.00
Db-11 1 2 2 6.30 1.00 1.00 25.20
Opening to toilet 1 2 2 6.20 1.00 1.00 24.80
130.00

D 20mm x 20mm moulded glazing beads. M


Db-11 1 2 2 3.10 1.00 1.00 12.40
Db-11 - Vision panels 2 2 2 2.40 1.00 1.00 19.20
Opening to toilet 1 2 2 2.00 1.00 1.00 8.00
39.60

Ironmongery to architect's approval and sartisfaction

E 100mm Pressed steel butt hinges Pr


1 1 8 1.50 1.00 1.00 12.00
Db-11 1 1 2 1.50 1.00 1.00 3.00
15.00

F 25mm diameter rubber door stop plugged to wall/floor No


1 1 25 1.00 1.00 1.00 25.00
25.00

H 3 - Lever motrice lock complete with approved door handles No


Db-11 1 1 2 1.00 1.00 1.00 2.00
2.00

H Commercial privacy Lock complete with occupancy indicator Oil


rubbed bronze and Lock restroom hardware brass door handles No
Db-12 1 1 8 1.00 1.00 1.00 8.00
8.00

I Coat hooks No
1 1 8 1.00 1.00 1.00 8.00
8.00

J Door closer No
1 1 0 1.00 1.00 1.00 -
-

K Mild steel aldrop bolt complete with all the necessary accessories No
1 1 3 1.00 1.00 1.00 3.00
3.00

L Stainless Steel Push plate size 300mm x 100mm No


1 2 8 1.00 1.00 1.00 16.00
1 2 2 1.00 1.00 1.00 4.00
20.00

M Stainless Steel kick plate size 800mm wide x 150mm high x 3mm
thick No
1 2 8 1.00 1.00 1.00 16.00
16.00

M Stainless Steel kick plate size 1000mm wide x 150mm high x 3mm
thick No
1 2 2 1.00 1.00 1.00 4.00
4.00

Glazing

5mm thick clear sheet glass fixed to hardwood frames with


glazing beads (measured seperately)
Db-11 - Vent 1 1 2 1.00 0.55 1.00 1.10
Db-11 - Vision panel 1 2 2 1.00 0.20 1.00 0.80
1.90

Steel casement doors; mild steel

Supply and Fix the following purpose made mild steel door
and door frames; all members in 3mm thick steel sections
complete with mild steel frame, hinges, fixing lugs, locking
device and a single coat of red oxide primer, all fixed as per
Architect's details and satisfaction

D Louvered door set; size 900 mm wide x 2650 mm high; complete


with louvered door shutter; door type [D2-14] No 1.00

D Louvered door set; size 700 mm wide x 2650 mm high; door type
[D2-15] No 1.00

D Louvered door set; size 500mm wide x 2650 mm high; complete


with 1 louvered door shutters; door type [D2-16] No 1.00

Anodised aluminium doors

Supply and fix purpose-made anodised aluminium casement


doors and frames; complete with 6mm thick translucent glass
and single glazing, ironmongery, fixing lugs, all accessories
and one coat of red oxide primer before delivery; fixing to
blockwork or concrete; all as per Architect's drawings;
Drawing No. NA(22)02-9/10; in:

Door set; size 1800 mm wide x 2650 mm high; complete as per the
Architect's details; door type [D2-03] 2.00

Sliding door set; size 1500mm wide x 2650 mm high; complete as


per the Architect's details; door type [D2-05] 2.00

Sliding door set; size 1500mm wide x 2650 mm high; complete as


per the Architect's details; door type [D1-06] 1.00

Sliding door set; size 1200mm wide x 2650 mm high; complete as


per the Architect's details; door type [D1-07] 1.00

Sliding door set; size 1000mm wide x 2650 mm high; complete as


per the Architect's details; door type [D1-08] 1.00
Prepare and apply undercoat and three coats of gloss oil paint
on:-

I General surfaces of metal M2


Louvered door set; size 900 mm wide x 2650 mm high; complete
with louvered door shutter; door type [D2-14] 1 2 1 0.90 1.00 2.65 4.77
Louvered door set; size 700 mm wide x 2650 mm high; door type
[D2-15] 1 2 1 0.70 1.00 2.65 3.71
Louvered door set; size 500mm wide x 2650 mm high; complete
with 1 louvered door shutters; door type [D2-16] 1 2 1 0.50 1.00 2.65 2.65
11.13

J General surfaces of wood M2


Wood frames; girth exceeding 300mm wide; 350mm wide
250mm x 50mm rebated frame 1 1 1 65.00 0.35 1.00 22.75
Ditto transomes 1 1 1 3.80 0.60 1.00 2.28
Door shutters; Db-12 1 2 5 0.85 2.15 1.00 18.28
Door shutters; Db-11 1 2 2 1.05 2.15 1.00 9.03
52.34

K Wood surfaces not exceeding 100mm girth M


40mm x 20mm Splayed architrave or qudrant beads where
applicable. 1 1 1 130.00 1.00 1.00 130.00
20mm x 20mm moulded glazing beads 1 1 1 39.60 1.00 1.00 39.60
169.60

BILL NO.2

ELEMENT NO. 8

INTERNAL FINISHINGS

Floor screed; Cement and sand (1:4); wood floated finish:

A 40mm thick; to receive quarry floor tiles (measured separately) M2


Verandah
Verandah 1 1 1 18.10 1.20 1.00 21.72
Verandah 1 1 1 0.30 0.60 1.00 0.18
Verandah 1 1 1 18.10 1.45 1.00 26.25
openings 1 1 3 4.00 0.30 1.00 3.60
D2-08 1 1 1 1.00 0.30 1.00 0.30
W2-05 1 1 6 1.60 0.30 1.00 2.88

Terrace 1 1 1 11.98 3.06 1.00 36.64


Terrace 1 1 1 9.70 2.82 1.00 27.34
Terrace 1 1 1 12.40 6.00 1.00 74.40
Terrace 1 1 1 12.40 2.52 1.00 31.25
224.56

A 40mm thick; to receive procelain floor tiles (measured separately) M2


300x300mm tiles; staircase areas
Staircase-01 1 1 1 4.15 3.29 1.00 13.65
Staircase-01 1 1 1 0.90 0.65 1.00 0.59

450x450mm tiles; hallways and washrooms


Hallways 1 1 1 5.80 2.86 1.00 16.59
Hallways 1 1 1 11.98 2.74 1.00 32.81
Hallways 1 1 1 2.31 2.82 1.00 6.50

Washrooms/master 1 1 1 2.76 2.00 1.00 5.52


Add: D12 door way 1 1 1 0.80 0.15 1.00 0.12
Shared toilet 1 1 2 3.84 1.59 1.00 12.21
Add: D12 door way 1 1 2 0.80 0.15 1.00 0.24
Shared toilet 1 1 1 3.60 1.59 1.00 5.72
Add: D12 door way 1 1 1 0.80 0.20 1.00 0.16
Washrooms/master 1 1 1 2.76 2.00 1.00 5.52
Add: D12 door way 1 1 1 0.80 0.15 1.00 0.12
Add: D16 door way 1 1 1 0.70 0.15 1.00 0.11

800x800mm tiles; other areas


Apartment #1
Lounge 1 1 1 7.84 5.81 1.00 45.51
Pantry 1 1 1 4.04 2.00 1.00 8.08
opening 1 1 1 2.40 0.20 1.00 0.48
Kitchen 1 1 1 4.04 3.81 1.00 15.39
D11 1 1 1 1.00 0.20 1.00 0.20
D2-5 1 1 1 1.50 0.20 1.00 0.30
Masterbedroom 1 1 1 5.80 5.64 1.00 32.68
Add: D12 1 1 1 0.80 0.20 1.00 0.16
Lobby 1 1 1 2.00 3.04 1.00 6.08
Add: D12 1 1 1 0.80 0.20 1.00 0.16
Bedroom 1 1 1 1 3.84 4.05 1.00 15.55
ddt: Duct -1 1 1 0.70 1.80 1.00 - 1.26
Door duct -1 1 1 0.60 0.15 1.00 - 0.09

Apartment #2
Lounge/dining 1 1 1 8.00 5.80 1.00 46.40
D5 1 1 1 1.50 0.20 1.00 0.30
d12 1 1 1 0.80 0.20 1.00 0.16
Lounge/dining 1 1 1 1.34 0.60 1.00 0.80
Kitchen 1 1 1 3.80 3.81 1.00 14.46
Pantry 1 1 1 1.80 3.80 1.00 6.82
Add 1 1 1 2.00 0.20 1.00 0.40
Lobby 1 1 1 2.89 2.00 1.00 5.78
D12 1 1 3 0.80 0.20 1.00 0.48
Master bedroom 1 1 1 5.80 5.80 1.00 33.64
D12 1 1 2 0.80 0.20 1.00 0.32
ddt: Duct -1 1 1 0.70 0.70 1.00 - 0.49
D15 1 1 1 0.70 0.20 1.00 0.14
Ddt 1 1 1 1.54 0.65 1.00 1.00
D12 1 1 1 0.80 0.15 1.00 0.12
Bedroom 1 1 1 1 3.60 4.01 1.00 14.44
ddt: Wall 1 1 1 0.60 0.15 1.00 0.09
347.97

D Ditto; on staircase landings ditto M2


Staircase 01
Landing 1 1 1 3.29 1.50 1.00 2.47
2.47

E Ditto; on treads 300mm wide ditto M


Staircase 01
Steps 1 26 1 1.50 1.00 1.00 19.50
19.50

F Ditto; to risers 150 mm high ditto M


Staircase 01
Steps 1 26 1 1.50 1.00 1.00 19.50
19.50

G Ditto; to stringer 375mm wide (maximum) M


Staircase 01
Waist 1 2 2 4.36 1.00 1.00 17.44
17.44

H Skirting; edge of landings M


Staircase 01
Landings 1 1 1 3.29 1.00 1.00 3.29
Landings 1 1 2 1.50 1.00 1.00 3.00
6.29

J Ditto; to receive skirting; 100mm high ditto M


Quarry tiles
Verandah
Verandah 1 1 2 18.00 1.00 1.00 36.00
Verandah 1 1 2 1.20 1.00 1.00 2.40
openings -1 1 3 3.70 1.00 1.00 - 11.10

Verandah 1 1 2 17.80 1.00 1.00 35.60


Verandah 1 1 2 1.45 1.00 1.00 2.90
D2-06 -1 1 1 1.00 1.00 1.00 - 1.00
W2-05 -1 1 6 1.60 1.00 1.00 - 9.60
D2-14 -1 1 1 0.90 1.00 1.00 - 0.90
Terrace 1 1 2 11.98 1.00 1.00 23.96
Terrace 1 1 2 3.06 1.00 1.00 6.12
Terrace 1 1 2 0.20 1.00 1.00 0.40
Terrace 1 1 2 0.10 1.00 1.00 0.20
D2-06 -1 1 1 1.50 1.00 1.00 - 1.50

Terrace 1 1 2 11.80 1.00 1.00 23.60


Terrace 1 1 2 2.42 1.00 1.00 4.83
D2-05 -1 1 1 2.20 1.00 1.00 - 2.20

Terrace 1 1 2 9.70 1.00 1.00 19.39


Terrace 1 1 2 14.81 1.00 1.00 29.62
D2-07 -1 1 1 1.20 1.00 1.00 - 1.20

450x450mm tiles; hallways and washrooms


Hallways 1 1 2 5.80 1.00 1.00 11.60
Hallways 1 1 2 11.98 1.00 1.00 23.95
Hallways 1 1 2 2.31 1.00 1.00 4.61
Hallways 1 1 2 2.82 1.00 1.00 5.64
D2-03 -1 1 1 1.80 1.00 1.00 - 1.80
D2-05 -1 1 2 1.50 1.00 1.00 - 3.00
D2-07 -1 1 1 1.20 1.00 1.00 - 1.20
D2-02 -1 1 1 1.00 1.00 1.00 - 1.00
W2-05 -1 1 2 1.60 1.00 1.00 - 3.20

Master toilet 1 1 2 2.76 1.00 1.00 5.52


Master toilet 1 1 2 2.00 1.00 1.00 4.00
D2-12 -1 1 1 0.80 1.00 1.00 - 0.80
D2-16 -1 1 1 0.50 1.00 1.00 - 0.50

Shared bathroom 1 2 2 3.84 1.00 1.00 15.36


Shared bathroom 1 2 2 1.59 1.00 1.00 6.36
D2-12 -1 2 1 0.80 1.00 1.00 - 1.60

Master toilet 1 1 2 2.76 1.00 1.00 5.52


Master toilet 1 1 2 2.00 1.00 1.00 4.00
D2-12 -1 1 1 0.80 1.00 1.00 - 0.80

300x300mm tiles; staircase areas


Staircase-01 1 1 2 4.15 1.00 1.00 8.30
Staircase-01 1 1 1 3.29 1.00 1.00 3.29
FHR 1 1 2 0.65 1.00 1.00 1.30
D2-03 -1 1 1 1.80 1.00 1.00 - 1.80

800x800mm tiles; other areas


Apartment #1
Lounge 1 1 2 7.84 1.00 1.00 15.68
Lounge 1 1 2 5.81 1.00 1.00 11.61
Recess 1 1 2 0.60 1.00 1.00 1.20
D2-05 -1 1 1 1.50 1.00 1.00 - 1.50
Opening -1 1 1 3.81 1.00 1.00 - 3.81

Pantry 1 1 2 4.04 1.00 1.00 8.08


Pantry 1 1 2 2.00 1.00 1.00 4.00
Opening -1 1 1 2.40 1.00 1.00 - 2.40

Kitchen 1 1 2 4.04 1.00 1.00 8.08


Kitchen 1 1 2 3.81 1.00 1.00 7.62
Opening -1 1 1 3.81 1.00 1.00 - 3.81

Masterbedroom 1 1 2 5.80 1.00 1.00 11.59


Masterbedroom 1 1 2 5.64 1.00 1.00 11.28
Add: D12 -1 1 1 0.80 1.00 1.00 - 0.80

Lobby 1 1 2 2.00 1.00 1.00 4.00


Lobby 1 1 2 3.04 1.00 1.00 6.08
Add: D12 -1 1 4 0.80 1.00 1.00 - 3.20

Bedroom 1 1 1 2 3.84 1.00 1.00 7.68


Bedroom 1 1 1 2 4.05 1.00 1.00 8.10
Door duct 1 1 2 0.68 1.00 1.00 1.35
Add: D12 -1 1 1 0.80 1.00 1.00 - 0.80

Apartment #2
Lounge/dining 1 1 2 8.00 1.00 1.00 16.00
Lounge/dining 1 1 2 5.80 1.00 1.00 11.60
D5 -1 1 1 1.50 1.00 1.00 - 1.50
d12 -1 1 1 0.80 1.00 1.00 - 0.80
Opening towards the kitchen -1 1 1 3.81 1.00 1.00 - 3.81
Lounge/dining 1 1 2 0.65 1.00 1.00 1.30

Kitchen 1 1 2 3.80 1.00 1.00 7.60


Kitchen 1 1 2 3.81 1.00 1.00 7.62
Opening towards the kitchen -1 1 1 3.81 1.00 1.00 - 3.81
Opening to the pantry -1 1 1 2.40 1.00 1.00 - 2.40

Pantry 1 1 2 1.80 1.00 1.00 3.59


Pantry 1 1 2 3.80 1.00 1.00 7.60
Opening to the pantry -1 1 1 2.40 1.00 1.00 - 2.40

Lobby 1 1 2 2.89 1.00 1.00 5.78


Lobby 1 1 2 2.00 1.00 1.00 4.00
d12 -1 1 4 0.80 1.00 1.00 - 3.20

Master bedroom 1 1 2 5.80 1.00 1.00 11.60


Master bedroom 1 1 2 5.80 1.00 1.00 11.60
D12 -1 1 2 0.80 1.00 1.00 - 1.60

Bedroom 1 1 1 2 3.60 1.00 1.00 7.20


Bedroom 1 1 1 2 4.01 1.00 1.00 8.02
Wall 1 1 2 0.68 1.00 1.00 1.35
416.65

Tiles (varying specifications)

M Quarry tiles M2
1 1 1 224.56 1.00 1.00 224.56
224.56

M Procelain tiles: Size 800 x 800 x 10 mm thick to floors M2


248.11

M Ditto; size 450 x 450 x 10mm thick to floors M2


85.62

M Ditto; size 300 x 300 x 10mm thick to floors M2


14.24

D Ditto; on staircase landings ditto M2


Staircase 01 & 02 1 1 1 2.47 1.00 1.00 2.47
2.47

E Ditto; on treads 275mm wide ditto M


Staircase 01 & 02 1 1 19.50 1.00 1.00 1.00 19.50
19.50

F Ditto; to risers 150 mm high ditto M


Staircase 01 & 02 1 1 19.50 1.00 1.00 1.00 19.50
19.50

G Ditto; to stringer 375mm wide (maximum) M


Staircase 01 & 02 1 1 17.44 1.00 1.00 1.00 17.44
17.44

H Edge of staircase landing; 200mm wide M


Staircase 01 & 02 1 1 2 4.80 1.00 1.00 9.60
9.60

J Ditto; to receive skirting; 100mm high ditto M


1 1 1 416.65 1.00 1.00 416.65
416.65
WALL FINISHES

Wall Tile backing

Screed backing to wall; Cement and sand (1:4); wood floated


finish:
C 12mm thick; to receive ceramic wall tiles (measured separately) M2
Master toilet 1 1 2 2.76 1.00 2.10 11.59
Master toilet 1 1 2 2.00 1.00 2.10 8.40
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68
D2-16 -1 1 1 0.50 1.00 2.10 - 1.05

Shared bathroom 1 2 2 3.84 1.00 2.10 32.26


Shared bathroom 1 2 2 1.59 1.00 2.10 13.36
D2-12 -1 2 1 0.80 1.00 2.10 - 3.36

Master toilet 1 1 2 2.76 1.00 2.10 11.59


Master toilet 1 1 2 2.00 1.00 2.10 8.40
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68

W2-14 -1 1 3 1.20 1.00 0.99 - 3.56


W2-11 -1 1 1 1.50 1.00 0.99 - 1.48
72.78

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm


second coat of cement and lime putty (1:10); steel trowelled
to:

D Walls M2
Quarry tiles
Verandah
Verandah 1 1 2 18.00 1.00 0.80 28.80
Verandah 1 1 2 1.20 1.00 0.80 1.92

Verandah 1 1 2 17.80 1.00 3.25 115.70


Verandah 1 1 2 1.45 1.00 3.25 9.42
D2-06 -1 1 1 1.00 1.00 2.65 - 2.65
D2-14 -1 1 1 0.90 1.00 2.65 - 2.39
openings -1 1 3 3.70 1.00 2.70 - 29.97
Add: Reveals and jambs
openings 1 1 3 9.10 0.30 1.00 8.19

Terrace 1 1 2 11.98 1.00 3.25 77.87


Terrace 1 1 2 3.06 1.00 3.25 19.89
Terrace 1 1 2 0.20 1.00 3.25 1.30
Terrace 1 1 2 0.10 1.00 3.25 0.65
D2-06 -1 1 1 1.50 1.00 2.65 - 3.97
Openings -1 1 1 5.45 1.00 2.70 - 14.72
Add: Reveals and jambs
Openings 1 1 1 10.85 0.30 1.00 3.26

Terrace 1 1 2 11.80 1.00 3.25 76.70


Terrace 1 1 2 2.42 1.00 3.25 15.70
D2-05 -1 1 1 2.20 1.00 1.00 - 2.20
Openings -1 1 1 11.80 1.00 2.70 - 31.86
Openings -1 1 2 2.42 1.00 2.70 - 13.04
Add: Reveals and jambs
Openings 1 1 1 17.20 0.30 1.00 5.16
Openings 1 1 1 7.82 0.30 1.00 2.34

Terrace 1 1 2 9.70 1.00 3.25 63.02


Terrace 1 1 2 14.81 1.00 3.25 96.27
D2-07 -1 1 1 1.20 1.00 2.65 - 3.18
Terrace 1 1 1 5.70 1.00 2.70 15.39
Terrace 1 1 1 14.81 1.00 2.70 39.99

450x450mm tiles; hallways and washrooms


Hallways 1 1 2 5.80 1.00 3.25 37.70
Hallways 1 1 2 11.98 1.00 3.25 77.84
Hallways 1 1 2 2.31 1.00 3.25 14.98
Hallways 1 1 2 2.82 1.00 3.25 18.33
D2-03 -1 1 1 1.80 1.00 2.65 - 4.77
D2-05 -1 1 2 1.50 1.00 2.65 - 7.95
D2-07 -1 1 1 1.20 1.00 2.65 - 3.18
D2-02 -1 1 1 1.00 1.00 2.65 - 2.65
W2-05 -1 1 2 1.60 1.00 2.65 - 8.48

Master toilet 1 1 2 2.76 1.00 3.25 17.94


Master toilet 1 1 2 2.00 1.00 3.25 13.00
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68
D2-16 -1 1 1 0.50 1.00 2.65 - 1.33

Shared bathroom 1 2 2 3.84 1.00 3.25 49.92


Shared bathroom 1 2 2 1.59 1.00 3.25 20.67
D2-12 -1 2 1 0.80 1.00 2.10 - 3.36

Master toilet 1 1 2 2.76 1.00 3.25 17.94


Master toilet 1 1 2 2.00 1.00 3.25 13.00
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68

300x300mm tiles; staircase areas


Staircase-01 1 1 2 8.95 1.00 3.25 58.18
Staircase-01 1 1 2 3.29 1.00 3.25 21.39
FHR 1 1 2 0.65 1.00 3.25 4.23
D2-03 -1 1 1 1.80 1.00 2.65 - 4.77

800x800mm tiles; other areas


Apartment #1
Lounge 1 1 2 7.84 1.00 3.25 50.96
Lounge 1 1 2 5.81 1.00 3.25 37.73
Recess 1 1 2 0.60 1.00 3.25 3.90
D2-05 -1 1 1 1.50 1.00 2.65 - 3.97
Opening -1 1 1 3.81 1.00 3.25 - 12.37

Pantry 1 1 2 4.04 1.00 3.25 26.26


Pantry 1 1 2 2.00 1.00 3.25 13.00
Opening -1 1 1 2.40 1.00 3.25 - 7.80

Kitchen 1 1 2 4.04 1.00 3.25 26.26


Kitchen 1 1 2 3.81 1.00 3.25 24.77
Opening -1 1 1 3.81 1.00 3.25 - 12.38

Masterbedroom 1 1 2 5.80 1.00 3.25 37.67


Masterbedroom 1 1 2 5.64 1.00 3.25 36.66
Add: D12 -1 1 1 0.80 1.00 2.10 - 1.68

Lobby 1 1 2 2.00 1.00 3.25 13.00


Lobby 1 1 2 3.04 1.00 3.25 19.76
Add: D12 -1 1 4 0.80 1.00 2.10 - 6.72

Bedroom 1 1 1 2 3.84 1.00 3.25 24.96


Bedroom 1 1 1 2 4.05 1.00 3.25 26.33
Door duct 1 1 2 0.68 1.00 3.25 4.39
Add: D12 -1 1 1 0.80 1.00 2.10 - 1.68

Apartment #2
Lounge/dining 1 1 2 8.00 1.00 3.25 52.00
Lounge/dining 1 1 2 5.80 1.00 3.25 37.70
D5 -1 1 1 1.50 1.00 2.65 - 3.97
D12 -1 1 1 0.80 1.00 2.10 - 1.68
Opening towards the kitchen -1 1 1 3.81 1.00 3.25 - 12.38
Lounge/dining 1 1 2 0.65 1.00 3.25 4.23

Kitchen 1 1 2 3.80 1.00 3.25 24.70


Kitchen 1 1 2 3.81 1.00 3.25 24.77
Opening towards the kitchen -1 1 1 3.81 1.00 3.25 - 12.38
Opening to the pantry -1 1 1 2.40 1.00 3.25 - 7.80

Pantry 1 1 2 1.80 1.00 3.25 11.67


Pantry 1 1 2 3.80 1.00 3.25 24.70
Opening to the pantry -1 1 1 2.40 1.00 3.25 - 7.80

Lobby 1 1 2 2.89 1.00 3.25 18.79


Lobby 1 1 2 2.00 1.00 3.25 13.00
D12 -1 1 4 0.80 1.00 2.10 - 6.72

Master bedroom 1 1 2 5.80 1.00 3.25 37.70


Master bedroom 1 1 2 5.80 1.00 3.25 37.70
D12 -1 1 2 0.80 1.00 2.10 - 3.36

Bedroom 1 1 1 2 3.60 1.00 3.25 23.40


Bedroom 1 1 1 2 4.01 1.00 3.25 26.06
Wall 1 1 2 0.68 1.00 3.25 4.39
Deduct all Windows
Glazed window and window frames size: 1600 mm wide x 2650
mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [W2-05] -1 1 6 1.60 1.00 2.65 - 25.44
Glazed window and window frames size: 1565 mm wide x 1590
mm high; overall window type [W2-08] -1 1 2 1.57 1.00 1.59 - 4.98
Glazed window and window frames size: 2200mm wide x 2650 mm
high; overall window type [W2-02] -1 1 1 2.20 1.00 2.65 - 5.83
Glazed window and window frames size: 2200mm wide x 1590 mm
high; overall window type [W2-03] -1 1 3 2.20 1.00 1.59 - 10.49
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [W2-10] -1 1 3 1.57 1.00 2.20 - 10.33
Glazed window and window frames size: 1500 mm wide x 1500
mm high; complete with 4 window panes size 750mm wide x
750mm high; overall window type [W2-11] -1 1 5 1.50 1.00 1.50 - 11.25
Glazed window and window frames size: 1200 mm wide x 1590
mm high; overall window type [W2-14] -1 1 4 1.20 1.00 1.59 - 7.63
Reveals and jambs
Glazed window and window frames size: 1600 mm wide x 2650
mm high; complete with 8 window panes size 600mm wide x
600mm high; overall window type [W2-05] 1 1 6 6.90 0.30 1.00 12.42
Glazed window and window frames size: 1565 mm wide x 1590
mm high; overall window type [W2-08] 1 1 2 6.31 0.30 1.00 3.79
Glazed window and window frames size: 2200mm wide x 2650 mm
high; overall window type [W2-02] 1 1 1 7.50 0.30 1.00 2.25
Glazed window and window frames size: 2200mm wide x 1590 mm
high; overall window type [W2-03] 1 1 3 7.58 0.30 1.00 6.82
Glazed window and window frames size: 1565 mm wide x 2200
mm high; complete with 6 window panes size 600mm wide x
750mm high; overall window type [W2-10] 1 1 3 7.53 0.30 1.00 6.78
Glazed window and window frames size: 1500 mm wide x 1500
mm high; complete with 4 window panes size 750mm wide x
750mm high; overall window type [W2-11] 1 1 5 6.00 0.30 1.00 9.00
Glazed window and window frames size: 1200 mm wide x 1590
mm high; overall window type [W2-14] 1 1 4 5.58 0.30 1.00 6.70
Less: Tiled area

Tiled area -1 1 1 72.78 1.00 1.00 - 72.78


1,285.60

E Concrete surfaces (exposed beam and column surfaces) M2 436.72

Supply and fix approved glazed ceramic wall tiles; 300mm x


200mm x 6mm thick; approved colour; bedding and jointing
on screed (measured separately) with approved water proof
adhesive; flush pointing in approved coloured grout to:

F Walls M2 72.78

SUNDRIES

Accessories

G Edge trim; plastic; quarter round; setting at edges of wall tile finish M
Master toilet 1 1 2 2.76 1.00 1.00 5.52
Master toilet 1 1 2 2.00 1.00 1.00 4.00
D2-12 1 2 1 1.00 1.00 2.10 4.20
D2-16 1 2 1 1.00 1.00 2.10 4.20

Shared bathroom 2 1 2 3.84 1.00 1.00 15.36


Shared bathroom 2 1 2 1.59 1.00 1.00 6.36
D2-12 2 2 1 1.00 1.00 2.10 8.40

Master toilet 1 1 2 2.76 1.00 1.00 5.52


Master toilet 1 1 2 2.00 1.00 1.00 4.00
D2-12 1 2 1 1.00 1.00 2.10 4.20

W2-14 1 1 3 3.18 1.00 1.00 9.54


W2-11 1 1 1 3.48 1.00 1.00 3.48
74.78

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm


second coat of cement and lime putty (1:10); steel trowelled
to:

G Concrete ceiling soffites. M2


1 1 1 353.06 1.00 1.00 353.06
353.06
H Staircase landing soffites M2 2.47

J Sloping staircase sofffites M2 13.08

K Moulded Ceiling cornice as per Architect's detail M


Quarry tiles
Verandah
Verandah 1 1 2 18.00 1.00 1.00 36.00
Verandah 1 1 2 1.20 1.00 1.00 2.40

Verandah 1 1 2 17.80 1.00 1.00 35.60


Verandah 1 1 2 1.45 1.00 1.00 2.90

Terrace 1 1 2 11.98 1.00 1.00 23.96


Terrace 1 1 2 3.06 1.00 1.00 6.12

Terrace 1 1 2 11.80 1.00 1.00 23.60


Terrace 1 1 2 2.42 1.00 1.00 4.83

Terrace 1 1 2 9.70 1.00 1.00 19.39


Terrace 1 1 2 14.81 1.00 1.00 29.62

450x450mm tiles; hallways and washrooms


Hallways 1 1 2 5.80 1.00 1.00 11.60
Hallways 1 1 2 11.98 1.00 1.00 23.95
Hallways 1 1 2 2.31 1.00 1.00 4.61
Hallways 1 1 2 2.82 1.00 1.00 5.64

Master toilet 1 1 2 2.76 1.00 1.00 5.52


Master toilet 1 1 2 2.00 1.00 1.00 4.00

Shared bathroom 1 2 2 3.84 1.00 1.00 15.36


Shared bathroom 1 2 2 1.59 1.00 1.00 6.36

Master toilet 1 1 2 2.76 1.00 1.00 5.52


Master toilet 1 1 2 2.00 1.00 1.00 4.00

300x300mm tiles; staircase areas


Staircase-01 1 1 2 8.95 1.00 1.00 17.90
Staircase-01 1 1 2 3.29 1.00 1.00 6.58
FHR 1 1 2 0.65 1.00 1.00 1.30

800x800mm tiles; other areas


Apartment #1
Lounge 1 1 2 7.84 1.00 1.00 15.68
Lounge 1 1 2 5.81 1.00 1.00 11.61
Recess 1 1 2 0.60 1.00 1.00 1.20

Pantry 1 1 2 4.04 1.00 1.00 8.08


Pantry 1 1 2 2.00 1.00 1.00 4.00

Kitchen 1 1 2 4.04 1.00 1.00 8.08


Kitchen 1 1 2 3.81 1.00 1.00 7.62

Masterbedroom 1 1 2 5.80 1.00 1.00 11.59


Masterbedroom 1 1 2 5.64 1.00 1.00 11.28

Lobby 1 1 2 2.00 1.00 1.00 4.00


Lobby 1 1 2 3.04 1.00 1.00 6.08

Bedroom 1 1 1 2 3.84 1.00 1.00 7.68


Bedroom 1 1 1 2 4.05 1.00 1.00 8.10
Door duct 1 1 2 0.68 1.00 1.00 1.35

Apartment #2
Lounge/dining 1 1 2 8.00 1.00 1.00 16.00
Lounge/dining 1 1 2 5.80 1.00 1.00 11.60
Lounge/dining 1 1 2 0.65 1.00 1.00 1.30

Kitchen 1 1 2 3.80 1.00 1.00 7.60


Kitchen 1 1 2 3.81 1.00 1.00 7.62

Pantry 1 1 2 1.80 1.00 1.00 3.59


Pantry 1 1 2 3.80 1.00 1.00 7.60

Lobby 1 1 2 2.89 1.00 1.00 5.78


Lobby 1 1 2 2.00 1.00 1.00 4.00

Master bedroom 1 1 2 5.80 1.00 1.00 11.60


Master bedroom 1 1 2 5.80 1.00 1.00 11.60

Bedroom 1 1 1 2 3.60 1.00 1.00 7.20


Bedroom 1 1 1 2 4.01 1.00 1.00 8.02
Wall 1 1 2 0.68 1.00 1.00 1.35
507.97

WATERPROOFING TO TOILETS and OTHER WET AREAS


Pure crystalline water proofing treatment in two coats using
"Vandex Super" manufactured by M/s. Vandex East Africa Limited
or approved equivalent to vertical and horizontal surfaces, with
proper gradient including surface preparation and applying slurry
coat of Vandex Super mixed with a cement sand mortar 1:3,
cleaning , pre-watering and then applying two coats of Vandex
Super (each coat approx. 0.75 kg per Sm) mixed to a slurry
consistency, curing, protecting the completed work by hessian
cloth, providing bonding keys for each coat, fillets, testing for water
tightness complete all as per manufacturer's specifications,
drawings and as directed by the Project Manager on:

To wet areas
37.06

A Horizontal or raking balustrade; 900mm high comprising of;


50mx3mm thick CHS handrail; 4 No. 25x2mm thick CHS
intermediate horizontal rails; 2/50x6mm thick MS flat balusters,
mild steel base plates; all rawl bolted into concrete; including
primer, spray painting wth three coats gloss oil paint and
decorations to approval.
M
Staircase 01
Waist 1 1 2 4.36 1.00 1.00 8.72
Void 1 1 1 1.70 1.00 1.00 1.70
Void 1 1 1 0.20 1.00 1.00 0.20
10.62

A Dado rails; Supply and fix 50mm diameter x 6mm thick CHS mild
steel handrail plugged with 25mm x 4mm thick mild steel support
fixed into wall; all painting and decorations M
Staircase 01
Waist 1 1 2 4.36 1.00 1.00 8.72
Landing 1 1 2 1.50 1.00 1.00 3.00
Landing 1 1 1 3.29 1.00 1.00 3.29
15.01

Glass railing; 900mm high comprising of 12mm thick tempered


(toughed) laminated glass fixed to and including 50x50mm chrome
plated stainless steel handrails, bottom rails and vertical balusters
spaced at 900mm centres; all chrome plated stainless brackets; all
cast in concrete.
M
Openings 1 1 1 19.60 1.00 1.00 19.60
Openings 1 1 1 5.60 1.00 1.00 5.60
Verandah 1 1 1 17.84 1.00 1.00 17.84
Verandah 1 1 1 20.66 1.00 1.00 20.66
63.70
Prepare and apply one undercoat and two finishing coats of
matt emulsion paint in accordance with manufacturer's
instructions to:

B Concrete ceiling soffites. M2 353.06

C Staircase landing soffites M2 2.47

D Sloping staircase sofffites M2 13.08

E Moulded Ceiling cornice as per Architect's detail M 507.97

Prepare and apply one undercoat and two finishing coats of


silk vinyl paint in accordance with manufacturer's instructions
to:

Plastered walls 1 1 1 648.36 1.00 1.00 648.36


648.36

Prepare and apply one undercoat and two finishing coats of


hygienic coating paint in accordance with the manufacturer's
instructions to:

Master toilet 1 1 2 2.76 1.00 3.25 17.94


Master toilet 1 1 2 2.00 1.00 3.25 13.00
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68
D2-16 -1 1 1 0.50 1.00 2.65 - 1.33

Shared bathroom 1 2 2 3.84 1.00 3.25 49.92


Shared bathroom 1 2 2 1.59 1.00 3.25 20.67
D2-12 -1 2 1 0.80 1.00 2.10 - 3.36

Master toilet 1 1 2 2.76 1.00 3.25 17.94


Master toilet 1 1 2 2.00 1.00 3.25 13.00
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68
Less:
tiled area -1 1 1 72.78 1.00 1.00 - 72.78
51.65
Prepare and apply 1.5mm thick layer of textured decorative
paint finishes to the plastered wall.
Verandah
Verandah 1 1 2 18.00 1.00 3.25 117.00
Verandah 1 1 2 1.20 1.00 3.25 7.80
openings -1 1 3 3.70 1.00 2.70 - 29.97

Verandah 1 1 2 17.80 1.00 3.25 115.70


Verandah 1 1 2 1.45 1.00 3.25 9.42
D2-06 -1 1 1 1.00 1.00 2.65 - 2.65
D2-14 -1 1 1 0.90 1.00 2.65 - 2.39
Add: Reveals and jambs
openings 1 1 3 9.10 0.30 2.70 22.11

Terrace 1 1 2 11.98 1.00 3.25 77.87


Terrace 1 1 2 3.06 1.00 3.25 19.89
Terrace 1 1 2 0.20 1.00 3.25 1.30
Terrace 1 1 2 0.10 1.00 3.25 0.65
D2-06 -1 1 1 1.50 1.00 2.65 - 3.97
Openings -1 1 1 5.45 1.00 2.70 - 14.72
Add: Reveals and jambs
Openings 1 1 1 10.85 0.30 1.00 3.26

Terrace 1 1 2 11.80 1.00 3.25 76.70


Terrace 1 1 2 2.42 1.00 3.25 15.70
D2-05 -1 1 1 2.20 1.00 1.00 - 2.20
Openings -1 1 1 11.80 1.00 2.70 - 31.86
Openings -1 1 2 2.42 1.00 2.70 - 13.04
Add: Reveals and jambs
Openings 1 1 1 17.20 0.30 1.00 5.16
Openings 1 1 1 7.82 0.30 1.00 2.34

Terrace 1 1 2 9.70 1.00 3.25 63.02


Terrace 1 1 2 14.81 1.00 3.25 96.27
D2-07 -1 1 1 1.20 1.00 2.65 - 3.18
Terrace 1 1 1 5.70 1.00 2.70 15.39
Terrace 1 1 1 14.81 1.00 2.70 39.99
585.59

Prepare and apply one undercoat and two finishing coats of


gloss oil paint in accordance with manufacturer's instructions
to:

J General surfaces of metal (measured flat both sides) M2


Balustrades
Staircase 01
Waist 1 2 2 4.36 1.00 0.90 15.70
Void 1 2 1 1.70 1.00 0.90 3.06
Void 1 2 1 0.20 1.00 0.90 0.36

Dado rails; M
Staircase 01
Waist 1 2 2 4.36 1.00 0.30 5.23
Landing 1 2 2 1.50 1.00 0.30 1.80
Landing 1 2 1 3.29 1.00 0.30 1.97
M2 28.12

ELEMENT NO. 8
INTERNAL FINISHINGS

BILL NO.2

ELEMENT NO. 9

EXTERNAL FINISHINGS

Roof drainage

Fulbora; 150mm diameter; stainless steel; complete with a clamp


ring and grating; including taking around the opening and making
good to distrubed concrete and finished surfaces; as per the
Architect's detail.
1 1 5 1.00 1.00 1.00 5.00
5.00

Piepwork measured elsewhere in plumbing installations

APP - Modified Bitumen


4mm thick APP modified bituminous water
proofing membrane reinforced with polyester with
50mm side and 75mm end laps, fully bonded and torch
applied in accordance with manufacturers
instructions; to
224.56

100mm high x 10mm thick skirting

1 1 1 130.10 1.00 1.00 130.10


130.10

Supply and Fix 600 x 600 x 10mm Thick approved Quarry floor tiles
in approved water adhesive, pointed with approved tri poly fortified
grout and admix grout to :
224.56

100mm high x 10mm thick skirting

1 1 1 149.00 1.00 1.00 149.00


130.10

20mm thick rendering in Cement and Sand (1:4) mortar; as


per Architect's details; on:

A Walls and concrete surfaces M2


G/L G(2-5) 1 1 2 17.80 1.00 3.50 124.60
Walls at telecom duct towards the lift shaft 1 1 2 0.84 1.00 3.50 5.88
Walls at telecom duct towards the lift shaft 1 1 1 2.36 1.00 3.50 8.26
Along G/L 5 1 1 1 13.63 1.00 3.50 47.69
Along G/L D1 1 1 1 9.70 1.00 3.50 33.93
Wall with exit door D2-07 1 1 1 2.82 1.00 3.50 9.85
Wall with exit door D2-07 1 1 1 3.70 1.00 3.50 12.93
Along G/L 2,B,4 1 1 3 12.10 1.00 3.50 127.05
Along G/L D 1 1 2 3.06 1.00 3.50 21.42
Along G/L 2' 1 1 1 11.28 1.00 3.50 39.46
Along G/L E 1 1 1 6.55 1.00 3.50 22.93
Along G/L 1 1 1 1 9.14 1.00 3.50 31.99

Deductions
Openings and doors
Verandah openings/front -1 1 3 3.70 1.00 2.70 - 29.97
Verandah openings/front -1 1 1 2.40 1.00 2.70 - 6.48
D2-08 -1 1 1 1.00 1.00 2.65 - 2.65
D2-07 -1 1 1 1.20 1.00 2.65 - 3.18
D2-03 -1 1 2 1.80 1.00 2.65 - 9.54
D2-06 -1 1 1 1.50 1.00 2.65 - 3.97
D2-14 -1 1 1 0.90 1.00 2.65 - 2.39

W2-05 -1 1 6 1.60 1.00 2.65 - 25.44


W2-11 -1 1 5 1.50 1.00 1.50 - 11.25
W2-03 -1 1 3 2.20 1.00 1.59 - 10.49
W2-14 -1 1 4 1.20 1.00 1.59 - 7.63
W2-02 -1 1 1 2.20 1.00 2.65 - 5.83
W2-10 -1 1 3 1.57 1.00 2.20 - 10.33
W2-08 -1 1 2 1.57 1.00 1.59 - 4.98

Lift shall walls 1 1 4 2.45 1.00 3.90 38.22


Less: Lift door "unamed" -1 1 1 1.22 1.00 2.10 - 2.56
387.52

Prepare and apply Plascon Architexture Grafiato coating in


accordance with manufacturer's instructions to:

387.52
BILL NO.2

ELEMENT NO. 10

FITTINGS

A Alow a provisional sum of Ushs. or fittings 39,565,500.00


Kitchen fittings; L shaped 2650mm x 3000mm x 900mm deep x
900mm high complete with 3000mm long x 300mm wide x
1200mm high tea table. 1 1 1 8.65 1.00 950,000.00 8,217,500.00
Kitchen fittings; L shaped 2800mm x 2600mm x 900mm deep x
900mm high complete with 2600mm long x 300mm wide x
1200mm high tea table. 1 1 1 8.00 1.00 950,000.00 7,600,000.00

Pantry cupboard; size 3840mm long x 600mm wide x 3250mm high 1 1 1 3.84 1.00 1,200,000.00 4,608,000.00

Pantry cupboard; size 3600mm long x 600mm wide x 3250mm high 1 1 1 3.60 1.00 1,200,000.00 4,320,000.00

Wardrobe fitting; size 4000mm long x 600mm wide x 3250mm high 1 1 1 4.00 1.00 1,200,000.00 4,800,000.00

Wardrobe fitting; size 2000mm long x 600mm wide x 3250mm high 1 1 1 2.00 1.00 1,200,000.00 2,400,000.00

Wardrobe fitting; size 3600mm long x 600mm wide x 3250mm high 1 1 1 3.60 1.00 1,200,000.00 4,320,000.00

Wardrobe fitting; size 2750mm long x 600mm wide x 3250mm high 1 1 1 2.75 1.00 1,200,000.00 3,300,000.00
CLIENT: CK COMPANY DATE: 4/5/2024
PROJECT: PROPOSED OFFICE BLOCK CALC BY: IB
LEVEL GROUND FLOOR
MEASUREMENTS PURPOSE: ESTIMATES
NO. DESCRIPTION UNIT EQ. PRTS EQ. PRTS EQ. PRTS L W H/D/kg/m QTY

THIRD FLOOR

SUPERSTRUCTURE

RC in grade 25 to columns M3
C1 9 1 1 0.40 0.40 3.25 4.68
C2 3 1 1 0.40 0.60 3.25 2.34
C3 5 1 1 0.40 0.60 3.25 3.90
C4 1 1 1 0.40 0.60 3.25 0.78
C5 3 1 1 0.40 0.60 3.25 2.34
C6 1 1 1 0.35 0.35 3.25 0.40
22 14.44

RC in grade 25 to beams M3
G/L E(1-2) & F(1-2) 1 1 2 3.14 0.40 0.55 1.38
G/L G(1-2) 1 1 1 1.10 0.40 0.55 0.24
G/L B,C,D,E,F(2-3) 1 1 5 5.50 0.40 0.55 6.05
G/L G(2-3) 1 1 1 5.60 0.40 0.55 1.23
G/L B(3-4) 1 1 1 5.45 0.40 0.55 1.20
G/L C(3-4) 1 1 1 5.45 0.40 0.55 1.20
G/L D(3-4) 1 1 1 5.45 0.40 0.55 1.20
G/L E(3-4) 1 1 1 11.45 0.40 0.55 2.52

G/L F(3-5) 1 1 1 11.45 0.40 0.55 2.52


G/L G(3-5) 1 1 1 11.25 0.40 0.55 2.48

G/L B2-C2 & B3-C3 1 1 2 5.60 0.40 0.55 2.46


G/L B4-C4 1 1 1 5.50 0.40 0.55 1.21
G/L 2,3 & 4 (C-D) 1 1 3 5.60 0.40 0.55 3.70
G/L 2,3,& 4(D-E) 1 1 3 5.60 0.40 0.55 3.70
G/L 1,2,3 & 5 (E-F) 1 1 4 5.60 0.40 0.55 4.93
G/L F1-G1 1 1 1 2.75 0.40 0.55 0.61
G/L 2,3 & 5 (F-G) 1 1 3 5.59 0.40 0.55 3.69
40.30

Upstand beam and moulding as per the Architects details.


Beam moulding 1 1 1 133.70 0.20 1.00 26.74
Beam moulding 1 1 1 116.20 0.11 1.00 12.20
38.94
RC in grade 25 to the lift walls 20mm thick M2
2 1 1 2.45 1.00 3.50 17.15
2 1 1 2.05 1.00 3.50 14.35
Less opening -1 1 1 1.22 1.00 2.10 - 2.56
28.94

250mm thick solid roof slab in RC grade 25 M2


Part 1; see planswift file 1 1 1 15.60 15.30 1.00 238.68
Part 2; see planswift file 1 1 1 6.00 2.40 1.00 14.40
Part 3; see planswift file 1 1 1 12.60 12.60 1.00 158.76
Part 4; see planswift file 1 1 1 12.60 6.50 1.00 81.90
Part 5; see planswift file 1 1 1 4.00 0.30 1.00 1.20
494.94

Reinforcements

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
RC in grade 25 to columns 1 1 150 14.44 1.00 1.00 2,165.72
RC in grade 25 to beams 1 1 150 40.30 1.00 1.00 6,045.10
Upstand beam and moulding as per the Architects details. 1 1 150 38.94 1.00 1.00 5,841.15
RC in grade 25 to the lift walls 20mm thick 1 1 150 28.94 0.20 1.00 868.14
250mm thick solid roof slab in RC grade 25 1 1 150 494.94 0.25 1.00 18,560.25
33,480.36

Sawn form work to;

Sides of columns M2
C1 9 1 2 0.80 1.00 3.25 46.80
C2 3 1 2 1.00 1.00 3.25 19.50
C3 5 1 2 1.00 1.00 3.25 32.50
C4 1 1 2 1.00 1.00 3.25 6.50
C5 3 1 2 1.00 1.00 3.25 19.50
C6 1 1 2 0.70 1.00 3.25 4.55
129.35

Sides and soffits of beams M2


G/L E(1-2) & F(1-2) 1 1 2 3.14 1.50 1.00 9.42
G/L G(1-2) 1 1 1 1.10 1.50 1.00 1.65
G/L B,C,D,E,F(2-3) 1 1 5 5.50 1.50 1.00 41.25
G/L G(2-3) 1 1 1 5.60 1.50 1.00 8.40
G/L B(3-4) 1 1 1 5.45 1.50 1.00 8.18
G/L C(3-4) 1 1 1 5.45 1.50 1.00 8.18
G/L D(3-4) 1 1 1 5.45 1.50 1.00 8.18
G/L E(3-4) 1 1 1 11.45 1.50 1.00 17.17
G/L F(3-5) 1 1 1 11.45 1.50 1.00 17.17
G/L G(3-5) 1 1 1 11.25 1.50 1.00 16.88

G/L B2-C2 & B3-C3 1 1 2 5.60 1.50 1.00 16.80


G/L B4-C4 1 1 1 5.50 1.50 1.00 8.25
G/L 2,3 & 4 (C-D) 1 1 3 5.60 1.50 1.00 25.20
G/L 2,3,& 4(D-E) 1 1 3 5.60 1.50 1.00 25.20
G/L 1,2,3 & 5 (E-F) 1 1 4 5.60 1.50 1.00 33.60
G/L F1-G1 1 1 1 2.75 1.50 1.00 4.13
G/L 2,3 & 5 (F-G) 1 1 3 5.59 1.50 1.00 25.13
274.78

Sides of upstand beams and mouldings


Beam moulding 1 1 1 133.70 1.80 1.00 240.66
Beam moulding 1 1 1 116.20 0.70 1.00 81.34
322.00

Extra over formwork to parapet walls for forming grooves,


chamfers, rebates, chases and mouldings.
322.00

Consider render and painting


Beam moulding 1 1 1 133.70 1.80 1.00 240.66
Beam moulding 1 1 1 116.20 0.70 1.00 81.34
322.00

Soffits of the slab 250mm thick M2


Part 1; see planswift file 1 1 1 15.60 15.30 1.00 238.68
Part 2; see planswift file 1 1 1 6.00 2.40 1.00 14.40
Part 3; see planswift file 1 1 1 12.60 12.60 1.00 158.76
Part 4; see planswift file 1 1 1 12.60 6.50 1.00 81.90
Part 5; see planswift file 1 1 1 4.00 0.30 1.00 1.20

Ddt: beam soffites


Method used because the structural engineer's do not
fully correspond with the architectural drawings
G/L E(1-2) & F(1-2) -1 1 2 3.14 0.40 1.00 - 2.51
G/L G(1-2) -1 1 1 1.10 0.40 1.00 - 0.44
G/L B,C,D,E,F(2-3) -1 1 5 5.50 0.40 1.00 - 11.00
G/L G(2-3) -1 1 1 5.60 0.40 1.00 - 2.24
G/L B(3-4) -1 1 1 5.45 0.40 1.00 - 2.18
G/L C(3-4) -1 1 1 5.45 0.40 1.00 - 2.18
G/L D(3-4) -1 1 1 5.45 0.40 1.00 - 2.18
G/L E(3-4) -1 1 1 11.45 0.40 1.00 - 4.58
G/L F(3-5) -1 1 1 11.45 0.40 1.00 - 4.58
G/L G(3-5) -1 1 1 11.25 0.40 1.00 - 4.50

G/L B2-C2 & B3-C3 -1 1 2 5.60 0.40 1.00 - 4.48


G/L B4-C4 -1 1 1 5.50 0.40 1.00 - 2.20
G/L 2,3 & 4 (C-D) -1 1 3 5.60 0.40 1.00 - 6.72
G/L 2,3,& 4(D-E) -1 1 3 5.60 0.40 1.00 - 6.72
G/L 1,2,3 & 5 (E-F) -1 1 4 5.60 0.40 1.00 - 8.96
G/L F1-G1 -1 1 1 2.75 0.40 1.00 - 1.10
G/L 2,3 & 5 (F-G) -1 1 3 5.59 0.40 1.00 - 6.70
421.67

Sides of the lift walls M2


1 2 2 2.45 1.00 3.25 31.85
1 2 2 2.05 1.00 3.25 26.65
Less: Lift door "unamed" -1 2 1 1.22 1.00 2.10 - 5.12
53.38

Edges of the slab 250mm wide M


Part 1; see planswift file 1 1 2 15.60 1.00 1.00 31.20
Part 2; see planswift file -1 1 2 6.00 1.00 1.00 - 12.00
Part 3; see planswift file 1 1 2 12.60 1.00 1.00 25.20
Part 4; see planswift file 1 1 2 12.60 1.00 1.00 25.20

Part 1; see planswift file 1 1 2 15.30 1.00 1.00 30.60


Less: 1 1 2 2.40 1.00 1.00 4.80
Part 4; see planswift file 1 1 2 6.50 1.00 1.00 13.00
Part 5; see planswift file 1 1 2 0.30 1.00 1.00 0.60
118.60
7800
Galvanised Steel CAT ladders

Welded Cat ladder 500mm wide and 8500mm long overall tank
room flat roof anchored to block/ concrete work including painting
as per Architect's details; Second floor up to the roof
1 1 1 1.00 1.00 1.00 1.00
1.00

600x600x4mm thick galvanised roof hatch cover; including


50x50x6mm galvanised angle cast into concrete; all joints, dressing
and bonding to sorrunding work, undercloaks and other associated
linings, ends, angles, bedding, pointing and fixings.
1 1 1 1.00 1.00 1.00 1.00
1.00

ELEMENT NO. 2
BILL NO.2

ELEMENT NO. 4

EXTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties
set in horizontal alternate courses:

A 300mm thick M2
G/L G(2-5) 1 1 2 17.80 1.00 2.70 96.12
Walls at telecom duct towards the lift shaft 1 1 2 0.84 1.00 2.70 4.54
Walls at telecom duct towards the lift shaft 1 1 1 2.36 1.00 2.70 6.37
Along G/L 5 1 1 1 13.63 1.00 2.70 36.79
Along G/L D1 1 1 1 9.70 1.00 2.70 26.18
Wall with exit door D2-07 1 1 1 2.82 1.00 2.70 7.60
Wall with exit door D2-07 1 1 1 3.70 1.00 2.70 9.98
Along G/L 2,B,4 1 1 3 12.10 1.00 2.70 98.01
Along G/L D 1 1 2 3.06 1.00 2.70 16.52
Along G/L 2' 1 1 1 11.28 1.00 2.70 30.44
Along G/L E 1 1 1 6.55 1.00 2.70 17.69
Along G/L 1 1 1 1 9.14 1.00 2.70 24.68

Deductions
Openings and doors
Verandah openings/front -1 1 3 3.70 1.00 2.70 - 29.97
Verandah openings -1 1 1 2.25 1.00 2.70 - 6.08
D3-08 -1 1 1 1.00 1.00 2.65 - 2.65

W3-06 -1 1 6 1.60 1.00 2.20 - 21.12


W3-10 -1 1 9 1.57 1.00 2.20 - 30.99
W3-01 -1 1 4 2.20 1.00 2.20 - 19.36
W3-13 -1 1 5 1.20 1.00 2.20 - 13.20
W3-04 -1 1 1 1.80 1.00 2.20 - 3.96
W3-07 -1 1 2 1.57 1.00 2.20 - 6.89
240.70

A 200mm thick
Wall along E2 to lift shaft 1 1 1 8.84 1.00 2.70 23.87
Ddt: D3-03 -1 1 1 1.80 1.00 2.65 - 4.77
19.10
A Ditto parapet walls
Wall along E2 to lift shaft 1 1 1 133.70 1.00 0.50 66.85
66.85

Reinforced Insitu concrete grade 25 in:-


Moulded concrete window Sill; Section size 250 x 85 x 50mm;
C M
weathered and throated; all as per Architect's details
Windows
W3-06 1 1 6 1.90 1.00 1.00 11.40
W3-10 1 1 9 1.87 1.00 1.00 16.79
W3-01 1 1 4 2.50 1.00 1.00 10.00
W3-13 1 1 5 1.50 1.00 1.00 7.50
W3-04 1 1 1 2.10 1.00 1.00 2.10
W3-07 1 1 2 1.87 1.00 1.00 3.73
51.52

Reinforced concrete grade 25 in:-


A Lintels M2
Verandah openings/front 1 1 3 4.70 0.30 0.30 1.27
Verandah openings/front 1 1 1 2.55 0.30 0.30 0.23
D3-08 1 1 1 1.30 0.30 0.30 0.12
D3-03 1 1 2 2.10 0.30 0.30 0.38

W3-06 1 1 6 1.90 0.30 0.30 1.03


W3-10 1 1 5 1.87 0.30 0.30 0.84
W3-01 1 1 3 2.50 0.30 0.30 0.67
W3-13 1 1 4 1.50 0.30 0.30 0.54
W3-04 1 1 1 2.10 0.30 0.30 0.19
W3-07 1 1 2 1.87 0.30 0.30 0.34
5.60

Sawn formwork to:-

Sides and soffites of lintels

Verandah openings/front 1 1 3 4.70 0.90 1.00 12.69


Verandah openings/front 1 1 1 2.55 0.90 1.00 2.30
D3-08 1 1 1 1.30 0.90 1.00 1.17
D3-03 1 1 2 2.10 0.90 1.00 3.78

W3-06 1 1 6 1.90 0.90 1.00 10.26


W3-10 1 1 5 1.87 0.90 1.00 8.39
W3-01 1 1 3 2.50 0.90 1.00 6.75
W3-13 1 1 4 1.50 0.90 1.00 5.40
W3-04 1 1 1 2.10 0.90 1.00 1.89
W3-07 1 1 2 1.87 0.90 1.00 3.36
55.98

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Lintels 1 1 150 5.60 1.00 1.00 839.77
839.77

BILL NO.2

ELEMENT NO. 5

INTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties
set in horizontal alternate courses:

A 200mm thick Wall M2


G/L D'3-E'3 & D4-E'4 1 1 2 12.08 1.00 3.25 78.52
Closet walls 1 1 1 0.60 1.00 3.25 1.95
G/L 3 & 3' (A-C) 1 1 2 5.80 1.00 3.25 37.70
L pantry 1 1 1 2.80 1.00 3.25 9.10
L pantry 1 1 1 2.80 1.00 3.25 9.10
Master/bathroom 1 1 1 5.80 1.00 3.25 18.83
Bedroom 1/Masterroom 1 1 1 5.80 1.00 3.25 18.83
Pantry towards the door 1 1 1 2.11 1.00 3.25 6.84
G/L D(2-3) 1 1 1 5.05 1.00 3.25 16.40
Master/lounge 1 1 1 5.80 1.00 3.25 18.85
Recess 1 1 1 0.45 1.00 3.25 1.46
Duct 1 1 1 0.70 1.00 3.25 2.28
Kitchen/shared bath 1 1 1 5.80 1.00 3.25 18.85
Bedroom/Bathroom 1 1 1 3.60 1.00 3.25 11.70
Bath/bedroom 1 1 1 1 2.84 1.00 3.25 9.23
Duct 1 1 1 2.80 1.00 3.25 9.10
Deductions
D3-12 -1 1 8 0.80 1.00 2.10 - 13.44
D3-11 -1 1 2 1.00 1.00 2.65 - 5.30
D3-05 -1 1 2 1.50 1.00 2.65 - 7.95
242.05

A 150mm thick walls M2


Masterbath/lobby both apartments 1 1 2 2.00 1.00 3.65 14.60
Masterbath/lobby both apartments 1 1 2 0.60 1.00 3.65 4.38
18.98
Reinforced concrete grade 25 in:-
A Lintels M
D3-12 1 1 8 1.10 0.20 0.30 0.53
D3-11 1 1 2 1.30 0.20 0.30 0.16
D3-05 1 1 2 1.80 0.20 0.30 0.22
0.90

Sawn formwork to:-

Sides and soffites of lintels


D3-12 1 1 8 1.10 0.80 1.00 7.04
D3-11 1 1 2 1.30 0.80 1.00 2.08
D3-05 1 1 2 1.80 0.80 1.00 2.88
12.00

High tensile steel bar reinforcement to BS 4461

A Re-bar Kg
Master/bathroom 1 1 150 0.90 1.00 1.00 135.00
135.00

BILL NO.2

ELEMENT NO. 6

WINDOWS, SCREENS AND LIGHTS

Anodized Aluminum casement windows. The color shall be to


client's approval; all additional costs are deemed included.

Provide and fix purpose-made anodized aluminum windows


and window frames complete with 5mm thick translucent
glass and single glazing, glazing beads, wash leather strips,
sealing, burglar proofing, fly mesh, all ironmongery and
accessories; fixing to blockwork or concrete; all as per
Architect's drawings; Drawing No. NA(22)02-9/10; in:

The contractor is expected to prepare and submit shop


drawings for approval prior to fabrication and erection of the
windows and screens

A Glazed window and window frames size: 1600 mm wide x 2200mm


high; overall window type [W3-06] No 6.00
A Glazed window and window frames size: 1565 mm wide x 2200
mm high; overall window type [W3-10] No 9.00
B Glazed window and window frames size: 2200mm wide x 2200 mm
high; overall window type [W3-01] No 4.00
B Glazed window and window frames size: 1200mm wide x 2200 mm
high; overall window type [W3-013] No 5.00
B Glazed window and window frames size: 1800 mm wide x 2200
mm high; overall window type [W3-04] No 1.00
B Glazed window and window frames size: 1565mm wide x 2200 mm
high; overall window type [W3-07] No 2.00

Reinforced Insitu concrete grade 25 in:-

Moulded concrete window Sill; Section size 350 x 85 x 50mm;


weathered and throated; all as per Architect's details
Glazed window and window frames size: 1600 mm wide x 2200mm
high; overall window type [W3-06] 1 1 6 1.90 1.00 1.00 11.40
Glazed window and window frames size: 1565 mm wide x 2200
mm high; overall window type [W3-10] 1 1 9 1.87 1.00 1.00 16.79
Glazed window and window frames size: 2200mm wide x 2200 mm
high; overall window type [W3-01] 1 1 4 2.50 1.00 1.00 10.00
Glazed window and window frames size: 1200mm wide x 2200 mm
high; overall window type [W3-013] 1 1 5 1.50 1.00 1.00 7.50
Glazed window and window frames size: 1800 mm wide x 2200
mm high; overall window type [W3-04] 1 1 1 2.10 1.00 1.00 2.10
Glazed window and window frames size: 1565mm wide x 2200 mm
high; overall window type [W3-07] 1 1 2 1.87 1.00 1.00 3.73
51.52

Window boards

Natural Stone Granite Window Board; size 150mm wide x 20mm


thick thick; all edges well finished with a coved mould; all as per
Architect's details
Glazed window and window frames size: 1600 mm wide x 2200mm
high; overall window type [W3-06] 1 1 6 1.60 1.00 1.00 9.60
Glazed window and window frames size: 1565 mm wide x 2200
mm high; overall window type [W3-10] 1 1 9 1.57 1.00 1.00 14.08
Glazed window and window frames size: 2200mm wide x 2200 mm
high; overall window type [W3-01] 1 1 4 2.20 1.00 1.00 8.80
Glazed window and window frames size: 1200mm wide x 2200 mm
high; overall window type [W3-013] 1 1 5 1.20 1.00 1.00 6.00
Glazed window and window frames size: 1800 mm wide x 2200
mm high; overall window type [W3-04] 1 1 1 1.80 1.00 1.00 1.80
Glazed window and window frames size: 1565mm wide x 2200 mm
high; overall window type [W3-07] 1 1 2 1.57 1.00 1.00 3.13
43.42
BILL NO.2

ELEMENT NO. 7

DOORS

DOORS, SHUTTERS AND HATCHES

Timber doors

The following in wrot hardwood to architect's satisfaction:-

Approved hardwood flush doors

A 45mm thick solid core timber flush door shutter size 800mm wide x
2100 mm high complete with a mahogany veneer; to Architect's
detail; door type [D3-12] No
1 1 8 1.00 1.00 1.00 8.00
8.00

Approved hardwood panelled doors;

A 45mm thick solid panelled door shutter size 1000mm wide x


2100mm high complete with 2 No. vision panels size 200mm wide
x 1000mm high; to Architect's detail; door type [D3-11] No
1 1 2 1.00 1.00 1.00 2.00
2.00

Door frames and finishings in in wrot hardwood

C 250mm x 50mm rebated frame M


D3-12 1 1 8 5.00 1.00 1.00 40.00
D3-11 1 1 2 6.30 1.00 1.00 12.60
Opening to toilet 1 1 2 6.20 1.00 1.00 12.40
65.00

C Ditto transomes M
D3-11 1 1 2 1.00 1.00 1.00 2.00
Opening to toilet 1 1 2 0.90 1.00 1.00 1.80
3.80

D 40mm x 20mm Splayed architrave or qudrant beads where


applicable. M
D3-12 1 2 8 5.00 1.00 1.00 80.00
D3-11 1 2 2 6.30 1.00 1.00 25.20
Opening to toilet 1 2 2 6.20 1.00 1.00 24.80
130.00

D 20mm x 20mm moulded glazing beads. M


D3-11 1 2 2 3.10 1.00 1.00 12.40
D3-11 - Vision panels 2 2 2 2.40 1.00 1.00 19.20
Opening to toilet 1 2 2 2.00 1.00 1.00 8.00
39.60

Ironmongery to architect's approval and sartisfaction

E 100mm Pressed steel butt hinges Pr


1 1 8 1.50 1.00 1.00 12.00
D3-11 1 1 2 1.50 1.00 1.00 3.00
15.00

F 25mm diameter rubber door stop plugged to wall/floor No


1 1 25 1.00 1.00 1.00 25.00
25.00

H 3 - Lever motrice lock complete with approved door handles No


D3-11 1 1 2 1.00 1.00 1.00 2.00
2.00

H Commercial privacy Lock complete with occupancy indicator Oil


rubbed bronze and Lock restroom hardware brass door handles No
D3-12 1 1 8 1.00 1.00 1.00 8.00
8.00

I Coat hooks No
1 1 8 1.00 1.00 1.00 8.00
8.00

J Door closer No
1 1 0 1.00 1.00 1.00 -
-

K Mild steel aldrop bolt complete with all the necessary accessories No
1 1 2 1.00 1.00 1.00 2.00
2.00

L Stainless Steel Push plate size 300mm x 100mm No


1 2 8 1.00 1.00 1.00 16.00
1 2 2 1.00 1.00 1.00 4.00
20.00
M Stainless Steel kick plate size 800mm wide x 150mm high x 3mm
thick No
1 2 8 1.00 1.00 1.00 16.00
16.00

M Stainless Steel kick plate size 1000mm wide x 150mm high x 3mm
thick No
1 2 2 1.00 1.00 1.00 4.00
4.00

Glazing

5mm thick clear sheet glass fixed to hardwood frames with


glazing beads (measured seperately)
D3-11 - Vent 1 1 2 1.00 0.55 1.00 1.10
D3-11 - Vision panel 1 2 2 1.00 0.20 1.00 0.80
1.90

Steel casement doors; mild steel

Supply and Fix the following purpose made mild steel door
and door frames; all members in 3mm thick steel sections
complete with mild steel frame, hinges, fixing lugs, locking
device and a single coat of red oxide primer, all fixed as per
Architect's details and satisfaction

D Louvered door set; size 900 mm wide x 2650 mm high; complete


with louvered door shutter; door type [D3-14] No 1.00

D Louvered door set; size 700 mm wide x 2650 mm high; door type
[D3-15] No 1.00

D Louvered door set; size 500mm wide x 2650 mm high; complete


with 1 louvered door shutters; door type [D3-16] No 1.00

Anodised aluminium doors

Supply and fix purpose-made anodised aluminium casement


doors and frames; complete with 6mm thick translucent glass
and single glazing, ironmongery, fixing lugs, all accessories
and one coat of red oxide primer before delivery; fixing to
blockwork or concrete; all as per Architect's drawings;
Drawing No. NA(22)02-9/10; in:

Door set; size 1800 mm wide x 2650 mm high; complete as per the
Architect's details; door type [D3-03] 1.00
Sliding door set; size 1500mm wide x 2650 mm high; complete as
per the Architect's details; door type [D3-05] 2.00

Sliding door set; size 1000mm wide x 2650 mm high; complete as


per the Architect's details; door type [D3-08] 1.00

Prepare and apply undercoat and three coats of gloss oil paint
on:-

I General surfaces of metal M2


Louvered door set; size 900 mm wide x 2650 mm high; complete
with louvered door shutter; door type [D3-14] 1 2 1 0.90 1.00 2.65 4.77
Louvered door set; size 700 mm wide x 2650 mm high; door type
[D3-15] 1 2 1 0.70 1.00 2.65 3.71
Louvered door set; size 500mm wide x 2650 mm high; complete
with 1 louvered door shutters; door type [D3-16] 1 2 1 0.50 1.00 2.65 2.65
11.13

J General surfaces of wood M2


Wood frames; girth exceeding 300mm wide; 350mm wide
250mm x 50mm rebated frame 1 1 1 65.00 0.35 1.00 22.75
Ditto transomes 1 1 1 3.80 0.60 1.00 2.28
Door shutters; D3-12 1 2 5 0.85 2.15 1.00 18.28
Door shutters; D3-11 1 2 2 1.05 2.15 1.00 9.03
52.34

K Wood surfaces not exceeding 100mm girth M


40mm x 20mm Splayed architrave or qudrant beads where
applicable. 1 1 1 130.00 1.00 1.00 130.00
20mm x 20mm moulded glazing beads 1 1 1 39.60 1.00 1.00 39.60
169.60

BILL NO.2

ELEMENT NO. 8

INTERNAL FINISHINGS

Floor screed; Cement and sand (1:4); wood floated finish:

A 40mm thick; to receive quarry floor tiles (measured separately) M2


Verandah
Verandah 1 1 1 1.45 1.45 1.00 2.10
2.10

A 40mm thick; to receive procelain floor tiles (measured separately) M2


300x300mm tiles; staircase areas
Staircase-01 1 1 1 4.15 3.29 1.00 13.65
Staircase-01 1 1 1 0.90 0.65 1.00 0.59

450x450mm tiles; hallways and washrooms


Hallways 1 1 1 5.80 2.86 1.00 16.59
Hallways 1 1 1 11.98 2.74 1.00 32.81
Hallways 1 1 1 2.31 2.82 1.00 6.50

Washrooms/master 1 1 1 2.76 2.00 1.00 5.52


Add: D12 door way 1 1 1 0.80 0.15 1.00 0.12
Shared toilet 1 1 2 3.84 1.59 1.00 12.21
Add: D12 door way 1 1 2 0.80 0.15 1.00 0.24
Shared toilet 1 1 1 3.60 1.59 1.00 5.72
Add: D12 door way 1 1 1 0.80 0.20 1.00 0.16
Washrooms/master 1 1 1 2.76 2.00 1.00 5.52
Add: D12 door way 1 1 1 0.80 0.15 1.00 0.12
Add: D16 door way 1 1 1 0.70 0.15 1.00 0.11

800x800mm tiles; other areas


Apartment #1
Lounge 1 1 1 7.84 5.81 1.00 45.51
Pantry 1 1 1 4.04 2.00 1.00 8.08
opening 1 1 1 2.40 0.20 1.00 0.48
Kitchen 1 1 1 4.04 3.81 1.00 15.39
D11 1 1 1 1.00 0.20 1.00 0.20
D2-5 1 1 1 1.50 0.20 1.00 0.30
Masterbedroom 1 1 1 5.80 5.64 1.00 32.68
Add: D12 1 1 1 0.80 0.20 1.00 0.16
Lobby 1 1 1 2.00 3.04 1.00 6.08
Add: D12 1 1 1 0.80 0.20 1.00 0.16
Bedroom 1 1 1 1 3.84 4.05 1.00 15.55
ddt: Duct -1 1 1 0.70 1.80 1.00 - 1.26
Door duct -1 1 1 0.60 0.15 1.00 - 0.09

Apartment #2
Lounge/dining 1 1 1 8.00 5.80 1.00 46.40
D5 1 1 1 1.50 0.20 1.00 0.30
d12 1 1 1 0.80 0.20 1.00 0.16
Lounge/dining 1 1 1 1.34 0.60 1.00 0.80
Kitchen 1 1 1 3.80 3.81 1.00 14.46
Pantry 1 1 1 1.80 3.80 1.00 6.82
Add 1 1 1 2.00 0.20 1.00 0.40
Lobby 1 1 1 2.89 2.00 1.00 5.78
D12 1 1 3 0.80 0.20 1.00 0.48
Master bedroom 1 1 1 5.80 5.80 1.00 33.64
D12 1 1 2 0.80 0.20 1.00 0.32
ddt: Duct -1 1 1 0.70 0.70 1.00 - 0.49
D15 1 1 1 0.70 0.20 1.00 0.14
Ddt 1 1 1 1.54 0.65 1.00 1.00
D12 1 1 1 0.80 0.15 1.00 0.12
Bedroom 1 1 1 1 3.60 4.01 1.00 14.44
ddt: Wall 1 1 1 0.60 0.15 1.00 0.09
347.97

J Ditto; to receive skirting; 100mm high ditto M


Quarry tiles
Verandah
Verandah 1 1 2 1.45 1.00 1.00 2.90
Verandah 1 1 1 1.45 1.00 1.00 1.45
D3-14 -1 1 1 0.90 1.00 1.00 - 0.90

450x450mm tiles; hallways and washrooms


Hallways 1 1 2 5.80 1.00 1.00 11.60
Hallways 1 1 2 11.98 1.00 1.00 23.95
Hallways 1 1 2 2.31 1.00 1.00 4.61
Hallways 1 1 2 2.82 1.00 1.00 5.64
D2-03 -1 1 1 1.80 1.00 1.00 - 1.80
D2-05 -1 1 2 1.50 1.00 1.00 - 3.00
D2-07 -1 1 1 1.20 1.00 1.00 - 1.20
D2-02 -1 1 1 1.00 1.00 1.00 - 1.00
W2-05 -1 1 2 1.60 1.00 1.00 - 3.20

Master toilet 1 1 2 2.76 1.00 1.00 5.52


Master toilet 1 1 2 2.00 1.00 1.00 4.00
D2-12 -1 1 1 0.80 1.00 1.00 - 0.80
D2-16 -1 1 1 0.50 1.00 1.00 - 0.50

Shared bathroom 1 2 2 3.84 1.00 1.00 15.36


Shared bathroom 1 2 2 1.59 1.00 1.00 6.36
D2-12 -1 2 1 0.80 1.00 1.00 - 1.60

Master toilet 1 1 2 2.76 1.00 1.00 5.52


Master toilet 1 1 2 2.00 1.00 1.00 4.00
D2-12 -1 1 1 0.80 1.00 1.00 - 0.80

300x300mm tiles; staircase areas


Staircase-01 1 1 2 4.15 1.00 1.00 8.30
Staircase-01 1 1 1 3.29 1.00 1.00 3.29
FHR 1 1 2 0.65 1.00 1.00 1.30
D2-03 -1 1 1 1.80 1.00 1.00 - 1.80

800x800mm tiles; other areas


Apartment #1
Lounge 1 1 2 7.84 1.00 1.00 15.68
Lounge 1 1 2 5.81 1.00 1.00 11.61
Recess 1 1 2 0.60 1.00 1.00 1.20
D2-05 -1 1 1 1.50 1.00 1.00 - 1.50
Opening -1 1 1 3.81 1.00 1.00 - 3.81

Pantry 1 1 2 4.04 1.00 1.00 8.08


Pantry 1 1 2 2.00 1.00 1.00 4.00
Opening -1 1 1 2.40 1.00 1.00 - 2.40

Kitchen 1 1 2 4.04 1.00 1.00 8.08


Kitchen 1 1 2 3.81 1.00 1.00 7.62
Opening -1 1 1 3.81 1.00 1.00 - 3.81

Masterbedroom 1 1 2 5.80 1.00 1.00 11.59


Masterbedroom 1 1 2 5.64 1.00 1.00 11.28
Add: D12 -1 1 1 0.80 1.00 1.00 - 0.80

Lobby 1 1 2 2.00 1.00 1.00 4.00


Lobby 1 1 2 3.04 1.00 1.00 6.08
Add: D12 -1 1 4 0.80 1.00 1.00 - 3.20

Bedroom 1 1 1 2 3.84 1.00 1.00 7.68


Bedroom 1 1 1 2 4.05 1.00 1.00 8.10
Door duct 1 1 2 0.68 1.00 1.00 1.35
Add: D12 -1 1 1 0.80 1.00 1.00 - 0.80

Apartment #2
Lounge/dining 1 1 2 8.00 1.00 1.00 16.00
Lounge/dining 1 1 2 5.80 1.00 1.00 11.60
D5 -1 1 1 1.50 1.00 1.00 - 1.50
d12 -1 1 1 0.80 1.00 1.00 - 0.80
Opening towards the kitchen -1 1 1 3.81 1.00 1.00 - 3.81
Lounge/dining 1 1 2 0.65 1.00 1.00 1.30

Kitchen 1 1 2 3.80 1.00 1.00 7.60


Kitchen 1 1 2 3.81 1.00 1.00 7.62
Opening towards the kitchen -1 1 1 3.81 1.00 1.00 - 3.81
Opening to the pantry -1 1 1 2.40 1.00 1.00 - 2.40

Pantry 1 1 2 1.80 1.00 1.00 3.59


Pantry 1 1 2 3.80 1.00 1.00 7.60
Opening to the pantry -1 1 1 2.40 1.00 1.00 - 2.40

Lobby 1 1 2 2.89 1.00 1.00 5.78


Lobby 1 1 2 2.00 1.00 1.00 4.00
d12 -1 1 4 0.80 1.00 1.00 - 3.20

Master bedroom 1 1 2 5.80 1.00 1.00 11.60


Master bedroom 1 1 2 5.80 1.00 1.00 11.60
D12 -1 1 2 0.80 1.00 1.00 - 1.60
Bedroom 1 1 1 2 3.60 1.00 1.00 7.20
Bedroom 1 1 1 2 4.01 1.00 1.00 8.02
Wall 1 1 2 0.68 1.00 1.00 1.35
262.58

Tiles (varying specifications)

M Quarry tiles M2
1 1 1 2.10 1.00 1.00 2.10
2.10

M Procelain tiles: Size 800 x 800 x 10 mm thick to floors M2


248.11

M Ditto; size 450 x 450 x 10mm thick to floors M2


85.62

M Ditto; size 300 x 300 x 10mm thick to floors M2


14.24

J Ditto; to receive skirting; 100mm high ditto M


1 1 1 262.58 1.00 1.00 262.58
262.58

WATERPROOFING TO TOILETS and OTHER WET AREAS

Pure crystalline water proofing treatment in two coats using


"Vandex Super" manufactured by M/s. Vandex East Africa Limited
or approved equivalent to vertical and horizontal surfaces, with
proper gradient including surface preparation and applying slurry
coat of Vandex Super mixed with a cement sand mortar 1:3,
cleaning , pre-watering and then applying two coats of Vandex
Super (each coat approx. 0.75 kg per Sm) mixed to a slurry
consistency, curing, protecting the completed work by hessian
cloth, providing bonding keys for each coat, fillets, testing for water
tightness complete all as per manufacturer's specifications,
drawings and as directed by the Project Manager on:

To wet areas
37.06

WALL FINISHES

Wall Tile backing


Screed backing to wall; Cement and sand (1:4); wood floated
finish:
C 12mm thick; to receive ceramic wall tiles (measured separately) M2
Master toilet 1 1 2 2.76 1.00 2.10 11.59
Master toilet 1 1 2 2.00 1.00 2.10 8.40
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68
D2-16 -1 1 1 0.50 1.00 2.10 - 1.05

Shared bathroom 1 2 2 3.84 1.00 2.10 32.26


Shared bathroom 1 2 2 1.59 1.00 2.10 13.36
D2-12 -1 2 1 0.80 1.00 2.10 - 3.36

Master toilet 1 1 2 2.76 1.00 2.10 11.59


Master toilet 1 1 2 2.00 1.00 2.10 8.40
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68

W2-14 -1 1 3 1.20 1.00 0.99 - 3.56


W2-11 -1 1 1 1.50 1.00 0.99 - 1.48
72.78
Plaster; 12 mm first coat of cement and sand (1:6); 3 mm
second coat of cement and lime putty (1:10); steel trowelled
to:

D Walls M2
Quarry tiles
Verandah
Verandah 1 1 2 17.80 1.00 3.25 115.70

openings -1 1 3 3.70 1.00 2.70 - 29.97


Add: Reveals and jambs
openings 1 1 3 9.10 0.30 2.70 22.11

450x450mm tiles; hallways and washrooms


Hallways 1 1 2 5.80 1.00 3.25 37.70
Hallways 1 1 2 11.98 1.00 3.25 77.84
Hallways 1 1 2 2.31 1.00 3.25 14.98
Hallways 1 1 2 2.82 1.00 3.25 18.33
D2-03 -1 1 1 1.80 1.00 2.65 - 4.77
D2-05 -1 1 2 1.50 1.00 2.65 - 7.95

Master toilet 1 1 2 2.76 1.00 3.25 17.94


Master toilet 1 1 2 2.00 1.00 3.25 13.00
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68
D2-16 -1 1 1 0.50 1.00 2.65 - 1.33
Shared bathroom 1 2 2 3.84 1.00 3.25 49.92
Shared bathroom 1 2 2 1.59 1.00 3.25 20.67
D2-12 -1 2 1 0.80 1.00 2.10 - 3.36

Master toilet 1 1 2 2.76 1.00 3.25 17.94


Master toilet 1 1 2 2.00 1.00 3.25 13.00
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68

300x300mm tiles; staircase areas


Staircase-01 1 1 2 8.95 1.00 3.25 58.18
Staircase-01 1 1 2 3.29 1.00 3.25 21.39
FHR 1 1 2 0.65 1.00 3.25 4.23
D2-03 -1 1 1 1.80 1.00 2.65 - 4.77

800x800mm tiles; other areas


Apartment #1
Lounge 1 1 2 7.84 1.00 3.25 50.96
Lounge 1 1 2 5.81 1.00 3.25 37.73
Recess 1 1 2 0.60 1.00 3.25 3.90
D2-05 -1 1 1 1.50 1.00 2.65 - 3.97
Opening -1 1 1 3.81 1.00 3.25 - 12.37

Pantry 1 1 2 4.04 1.00 3.25 26.26


Pantry 1 1 2 2.00 1.00 3.25 13.00
Opening -1 1 1 2.40 1.00 3.25 - 7.80

Kitchen 1 1 2 4.04 1.00 3.25 26.26


Kitchen 1 1 2 3.81 1.00 3.25 24.77
Opening -1 1 1 3.81 1.00 3.25 - 12.38

Masterbedroom 1 1 2 5.80 1.00 3.25 37.67


Masterbedroom 1 1 2 5.64 1.00 3.25 36.66
Add: D12 -1 1 1 0.80 1.00 2.10 - 1.68

Lobby 1 1 2 2.00 1.00 3.25 13.00


Lobby 1 1 2 3.04 1.00 3.25 19.76
Add: D12 -1 1 4 0.80 1.00 2.10 - 6.72

Bedroom 1 1 1 2 3.84 1.00 3.25 24.96


Bedroom 1 1 1 2 4.05 1.00 3.25 26.33
Door duct 1 1 2 0.68 1.00 3.25 4.39
Add: D12 -1 1 1 0.80 1.00 2.10 - 1.68

Apartment #2
Lounge/dining 1 1 2 8.00 1.00 3.25 52.00
Lounge/dining 1 1 2 5.80 1.00 3.25 37.70
D5 -1 1 1 1.50 1.00 2.65 - 3.97
D12 -1 1 1 0.80 1.00 2.10 - 1.68
Opening towards the kitchen -1 1 1 3.81 1.00 3.25 - 12.38
Lounge/dining 1 1 2 0.65 1.00 3.25 4.23

Kitchen 1 1 2 3.80 1.00 3.25 24.70


Kitchen 1 1 2 3.81 1.00 3.25 24.77
Opening towards the kitchen -1 1 1 3.81 1.00 3.25 - 12.38
Opening to the pantry -1 1 1 2.40 1.00 3.25 - 7.80

Pantry 1 1 2 1.80 1.00 3.25 11.67


Pantry 1 1 2 3.80 1.00 3.25 24.70
Opening to the pantry -1 1 1 2.40 1.00 3.25 - 7.80

Lobby 1 1 2 2.89 1.00 3.25 18.79


Lobby 1 1 2 2.00 1.00 3.25 13.00
D12 -1 1 4 0.80 1.00 2.10 - 6.72

Master bedroom 1 1 2 5.80 1.00 3.25 37.70


Master bedroom 1 1 2 5.80 1.00 3.25 37.70
D12 -1 1 2 0.80 1.00 2.10 - 3.36

Bedroom 1 1 1 2 3.60 1.00 3.25 23.40


Bedroom 1 1 1 2 4.01 1.00 3.25 26.06
Wall 1 1 2 0.68 1.00 3.25 4.39
Deduct all Windows
Glazed window and window frames size: 1600 mm wide x 2200mm
high; overall window type [W3-06] -1 1 6 1.60 1.00 2.20 - 21.12
Glazed window and window frames size: 1565 mm wide x 2200
mm high; overall window type [W3-10] -1 1 9 1.57 1.00 2.20 - 30.99
Glazed window and window frames size: 2200mm wide x 2200 mm
high; overall window type [W3-01] -1 1 4 2.20 1.00 2.20 - 19.36
Glazed window and window frames size: 1200mm wide x 2200 mm
high; overall window type [W3-013] -1 1 5 1.20 1.00 2.20 - 13.20
Glazed window and window frames size: 1800 mm wide x 2200
mm high; overall window type [W3-04] -1 1 1 1.80 1.00 2.20 - 3.96
Glazed window and window frames size: 1565mm wide x 2200 mm
high; overall window type [W3-07] -1 1 2 1.57 1.00 2.20 - 6.89
Reveals and jambs
Glazed window and window frames size: 1600 mm wide x 2200mm
high; overall window type [W3-06] 1 1 6 7.60 0.30 1.00 13.68
Glazed window and window frames size: 1565 mm wide x 2200
mm high; overall window type [W3-10] 1 1 9 7.53 0.30 1.00 20.33
Glazed window and window frames size: 2200mm wide x 2200 mm
high; overall window type [W3-01] 1 1 4 8.80 0.30 1.00 10.56
Glazed window and window frames size: 1200mm wide x 2200 mm
high; overall window type [W3-013] 1 1 5 6.80 0.30 1.00 10.20
Glazed window and window frames size: 1800 mm wide x 2200
mm high; overall window type [W3-04] 1 1 1 8.00 0.30 1.00 2.40
Glazed window and window frames size: 1565mm wide x 2200 mm
high; overall window type [W3-07] 1 1 2 7.53 0.30 1.00 4.52
Less: Tiled area

Tiled area -1 1 1 72.78 1.00 1.00 - 72.78


924.54

E Concrete surfaces (exposed beam and column surfaces) M2 726.13

Supply and fix approved glazed ceramic wall tiles; 300mm x


200mm x 6mm thick; approved colour; bedding and jointing
on screed (measured separately) with approved water proof
adhesive; flush pointing in approved coloured grout to:
72.78

SUNDRIES

Accessories

G Edge trim; plastic; quarter round; setting at edges of wall tile finish M
Master toilet 1 1 2 2.76 1.00 1.00 5.52
Master toilet 1 1 2 2.00 1.00 1.00 4.00
D2-12 1 2 1 1.00 1.00 2.10 4.20
D2-16 1 2 1 1.00 1.00 2.10 4.20

Shared bathroom 2 1 2 3.84 1.00 1.00 15.36


Shared bathroom 2 1 2 1.59 1.00 1.00 6.36
D2-12 2 2 1 1.00 1.00 2.10 8.40

Master toilet 1 1 2 2.76 1.00 1.00 5.52


Master toilet 1 1 2 2.00 1.00 1.00 4.00
D2-12 1 2 1 1.00 1.00 2.10 4.20

W2-14 1 1 3 3.18 1.00 1.00 9.54


W2-11 1 1 1 3.48 1.00 1.00 3.48
74.78

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm


second coat of cement and lime putty (1:10); steel trowelled
to:

G Concrete ceiling soffites. M2


1 1 1 421.67 1.00 1.00 421.67
421.67
K Moulded Ceiling cornice as per Architect's detail M
Quarry tiles
Verandah
Verandah 1 1 2 17.80 1.00 1.00 35.60
Verandah 1 1 2 1.45 1.00 1.00 2.90

450x450mm tiles; hallways and washrooms


Hallways 1 1 2 5.80 1.00 1.00 11.60
Hallways 1 1 2 11.98 1.00 1.00 23.95
Hallways 1 1 2 2.31 1.00 1.00 4.61
Hallways 1 1 2 2.82 1.00 1.00 5.64

Master toilet 1 1 2 2.76 1.00 1.00 5.52


Master toilet 1 1 2 2.00 1.00 1.00 4.00

Shared bathroom 1 2 2 3.84 1.00 1.00 15.36


Shared bathroom 1 2 2 1.59 1.00 1.00 6.36

Master toilet 1 1 2 2.76 1.00 1.00 5.52


Master toilet 1 1 2 2.00 1.00 1.00 4.00

300x300mm tiles; staircase areas


Staircase-01 1 1 2 8.95 1.00 1.00 17.90
Staircase-01 1 1 2 3.29 1.00 1.00 6.58
FHR 1 1 2 0.65 1.00 1.00 1.30

800x800mm tiles; other areas


Apartment #1
Lounge 1 1 2 7.84 1.00 1.00 15.68
Lounge 1 1 2 5.81 1.00 1.00 11.61
Recess 1 1 2 0.60 1.00 1.00 1.20

Pantry 1 1 2 4.04 1.00 1.00 8.08


Pantry 1 1 2 2.00 1.00 1.00 4.00

Kitchen 1 1 2 4.04 1.00 1.00 8.08


Kitchen 1 1 2 3.81 1.00 1.00 7.62

Masterbedroom 1 1 2 5.80 1.00 1.00 11.59


Masterbedroom 1 1 2 5.64 1.00 1.00 11.28

Lobby 1 1 2 2.00 1.00 1.00 4.00


Lobby 1 1 2 3.04 1.00 1.00 6.08

Bedroom 1 1 1 2 3.84 1.00 1.00 7.68


Bedroom 1 1 1 2 4.05 1.00 1.00 8.10
Door duct 1 1 2 0.68 1.00 1.00 1.35
Apartment #2
Lounge/dining 1 1 2 8.00 1.00 1.00 16.00
Lounge/dining 1 1 2 5.80 1.00 1.00 11.60
Lounge/dining 1 1 2 0.65 1.00 1.00 1.30

Kitchen 1 1 2 3.80 1.00 1.00 7.60


Kitchen 1 1 2 3.81 1.00 1.00 7.62

Pantry 1 1 2 1.80 1.00 1.00 3.59


Pantry 1 1 2 3.80 1.00 1.00 7.60

Lobby 1 1 2 2.89 1.00 1.00 5.78


Lobby 1 1 2 2.00 1.00 1.00 4.00

Master bedroom 1 1 2 5.80 1.00 1.00 11.60


Master bedroom 1 1 2 5.80 1.00 1.00 11.60

Bedroom 1 1 1 2 3.60 1.00 1.00 7.20


Bedroom 1 1 1 2 4.01 1.00 1.00 8.02
Wall 1 1 2 0.68 1.00 1.00 1.35
362.05

Glass railing; 900mm high comprising of 12mm thick tempered


(toughed) laminated glass fixed to and including 50x50mm chrome
plated stainless steel handrails, bottom rails and vertical balusters
spaced at 900mm centres; all chrome plated stainless brackets; all
cast in concrete.
M
Openings 1 1 1 1.45 1.00 1.00 1.45
1.45

Prepare and apply one undercoat and two finishing coats of


matt emulsion paint in accordance with manufacturer's
instructions to:

B Concrete ceiling soffites. M2 421.67

E Moulded Ceiling cornice as per Architect's detail M 362.05

Prepare and apply one undercoat and two finishing coats of


silk vinyl paint in accordance with manufacturer's instructions
to:

Plastered walls 1 1 1 769.55 1.00 1.00 769.55


769.55
Prepare and apply one undercoat and two finishing coats of
hygienic coating paint in accordance with the manufacturer's
instructions to:

Master toilet 1 1 2 2.76 1.00 3.25 17.94


Master toilet 1 1 2 2.00 1.00 3.25 13.00
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68
D2-16 -1 1 1 0.50 1.00 2.65 - 1.33

Shared bathroom 1 2 2 3.84 1.00 3.25 49.92


Shared bathroom 1 2 2 1.59 1.00 3.25 20.67
D2-12 -1 2 1 0.80 1.00 2.10 - 3.36

Master toilet 1 1 2 2.76 1.00 3.25 17.94


Master toilet 1 1 2 2.00 1.00 3.25 13.00
D2-12 -1 1 1 0.80 1.00 2.10 - 1.68
Less:
tiled area -1 1 1 72.78 1.00 1.00 - 72.78
51.65

Prepare and apply 1.5mm thick layer of textured decorative


paint finishes to the plastered wall.
Verandah
Verandah 1 1 2 17.80 1.00 3.25 115.70
Verandah 1 1 2 1.45 1.00 3.25 9.42
openings -1 1 3 3.70 1.00 2.70 - 29.97

Add: Reveals and jambs


openings 1 1 3 9.10 0.30 1.00 8.19

103.35

BILL NO.2

ELEMENT NO. 9

EXTERNAL FINISHINGS

Roof drainage

Fulbora; 150mm diameter; stainless steel; complete with a clamp


ring and grating; including taking around the opening and making
good to distrubed concrete and finished surfaces; as per the
Architect's detail.
1 1 6 1.00 1.00 1.00 6.00
6.00

Piepwork measured elsewhere in plumbing installations


APP - Modified Bitumen
4mm thick APP modified bituminous water
proofing membrane reinforced with polyester with
50mm side and 75mm end laps, fully bonded and torch
applied in accordance with manufacturers
instructions; to

Flat roof terrace


Part 1; see planswift file 1 1 1 15.60 15.30 1.00 238.68
Part 2; see planswift file 1 1 1 6.00 2.40 1.00 14.40
Part 3; see planswift file 1 1 1 12.60 12.60 1.00 158.76
Part 4; see planswift file 1 1 1 12.60 6.50 1.00 81.90
Part 5; see planswift file 1 1 1 4.00 0.30 1.00 1.20

Deduct wall

Ditto parapet walls


Wall along E2 to lift shaft -1 1 2 #REF! 0.20 1.00 #REF!
#REF!

100mm high x 10mm thick skirting

1 1 1 149.00 1.00 1.00 149.00


149.00

Supply and Fix 600 x 600 x 10mm Thick approved Quarry floor tiles
in approved water adhesive, pointed with approved tri poly fortified
grout and admix grout to :

Floors
Part 1; see planswift file 1 1 1 15.60 15.30 1.00 238.68
Part 2; see planswift file 1 1 1 6.00 2.40 1.00 14.40
Part 3; see planswift file 1 1 1 12.60 12.60 1.00 158.76
Part 4; see planswift file 1 1 1 12.60 6.50 1.00 81.90
Part 5; see planswift file 1 1 1 4.00 0.30 1.00 1.20

Deduct wall

Ditto parapet walls


Wall along E2 to lift shaft -1 1 2 3.84 0.20 1.00 - 1.54
493.40

100mm high x 10mm thick skirting

1 1 1 149.00 1.00 1.00 149.00


149.00
20mm thick rendering in Cement and Sand (1:4) mortar; as
per Architect's details; on:

A Walls and concrete surfaces M2


648.65

Prepare and apply Plascon Architexture Grafiato coating in


accordance with manufacturer's instructions to:

648.65

Natural Stone coping; size 600mm wide x 20mm thick thick; all
edges well finished with a coved mould; including cement mortar
(1:4) backing all as per Architect's details

134.00

BILL NO.2

ELEMENT NO. 10

FITTINGS

A Alow a provisional sum of Ushs. or fittings 39,565,500.00


Kitchen fittings; L shaped 2650mm x 3000mm x 900mm deep x
900mm high complete with 3000mm long x 300mm wide x
1200mm high tea table. 1 1 1 8.65 1.00 950,000 8,217,500.00
Kitchen fittings; L shaped 2800mm x 2600mm x 900mm deep x
900mm high complete with 2600mm long x 300mm wide x
1200mm high tea table. 1 1 1 8.00 1.00 950,000 7,600,000.00

Pantry cupboard; size 3840mm long x 600mm wide x 3250mm high 1 1 1 3.84 1.00 1,200,000 4,608,000.00

Pantry cupboard; size 3600mm long x 600mm wide x 3250mm high 1 1 1 3.60 1.00 1,200,000 4,320,000.00

Wardrobe fitting; size 4000mm long x 600mm wide x 3250mm high 1 1 1 4.00 1.00 1,200,000 4,800,000.00

Wardrobe fitting; size 2000mm long x 600mm wide x 3250mm high 1 1 1 2.00 1.00 1,200,000 2,400,000.00

Wardrobe fitting; size 3600mm long x 600mm wide x 3250mm high 1 1 1 3.60 1.00 1,200,000 4,320,000.00

Wardrobe fitting; size 2750mm long x 600mm wide x 3250mm high 1 1 1 2.75 1.00 1,200,000 3,300,000.00
CLIENT: THE
CK &PROPOSED
COMPANY LTD
COMMERCIAL BUILDING TO BE BUILT ON PLOT NO. 2969, BLOCK NO. 206, DATE: 4/5/2024
PROJECT: MPERERWE, ALONG KAMPALA, GAYAZA ROAD, KAMPALA DISTRICT CALC BY: IB
MEASUREMENTS PURPOSE: ESTIMATES
NO. DESCRIPTION UNIT EQ. PRTS EQ. PRTS EQ. PRTS L W H/D/kg/m QTY

Boundary Wall; sloping and stepped as per Architect's details

Earthworks

A Excavate trench for strip foundation not exceeding 1.50M deep


from ground level. M3
Along slope 1 1 1 22.30 0.60 1.50 20.07
Along slope 1 1 1 31.90 0.60 1.50 28.71
Lower side 1 1 1 38.94 0.60 1.50 35.05
83.83

B Ditto pit for pier bases not exceeding 1.5M deep ditto M3
Along slope 1 1 9 0.80 0.80 1.50 8.64
Along slope 1 1 12 0.80 0.80 1.50 11.52
Lower side 1 1 17 0.80 0.80 1.50 16.32
36.48

D Remove surplus excavated materials from site M3


Excavate trench for strip foundation not exceeding 1.50M deep
from ground level. 1 1 1 83.83 1.00 1.00 83.83
Ditto pit for pier bases not exceeding 1.5M deep ditto 1 1 1 36.48 1.00 1.00 36.48
120.31

Plain Insitu concrete grade 15 in:-

F Strip foundation M3
Along slope 1 1 1 26.30 0.60 0.20 3.16
Along slope 1 1 1 31.90 0.60 0.20 3.83
Lower side 1 1 1 38.94 0.60 0.20 4.67
Along slope 1 1 9 0.80 0.80 0.20 1.15
Along slope 1 1 12 0.80 0.80 0.20 1.54
Lower side 1 1 17 0.80 0.80 0.20 2.18
16.52

Reinforced concrete grade 25 in:-


F Ground beams M3
Along slope 1 1 1 22.30 0.30 0.30 2.01
Along slope 1 1 1 31.90 0.30 0.30 2.87
Lower side 1 1 1 38.94 0.30 0.30 3.50

Along slope 1 1 9 0.40 0.40 0.30 0.43


Along slope 1 1 12 0.40 0.40 0.30 0.58
Lower side 1 1 17 0.40 0.40 0.30 0.82
10.21

High tensile steel bar reinforcement to BS 4449 as described;


including all bends, hooks, tying wire, distance blocks,
spacers and the like

Rebars up to 16mm diameter (provisional)


Ground beams 1 1 120 10.21 1.00 1.00 1,224.79
1,224.79

Sawn formwork to:-

J Sides of column bases M2


Along slope 1 1 9 0.80 0.80 0.20 1.15
Along slope 1 1 12 0.80 0.80 0.20 1.54
Lower side 1 1 17 0.80 0.80 0.20 2.18
4.86

F Vertical sides of the ground beams M3


Along slope 1 1 2 22.30 1.00 0.30 13.38
Along slope 1 1 2 31.90 1.00 0.30 19.14
Lower side 1 1 2 38.94 1.00 0.30 23.36

Along slope 1 1 9 1.20 1.00 0.30 3.24


Along slope 1 1 12 1.20 1.00 0.30 4.32
Lower side 1 1 17 1.20 1.00 0.30 6.12
69.56

Stone mansory wall as per the structural engineer's details

Natural stone rubble walling and dressings

500mm average thick walls; in approved natural stone; battered


both sides; bedded and jointed in cement mortar (1:4); including
flush pointing bothsides
Along slope 1 1 1 22.30 1.00 1.70 37.91
Along slope 1 1 1 31.90 1.00 1.70 54.23
Lower side 1 1 1 38.94 1.00 1.70 66.20
158.34

EXT/190 BILL NO.6 - EXTERNAL WORKS


Extra over stone mansory walling; for piers; size 800mm wide x
800mm thick; ditto
Along slope 1 1 9 1.00 1.00 1.70 15.30
Along slope 1 1 12 1.00 1.00 1.70 20.40
Lower side 1 1 17 1.00 1.00 1.70 28.90
64.60

Solid concrete blocks with minimum compressive strength


3.5N/mm2; bedded and jointed in cement mortar (1:4);
reinforced with 40mm wide x 1.6mm thick galvanised mild
steel straps built into every second course and laped 300mm
at joints and intersections and carried at least 115mm into
abutting walls in:
K 230mm thick M2
Along slope 1 1 1 29.50 1.00 2.40 70.80
Along slope 1 1 1 41.50 1.00 2.40 99.60
Lower side 1 1 1 52.54 1.00 2.40 126.10
296.50

L Attached Vertical piers; 460mm long x 225mm thick M


Along slope 1 1 9 1.00 1.00 2.40 21.60
Along slope 1 1 12 1.00 1.00 2.40 28.80
Lower side 1 1 17 1.00 1.00 2.40 40.80
91.20

Hessian based bitumenous damp proof course to


BS 743 type 5A bedded in cement/sand (1:4)
mortar on anti proof course with 150mm end laps
and full width at passings

A Under 230mm thick walls M


Along slope 1 1 1 29.50 1.00 1.00 29.50
Along slope 1 1 1 41.50 1.00 1.00 41.50
Lower side 1 1 1 52.54 1.00 1.00 52.54
123.54

Precast concrete grade 25, finished fair on all exposed


surfaces including bedding and jointing in cement sand (1:3)
mortar

B 280mm x 75 mm average thick twice weathered and throated


coping to wall top; 600mm long pre-cast concrete units. M
Along slope 1 1 1 29.50 1.00 1.00 29.50
Along slope 1 1 1 41.50 1.00 1.00 41.50
Lower side 1 1 1 52.54 1.00 1.00 52.54
123.54

C Pier cap; size 500 x 500mm with mouldings; 50 x 25mm


projections; weathered and throated; as per Architect's details No
Along slope 1 1 9 1.00 1.00 1.00 9.00
Along slope 1 1 12 1.00 1.00 1.00 12.00
Lower side 1 1 17 1.00 1.00 1.00 17.00
38.00

20mm thick rendering in Cement and Sand (1:4) mortar;


trowelled smooth on:

E Wall M2
Along slope 1 1 2 29.50 1.00 2.40 141.60
Along slope 1 1 2 41.50 1.00 2.40 199.20
Lower side 1 1 2 52.54 1.00 2.40 252.19
592.99

F Sides of attached pier M2


Along slope 1 2 9 0.20 1.00 2.40 8.64
Along slope 1 2 12 0.20 1.00 2.40 11.52
Lower side 1 2 17 0.20 1.00 2.40 16.32
36.48

E 50mm wide x 50mm thick moulding along edges of stone mansory


wall top M2
Along slope 1 1 2 29.50 1.00 1.00 59.00
Along slope 1 1 2 41.50 1.00 1.00 83.00
Lower side 1 1 2 52.54 1.00 1.00 105.08
247.08

Prepare and apply approved weatherguard textured emulsion


paint in accordance with manufacturer's instructions to:

G Rendered Surfaces M2
Rendered wall surfaces 1 1 1 592.99 1.00 1.00 592.99
Pier surfaces 1 1 1 36.48 1.00 1.00 36.48
Existing wall 1 1 1 74.30 1.00 2.40 178.32
807.79

Electric Security Fencing Systems

EXT/191 BILL NO.6 - EXTERNAL WORKS


Allow a prime cost sum of Uganda shillings Thirteen Miliion Only
for the electric fencing technology offers the most effective 24 hour
security surveillance by a nominated sub-contractor.
Existing boundary walls 1 1 1 74.30 1.00 1.00 74.30
Along slope 1 1 1 25.50 1.00 1.00 25.50
Along slope 1 1 1 41.50 1.00 1.00 41.50
Lower side 1 1 1 52.54 1.00 1.00 52.54
193.84

Allow for general attendances. %

Allow for the main contractor's overheads and profit. %

Roads, Parking and walkways

Excavations and Earthwork

C Excavation; to reduce levels M3


Exit ramp/drive way 1 1 1 303.98 1.02 0.50 155.03
Entrance ramp/drive in 1 1 1 424.09 1.02 0.50 216.29
Area in front of the building towards the road 1 1 1 514.42 1.00 0.50 257.21
Lower area; swampy 1 1 1 1034.23 1.00 0.50 517.12
Ramp and culvert area 1 1 1 196.02 1.02 0.50 99.97
1,245.61

Disposal

D Remove surplus excavated materials from site M3


Exit ramp/drive way 1 1 1 303.98 1.02 0.50 155.03
Entrance ramp/drive in 1 1 1 424.09 1.02 0.50 216.29
Area in front of the building towards the road 1 1 1 514.42 1.00 0.50 257.21
Lower area; swampy 1 1 1 1034.23 1.00 0.50 517.12
Ramp and culvert area 1 1 1 196.02 1.02 0.50 99.97
1,245.61

Compaction of surfaces

E Compaction of ground surfaces under paving, including scarifying


for a depth of 150mm, breaking down oversize material, adding
suitable material where necessary and compacting to 93% Mod
AASHTO density at OMC M2
Exit ramp/drive way 1 1 1 303.98 1.00 1.02 310.06
Entrance ramp/drive in 1 1 1 424.09 1.00 1.02 432.57
Area in front of the building towards the road 1 1 1 514.42 1.00 1.00 514.42
Lower area; swampy 1 1 1 1034.23 1.00 1.00 1,034.23
Ramp and culvert area 1 1 1 196.02 1.00 1.02 199.94
2,491.22

Filling under roads

Murram Filling oversite to make up levels

F Generally; depositing and compacting in layers maximum 150 mm


thick; grading to slopes, falls and cross falls M3
Exit ramp/drive way 1 1 1 303.98 1.02 0.30 93.02
Entrance ramp/drive in 1 1 1 424.09 1.02 0.30 129.77
Area in front of the building towards the road 1 1 1 514.42 1.00 0.30 154.33
Lower area; swampy 1 1 1 1034.23 1.00 0.30 310.27
Ramp and culvert area 1 1 1 196.02 1.02 0.30 59.98
747.37

Aggregate Filling in making up levels

G Generally; depositing and compacting in layers maximum 150 mm


thick; grading to slopes, falls and cross falls M3
Exit ramp/drive way 1 1 1 303.98 1.02 0.30 93.02
Entrance ramp/drive in 1 1 1 424.09 1.02 0.30 129.77
Area in front of the building towards the road 1 1 1 514.42 1.00 0.30 154.33
Lower area; swampy 1 1 1 1034.23 1.00 0.30 310.27
Ramp and culvert area 1 1 1 196.02 1.02 0.30 59.98
747.37

Hardcore Filling

Hardcore comprising hard clean stone, laterite or broken


concrete to pass a 75mm ring, deposited in layers and
consolidated by ramming

Depositing and compacting in layers maximum 150 mm thick;


levelling; 200mm average thickness; blinding with 50mm thick sand
to receive polythene sheet (measured separately)
Exit ramp/drive way 1 1 1 303.98 1.00 1.02 310.06
Entrance ramp/drive in 1 1 1 424.09 1.00 1.02 432.57
Area in front of the building towards the road 1 1 1 514.42 1.00 1.00 514.42
Lower area; swampy 1 1 1 1034.23 1.00 1.00 1,034.23
Ramp and culvert area 1 1 1 196.02 1.00 1.02 199.94
2,491.22

Concrete paving blocks; 50 N/sq mm; to approved pattern; on


and including 50 mm thick sand bed; compacting with
approved vibrator; filling joints with sand
EXT/192 BILL NO.6 - EXTERNAL WORKS
H 80 mm thick; to blinded base; generally to roads; laid to falls,
crossfalls or sloping M2
Exit ramp/drive way 1 1 1 303.98 1.00 1.02 310.06
Entrance ramp/drive in 1 1 1 424.09 1.00 1.02 432.57
Area in front of the building towards the road 1 1 1 514.42 1.00 1.00 514.42
Lower area; swampy 1 1 1 1034.23 1.00 1.00 1,034.23
Ramp and culvert area 1 1 1 196.02 1.00 1.02 199.94
2,491.22

Precast concrete grade 25 kerbs ; vibrated; Size 150 x 250mm


high; splayed one face; part fair finish all exposed surfaces;
bedded, jointed and pointed in cement mortar (1:3); laid on
and including plain insitu concrete grade 15 bedding size
325mm wide x 100mm deep and 100mm wide haunching both
sides; including all necessary formwork, excavations and
earthworks; all to Engineer's details

K Straight on plan M
All 1 1 1 201.00 1.00 1.00 201.00
201.00

L Curved ditto M
All 1 1 4 2.00 1.00 1.00 8.00
8.00

Allow for creating joint between main street road and the access
road; ramps and parking areas using granite setts bedded on
concrete grade 25; average with 300mm.
All 1 1 1 59.80 1.00 1.00 59.80
59.80

Prepare and apply three coats of road marking paint on:

A Kerbs 200 - 300mm girth M


All 1 1 1 203.00 1.00 1.00 203.00
203.00

Road marking; not exceeding 100mm girth.

Parking lines 1 1 13 5.50 1.00 1.00 71.50


Demarcated slots 1 1 1 168.40 1.00 1.00 168.40
239.90

External signage

Providing and fixing internal and external signages in Acrylic/stove


enamel painted MS approved quality and make mounted on
floor/walls/doors/ceiling at various and/or any other locations
including all accessories, scaffolding, all builder's work, drilling,
making holes in wooden,rendered masonry/concrete, making good
the damages as per drawing as spcified as directed by Engineer.
Providing & Fixing of Sign including all operations from Fabrication
to Installation all Complete as per Drawings, Artwork and Detailed
Technical Specifications to the Complete Satisfaction of the
Authorized Personnal Incharge
Above description generally holds good for all the units of signage
mentioned in this item unless otherwise specified except due
modification with special mention
Providing & Fixing of all Fixing Details & Accessories such as
screws, reverse screws, nut, bolts, washers, rivets, tapes, anchors
etc. as per drawing or as required for joinery
The Contractor shall prepare & take approval on Shop Drawings
before Production

LOGO IDENTIFICATION SIGNAGES


Logo ID. Sign – A

Sign – 10mm thick Acrylic base to be used with digital printed print
to be pasted
Content - Artwork to be digitally printed print.
Size : 1600 MM x 600 MM.
Location : Reception Area
Sided – Single sided
Fixing – Stud Fixing
1
240000
Logo LG01B

Sign – 2mm thick Aluminum Channel Letters.


LED Lights Glow letters.
Content - as per artwork.
Size : 1200 MM height letters
Location : Facade
Sided – Single sided
Fixing – MS Structure Fixing
2
240,000
Area ID. - 4D

EXT/193 BILL NO.6 - EXTERNAL WORKS


Sign – 3MM butler finish ACP is clad ed over Aluminum Section
Frame. The Edges are well finished. 1.5"x 1.5" Aluminum Section
Frame.
Content - Logo & Artwork to be in Plotter cut High Grade Vinyl .
Vinyl to match approved pan-tone (Blue 2935C) and Black color.
Size – 750 MM x 200 MM
Location – At Entrance of Given Area
Sided – Single sided
Fixing - Fixing of Sign with Key hole fixing details 2
240,000
Area ID. - 4C

Sign - Base is 5mm thick Acrylic plate PU Coated with Silver Pan-
tone PU color
Content - Logo & Artwork to be in Plotter cut High Grade Vinyl .
Vinyl to match approved pan-tone (Blue 2935C) and Black color
Bubble free Glossy Lacquer Coating to be done after Vinyl Pasting
Size – 250 MM x 150 MM
Location – Entrance of given Area
Sided – Single sided
Fixing - Fixing of Sign with Reverse Screws 2
284000
DIRECTIONAL SIGNAGES
External Directional – 1A

Sign - 4MM Silver finish ACP is claded over MS Frame. The Edges
are well finished. 2"x 2" MS Square Pipes welded as frame along
with 2” X 2” aluminum frame. Entire MS structure shall be hot
dipped galvanized after complete fabrication and installed at
location before ACP Cladding.
Content – Artwork to be in Ploter cut High Grade Reflective Vinyl .
Vinyl to match approved pantone colour .
Size : 500 MM X 1800 MM
Location : external Site Area / Parking area
Sided – Single sided
Fixing - Fixing of Sign with Concrete fixing details as details
provided 2
684000
FIRE SIGNAGES
Assembly point Sign

Sign – Green ACP is clad ed over 1.5” x 1.5” MS Section Frame.


Entire MS structure shall be hot dipped galvanized after complete
fabrication and installed at location before ACP Cladding..
Content - Logo & Artwork to be in Plotter cut Photoluminiscent
pasted on the base
Size – 480 MM x 125 MM
Location – at given external Assembly Points
Sided – Double sided
Fixing – Ground fixing with concrete as per details provided in
manual 1
220,000
Culvert crossings at access points

Excavate to enlarge and shape drain trench as as per the attached


drawings; over 1000mm but not exceeding 150mm deep including
backfilling and disposal of excavated materials from site. Levelling
and compacting bottoms is deemed included.
Triangular areas added to achieve the desired shape. 1 1 2 12.00 0.31 1.20 8.93
Diposal of excavated material 1 1 2 12.00 0.31 1.20 8.93
17.86

Plain insitu concrete grade 15 culvert base.


1 1 2 12.00 1.02 0.30 7.34
7.34

Culverts; nominal diameter 600mm; heavy duty precast concrete


culvert; bedded and jointed in cement and sand (1:3);
1 1 2 12.00 1.00 1.00 24.00
24.00

Reinforced insitu concrete grade 25 encasing the culvert (sides and


tops)
1 2 1 12.00 1.02 0.86 21.05
-1 2 3.14 12.00 0.30 0.30 (6.78)
14.27

200mm thick thick plain insitu concrete grade 25 topping to culvert.

1 1 2 12.00 1.32 1.00 31.68


31.68

300mm thick reinforced in-situ concrete head walls.


1 2 2 1.32 1.00 0.30 1.58
1.58

Fomwork to sides of concrete head walls


1 2 2 1.32 1.00 0.30 1.58
1 2 4 0.30 1.00 0.30 0.72
2.30

Soft landscaping
EXT/194 BILL NO.6 - EXTERNAL WORKS
Grass

B Take delivery, spread and level 150mm thick approved vegetable


soil where directed to a fine tilth; plant approved grass seedlings at
150mm centers in both directions and keep well watered and
maintained until well established M2
1 1 1 444.70 1.00 1.00 444.70
444.70

Trees

C
Planting; trees and shrubs as per Architect's landscape drawing
where directed; keep well watered and maintained until well
established No
1 1 21 1.00 1.00 1.00 21.00
21.00

Pallisade fence as per the Architect's details;

Earthworks

Excavate trench for strip foundation not exceeding 1.50M deep


from ground level.

Wall for the fence 1 1 2 2.70 0.60 0.90 2.92


2.92

Ditto pit to receive piers ditto

Hollow piers 1 1 4 1.30 1.30 1.00 6.76


6.76

Return, fill in and ram well selected material around


foundations. 5.72

Remove surplus excavated materials from site.

Blinding 1 1 1 6.76 0.05 1.00 0.34


strip 1 1 1 0.65 1.00 1.00 0.65
Walls 1 1 2 2.50 0.20 0.70 0.70
1 1 4 0.90 0.90 0.70 2.27
3.95

Plain Insitu concrete grade 15 in:-

50mm thick blinding.


Hollow piers 1 1 4 1.30 1.30 1.00 6.76
6.76

Plain Insitu concrete grade 20 in:-

Strip foundations
Wall for the fence 1 1 2 2.70 0.60 0.20 0.65
0.65

Reinforced Insitu concrete grade 25 in:-

Pier bases
Hollow piers 1 1 4 1.30 1.30 0.20 1.35
1.35

High tensile steel bar reinforcement to BS 4449 as described;


including all bends, hooks, tying wire, distance blocks,
spacers and the like

Rebars up to 16mm diameter (provisional)


Hollow piers 1 120 4 1.30 1.30 0.20 162.24
162.24

Sawn formwork to:-

Sides of foundations
Hollow piers 1 4 4 1.30 1.00 0.20 4.16
4.16

Solid concrete blocks with minimum compressive strength


3.5N/mm2; bedded and jointed in cement mortar (1:4);
reinforced with 40mm wide x 1.6mm thick galvanised mild
steel straps built into every second course and laped 300mm
at joints and intersections and carried at least 115mm into
abutting walls in:

200mm thick walls


Walls 1 1 2 2.50 1.00 1.63 8.15
Hollow piers 1 1 4 2.80 1.00 3.63 40.66
48.81

Hessian based bitumenous damp proof course to


BS 743 type 5A bedded in cement/sand (1:4)
EXT/195 BILL NO.6 - EXTERNAL WORKS
mortar on anti proof course with 150mm end laps
and full width at passings

Under 200mm thick walls


Walls 1 1 2 2.50 1.00 1.00 5.00
Hollow piers 1 1 4 2.80 1.00 1.00 11.20
16.20

Pre-Cast Concrete grade 25; vibrated; part surface fair finish


coping as per Architect's details

F Size 175 mm thick average x 300 mm deep average; weathered on


top; throated; reinforced as necessary for handling; bedding,
jointing and pointing in cement mortar (1:4); as per the Architect's
details M
Walls 1 1 2 2.50 1.00 1.00 5.00
5.00

Horizontal Pier cap mouldings; size 1300 x 1300mm x 100mm


projections; weathered and throated; as per Architect's details.
Hollow piers 1 1 4 1.00 1.00 1.00 4.00
4.00

20mm thick rendering in Cement and Sand (1:4) mortar;


trowelled smooth on:

Block walls and piers


Walls 1 2 2 2.50 1.00 1.63 16.30
Hollow piers 1 2 4 2.80 1.00 3.63 81.31
97.61

Mild steel grilles to Architect's details

1800mm high overall; comprising 20 x 20 x 4mm thick SHS vertical


infills spaced 200mm centres spiked at top; welded onto 2 No. 50 x
50 x 4mm SHS horizontal framing (top and bottom); 80x80x4mm
SHS vertical posts cast in concrete coping to the planter walls
(measured seperately); complete with one coat of red oxide primer,
fixing lugs and plugged to wall.
Along the road below the pallisade fence
2 Legs 1 1 1 27.67 1.00 1.00 27.67
27.67

Prepare and apply approved weatherguard emulsion paint in


accordance with manufacturer's instructions to:

Rendered Surfaces.
Walls 1 2 2 2.50 1.00 1.63 16.30
Hollow piers 1 1 4 2.80 1.00 3.63 40.66
Coping 1 1 2 2.50 1.00 0.93 4.65
Top 1 1 4 1.30 1.30 1.00 6.76
Bottom 1 1 4 1.30 1.30 1.00 6.76
Less: void -1 1 4 0.90 0.90 1.00 (3.24)
Edges 1 4 4 1.30 1.00 0.10 2.08
73.97

Prepare and apply one undercoat and two finishing coats of


gloss oil paint in accordance with manufacturer's instructions
to:

Grilled metal surfaces (measured flat both sides)


Along the road below the pallisade fence
2 Legs 1 1 2 27.67 1.00 2.00 110.68
Gates
Entrance 1 1 2 7.50 1.00 2.40 36.00
Exit gate 1 1 2 8.23 1.00 2.40 39.50
186.18

Gates

Mild steel gate to Architect's details

Sliding folding gate; comprising; comprising 20 x 20 x 4mm thick


SHS vertical infills spaced 200mm centres spiked at top; welded
onto 2 No. 50 x 50 x 4mm SHS horizontal framing (top and
bottom); 80x80x4mm SHS vertical posts cast in concrete coping to
the planter walls (measured seperately), counter weight; complete
with one coat of red oxide primer, fixing lugs and plugged to wall.

Size: 7500mm wide x 2400mm high


Entrance 1 1 1 1.00 1.00 1.00 1.00
1.00

Size: 8230mm wide x 2400mm high


Exit gate 1 1 1 1.00 1.00 1.00 1.00
1.00

Traffic barrier

BOOM BARRIERS
EXT/196 BILL NO.6 - EXTERNAL WORKS
Excavate pit for boom barrier stand foundations.
1 1 4 1.00 1.00 1.00 4.00
4.00

Remove excavated from site.


1 1 4 1.00 1.00 1.00 4.00
4.00

Reinforced Insitu concrete grade 25 in:-

Foundation for the boom barrier stands.


1 1 4 1.00 1.00 1.00 4.00
4.00

A Re-bar Kg
Foundation for the boom barrier stands. 1 1 150 4.00 1.00 1.00 600.00
600.00

Boom barrier

Allow a prime cost sum of uganda shillings Fifty Million only for
supply and installation of 2 No. HIGH-VOLUME INDUSTRIAL
TRAFFIC BARRIERS; SECTOR 6 – Standard speed high-volume
barrier, 6m boom pole complete with a control box with 6m boom
barrier, backup battery and 2 remotes; to be supplied and installed
by Sekanyolya Systems, P.O BOX 3388, Kampala, Cell; +256 706
130 867 as per specifications attached. 50,000,000.00
Boom barriers should comprise the following features:

Battery backup
High volume capability
Rapid boom pole raises (3m version < 1.2sec)
Smooth intelligent speed control
High torque boom pole operation
Robust, durable and slim-line operator casing
LCD user interface for simple set up
Onboard NOVA rolling code (KeeloqTM encryption) multichannel
receiver with selective delete
Integral Chrono Guard (patent pending) timer functionality

Allow for contractors overheads and profit. 25%

Allow for any general and specific attendances. 10%

The following in Planters

Excavations and Earthworks

A Excavate trench for strip foundation not exceeding 1.50M deep


starting from stripped level M3
Planter close to the ramp
Leg 01 1 1 2 17.91 0.45 0.60 9.67
Leg 02 1 1 1 2.80 0.45 0.60 0.76
Leg 03 1 1 1 1.98 0.45 0.60 0.53
Leg 04 1 1 1 16.50 0.45 0.60 4.46
Leg 05 1 1 1 0.60 0.45 0.60 0.16
Drive in side
Sloping planter behind the retaining walls
Leg 01 1 1 1 35.00 0.45 0.60 9.45
Partitions 1 1 3 0.60 0.45 0.60 0.49
Drive out side
Leg 01 1 1 1 25.50 0.45 0.60 6.89

Along the road below the pallisade fence


2 Legs 1 1 2 22.67 0.60 0.90 24.48

56.88

B Return, fill in and ram well selected material around


foundations M3
Excavations 1 1 1 56.88 1.00 1.00 56.88
Deduct the structures
Strip foundations -1 1 1 11.82 1.00 1.00 (11.82)
Planter close to the ramp
Leg 01 -1 1 2 17.91 0.15 0.45 (2.42)
Leg 02 -1 1 1 2.80 0.15 0.45 (0.19)
Leg 03 -1 1 1 1.98 0.15 0.45 (0.13)
Leg 04 -1 1 1 16.50 0.15 0.45 (1.11)
Leg 05 -1 1 1 0.60 0.15 0.45 (0.04)
41.17

C Remove surplus excavated materials from site M3


Strip foundations 1 1 1 11.82 1.00 1.00 11.82
Planter close to the ramp
Leg 01 1 1 2 17.91 0.15 0.45 2.42
Leg 02 1 1 1 2.80 0.15 0.45 0.19
Leg 03 1 1 1 1.98 0.15 0.45 0.13
Leg 04 1 1 1 16.50 0.15 0.45 1.11
Leg 05 1 1 1 0.60 0.15 0.45 0.04
15.71

EXT/197 BILL NO.6 - EXTERNAL WORKS


Plain Insitu concrete grade 20 in:-

D Strip foundation M3
Planter close to the ramp
Leg 01 1 1 2 17.91 0.45 0.15 2.42
Leg 02 1 1 1 2.80 0.45 0.15 0.19
Leg 03 1 1 1 1.98 0.45 0.15 0.13
Leg 04 1 1 1 16.50 0.45 0.15 1.11
Leg 05 1 1 1 0.60 0.45 0.15 0.04

Sloping planter behind the retaining walls


Leg 01 1 1 1 35.00 0.45 0.15 2.36
Partitions 1 1 3 0.60 0.45 0.15 0.12

Along the road below the pallisade fence


2 Legs 1 1 2 22.67 0.60 0.20 5.44

11.82

Solid concrete blocks with minimum compressive strength


3.5N/mm2; bedded and jointed in cement mortar (1:4);
reinforced with 40mm wide x 1.6mm thick galvanised mild
steel straps built into every second course and laped 300mm
at joints and intersections and carried at least 115mm into
abutting walls in:

E 150mm thick wall M2


Planter close to the ramp
Leg 01 1 1 2 17.91 1.00 1.35 48.36
Leg 02 1 1 1 2.80 1.00 1.35 3.78
Leg 03 1 1 1 1.98 1.00 1.05 2.08
Leg 04 1 1 1 16.50 1.00 1.05 17.32
Leg 05 1 1 1 0.60 1.00 1.35 0.81

Sloping planter behind the retaining walls


Leg 01 1 1 1 35.00 1.00 1.05 36.75
Partitions 1 1 3 0.60 1.00 1.05 1.89

Along the road below the pallisade fence


2 Legs 1 1 2 22.67 1.00 1.60 72.54

183.54

Pre-Cast Concrete grade 25; vibrated; part surface fair finish


coping as per Architect's details

F Size 175 mm thick average x 300 mm deep average; weathered on


top; throated; reinforced as necessary for handling; bedding,
jointing and pointing in cement mortar (1:4); as per the Architect's
details M
Planter close to the ramp
Leg 01 1 1 2 17.91 1.00 1.00 35.82
Leg 02 1 1 1 2.80 1.00 1.00 2.80
Leg 03 1 1 1 1.98 1.00 1.00 1.98
Leg 04 1 1 1 16.50 1.00 1.00 16.50
Leg 05 1 1 1 0.60 1.00 1.00 0.60

Sloping planter behind the retaining walls


Leg 01 1 1 1 35.00 1.00 1.00 35.00
Partitions 1 1 3 0.60 1.00 1.00 1.80

Along the road below the pallisade fence


2 Legs 1 1 2 22.67 1.00 1.00 45.34

139.84

15mm thick rendering in Cement and Sand (1:4) mortar;


trowelled smooth on:

G Walls and concrete surfaces M2


Planter close to the ramp
Leg 01 1 2 2 17.91 1.00 1.35 96.71
Leg 02 1 2 1 2.80 1.00 1.35 7.56
Leg 03 1 2 1 1.98 1.00 1.05 4.16
Leg 04 1 2 1 16.50 1.00 1.05 34.65
Leg 05 1 2 1 0.60 1.00 1.35 1.62
Coping
Leg 01 1 1 2 17.91 1.00 0.90 32.24
Leg 02 1 1 1 2.80 1.00 0.90 2.52
Leg 03 1 1 1 1.98 1.00 0.90 1.78
Leg 04 1 1 1 16.50 1.00 0.90 14.85
Leg 05 1 1 1 0.60 1.00 0.90 0.54

Sloping planter behind the retaining walls


Leg 01 1 1 1 35.00 1.00 1.05 36.75
Partitions 1 1 3 0.60 1.00 1.05 1.89

Coping
Leg 01 1 1 1 35.00 1.00 0.90 31.50
Partitions 1 1 3 0.60 1.00 0.90 1.62

EXT/198 BILL NO.6 - EXTERNAL WORKS


Along the road below the pallisade fence
2 Legs 1 2 2 22.67 1.00 1.60 145.09

413.48

Soft landscaping

All soft landscaping is deemed to include: all excavations and


filling, disposal of any excavated materials, removal of stones and
rubbish, watering, labelling and maintenance untill the end of the
defects liability period.

Top soil filling

H 600mm thick approved imported top soil fill to planters. M3


Planters 1 1 1 17.50 0.60 0.60 6.30
Planters 1 1 1 2.20 1.40 0.60 1.85

Sloping planter behind the retaining walls


Leg 01 1 1 1 35.00 0.60 0.60 12.60
Partitions 1 1 3 0.60 0.60 0.60 0.65

Along the road below the pallisade fence


2 Legs 1 1 1 22.67 0.80 0.60 10.88
32.28

Drainage gravel bed filling

H 20mm thick angular crushed clear stone ASTM number 57 to


planters. M3
Planters 1 1 1 17.50 0.30 0.60 3.15
Planters 1 1 1 2.20 0.30 0.60 0.40
Planters 1 1 1 17.50 0.30 0.60 3.15
Planters 1 1 1 2.20 0.30 0.60 0.40

Sloping planter behind the retaining walls


Leg 01 1 1 1 35.00 0.60 0.60 12.60
Partitions 1 1 3 0.60 0.60 0.60 0.65

Along the road below the pallisade fence


2 Legs 1 1 1 22.67 0.80 0.60 10.88
31.22

River Washed Gravel-¾ Inch & 2 Inch mulch filling to:

H In planters M3
Planters 1 1 1 17.50 0.60 1.00 10.50
Planters 1 1 1 2.20 1.40 1.00 3.08

Sloping planter behind the retaining walls


Leg 01 1 1 1 35.00 0.60 1.00 21.00
Partitions 1 1 3 0.60 0.60 1.00 1.08

Along the road below the pallisade fence


2 Legs 1 1 1 22.67 0.80 1.00 18.14

53.80

Permeable membrane

In planters M2
Planters 1 1 1 17.50 0.60 1.00 10.50
Planters 1 1 1 2.20 1.40 1.00 3.08
Planter close to the ramp
Leg 01 1 1 2 17.91 1.00 1.35 48.36
Leg 02 1 1 1 2.80 1.00 1.35 3.78
Leg 03 1 1 1 1.98 1.00 1.05 2.08
Leg 04 1 1 1 16.50 1.00 1.05 17.32
Leg 05 1 1 1 0.60 1.00 1.35 0.81

Sloping planter behind the retaining walls


Leg 01 1 1 1 35.00 0.60 1.00 21.00
Partitions 1 1 3 0.60 0.60 1.00 1.08

Leg 01 1 2 1 35.00 0.60 1.05 44.10


Partitions 1 2 3 0.60 0.60 1.05 2.27

Along the road below the pallisade fence


2 Legs 1 1 1 22.67 0.80 1.00 18.14
2 Legs 1 1 2 22.67 1.60 1.00 72.54

245.06

Grass planting and seeding

Planting

H Tropical shurbs as specified by the Architect. No.


Planters 1 1 30 1.00 1.00 1.00 30.00
Sloping planter behind the retaining walls
EXT/199 BILL NO.6 - EXTERNAL WORKS
Leg 01 1 1 60 1.00 1.00 1.00 60.00

Along the road below the pallisade fence


2 Legs 1 1 24 1.00 1.00 1.00 24.00

114.00

H Plants; Albizia coriaria No.


Planters 1 1 8 1.00 1.00 1.00 8.00
8.00

50mm diameter PVC heavy gauge perforated pipes (6mm thick)


PN10 complete with bends, exit points; and all accessories at the
foot of planter structures
Planters 1 1 1 17.50 1.00 1.00 17.50
Planters 1 1 1 2.20 1.00 1.00 2.20
Planters 1 1 1 5.00 1.00 1.00 5.00
Sloping planter behind the retaining walls
Leg 01 1 1 1 40.00 1.00 1.00 40.00
Along the road below the pallisade fence
2 Legs 1 1 1 30.00 1.00 1.00 30.00
94.70

Facing bricks to planter at the ramp areas

Smooth selected facing clay bricks; size 230mm long x 115mm


wide x 75mm high; bedded on 20mm thick cement mortar backing
(1:4); including recessed pointing and polishing.
Planter close to the ramp
Leg 01 1 2 2 17.91 1.00 1.35 96.71
Leg 02 1 2 1 2.80 1.00 1.35 7.56
Leg 03 1 2 1 1.98 1.00 1.05 4.16
Leg 04 1 2 1 16.50 1.00 1.05 34.65
Leg 05 1 2 1 0.60 1.00 1.35 1.62
144.70

Concrete ramps

Excavations and Earthworks

A Excavate trench for ground beams not exceeding 1.50M deep


starting from stripped level M3
Ground beams 1 1 1 1.45 0.20 0.30 0.09
0.09

C Remove surplus excavated materials from site M3


Ground beams 1 1 1 1.45 0.20 0.30 0.09
0.09

Earth filling

Imported selected murram filling on formation deposited in 150mm


thick layers and compacted with a 5-tonne roller to 98% MDD to
receive hardcore filling as described (measured separately). M3
Ramp slabs 1 1 1 9.16 1.40 0.65 8.34
Landing 1 1 1 7.20 1.45 1.25 13.05
Landing 1 1 1 1.60 0.55 1.25 1.10
22.49

Hardcore Filling

Hardcore comprising hard clean stone, laterite or broken


concrete to pass a 75mm ring, deposited in layers and
consolidated by ramming

generally; depositing and compacting in layers maximum 200 mm


thick; levelling; blinding with 50mm thick sand to receive polythene
sheet (measured separately) M2
Ramp slabs 1 1 1 9.16 1.40 1.00 12.82
Landing 1 1 1 7.20 1.45 1.00 10.44
Landing 1 1 1 1.60 0.55 1.00 0.88
23.26

Reinforced Insitu concrete grade 30 in:-

D Ground beams M3
Ground beams 1 1 1 1.45 0.20 0.30 0.09
0.09

D 200mm thick slab sloping not exceeding 15 degrees M3


Ramp slabs 1 1 1 9.16 1.40 1.00 12.82
12.82

D 200mm thick ramp landing slab; horizontal M3


Landing 1 1 1 7.20 1.45 1.00 10.44
Landing 1 1 1 1.60 0.55 1.00 0.88
11.32

Reinforcement
EXT/200 BILL NO.6 - EXTERNAL WORKS
High tensile steel bar reinforcement to BS 4449 as described;
including all bends, hooks, tying wire, distance blocks,
spacers and the like
Assorted bars up to H32 Kg
Ground beams 1 1 120 1.45 0.20 0.30 10.44
200mm thick slab sloping not exceeding 15 degrees 1 1 120 12.82 0.20 1.00 307.78
200mm thick ramp landing slab; horizontal 1 1 120 11.32 0.20 1.00 271.68
589.90

Sawn formwork as described to:-


M2
Sides of column bases
Ground beams 1 1 1 1.85 1.00 0.30 0.55
0.55

Edge of slab 200mm high M


Ramp 1 1 1 1.45 1.00 1.00 1.45
1.45

Floor screed; Cement and sand (1:4); wood floated finish to


receive floor tiles m/s:

A Floors M2
Ramp slabs 1 1 1 9.16 1.40 1.00 12.82
Landing 1 1 1 7.20 1.45 1.00 10.44
Landing 1 1 1 1.60 0.55 1.00 0.88
24.14

Supply and fix approved 18 mm thick grooved black granite;


non-slip; laid in an approved pattern; bedded in approved
adhesive cement and pointed with an approved tile grout

Floors

Ramp slabs 1 1 1 9.16 1.40 1.00 12.82


Landing 1 1 1 7.20 1.45 1.00 10.44
Landing 1 1 1 1.60 0.55 1.00 0.88
24.14

20mm thick 100mm high skirting with rounded top edge and
slight cove at bottom
Ramp slabs 1 1 1 16.00 1.00 1.00 16.00
Landing 1 1 1 2.00 1.00 1.00 2.00
Landing 1 1 1 1.60 1.00 1.00 1.60
Landing 1 1 1 0.55 1.00 1.00 0.55
Landing 1 1 1 14.50 1.00 1.00 14.50
34.65

STORM WATER MANAGEMENT

Open drain

Form concrete water channel in in-situ concrete grade 25 with a


slope of 1:100; 300mm wide x 250mm average deep internal
dimensions; 100mm thick walls and bases reinforced with 1- layer
BRC mesh A142 including forming rebates, excavation, formwork,
finishing fair with cement sand screed 1.3 and a grated cover
comprising of 50x50x6mm HRA cast into concrete with lugs,
50x6mm vertical falts welded on framing in 50x6mm flats including
formed rebates, earthworks and formwork to Architect's details. M
1 1 1 118.20 1.00 1.00 118.20
118.20

Off shot drain

100mm diameter PVC heavy gauge (6mm thick) PN10 complete


with bends, exit points; and all accessories including all associated
excavations and filling.
1 1 2 6.00 1.00 1.00 12.00
12.00

To collection

EXT/201 BILL NO.6 - EXTERNAL WORKS


Item Description Unit Length Width Height ABSTRACT

BILL NO. 3

ELEMENT NO. 1

SUBSTRUCTURE
(All Provisional)

Excavations and Earthworks

D Ditto trench for strip foundation not exceeding 1.50M deep


starting from stripped level M3
External wall 1 1 1 1 1 14.00 0.60 1.50 12.60
Internal strip 1 1 1 1 1 3.81 0.60 1.50 3.43
16.03
Rock
F Extra over excavation for breaking up rock M3 1 1 1 1 0 16.03 1.00 1.00 1.60
-
G Return, fill in and ram well selected material around
foundations
Excavations: Trenches
Strip foundatons M3 1 1 1 1 1 16.03 1.00 1.00 16.03
Less: structures within the excavatons = RFS (1) 1 1 1 1 6.94 1.00 1.00 (6.94)
9.09
-
H Remove surplus excavated materials from site M3 -

Strip foundatons M3 1 1 1 1 1 2.13 1.00 1.00 2.13


Plinth walls/considering total length 1 1 1 1 1 18.50 0.20 1.30 4.81
6.94

Planking and Strutting 1

J Allow for provision and subsequent removal of planking and


strutting to uphold and maintain the faces and excavations Item Item

Disposal of Water

K Allow for keeping the whole of the excavations free from water
and silt and mud by pumping, bailing or otherwise Item Item

Anti-Termite Treatment

L Provide and apply an approved toxic chemical solution; applied


at the manufacturer's recommended concentration and rate; to
hardcore beds and tops of foundation walls M2

Bottoms 1 1 1 1 1 3.80 4.80 1.00 18.24


Ext. trenches 1 1 1 1 2 14.00 1.00 1.50 42.00
Int trenches 1 1 1 1 2 3.81 1.00 1.50 11.43
Top of the trenches after backfilling
Ext. trenches 1 1 1 1 1 14.00 0.60 1.00 8.40
Int trenches 1 1 1 1 1 3.81 0.60 1.00 2.29
Deduct; walls along the trenches
Ext. trenches (1) 1 1 1 1 14.00 0.20 1.00 (2.80)
Int trenches (1) 1 1 1 1 3.81 0.20 1.00 (0.76)
78.79

Murram Filling

M Imported selected murram filling; 150mm average compacted


thickness; on formation deposited in 150mm thick layers and
compacted with a 5-tonne roller to receive hardcore filling
(measured separately) M2 1 1 1 1 1 9.60 1.00 1.00 9.60
Hardcore Filling

Hardcore comprising hard clean stone, laterite or broken


concrete to pass a 75mm ring, deposited in layers and
consolidated by ramming

A 200mm thick filling compacted with a 5-tonne roller and blinded


with 50mm thick sand to receive polythene sheet (measured
separately) M2 1 1 1 1 1 9.60 1.00 1.00 9.60
-
The prices for the following concrete are to include for
filling into formwork, well vibrating and packing around
rod reinforcement (formwork and reinforcement measured
separately) -
-
Plain Insitu concrete grade 15 in:- -
-
Strip foundation M3 -
External wall 1 1 1 1 1 13.90 0.60 0.20 1.67
Internal strip 1 1 1 1 1 3.81 0.60 0.20 0.46
2.13

G 200mm thick floor slab, mechanically floated M2 1 1 1 1 1 3.20 4.20 1.00 13.44

L Reference A142; mesh size 200mm x 200mm; weighing


2.22kg/sq.m with minimum 300mm end and side laps M2 1 1 1 1 1 13.44 1.00 1.00 13.44
-
-
Q Edge of slab 125mm high M 1 1 1 1 2 7.40 1.00 1.00 14.80

BILL NO.3: PROPOSED STAFF HOUSE


Item Description Unit Length Width Height ABSTRACT

Solid burnt clay brick work; bedded and jointed in cement


mortar (1:4); reinforced with approved 40mm wide x 1.6mm
thick galvanised mild steel straps built into every second
course and laped 300mm at joints and intersections and
carried at least 115mm into abutting walls in:

A 200mm thick Wall plinth wall -


External plinth brick wrk M2 1 1 1 1 1 14.00 1.00 1.60 22.40
Internal strip 1 1 1 1 1 4.50 1.00 1.60 7.20
29.60

Damp Proof Membrane -


-
B 1000 Gauge polythene oversite damp proof membrane; laid M 2
1 1 1 1 1 13.44 1.00 1.00 13.44

Damp proof courses; under


Under; 200mm thick walls 1 1 1 1 1 13.50 1.00 1.00 13.50
Deduct; opening (1) 1 1 1 1 0.90 1.00 1.60 (1.44)
12.06

Under; 150mm thick walls


Walls 1 1 1 1 1 4.50 1.00 1.00 4.50
Deduct; opening; Dg-18 (1) 1 1 1 1 0.90 1.00 1.60 (1.44)
Deduct; opening; Dg-12 (1) 1 1 1 1 0.80 1.00 1.60 (1.28)
1.78

20mm thick; two coat rendering in Cement and Sand (1:4)


mortar; trowelled smooth on: -
-
C Plinth wall (external surfaces)
Perimeter of the building/externally M2 1 1 1 1 1 14.80 1.00 1.80 26.64

Prepare and apply one primer coat and two coats of


approved bituminous paint to: -
-
D Rendered plinth wall M2 1 1 1 1 1 14.80 1.00 1.80 26.64

BILL NO. 3

ELEMENT NO. 2

SUPERSTRUCTURE
The prices for the following concrete are to include for
filling into formwork, well vibrating and packing around
rod reinforcement (formwork and reinforcement measured
separately)

Reinforced Insitu concrete grade 25 in:-

A Ring beam M3 -
In external walls 1 1 1 1 1 14.00 0.20 0.50 1.40
Dedcut; rebate for drip (1) 1 1 1 1 14.60 0.10 0.10 (0.15)
Dedcut; rebate for drip 1 1 1 1 1 15.00 0.10 0.10 0.15

In internal walls 1 1 1 1 1 4.50 0.15 0.20 0.13


1.54

A 150mm thick suspended solid slab M3 -


In internal walls 1 1 1 1 1 3.20 4.20 1.00 13.44
13.44

A Parapet walls; moulded as per the Architects details. M3 C/Area


In external walls 1 1 1 1 1 14.00 0.16 1.00 2.24

High tensile steel bar reinforcement to BS 4461 -


-
C Assorted bars to 32mm diameter Kg -
Ring beams 1 1 1 150 1 1.54 1.00 1.00 230.85
Suspended slab 1 1 1 150 1 13.44 0.15 1.00 302.40
Parapet walls 1 1 1 150 1 2.24 1.00 1.00 336.00
869.25

Sawn formwork to:

Sides and soffites of ring beams


In external walls/sides 1 1 1 1 2 14.00 0.50 1.00 14.00
Dedcut; rebate for drip/external/soffites 1 1 1 1 1 15.00 0.10 1.00 1.50
Soffites of windows and doors
Opening 1 1 1 1 1 0.90 0.20 1.00 0.18
Wg-16 1 1 1 1 1 0.60 0.20 1.00 0.12
Wg-17 1 1 1 1 2 1.45 0.20 1.00 0.58

In internal walls 1 1 1 1 2 4.50 0.20 1.00 1.80


Dg-12 (1) 1 1 1 1 0.80 0.15 1.00 (0.12)
Dg-18 (1) 1 1 1 1 0.90 0.15 1.00 (0.14)
17.92

A Soffites of suspended solid slab M3 -


In internal walls 1 1 1 1 1 2.80 3.80 1.00 10.64
10.64

A Edges of the suspended slab; 75 - 150mm wide M3 -


BILL NO.3: PROPOSED STAFF HOUSE
Item Description Unit Length Width Height ABSTRACT
In internal walls 1 1 1 1 2 7.40 1.00 1.00 14.80
14.80
A Sides of the parapet walls; M3 Girth
In external walls 1 1 1 1 1 14.00 1.28 1.00 17.85

A Extra over formwork to parapet walls for forming grooves,


chamfers, rebates, chases and mouldings. M3 Girth
In external walls 1 1 1 1 1 14.00 1.28 1.00 17.85

BILL NO. 3

ELEMENT NO. 4

EXTERNAL WALLS

Solid burnt clay brick work; bedded and jointed in cement


mortar (1:4); reinforced with approved 40mm wide x 1.6mm
thick galvanised mild steel straps built into every second
course and laped 300mm at joints and intersections and
carried at least 115mm into abutting walls in:

A 200mm thick wall M2


External walls; girth 1 1 1 1 1 14.00 1.00 2.40 33.60
Deductions ; door and windows
Opening (1) 1 1 1 1 0.90 1.00 2.40 (2.16)
Wg-16 (1) 1 1 1 1 0.60 1.00 0.80 (0.48)
Wg-17 (1) 1 1 1 2 1.45 1.00 1.50 (4.35)
26.61
-
Pre-cast reinforced Concrete grade 25 in:- -
-
G 150mm wide x 65mm thick average rebated, weathered and
throated window cill; bedded and jointed in cement and sand M -
Wg-16
(1:4) mortar 1 1 1 1 1 0.90 1.00 0.80 0.72
Wg-17 1 1 1 1 2 1.75 1.00 1.50 5.25
5.97

ELEMENT NO. 5

INTERNAL WALLS

Solid burnt clay brick work; bedded and jointed in cement


mortar (1:4); reinforced with approved 40mm wide x 1.6mm
thick galvanised mild steel straps built into every second
course and laped 300mm at joints and intersections and
carried at least 115mm into abutting walls in:

A 150mm thick walls; blockwork M2


External walls; girth 1 1 1 1 1 4.50 1.00 3.03 13.61
Deductions ; door and windows
Dg-12 (1) 1 1 1 1 0.80 1.00 2.10 (1.68)
Dg-18 (1) 1 1 1 1 0.90 1.00 2.40 (2.16)
9.77
Reinforced concrete grade 25 in:-

Lintels
Dg-12 1 1 1 1 1 1.10 0.15 0.15 0.02
0.02

Sawn formwork to:-

Sides and soffites of lintels


Dg-12 1 1 1 1 1 1.10 0.45 1.00 0.50
0.50

High tensile steel bar reinforcement to BS 4461

12mm diameter rebars


Dg-12 1 1 1 1 4 1.20 1.00 0.89 4.27
4.27

8mm diameter rebars


Dg-12 1 1 1 1 7 0.50 1.00 0.40 1.38
BILL NO. 3

ELEMENT NO. 6

WINDOWS, SCREENS AND LIGHTS

Anodized Aluminum casement windows. The color shall be


to client's approval; all additional costs are deemed
included.
-

Provide and fix purpose-made anodized aluminum


windows and window frames complete with 5mm thick
translucent glass and single glazing, glazing beads, wash
leather strips, sealing, burglar proofing, fly mesh, all
ironmongery and accessories; fixing to blockwork or
concrete; all as per Architect's drawings; Drawing No.
NA(22)02-9/10; in: -
-
BILL NO.3: PROPOSED STAFF HOUSE
Item Description Unit Length Width Height ABSTRACT
The contractor is expected to prepare and submit shop
drawings for approval prior to fabrication and erection of
the windows and screens -
-
Glazed window and window frames size: 600 mm wide x 800
mm high; complete with 1 No. tophung window panes size
600mm wide x 800mm high; overall window type [Wg-16] No 1.00

Glazed window and window frames size: 1450 mm wide x 1500


mm high; complete with 2 No.sliding window panes size
725mm wide x 1500mm high; overall window type [Wg-17] No 2.00

Window boards

Natural Stone Granite Window Board; size 150mm wide x


Glazed window
20mm thick and
thick; allwindow frames
edges well size:with
finished 600 amm widemould;
coved x 800 all
Glazed
mm window
high;
as per and
complete
Architect's window
with
details1 No.frames
tophungsize:window
1450 mm wide
panes x 1500
size
mm high;wide
600mm complete
x 800mm withhigh;
2 No.sliding windowtype
overall window panes size
[Wg-16] 1 1 1 1 1 0.60 1.00 1.00 0.60
725mm wide x 1500mm high; overall window type [Wg-17] 1 1 1 1 2 1.45 1.00 1.00 2.90
3.50

ELEMENT NO. 7

DOORS, SHUTTERS AND HATCHES

Timber doors

The following in wrot hardwood to architect's satisfaction:-

Approved hardwood flush doors

45mm thick solid core timber flush door shutter size 800mm
wide x 2100 mm high complete with a mahogany veneer; to
Architect's detail; door type [Db-12] 1.00

Door frames and finishings in in wrot hardwood

250mm x 50mm rebated frame


Db-12 1 1 1 1 1 5.00 1.00 1.00 5.00
5.00

40mm x 20mm Splayed architrave or qudrant beads where applicable.


Db-12 1 1 1 1 2 5.00 1.00 1.00 10.00
10.00

Ironmongery to architect's approval and sartisfaction

100mm Pressed steel butt hinges


Db-12 1 1 1 1 1 1.50 1.00 1.00 1.50
1.50
25mm diameter rubber door stop plugged to wall/floor
Db-12 1 1 1 1 2 1.00 1.00 1.00 2.00
2.00

Commercial privacy Lock complete with occupancy indicator


Oil rubbed bronze and Lock restroom hardware brass door
handles
Db-12 1 1 1 1 1 1.00 1.00 1.00 1.00
1.00

Coat hooks
Db-12 1 1 1 1 1 1.00 1.00 1.00 1.00
1.00

Door closer
Db-12 1 1 1 1 1 1.00 1.00 1.00 1.00
1.00

Stainless Steel Push plate size 300mm x 100mm


Db-12 1 1 1 1 2 1.00 1.00 1.00 2.00
2.00

Stainless Steel kick plate size 800mm wide x 150mm high x 3mm thick
Db-12 1 1 1 1 2 1.00 1.00 1.00 2.00
2.00

Symbol (Toilet)
Db-12 1 1 1 1 1 1.00 1.00 1.00 1.00
1.00

Anodised aluminium doors

Supply and fix purpose-made anodised aluminium


casement doors and frames; complete with 6mm thick
translucent glass and single glazing, ironmongery, fixing
lugs, all accessories and one coat of red oxide primer
before delivery; fixing to blockwork or concrete; all as per
Architect's drawings; Drawing No. NA(22)02-9/10; in:

Glazed door set; size 900 mm wide x 2400 mm high; complete


with 1 No. light panes size 900 mm wide x 2400mm high with
6mm thick frosted glass, 3 lever mortice lock; all as per the
Architect's details; door type [Dg-18] 1.00

BILL NO.3: PROPOSED STAFF HOUSE


Item Description Unit Length Width Height ABSTRACT
Prepare and apply undercoat and three coats of gloss oil
paint on:-

General surfaces of wood


Db-12 1 1 1 1 2 0.85 1.00 2.15 3.63

Wood frames; 200-300


Db-12 1 1 1 1 1 5.00 1.00 1.00 5.00

Wood surfaces not exceeding 100mm girth


Db-12 1 1 1 1 1 10.00 1.00 1.00 10.00

INTERNAL FINISHES

FLOOR FINISHES

Floor screed; Cement and sand (1:4); wood floated finish


to receive floor tiles m/s:

Floors
Toilet 1 1 1 1 1 1.80 1.00 1.00 1.80
Toilet 1 1 1 1 1 1.00 0.33 1.00 0.33
Guard's room 1 1 1 1 1 2.70 1.75 1.00 4.73
Guard's room 1 1 1 1 1 0.80 1.55 1.00 1.24
Lobby 1 1 1 1 1 1.00 1.26 1.00 1.26
Door ways
Dg-18 1 1 1 1 1 0.90 0.15 1.00 0.14
Dg-12 1 1 1 1 1 0.80 0.15 1.00 0.12
Opening 1 1 1 1 1 0.90 0.20 1.00 0.18
9.79
20mm thick 100mm high skirting with rounded top edge and
slight cove at bottom
Guard's room 1 1 1 1 2 5.25 1.00 1.00 10.50
Lobby 1 1 1 1 2 2.26 1.26 1.00 5.66

Door ways
Dg-18 (1) 1 1 1 2 0.90 1.00 1.00 (1.80)
Dg-12 (1) 1 1 1 1 0.80 1.00 1.00 (0.80)
Opening (1) 1 1 1 1 0.90 1.00 1.00 (0.90)
12.66

Supply and Fix approved Porcelain tiles; non-slip; laid in


an approved pattern; bedded in approved adhesive cement
and pointed with an approved tile grout

Floors
Toilet 1 1 1 1 1 1.80 1.00 1.00 1.80
Toilet 1 1 1 1 1 1.00 0.33 1.00 0.33
Guard's room 1 1 1 1 1 2.70 1.75 1.00 4.73
Guard's room 1 1 1 1 1 0.80 1.55 1.00 1.24
Lobby 1 1 1 1 1 1.00 1.26 1.00 1.26
Door ways
Dg-18 1 1 1 1 1 0.90 0.15 1.00 0.14
Dg-12 1 1 1 1 1 0.80 0.15 1.00 0.12
9.61

100mm high skirting with rounded top edge and


slight cove at bottom
12.66
WALL FINISHES

Cement and sand plaster

Walls
Toilet 1 1 1 1 2 3.13 1.00 2.85 17.84
Deductions
Dg-12 (1) 1 1 1 1 0.80 1.00 2.10 (1.68)
Wg-16 (1) 1 1 1 1 0.60 1.00 0.80 (0.48)
Addition for reveals and jambs
Dg-12 1 1 1 1 1 5.00 0.15 1.00 0.75
Wg-16 1 1 1 1 1 2.80 0.20 1.00 0.56

Guard's room 1 1 1 1 2 5.25 1.00 2.85 29.93


Deductions
Wg-17 (1) 1 1 1 2 1.45 1.00 1.50 (4.35)
Dg-18 (1) 1 1 1 1 0.90 1.00 2.40 (2.16)
Addition for reveals and jambs
Wg-17 1 1 1 1 2 5.90 0.20 1.00 2.36
Dg-18 1 1 1 1 1 5.70 0.15 1.00 0.85

Lobby 1 1 1 1 2 2.26 1.26 2.85 16.13


Deductions
Dg-18 (1) 1 1 1 1 0.90 1.00 2.40 (2.16)
Dg-12 (1) 1 1 1 1 0.80 1.00 2.10 (1.68)
Opening (1) 1 1 1 1 0.90 1.00 2.40 (2.16)
Addition for reveals and jambs
Opening 1 1 1 1 1 5.70 0.20 1.00 1.14

Deductions
Wall tiles (11.49)
43.41

Cement and sand render to receive wall tiles


Toilet 1 1 1 1 2 3.13 1.00 2.10 13.15

BILL NO.3: PROPOSED STAFF HOUSE


Item Description Unit Length Width Height ABSTRACT
Deductions
Dg-12 (1) 1 1 1 1 0.80 1.00 2.10 (1.68)
Wg-16 (1) 1 1 1 1 0.60 1.00 0.50 (0.30)

Addition for reveals and jambs


Wg-16 1 1 1 1 1 1.60 0.20 1.00 0.32

11.49

BILL NO.3: PROPOSED STAFF HOUSE


Item Description Unit Length Width Height ABSTRACT

Wall tiles
11.49

Approved plastic/aluminium corner pieces/beads


Toilet 1 1 1 1 2 3.13 1.00 1.00 6.26

Deductions
Dg-12 1 1 1 1 1 4.20 1.00 1.00 4.20
Wg-16 1 1 1 1 1 1.60 1.00 1.00 1.60

12.06
Oil paint to walls
43.41

CEILING FINISHES

Cement and sand plaster to ceiling soffites


Internally 1 1 1 1 1 2.80 3.80 1.00 10.64
10.64

Cornices; 150mm x 150mm


Toilets 1 1 1 1 2 3.13 1.00 1.00 6.26
Guard's room 1 1 1 1 2 5.25 1.00 1.00 10.50
Lobby 1 1 1 1 2 2.26 1.26 1.00 5.66
22.42

Matt emulsion paint to ceiling soffites


Internally 1 1 1 1 1 2.80 3.80 1.00 10.64
10.64

EXTERNAL WALLS

Cement and sand render to walls


External walls; girth 1 1 1 1 1 14.00 1.00 2.40 33.60
Deductions ; door and windows
Opening (1) 1 1 1 1 0.90 1.00 2.40 (2.16)
Wg-16 (1) 1 1 1 1 0.60 1.00 0.80 (0.48)
Wg-17 (1) 1 1 1 2 1.45 1.00 1.50 (4.35)
26.61

Ditto to concrete surfaces


Ring beams
In external walls/sides 1 1 1 1 1 14.00 0.50 1.00 7.00
Dedcut; rebate for drip/external/soffites /rebates 1 1 1 1 2 15.00 0.10 1.00 3.00
Parapet walls
In external walls 1 1 1 1 1 14.00 1.70 1.00 23.80
33.80

Floor screed; Cement and sand (1:4); wood floated finish

Roof slab
1 1 1 1 1 2.80 3.80 1.00 10.64
10.64
Water proofing; tanking

4mm thick APP - modified bitumen torch - on vertical


membrane on concrete retaining wall or any other approved
tanking layed as recommended by the manufacturer
Concrete Flat roofs
1 1 1 1 1 2.80 3.80 1.00 10.64
10.64

Water proofing; tanking

4mm thick APP - modified bitumen torch - on vertical


membrane on concrete retaining wall or any other approved
tanking layed as recommended by the manufacturer
Sides of upstand beams
1 1 1 1 2 6.60 0.55 1.00 7.20
1 1 1 1 1 14.00 0.43 1.00 5.95
13.15

Floor screed; Cement and sand (1:4); wood floated finish


to receive floor tiles m/s:

Roof slab
1 1 1 1 1 2.80 3.80 1.00 10.64
10.64

Quarry tiles

Roof slab
1 1 1 1 1 2.80 3.80 1.00 10.64
10.64

100mm skirting
1 1 1 1 2 6.60 1.00 1.00 13.20
13.20

Roof drainage
Fulbora; 150mm diameter; stainless steel; complete with a
clamp ring and grating; including taking around the opening
and making good to distrubed concrete and finished surfaces;
as per the Architect's detail.
1.00

BILL NO.3: PROPOSED STAFF HOUSE


Item Description Unit Length Width Height ABSTRACT
150mm diameter upvc down pipe
3.00

Projecting offsets 1.00

Shoe outlet 1.00

Splash apron

Kerbs 22.80

Paving slabs for splash apron including jointing and pointng 18.80

BILL NO.3: PROPOSED STAFF HOUSE


BILL NO.2: FIRST FLOOR
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT: COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB
MEASUREMENTS PURPOSE: ESTIMATES
NO. DESCRIPTION UNIT EQ. PRTS EQ. PRTS EQ. PRTS L W H/D/kg/m

BILL NO.2

FIRST FLOOR

ELEMENT NO. 2

SUPERSTRUCTURE

The prices for the following concrete are to include for


filling into formwork, well vibrating and packing around
rod reinforcement (formwork and reinforcement
measured separately)

Reinforced Insitu concrete grade 25 in:-

A Beams including staircase landing beams and lintels M3


beams measured with planswift 1 1 1 178.10 0.30 0.25
Half landing beams 1 1 1 2.70 0.30 0.25

B Columns M3
C1 as per the structural drawings; Sheet A1 of 2 1 1 26 0.30 0.30 3.25

C Staircase M3
Staircase 02 waist 1 1 2 3.50 1.30 0.25
Steps 1 22 0.5 0.28 0.16 1.00

E 250mm thick Suspended solid slab margins. M2


1 1 1 89.60 1.00 1.00

E 250mm thick Suspended solid slab M2


1 1 1 8.08 1.00 1.00

F 200mm thick staircase landing M2


Staircase 02 - landing 1 1 2 2.70 1.65 1.00

Suspended Hollow slab

G 250mm thick overall horizontal composite suspended slab comprising


300mm x 300mm x 175mm deep maxpan hollow blocks with 150mm wide
reinforced concrete grade 25 ribs at 450mm centre and laid on temporary
timber wrot formwork (measured separately) and including 75mm thick
grade 25 topping, reinforced with fabric mesh reinforcement ref. A142
(measured separately), mechanically floated.
M2
1 1 1 241.40 1.00 1.00

H Temporary formwork to soffites of the hollow block suspended


slab M2
1 1 1 241.40 1.00 1.00

Reinforcement

High tensile steel bar reinforcement to BS 4449 as described;


including all bends, hooks, tying wire, distance blocks, spacers and
the like 0.183 0.1270833333

J Assorted rebar up to 16mm diameter. Kg


Columns 1 1 1 7.60 1.00 150.00
Beams 1 1 1 13.56 1.00 150.00
Staircases 1 1 1 2.76 1.00 150.00
Slab margins 1 1 1 89.60 0.25 150.00
Solid slabs 1 1 1 8.08 0.25 150.00
Hollow block slab 1 1 1 241.40 0.13 150.00
Staircase landings 1 1 1 8.91 0.25 150.00

Fabric mesh reinforcement to B.S. 4483

K Reference A142; mesh size 200mm x 200mm; weighing 2.22kg/sq.m with


minimum 300mm end and side laps M2
1 1 1 330.80 1.00 1.00
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT: COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB

Sawn Formwork as described to:-

A Sides of Columns M2
C1 as per the structural drawings; Sheet A1 of 2 1 4 26 0.30 1.00 3.25

B Sides and Soffites of beams including landing beams M2


beams measured with planswift 1 1 1 178.10 0.80 1.00
Half landing beams 1 1 1 2.70 0.80 1.00

C Soffites of suspended slab margins M2


1 1 1 52.50 1.00 1.00

D Soffites of suspended solid slab M2


1 1 1 6.40 1.00 1.00

E Sloping Soffites of staircase M2


Staircase 02 waist 1 1 2 3.50 1.30 1.00

F Soffites of staircase landing M2


Staircase 02 - landing 1 1 2 2.70 1.35 1.00

G Risers 150mm high M


Steps 1 22 1 1.30 1.00 1.00

H Edges of staircase landing; 200mm wide M


Staircase 02 - landing 1 1 2 8.80 1.00 1.00

J Sides of staircase stringer 375mm wide overall including


cutting to profile of treads and risers M
Staircase 02 waist 1 2 2 3.50 1.00 1.00

K Edge of suspended slab; 250mm high M


1 1 1 104.00 1.00 1.00

ELEMENT NO. 2
RC SUPERSTRUCTURE 2/2/2

BILL NO.2

ELEMENT NO. 4

EXTERNAL WALLS

Solid concrete blockwork 3.5Mpa; jointed and pointed in cement and


sand (1:3) mortar in;reinforced with 25mm wide x 1mm thick mild
steel straps in horizontal alternate courses in:-

A 200mm thick M2
Walls (plan swift) 1 1 1 110.70 1.00 3.00
Deductions
Ddt: W3 -1 1 5 2.40 1.00 2.00
Ddt: Opening -1 1 1 6.19 1.00 3.00
Ddt: W5 -1 1 1 1.50 1.00 1.30
Ddt: W4 -1 1 3 0.75 1.00 1.30
Ddt: Curtain wall at the staircase -1 1 1 4.41 1.00 3.00
Ddt: Curtain wall L shaped -1 1 1 4.00 1.00 3.00
Ddt: D10 -1 1 1 3.50 1.00 3.00
Ddt: D11 -1 1 2 0.90 1.00 2.40
Ddt: Opening -1 1 1 1.28 1.00 3.00
Ddt: D9 -1 1 1 2.00 1.00 3.00
Ddt: D3 -1 1 3 3.00 1.00 3.00
Ddt: Curtain wall at the resturant -1 1 1 2.71 1.00 3.00
Ddt: Curtain wall at the resturant -1 1 1 10.83 1.00 3.00

Reinforced Insitu concrete grade 25 in:-

C Moulded concrete window Sill; Section size 250 x 85 x 50mm; weathered


and throated; all as per Architect's details M
Ddt: W3 1 1 5 2.70 1.00 1.00
Ddt: Window not labelled 1 1 1 1.80 1.00 1.00
Ddt: W4 1 1 3 1.05 1.00 1.00

Concrete lintel; 200mm thick x 200mm deep; in insitu concrete grade 25


reinforced with 4 T12 and T8 stirrups spaced at 200mm centers; including
all the necessary formwork.
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT: COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB
Deductions
Ddt: D11 1 1 2 1.20 1.00 1.00

Curtain walling

D Structural glazing in approved aluminium hollow frames comprising of


6mm thick one way solar control reflective glass of approved colour
including beads, wash leather,sealants etc. to the manufacturer's
specifications. M2
Curtain wall at the staircase 1 1 1 4.41 1.00 3.00
Curtain wall L shaped 1 1 1 4.00 1.00 3.00
Curtain wall at the resturant 1 1 1 2.71 1.00 3.00
Curtain wall at the resturant 1 1 1 10.83 1.00 3.00

ELEMENT NO. 4
EXTERNAL WALING 2/4/1

BILL NO.2

ELEMENT NO. 5

INTERNAL WALLS

Solid concrete blockwork 3.5Mpa; jointed and pointed in cement and


sand (1:3) mortar in;reinforced with 25mm wide x 1mm thick mild
steel straps in horizontal alternate courses in:-

A 200mm thick Wall M2


Walls (plan swift) 1 1 1 35.00 1.00 3.00
Deductions
Ddt: D9 -1 1 1 2.00 1.00 3.00

A 150mm thick walls M2


Walls (plan swift) 1 1 1 11.80 1.00 3.00
Deductions
Ddt: D6 -1 1 4 0.80 1.00 2.40

Concrete lintel; 150mm thick x 200mm deep; in insitu concrete grade 25


reinforced with 4 T12 and T8 stirrups spaced at 200mm centers; including
all the necessary formwork.
Deductions
D6 1 1 4 1.10 1.00 1.00

ELEMENT NO. 5
INTERNAL WALING 2/5/1

BILL NO.2

ELEMENT NO. 6

WINDOWS AND SCREENS

ALUMINIUM WINDOWS

Purpose made powder coated Aluminium windows complete with


Aluminium section frames and subframes for single glazing
including glazing beads, wash leather strips, sealing, all
ironmongery and accessories all as per Architect's detailed
drawings in:

Windows; extruded aluminium alloy; including frames; subframes;


fly screens; hardware; glazing; 5mm thick glass and glazing beads
and gaskets; as Drg. A100

Window size: 2400mm wide x 2000mm high; overall window type W3 No. 1 1 5 1 1 1

Window size: 750mm wide x 1300mm high; overall window type W4 No. 1 1 3 1 1 1

Window size: 1500mm wide x 1300mm high; overall window type W5 No. 1 1 1 1 1 1

Curtain rod combination complete with rings and all necessary


fixing accessories as per Architect's details

E 20mm stainless steel curtain rods including curtain rings all fixed on
aluminum brackets screwed to wall M

Window size: 2400mm wide x 2000mm high; overall window type W3 No. 1 1 5 3.00 1.00 1.00
Window size: 750mm wide x 1300mm high; overall window type W4 No. 1 1 3 1.20 1.00 1.00
Window size: 1500mm wide x 1300mm high; overall window type W5 No. 1 1 1 2.00 1.00 1.00
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT: COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB

ELEMENT NO. 6
WINDOWS 2/6/1

BILL NO.2

ELEMENT NO. 7

DOORS

Door frames, linings and mouldings in wrought mahogany as


described to Architect's details:-

A 250mm x 50mm rebated frame; plugging M


D11 1 1 2 5.70 1.00 1.00

A 200mm x 50mm rebated frame; plugging M


D6 1 1 4 5.60 1.00 1.00

B 250mm x 50mm rebated transome M


D11 1 1 2 0.90 1.00 1.00

B 200mm x 50mm rebated transome M


D6 1 1 4 0.80 1.00 1.00

C 25 x 50 mm; moulded bevelled architrave M


D11 1 1 2 5.70 1.00 1.00
D6 1 1 4 5.60 1.00 1.00

D 25 x 25 mm; moulded glazing beads. M


D11 1 2 2 2.40 1.00 1.00
D6 1 2 4 2.20 1.00 1.00

Provide and fix the following standard wrought hardwood solid


panelled door ; all as per Architect's details

E 45mm thick; Size 900mm x 2100 mm high - D9 No 1 1 2 1 1 1

E 45mm thick; Size 800mm x 2100 mm high - D6 No 1 1 4 1 1 1

Suppy and Fix the following "ASSA ABLOY UNION" or equal


approved Ironmongery

102mm x 76mm Pressed steel butt hinges Prs.


D11 1 1 2 1.50 1.00 1.00
D6 1 1 4 1.50 1.00 1.00

Three lever mortice lock complete with furniture No


D11 1 1 2 1.00 1.00 1.00
D6 1 1 0 1.50 1.00 1.00

Bathroom locks with indicator bolts No


D11 1 1 0 1.00 1.00 1.00
D6 1 1 4 1.50 1.00 1.00

J 25mm diameter rubber door stop No


1 1 10 1.00 1.00 1.00

K Stainless steel kick plates 800mm long x 100mm high No


D11 1 2 2 1.00 1.00 1.00
D6 1 2 4 1.00 1.00 1.00

L Stainless steel push/pulll plates size 100mm wide x 300mm long No


D11 1 2 2 1.00 1.00 1.00
D6 1 2 4 1.00 1.00 1.00

M Coat hooks No
D6 1 1 4 1.00 1.00 1.00

N Automatic Door closer (Office and washroom main entrance) No


1 1 4 1.00 1.00 1.00

P Approved PVC Symbol- Gents washrooms No


1 1 1 1.00 1.00 1.00
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT: COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB

Q Approved PVC Symbol- Ladies washrooms No


1 1 1 1.00 1.00 1.00

R Approved PVC Symbol - Shops No


1 1 2 1.00 1.00 1.00

S Approved PVC Symbol- Restaurant and No


1 1 5 1.00 1.00 1.00

Glass and glazing

T 5mm clear sheet glass in panes fixed to timber frame with glazing beads
(measured separately) M2
D11 1 1 2 0.90 1.00 0.30
D6 1 1 4 0.80 1.00 0.30

Prepare and apply one undercoat and two finishing coats of


polyurethane varnish in accordance with manufacturer's
instructions to:

D Wood general surfaces. M2


D11 1 2 2 0.95 1.00 2.15
D6 1 2 4 0.85 1.00 2.15

E Ditto over 200mm but not exceeding 300mm girth M


1 1 1 38.80 1.00 1.00

E Ditto not exceeding 100mm girth M


1 1 1 61.00 1.00 1.00

F Priming back of the door frames before fixing; 200 -300mm girth M
1 1 1 33.80 1.00 1.00

Aluminium doors

Door set; size 3500mm wide x 3000mm high; overall door type D10 1 1 1 1 1 1
Door set; size 3000mm wide x 3000mm high; overall door type D3 1 1 3 1 1 1

ELEMENT NO. 7
DOORS 2/7/2

BILL NO.2

ELEMENT NO. 8

INTERNAL FINISHINGS

Floor screed; Cement and sand (1:4); wood floated finish:

A 47mm thick; to receive micro-topping finish (measured separately) M2


1 1 1 186.50 1.00 1.00

A 40mm thick; to receive floor tiles (measured separately) M2


1 1 1 127.39 1.00 1.00

D Ditto; on staircase landings ditto M2


Staircase 01 1 1 2 1.35 2.70 1.00

E Ditto; on treads 275mm wide ditto M


Staircase 01 1 1 22 1.30 1.00 1.00

F Ditto; to risers 160 mm high ditto M


Staircase 01 1 1 22 1.30 1.00 1.00

G Ditto; to stringer 375mm wide (maximum) M


Staircase 01 1 1 1 14.00 1.00 1.00

H Edge of staircase landing; 200mm wide M


Staircase 01 1 1 2 0.20 1.00 1.00
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT: COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB

J Ditto; to receive skirting; 100mm high ditto M


1 1 1 165.80 1.00 1.00

3mm think micro top polymeric-cement floor system

3mm think micro top polymeric-cement floor system applied in multiple


thin coats to a maximum of 3 mm depth; 3 separate layers Primer coat
applied at 1.5 mm depth, a basecoat applied at a nominal 1mm depth
then a finish coat applied at 0.5mm depth. In between each coat the floor
is sanded and vacuumed ready to receive the following coat. Once the
above has been completed a minimum of two sealer coats is applied
1 1 1 186.50 1.00 1.00

Skirting; 100mm high ditto M


1 1 1 91.70 1.00 1.00

Supply and Fix approved ceramic tiles; non-slip; laid in an approved


pattern; bedded in approved adhesive cement and pointed with an
approved tile grout

M Size 450 x 450 x 10 mm thick to floors M2


1 1 1 127.39 1.00 1.00
Door ways
Ddt: Curtain wall at the staircase 1 1 1 4.41 0.20 1.00
Ddt: Curtain wall L shaped 1 1 1 4.00 0.20 1.00
Ddt: D10 1 1 1 3.50 0.20 1.00
Ddt: D11 1 1 2 0.90 0.20 1.00
Ddt: D9 1 1 1 2.00 0.20 1.00
Ddt: D3 1 1 3 3.00 0.20 1.00
Ddt: Curtain wall at the resturant 1 1 1 2.71 0.20 1.00
Ddt: Curtain wall at the resturant 1 1 1 10.83 0.20 1.00

D11 1 1 2 0.90 0.20 1.00


D6 1 1 4 0.80 0.15 1.00

D Ditto; on staircase landings ditto M2


Staircase 01 1 1 2 1.35 2.70 1.00

E Ditto; on treads 275mm wide ditto M


Staircase 01 1 1 22 1.30 1.00 1.00

F Ditto; to risers 150 mm high ditto M


Staircase 01 1 1 22 1.30 1.00 1.00

G Ditto; to stringer 375mm wide (maximum) M


Staircase 01 1 1 1 18.45 1.00 1.00

H Edge of staircase landing; 200mm wide M


Staircase 01 1 1 2 0.20 1.00 1.00

J Ditto; to receive skirting; 100mm high ditto M


1 1 1 74.10 1.00 1.00

Wall Tile backing

Screed backing to wall; Cement and sand (1:4); wood floated finish:

C 12mm thick; to receive ceramic wall tiles (measured separately) M2


Total girth 1 1 1 41.25 1.00 3.00
Deductions
D6 -1 2 4 0.80 1.00 2.40
D11 -1 1 2 0.90 1.00 2.40
Ddt: W5 -1 1 1 1.50 1.00 1.30
Ddt: W4 -1 1 3 0.75 1.00 1.30

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm second


coat of cement and lime putty (1:10); steel trowelled to:

D Walls M2
External wall area 1 1 1 167.16 1.00 1.00
Internal wall areas x2 1 1 2 126.72 1.00 1.00
Add reveals and jambs for openings; external walls
Add W3 1 1 5 8.80 0.20 1.00
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT: COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB
Add Opening 1 1 1 12.18 0.20 1.00
Add W5 1 1 1 5.60 0.20 1.00
Add W4 1 1 3 4.10 0.20 1.00
Add Curtain wall at the staircase 1 1 1 10.41 0.20 1.00
Add Curtain wall L shaped 1 1 1 10.00 0.20 1.00
Add D10 1 1 1 9.50 0.20 1.00
Add D11 1 1 2 5.70 0.20 1.00
Add Opening 1 1 1 7.28 0.20 1.00
Add D9 1 1 1 8.00 0.20 1.00
Add D3 1 1 3 9.00 0.20 1.00
Add Curtain wall at the resturant 1 1 1 8.71 0.20 1.00
Add Curtain wall at the resturant 1 1 1 16.83 0.20 1.00
Add reveals and jambs for openings; internal walls
D6 1 1 4 5.60 0.15 1.00
Ddt: Tiled area -1 1 1 99.20 1.00 1.00
F Walls M2

E Concrete surfaces (exposed beam and column surfaces) M2

Supply and fix approved glazed ceramic wall tiles; 300mm x 200mm
x 6mm thick; approved colour; bedding and jointing on screed
(measured separately) with approved water proof adhesive; flush
pointing in approved coloured grout to:

F Walls M2

SUNDRIES

Accessories

G Edge trim; plastic; quarter round; setting at edges of wall tile finish M
D6 1 2 4 1.00 1.00 1.00
D11 1 1 2 1.00 1.00 1.00
Ddt: W5 1 2 1 2.80 1.00 1.00
Ddt: W4 1 2 3 4.10 1.00 1.00

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm second


coat of cement and lime putty (1:10); steel trowelled to:

G Concrete ceiling soffites. M2


Formwork area to margins 1 1 1 52.50 1.00 1.00
Formwork area to maxspan slab 1 1 1 241.40 1.00 1.00
Formwork area to solid slab 1 1 1 6.40 1.00 1.00

H Staircase landing soffites M2

J Sloping staircase sofffites M2

K Moulded Ceiling cornice as per Architect's detail M

Mild steel Staircase balustrade; welded construction; shop primed


with red oxide

A Horizontal or raking balustrade; 900mm high comprising of; 50mx3mm


thick CHS handrail; 4 No. 25x2mm thick CHS intermediate horizontal
rails; 2/50x6mm thick MS flat balusters, mild steel base plates; all rawl
bolted into concrete; including primer, spray painting wth three coats
gloss oil paint and decorations to approval. M
Staircase 02 waist 1 1 2 3.50 1.00 1.00

A Dado rails; M
1 1 2 3.50 1.00 1.00
1 1 1 14.10 1.00 1.00

Glass railing; 900mm high comprising of: 12mm thick tempered (toughed)
laminated glass fixed to and including: 50mm diameter chrome plated
stainless steel hand rails and and vertical balusters spaced at 900mm
centres; all chrome plated stainless brackets; fixed to walls and staircase
steel frame. M
1 1 1 34.60 1.00 1.00

Prepare and apply one undercoat and two finishing coats of matt
emulsion paint in accordance with manufacturer's instructions to:

B Concrete ceiling soffites. M2

C Staircase landing soffites M2

D Sloping staircase sofffites M2

E Moulded Ceiling cornice as per Architect's detail M


CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT: COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB

Prepare and apply one undercoat and two finishing coats of silk
vinyl paint in accordance with manufacturer's instructions to:

H Plastered walls and concrete surfaces. M2

Prepare and apply one undercoat and two finishing coats of gloss
oil paint in accordance with manufacturer's instructions to:

J Grilled metal surfaces (balustrade) M2

ELEMENT NO. 8
INTERNAL FINISHINGS

BILL NO.2

ELEMENT NO. 9

EXTERNAL FINISHINGS

20mm thick rendering in Cement and Sand (1:4) mortar; as per


Architect's details; on:

A Walls M2

Prepare and apply approved weatherguard emulsion paint in


accordance with manufacturer's instructions to:

C Rendered surfaces M2

ELEMENT NO. 9
EXTERNAL FINISHINGS

BILL NO.2

ELEMENT NO. 10

FITTINGS

A Alow a provisional sum of Ushs. 22,000,000 for fittings


Friday, April 5, 2024
IB
PURPOSE: ESTIMATES
QTY

13.36
0.20
13.56

7.60
7.60

2.27
0.48
2.76

89.60
89.60

8.08
8.08

8.91
8.91

241.40
241.40

241.40
241.40

1,140.75
2,034.00
413.83
3,360.00
303.00
4,601.69
334.13
12,187.39

330.80
330.80
Friday, April 5, 2024
IB

101.40
101.40

142.48
2.16
144.64

52.50
52.50

6.40
6.40

9.10
9.10

7.29
7.29

28.60
28.60

17.60
17.60

14.00
14.00

104.00
104.00

332.10

- 24.00
- 18.56
- 1.95
- 2.93
- 13.23
- 12.00
- 10.50
- 4.32
- 3.84
- 6.00
- 27.00
- 8.13
- 32.49
167.16

13.50
1.80
3.15
18.45
Friday, April 5, 2024
IB

2.40
2.40

13.23
12.00
8.13
32.49
65.85

105.00

- 6.00
99.00

35.40

- 7.68
27.72

4.40
4.40

15.00
3.60
2.00
20.60
Friday, April 5, 2024
IB

11.40
11.40

22.40
22.40

1.80
1.80

3.20
3.20

11.40
22.40
33.80

9.60
17.60
27.20

3.00
6.00
9.00

2.00
-
2.00

-
6.00
6.00

10.00
10.00

4.00
8.00
12.00

4.00
8.00
12.00

4.00
4.00

4.00
4.00

1.00
Friday, April 5, 2024
IB
1.00

1.00
1.00

2.00
2.00

5.00
5.00

0.54
0.96
1.50

8.13
14.53
22.66

38.80
38.80

61.00
61.00

33.80
33.80

1
3

186.50
186.50

127.39
127.39

7.29
7.29

28.60
28.60

28.60
28.60

14.00
14.00

0.40
Friday, April 5, 2024
IB
0.40

165.80
165.80

186.50
186.50

91.70
91.70

127.39

0.88
0.80
0.70
0.36
0.40
1.80
0.54
2.17

0.36
0.48
135.88

7.29
7.29

28.60
28.60

28.60
28.60

18.45
18.45

0.40
0.40

74.10
74.10

123.75

- 15.36
- 4.32
- 1.95
- 2.93
99.20

167.16
253.44

8.80
Friday, April 5, 2024
IB
2.44
1.12
2.46
2.08
2.00
1.90
2.28
1.46
1.60
5.40
1.74
3.37

3.36
- 99.20
361.41

246.04

99.20

8.00
2.00
5.60
24.60
40.20

52.50
241.40
6.40
300.30

8.91

9.10

287.67

7.00
7.00

7.00
14.10
21.10

34.60
34.60

300.30

8.91

9.10

287.67
Friday, April 5, 2024
IB

361.41

23.15

193.16

193.16

17,000,000
BILL NO.2: SECOND FLOOR
Item Unit Qty Rate Amount
USHS USHS

BILL NO.2

SECOND FLOOR

ELEMENT NO. 2

SUPERSTRUCTURE

The prices for the following concrete are to include for


filling into formwork, well vibrating and packing around
rod reinforcement (formwork and reinforcement
measured separately)

Reinforced Insitu concrete grade 25 in:-

A Beams including staircase landing beams and lintels M3 17 Err:509 Err:509

B Columns M3 7 Err:509 Err:509

C Staircase M3 Err:509 Err:509 Err:509

G 175mm thick Suspended solid slab M2 355 Err:509 Err:509

K 175mm thick staircase landing M2 30 Err:509 Err:509

Reinforcement

High tensile steel bar reinforcement to BS 4449 as described;


including all bends, hooks, tying wire, distance blocks, spacers
and the like

N Assorted rebar up to 16mm diameter. Kg Err:509 Err:509 Err:509

Sawn Formwork as described to:-

A Sides of Columns M2 120 Err:509 Err:509

C Sides and Soffites of beams including landing beams M2 225 Err:509 Err:509

F Soffites of suspended soild slab M2 323 Err:509 Err:509

G Sloping Soffites of staircase M2 25 Err:509 Err:509

J Soffites of staircase landing M2 30 Err:509 Err:509

L Risers 150mm high M 76 Err:509 Err:509

N Edges of staircase landing; 175mm high M 10 Err:509 Err:509

P Sides of staircase stringer 375mm wide overall including


cutting to profile of treads and risers M 38 Err:509 Err:509

Q Edge of suspended slab; 175mm wide M 145 Err:509 Err:509

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS Err:509
ELEMENT NO. 2
RC SUPERSTRUCTURE 2/2/2
Item Unit Qty Rate Amount
USHS USHS

BILL NO.2

ELEMENT NO. 4

EXTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties set
in horizontal alternate courses:

A 200mm thick M2 121 Err:509 Err:509

B 100mm thick M2 40 Err:509 Err:509

Reinforced Insitu concrete grade 25 in:-

C Moulded concrete window Sill; Section size 250 x 85 x 50mm;


weathered and throated; all as per Architect's details M 20 Err:509 Err:509

Curtain walling

D Structural glazing in approved aluminium hollow frames comprising of


6mm thick one way solar control reflective glass of approved colour
including beads, wash leather,sealants etc. to the manufacturer's
specifications. M2 35 650,000 22,620,000

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS Err:509
ELEMENT NO. 3
EXTERNAL WALING 2/4/1
Item Unit Qty Rate Amount
USHS USHS
BILL NO.2

ELEMENT NO. 5

INTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties set
in horizontal alternate courses:

A 200mm thick Wall M2 508 Err:509 Err:509

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS Err:509
ELEMENT NO. 4
INTERNAL WALING 2/5/1
Item Unit Qty Rate Amount
USHS USHS
BILL NO.2

ELEMENT NO. 6

WINDOWS AND SCREENS

Mild steel casement windows and fly screens

Provide and fix purpose made mild steel casement windows and
window 5mm thick transluscent glass, glazing beads, wash
leather strips, sealing, burglar proofing, fly mesh all ironmongery
and accessories; fixing to blockwork or concrete; all as per
Architect's drawings in:

A Top hung window type W2; Size 600mm wide x 1800mm high. No. 10 432,000 4,320,000

B Louvered window type W3; Size 450mm wide x 1500mm high. No. 6 168,750 1,012,500

B Side hinged window type W4; Size 1500mm wide x 1500mm high. No. 3 900,000 2,700,000

Glass and glazing; fixed to steel with approved silicone sealant

C 5mm thick clear sheet glass and glazing to steel with putty M2 6 80,000 480,000

D Ditto obscure sheet glass diito M2 9 85,000 765,000

Curtain rod combination complete with rings and all necessary


fixing accessories as per Architect's details

E 20mm stainless steel curtain rods including curtain rings all fixed on
aluminum brackets screwed to wall (offices only) M 14 55,000 792,000

Prepare and apply one undercoat and two finishing coats of


gloss oil paint in accordance with manufacturer's instructions to:

F Metal surfaces (Measured flat both sides) M2 40 12,000 480,000

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS 10,549,500
ELEMENT NO. 6
WINDOWS 2/6/1
Item Unit Qty Rate Amount
USHS USHS

BILL NO.2

ELEMENT NO. 7

DOORS

Door frames, linings and mouldings in wrought mahogany as


described to Architect's details:-

A 250mm x 50mm rebated frame; plugging M 125 75,000 9,375,000

B 250mm x 50mm rebated transome M 20 75,000 1,500,000

C 25 x 50 mm; moulded bevelled architrave M 251 15,000 3,765,000

D 25 x 25 mm; moulded glazing beads. M 106 10,000 1,060,000

Provide and fix the following standard wrought hardwood solid


panelled door ; all as per Architect's details

E 45mm thick; Size 900mm x 2100 mm high - D2 No 22 750,000 16,500,000

Suppy and Fix the following "ASSA ABLOY UNION" or equal


approved Ironmongery

F 102mm x 76mm Pressed steel butt hinges Prs. 33 25,000 825,000

G Three lever mortice lock complete with furniture No 12 350,000 4,200,000

H Bathroom locks with indicator bolts. No 10 100,000 1,000,000

J 25mm diameter rubber door stop No 22 25,000 550,000

K Stainless steel kick plates 800mm long x 100mm high No 44 140,000 6,160,000

L Stainless steel push/pulll plates size 100mm wide x 300mm long No 44 85,000 3,740,000

M Coat hooks No 10 25,000 250,000

N Automatic Door closer (Office and washroom main entrance) No 2 300,000 600,000

R Approved PVC Symbol - Rooms 6-15 No 10 Err:509 Err:509

S Approved PVC Symbol- Wing No 2 Err:509 Err:509

Glass and glazing

T 5mm clear sheet glass in panes fixed to timber frame with glazing
beads (measured separately) M2 6 80,000 480,000

To collection Err:509
ELEMENT NO. 7
DOORS 2/71
Item Unit Qty Rate Amount
USHS USHS

Mild Steel Doors

Supply and fix purpose made mild steel casement doors in steel
framing; complete with all ironmongery, fixing lugs, all
accessories and one coat of red oxide primer before delivery as
per Architect's details

A Double side Hinged door set; size 1500mm wide x 2550mm high fixed
to brick wall background- D1 No. 10 1,200,000 12,000,000

Glass and glazing; fixed to steel with approved silicone sealant

B 5mm thick clear sheet glass and glazing to steel with putty M2 42 80,000 3,360,000

Prepare and apply one undercoat and two finishing coats of


gloss oil paint in accordance with manufacturer's instructions to:

C Metal surfaces M2 96 12,000 1,152,000

Prepare and apply one undercoat and two finishing coats of


polyurethane varnish in accordance with manufacturer's
instructions to:

D Wood general surfaces. M2 101 12,000 1,208,220

E Ditto not exceeding 100mm girth M 357 1,200 428,400

F Priming back of the door frames before fixing; 200 -300mm girth M 125 3,600 450,000

To collection 18,598,620

COLLECTION

Page No. 2/7/1 Err:509

Page No. 2/7/2 18,598,620

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS Err:509
ELEMENT NO. 7
DOORS 2/7/2

BILL NO.2
Item Unit Qty Rate Amount
USHS USHS

ELEMENT NO. 8

INTERNAL FINISHINGS

Floor screed; Cement and sand (1:4); wood floated finish:

A 40mm thick; to receive floor tile finish (measured separately) M2 248 25,000 6,200,000

D Ditto; on staircase landings ditto M2 30 25,000 750,000

E Ditto; on treads 275mm wide ditto M 76 6,250 475,000

F Ditto; to risers 150 mm high ditto M 76 3,750 285,000

G Ditto; to stringer 375mm wide (maximum) M 38 9,375 356,250

H Edge of staircase landing; 200mm wide M 10 5,000 50,000

J Ditto; to receive skirting; 100mm high ditto M 320 2,500 800,000

Supply and Fix approved ceramic tiles; non-slip; laid in an


approved pattern; bedded in approved adhesive cement and
pointed with an approved tile grout

M Size 450 x 450 x 10 mm thick to floors M2 248 85,000 21,080,000

D Ditto; on staircase landings ditto M2 30 85,000 2,550,000

E Ditto; on treads 275mm wide ditto M 76 21,250 1,615,000

F Ditto; to risers 150 mm high ditto M 76 12,750 969,000

G Ditto; to stringer 375mm wide (maximum) M 38 31,875 1,211,250

H Edge of staircase landing; 200mm wide M 10 17,000 170,000

J Ditto; to receive skirting; 100mm high ditto M 320 8,500 2,720,000

Wall Tile backing

Screed backing to wall; Cement and sand (1:4); wood floated


finish:

C 12mm thick; to receive ceramic wall tiles (measured separately) M2 188 16,000 3,008,000

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm second


coat of cement and lime putty (1:10); steel trowelled to:

D Walls M2 1214 17,000 20,638,000

E Concrete surfaces (exposed beam and column surfaces) M2 285 17,000 4,845,000

Supply and fix approved glazed ceramic wall tiles; 300mm x


200mm x 6mm thick; approved colour; bedding and jointing on
screed (measured separately) with approved water proof
adhesive; flush pointing in approved coloured grout to:

F Walls M2 188 65,000 12,220,000

To collection 79,942,500
ELEMENT NO. 8
INTERNAL FINISHINGS 2/8/1

SUNDRIES
Item Unit Qty Rate Amount
USHS USHS
Accessories

G Edge trim; plastic; quarter round; setting at edges of wall tile finish M 54 4,500 243,000

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm second


coat of cement and lime putty (1:10); steel trowelled to:

G Concrete ceiling soffites. M2 323 Err:509 Err:509

H Staircase landing soffites M2 30 Err:509 Err:509

J Sloping staircase sofffites M2 25 Err:509 Err:509

K Moulded Ceiling cornice as per Architect's detail M 350 Err:509 Err:509

Mild steel Staircase balustrade; welded construction; shop


primed with red oxide

A Horizontal or raking balustrade; 900mm high comprising of;


50mx3mm thick CHS handrail; 4 No. 25x2mm thick CHS intermediate
horizontal rails; 2/50x6mm thick MS flat balusters, mild steel base
plates; all rawl bolted into concrete; including primer, spray painting
wth three coats gloss oil paint and decorations to approval.
M 30 125,000 3,750,000

Glass railing; 900mm high comprising of: 12mm thick tempered


(toughed) laminated glass fixed to and including: 50mm diameter
chrome plated stainless steel hand rails and and vertical balusters
spaced at 900mm centres; all chrome plated stainless brackets; fixed
to walls and staircase steel frame. M 62 450,000 27,900,000

Prepare and apply one undercoat and two finishing coats of matt
emulsion paint in accordance with manufacturer's instructions
to:

B Concrete ceiling soffites. M2 323 12,000 3,876,000

C Staircase landing soffites M2 30 12,000 360,000

D Sloping staircase sofffites M2 25 12,000 300,000

E Moulded Ceiling cornice as per Architect's detail M 350 3,600 1,260,000

Prepare and apply one undercoat and two finishing coats of silk
vinyl paint in accordance with manufacturer's instructions to:

H Plastered walls and concrete surfaces. M2 1499 Err:509 Err:509

Prepare and apply one undercoat and two finishing coats of


gloss oil paint in accordance with manufacturer's instructions to:

J Grilled metal surfaces (balustrade) M2 Err:509 Err:509 Err:509

To collection Err:509
ELEMENT NO. 8
INTERNAL FINISHINGS 2/8/2

COLLECTION
Item Unit Qty Rate Amount
USHS USHS

Page No. 2/8/1 79,942,500

Page No. 2/8/2 Err:509

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS Err:509
ELEMENT NO. 8
INTERNAL FINISHINGS 2/8/3

BILL NO.2

ELEMENT NO. 9
Item Unit Qty Rate Amount
USHS USHS

EXTERNAL FINISHINGS

20mm thick rendering in Cement and Sand (1:4) mortar; as per


Architect's details; on:

A Walls M2 161 16,000 2,576,000

B Concrete surfaces (beam soffites and exposed columns) M2 30 16,000 480,000

Prepare and apply approved weatherguard emulsion paint in


accordance with manufacturer's instructions to:

C Rendered surfaces M2 191 Err:509 Err:509

Natural stone cladding (Columns and beams)

E Granite stone cladding; mechanically fixed; including backing; as


described. M2 92 95,000 8,740,000

TOTAL CARRIED TO SUMMARY AT THE END


OF ELEMENTS Err:509
2/9/1
ELEMENT NO. 9
EXTERNAL FINISHINGS

BILL NO.2

ELEMENT NO. 10
Item Unit Qty Rate Amount
USHS USHS

FITTINGS

A Alow a provisional sum of Ushs. 20,000,000 for fittings Sum 20,000,000

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS 20,000,000
2/10/1
ELEMENT NO.10
FITTINGS

Err:509

Err:509
Item Unit Qty Rate Amount
USHS USHS

BILL NO.2

SECOND FLOOR

SUMMARY OF ELEMENTS

Element No. 2: R.C. Superstructure Err:509

Element No. 4: External Walls Err:509

Element No. 5: Internal Walls Err:509

Element No. 6: Windows and screens 10,549,500

Element No. 7: Doors Err:509

Element No. 8: Internal Finishings Err:509

Element No. 9: External Finishings Err:509

Element No. 10: Fittings 20,000,000

TOTAL CARRIED TO GENERAL SUMMARY Shs. Err:509


2/S/E
BILL NO.2: THIRD FLOOR
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT:COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB
MEASUREMENTS PURPOSE: ESTIMATES
NO. DESCRIPTION UNIT EQ. PRTS EQ. PRTS EQ. PRTS L W H/D/kg/m

BILL NO.2

FIRST FLOOR

ELEMENT NO. 2

SUPERSTRUCTURE

The prices for the following concrete are to include for


filling into formwork, well vibrating and packing around
rod reinforcement (formwork and reinforcement
measured separately)

Reinforced Insitu concrete grade 25 in:-

A Beams including staircase landing beams and lintels M3


beams measured with planswift 1 1 1 178.10 0.30 0.25
Half landing beams 1 1 1 2.70 0.30 0.25

B Columns M3
C1 as per the structural drawings; Sheet A1 of 2 1 1 26 0.30 0.30 3.25

C Staircase M3
Staircase 02 waist 1 1 2 3.50 1.30 0.25
Steps 1 22 0.5 0.28 0.16 1.00

E 250mm thick Suspended solid slab margins. M2


1 1 1 89.60 1.00 1.00

E 250mm thick Suspended solid slab M2


1 1 1 8.08 1.00 1.00

F 200mm thick staircase landing M2


Staircase 02 - landing 1 1 2 2.70 1.65 1.00

Suspended Hollow slab

G 250mm thick overall horizontal composite suspended slab comprising


300mm x 300mm x 175mm deep maxpan hollow blocks with 150mm wide
reinforced concrete grade 25 ribs at 450mm centre and laid on temporary
timber wrot formwork (measured separately) and including 75mm thick
grade 25 topping, reinforced with fabric mesh reinforcement ref. A142
(measured separately), mechanically floated.
M2
1 1 1 241.40 1.00 1.00

H Temporary formwork to soffites of the hollow block suspended


slab M2
1 1 1 241.40 1.00 1.00

Reinforcement

High tensile steel bar reinforcement to BS 4449 as described;


including all bends, hooks, tying wire, distance blocks, spacers and
the like 0.18 0.13

J Assorted rebar up to 16mm diameter. Kg


Columns 1 1 1 7.60 1.00 150.00
Beams 1 1 1 13.56 1.00 150.00
Staircases 1 1 1 2.76 1.00 150.00
Slab margins 1 1 1 89.60 0.25 150.00
Solid slabs 1 1 1 8.08 0.25 150.00
Hollow block slab 1 1 1 241.40 0.25 150.00
Staircase landings 1 1 1 8.91 0.25 150.00

Fabric mesh reinforcement to B.S. 4483

K Reference A142; mesh size 200mm x 200mm; weighing 2.22kg/sq.m with


minimum 300mm end and side laps M2
1 1 1 330.80 1.00 1.00
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT:COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB
Sawn Formwork as described to:-

A Sides of Columns M2
C1 as per the structural drawings; Sheet A1 of 2 1 4 26 0.30 1.00 3.25

B Sides and Soffites of beams including landing beams M2


beams measured with planswift 1 1 1 178.10 0.80 1.00
Half landing beams 1 1 1 2.70 0.80 1.00

C Soffites of suspended slab margins M2


1 1 1 52.50 1.00 1.00

D Soffites of suspended solid slab M2


1 1 1 6.40 1.00 1.00

E Sloping Soffites of staircase M2


Staircase 02 waist 1 1 2 3.50 1.30 1.00

F Soffites of staircase landing M2


Staircase 02 - landing 1 1 2 2.70 1.35 1.00

G Risers 150mm high M


Steps 1 22 1 1.30 1.00 1.00

H Edges of staircase landing; 200mm wide M


Staircase 02 - landing 1 1 2 8.80 1.00 1.00

J Sides of staircase stringer 375mm wide overall including


cutting to profile of treads and risers M
Staircase 02 waist 1 2 2 3.50 1.00 1.00

K Edge of suspended slab; 250mm high M


1 1 1 104.00 1.00 1.00

ELEMENT NO. 2
RC SUPERSTRUCTURE 2/2/2

BILL NO.2

ELEMENT NO. 4

EXTERNAL WALLS

Solid concrete blockwork 3.5Mpa; jointed and pointed in cement and


sand (1:3) mortar in; reinforced with 25mm wide x 1mm thick mild
steel straps in horizontal alternate courses in:-

A 200mm thick M2
Walls (plan swift) 1 1 1 89.10 1.00 3.00
Deductions
Ddt: W1 -1 1 8 0.90 1.00 1.50
Ddt: W2 -1 1 6 0.90 1.00 2.10
Ddt: W3 -1 1 3 2.40 1.00 2.00
Ddt: Opening -1 1 1 4.90 1.00 3.00
Ddt: Curtain walling -1 1 1 4.41 1.00 3.00
Ddt: Curtain walling -1 1 1 5.00 1.00 3.00
Ddt: Curtain walling -1 1 1 5.78 1.00 3.00
Ddt: Curtain walling -1 1 1 4.50 1.00 3.00
Ddt: D3 -1 1 1 3.00 1.00 3.00

Reinforced Insitu concrete grade 25 in:-

C Moulded concrete window Sill; Section size 250 x 85 x 50mm; weathered


and throated; all as per Architect's details M
Ddt: W1 1 1 8 1.20 1.00 1.00
Ddt: W2 1 1 6 1.20 1.00 1.00
Ddt: W3 1 1 3 2.70 1.00 1.00

Concrete lintel; 200mm thick x 200mm deep; in insitu concrete grade 25


reinforced with 4 T12 and T8 stirrups spaced at 200mm centers; including
all the necessary formwork.
Deductions
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT:COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB

Curtain walling

D Structural glazing in approved aluminium hollow frames comprising of


6mm thick one way solar control reflective glass of approved colour
including beads, wash leather,sealants etc. to the manufacturer's
specifications. M2
Curtain walling 1 1 1 4.41 1.00 3.00
Curtain walling 1 1 1 5.00 1.00 3.00
Curtain walling 1 1 1 5.78 1.00 3.00
Curtain walling 1 1 1 4.50 1.00 3.00

ELEMENT NO. 4
EXTERNAL WALING 2/4/1

BILL NO.2

ELEMENT NO. 5

INTERNAL WALLS

Solid concrete blockwork 3.5Mpa; jointed and pointed in cement and


sand (1:3) mortar in;reinforced with 25mm wide x 1mm thick mild
steel straps in horizontal alternate courses in:-

A 200mm thick Wall M2


Walls (plan swift) 1 1 1 111.10 1.00 3.00
Deductions
Ddt: D1 -1 1 6 0.80 1.00 2.40
Ddt: D2 -1 1 1 0.90 1.00 2.40
Ddt: D7 -1 1 5 1.20 1.00 2.40
Ddt: D7 -1 1 1 1.30 1.00 2.40
Ddt: Opening -1 1 2 1.30 1.00 2.40

A 150mm thick walls M2


Walls (plan swift) 1 1 1 9.00 1.00 3.00
Deductions
Ddt: D1 -1 1 4 0.80 1.00 2.40

Concrete lintel; 200mm thick x 200mm deep; in insitu concrete grade 25


reinforced with 4 T12 and T8 stirrups spaced at 200mm centers; including
all the necessary formwork.
Ddt: D1 1 1 6 1.10 1.00 1.00
Ddt: D2 1 1 1 1.20 1.00 1.00
Ddt: D7 1 1 5 1.50 1.00 1.00
Ddt: D7 1 1 1 1.60 1.00 1.00
Ddt: Opeing 1 1 1 1.50 1.00 1.00

Concrete lintel; 150mm thick x 200mm deep; in insitu concrete grade 25


reinforced with 4 T12 and T8 stirrups spaced at 200mm centers; including
all the necessary formwork.
Deductions
D6 1 1 4 1.10 1.00 1.00

ELEMENT NO. 5
INTERNAL WALING 2/5/1

BILL NO.2

ELEMENT NO. 6

WINDOWS AND SCREENS

ALUMINIUM WINDOWS

Purpose made powder coated Aluminium windows complete with


Aluminium section frames and subframes for single glazing
including glazing beads, wash leather strips, sealing, all
ironmongery and accessories all as per Architect's detailed
drawings in:

Windows; extruded aluminium alloy; including frames; subframes;


fly screens; hardware; glazing; 5mm thick glass and glazing beads
and gaskets; as Drg. A100

Window size: 900mm wide x 1500mm high; overall window type W1 No. 1 1 8 1 1 1

Window size: 900mm wide x 2100mm high; overall window type W2 No. 1 1 6 1 1 1

Window size: 2400mm wide x 2000mm high; overall window type W3 No. 1 1 3 1 1 1
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT:COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB

Curtain rod combination complete with rings and all necessary


fixing accessories as per Architect's details

E 20mm stainless steel curtain rods including curtain rings all fixed on
aluminum brackets screwed to wall M
Window size: 900mm wide x 1500mm high; overall window type W1 No. 1 2 8 0.90 1.00 1.50
Window size: 900mm wide x 2100mm high; overall window type W2 No. 1 2 6 0.90 1.00 2.10
Window size: 2400mm wide x 2000mm high; overall window type W3 No. 1 2 3 2.40 1.00 2.00

ELEMENT NO. 6
WINDOWS 2/6/1

BILL NO.2

ELEMENT NO. 7

DOORS

Door frames, linings and mouldings in wrought mahogany as


described to Architect's details:-

A 250mm x 50mm rebated frame; plugging M


D1 1 1 6 3.20 1.00 1.00
D2 1 1 1 5.70 1.00 1.00
D7 1 1 5 6.00 1.00 1.00
D8 1 1 1 6.10 1.00 1.00

A 200mm x 50mm rebated frame; plugging M


D1 1 1 4 5.60 1.00 1.00

B 250mm x 50mm rebated transome M


D1 1 1 6 0.80 1.00 1.00
D2 1 1 1 0.90 1.00 1.00
D7 1 1 5 1.20 1.00 1.00
D8 1 1 1 1.30 1.00 1.00

B 200mm x 50mm rebated transome M


D6 1 1 4 0.80 1.00 1.00

C 25 x 50 mm; moulded bevelled architrave M


D1 1 2 10 3.20 1.00 1.00
D2 1 2 1 5.70 1.00 1.00
D7 1 2 5 6.00 1.00 1.00
D8 1 2 1 6.10 1.00 1.00

D 25 x 25 mm; moulded glazing beads. M


D1 1 2 10 2.20 1.00 1.00
D2 1 2 1 2.40 1.00 1.00
D7 1 2 5 3.00 1.00 1.00
D8 1 2 1 3.20 1.00 1.00

Provide and fix the following standard wrought hardwood solid


panelled door ; all as per Architect's details

45mm thick; Size 900mm x 2100 mm high - D1 No 1 1 1 1.00 1.00 1.00

45mm thick; Size 800mm x 2100 mm high - D2 No 1 1 10 1.00 1.00 1.00

45mm thick; Size 900mm x 2100 mm high - D8; Large No 1 1 1 1.00 1.00 1.00

45mm thick; Size 400mm x 2100 mm high - D8; Small No 1 1 1 1.00 1.00 1.00

45mm thick; Size 900mm x 2100 mm high - D7; Large No 1 1 5 1.00 1.00 1.00

45mm thick; Size 300mm x 2100 mm high - D7; Small No 1 1 5 1.00 1.00 1.00

Suppy and Fix the following "ASSA ABLOY UNION" or equal


approved Ironmongery

102mm x 76mm Pressed steel butt hinges Prs.


45mm thick; Size 900mm x 2100 mm high - D1 No 1 1 1 1.50 1.00 1.00
45mm thick; Size 800mm x 2100 mm high - D2 No 1 1 10 1.50 1.00 1.00
45mm thick; Size 900mm x 2100 mm high - D8; Large No 1 1 1 1.50 1.00 1.00
45mm thick; Size 400mm x 2100 mm high - D8; Small No 1 1 1 1.50 1.00 1.00
45mm thick; Size 900mm x 2100 mm high - D7; Large No 1 1 5 1.50 1.00 1.00
45mm thick; Size 300mm x 2100 mm high - D7; Small No 1 1 5 1.50 1.00 1.00
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT:COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB
Three lever mortice lock complete with furniture No
45mm thick; Size 800mm x 2100 mm high - D2 No 1 1 1 1.00 1.00 1.00
45mm thick; Size 900mm x 2100 mm high - D8; Large No 1 1 1 1.00 1.00 1.00
45mm thick; Size 400mm x 2100 mm high - D8; Small No 1 1 0 1.00 1.00 1.00
45mm thick; Size 900mm x 2100 mm high - D7; Large No 1 1 5 1.00 1.00 1.00
45mm thick; Size 300mm x 2100 mm high - D7; Small No 1 1 0 1.00 1.00 1.00

Bathroom locks with indicator bolts No


45mm thick; Size 900mm x 2100 mm high - D1 No 1 1 10 1.00 1.00 1.00

J 25mm diameter rubber door stop No


45mm thick; Size 900mm x 2100 mm high - D1 No 1 1 1 1.00 1.00 1.00
45mm thick; Size 800mm x 2100 mm high - D2 No 1 1 10 1.00 1.00 1.00
45mm thick; Size 900mm x 2100 mm high - D8; Large No 1 1 1 1.00 1.00 1.00
45mm thick; Size 400mm x 2100 mm high - D8; Small No 1 1 1 1.00 1.00 1.00
45mm thick; Size 900mm x 2100 mm high - D7; Large No 1 1 5 1.00 1.00 1.00
45mm thick; Size 300mm x 2100 mm high - D7; Small No 1 1 5 1.00 1.00 1.00

K Stainless steel kick plates 800mm long x 100mm high No


45mm thick; Size 900mm x 2100 mm high - D1 No 1 2 1 1.00 1.00 1.00
45mm thick; Size 800mm x 2100 mm high - D2 No 1 2 10 1.00 1.00 1.00
45mm thick; Size 900mm x 2100 mm high - D8; Large No 1 2 1 1.00 1.00 1.00
45mm thick; Size 900mm x 2100 mm high - D7; Large No 1 2 5 1.00 1.00 1.00

K Stainless steel kick plates 250mm long x 100mm high No


45mm thick; Size 400mm x 2100 mm high - D8; Small No 1 2 1 1.00 1.00 1.00
45mm thick; Size 300mm x 2100 mm high - D7; Small No 1 2 5 1.00 1.00 1.00

L Stainless steel push/pulll plates size 100mm wide x 300mm long No


45mm thick; Size 900mm x 2100 mm high - D1 No 1 2 1 1.00 1.00 1.00
45mm thick; Size 800mm x 2100 mm high - D2 No 1 2 10 1.00 1.00 1.00
45mm thick; Size 900mm x 2100 mm high - D8; Large No 1 2 1 1.00 1.00 1.00
45mm thick; Size 400mm x 2100 mm high - D8; Small No 1 2 1 1.00 1.00 1.00
45mm thick; Size 900mm x 2100 mm high - D7; Large No 1 2 5 1.00 1.00 1.00
45mm thick; Size 300mm x 2100 mm high - D7; Small No 1 2 5 1.00 1.00 1.00

M Coat hooks No
D1 1 1 10 1.00 1.00 1.00

N Automatic Door closer (Office and washroom main entrance) No


1 1 1 1.00 1.00 1.00

P Approved PVC Symbol- Gents washrooms No


1 1 1 1.00 1.00 1.00

Q Approved PVC Symbol- Ladies washrooms No


1 1 1 1.00 1.00 1.00

R Approved PVC Symbol - Rooms No


1 1 6 1.00 1.00 1.00

Glass and glazing

T 5mm clear sheet glass in panes fixed to timber frame with glazing beads
(measured separately) M2
D1 1 1 10 0.80 0.30 1.00
D2 1 1 1 0.90 0.30 1.00
D7 1 1 5 1.20 0.30 1.00
D8 1 1 1 1.30 0.30 1.00

Prepare and apply one undercoat and two finishing coats of


polyurethane varnish in accordance with manufacturer's
instructions to:

D Wood general surfaces. M2


45mm thick; Size 900mm x 2100 mm high - D1 1 2 1 0.95 2.15 1.00
45mm thick; Size 800mm x 2100 mm high - D2 1 2 10 0.85 2.15 1.00
45mm thick; Size 900mm x 2100 mm high - D8; Large 1 2 1 0.95 2.15 1.00
45mm thick; Size 400mm x 2100 mm high - D8; Small 1 2 1 0.45 2.15 1.00
45mm thick; Size 900mm x 2100 mm high - D7; Large 1 2 5 0.95 2.15 1.00
45mm thick; Size 300mm x 2100 mm high - D7; Small 1 2 5 0.35 2.15 1.00

E Ditto over 200mm but not exceeding 300mm girth M


1 1 1 99.60 1.00 1.00
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT:COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB

E Ditto not exceeding 100mm girth M


1 1 1 160.60 1.00 1.00

F Priming back of the door frames before fixing; 200 -300mm girth M
1 1 1 83.40 1.00 1.00

ELEMENT NO. 7
DOORS 2/7/2

BILL NO.2

ELEMENT NO. 8

INTERNAL FINISHINGS

Floor screed; Cement and sand (1:4); wood floated finish:

A 47mm thick; to receive micro-topping finish (measured separately) M2


1 1 1 235.80 1.00 1.00

45mm thick; Size 900mm x 2100 mm high - D1 No 1 1 1 0.90 0.20 1.00


45mm thick; Size 800mm x 2100 mm high - D2 No 1 1 6 0.80 0.20 1.00
45mm thick; Size 800mm x 2100 mm high - D2 No 1 1 4 0.80 0.15 1.00
45mm thick; Size 900mm x 2100 mm high - D8; Large No 1 1 1 0.90 0.20 1.00
45mm thick; Size 400mm x 2100 mm high - D8; Small No 1 1 1 0.40 0.20 1.00
45mm thick; Size 900mm x 2100 mm high - D7; Large No 1 1 5 0.90 0.20 1.00
45mm thick; Size 300mm x 2100 mm high - D7; Small No 1 1 5 0.30 0.20 1.00

A 40mm thick; to receive floor tiles (measured separately) M2


1 1 1 62.60 1.00 1.00

D Ditto; on staircase landings ditto M2


Staircase 01 1 1 2 1.35 2.70 1.00

E Ditto; on treads 275mm wide ditto M


Staircase 01 1 1 22 1.30 1.00 1.00

F Ditto; to risers 160 mm high ditto M


Staircase 01 1 1 22 1.30 1.00 1.00

G Ditto; to stringer 375mm wide (maximum) M


Staircase 01 1 1 1 14.00 1.00 1.00

H Edge of staircase landing; 200mm wide M


Staircase 01 1 1 2 0.20 1.00 1.00

J Ditto; to receive skirting; 100mm high ditto M


1 1 1 165.80 1.00 1.00

3mm think micro top polymeric-cement floor system

3mm think micro top polymeric-cement floor system applied in multiple


thin coats to a maximum of 3 mm depth; 3 separate layers Primer coat
applied at 1.5 mm depth, a basecoat applied at a nominal 1mm depth
then a finish coat applied at 0.5mm depth. In between each coat the floor
is sanded and vacuumed ready to receive the following coat. Once the
above has been completed a minimum of two sealer coats is applied
1 1 1 235.80 1.00 1.00

Skirting; 100mm high ditto M


1 1 1 163.90 1.00 1.00

Supply and Fix approved ceramic tiles; non-slip; laid in an approved


pattern; bedded in approved adhesive cement and pointed with an
approved tile grout

M Size 450 x 450 x 10 mm thick to floors M2


1 1 1 62.60 1.00 1.00
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT:COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB
D Ditto; on staircase landings ditto M2
Staircase 01 1 1 2 1.35 2.70 1.00

E Ditto; on treads 275mm wide ditto M


Staircase 01 1 1 22 1.30 1.00 1.00

F Ditto; to risers 150 mm high ditto M


Staircase 01 1 1 22 1.30 1.00 1.00

G Ditto; to stringer 375mm wide (maximum) M


Staircase 01 1 1 1 24.90 1.00 1.00

H Edge of staircase landing; 200mm wide M


Staircase 01 1 1 2 0.20 1.00 1.00

J Ditto; to receive skirting; 100mm high ditto M


1 1 1 70.60 1.00 1.00

Wall Tile backing

Screed backing to wall; Cement and sand (1:4); wood floated finish:

C 12mm thick; to receive ceramic wall tiles (measured separately) M2


Total girth 1 1 1 83.78 1.00 3.00
Deductions
D1 -1 1 12 0.80 1.00 2.40
Ddt: W1 -1 1 8 0.90 1.00 1.50

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm second


coat of cement and lime putty (1:10); steel trowelled to:

D Walls M2
External wall area 1 1 1 147.99 1.00 1.00
Internal wall areas x2 1 1 2 315.18 1.00 1.00
Add reveals and jambs for openings; external walls
Add: W1 1 1 8 4.80 0.20 1.00
Add: W2 1 1 6 6.00 0.20 1.00
Add: W3 1 1 3 8.80 0.20 1.00
Add: Opening 1 1 1 10.90 0.20 1.00
Add: Curtain walling 1 1 1 10.41 0.20 1.00
Add: Curtain walling 1 1 1 11.00 0.20 1.00
Add: Curtain walling 1 1 1 11.78 0.20 1.00
Add: Curtain walling 1 1 1 10.50 0.20 1.00
Add: D3 1 1 1 9.00 0.20 1.00
Add: D1 1 1 6 5.60 0.20 1.00
Add: D2 1 1 1 5.70 0.20 1.00
Add: D7 1 1 5 6.00 0.20 1.00
Add: D7 1 1 1 6.10 0.20 1.00
Add: Opening 1 1 2 6.10 0.20 1.00
Add: D1 1 1 4 5.60 0.15 1.00
F Walls M2

E Concrete surfaces (exposed beam and column surfaces) M2

Supply and fix approved glazed ceramic wall tiles; 300mm x 200mm
x 6mm thick; approved colour; bedding and jointing on screed
(measured separately) with approved water proof adhesive; flush
pointing in approved coloured grout to:

F Walls M2

SUNDRIES

Accessories

G Edge trim; plastic; quarter round; setting at edges of wall tile finish M
D1 1 1 12 5.60 1.00 1.00
Ddt: W1 1 1 8 4.80 1.00 1.00

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm second


coat of cement and lime putty (1:10); steel trowelled to:

G Concrete ceiling soffites. M2


Formwork area to margins 1 1 1 52.50 1.00 1.00
Formwork area to maxspan slab 1 1 1 241.40 1.00 1.00
Formwork area to solid slab 1 1 1 6.40 1.00 1.00
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT:COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB

H Staircase landing soffites M2

J Sloping staircase sofffites M2

K Moulded Ceiling cornice as per Architect's detail M

Mild steel Staircase balustrade; welded construction; shop primed


with red oxide

A Horizontal or raking balustrade; 900mm high comprising of; 50mx3mm


thick CHS handrail; 4 No. 25x2mm thick CHS intermediate horizontal
rails; 2/50x6mm thick MS flat balusters, mild steel base plates; all rawl
bolted into concrete; including primer, spray painting wth three coats
gloss oil paint and decorations to approval. M
Staircase 02 waist 1 1 2 3.50 1.00 1.00

A Dado rails; M
1 1 2 3.50 1.00 1.00
1 1 1 14.10 1.00 1.00

Glass railing; 900mm high comprising of: 12mm thick tempered (toughed)
laminated glass fixed to and including: 50mm diameter chrome plated
stainless steel hand rails and and vertical balusters spaced at 900mm
centres; all chrome plated stainless brackets; fixed to walls and staircase
steel frame. M
1 1 1 34.60 1.00 1.00

Prepare and apply one undercoat and two finishing coats of matt
emulsion paint in accordance with manufacturer's instructions to:

B Concrete ceiling soffites. M2

C Staircase landing soffites M2

D Sloping staircase sofffites M2

E Moulded Ceiling cornice as per Architect's detail M

Prepare and apply one undercoat and two finishing coats of silk
vinyl paint in accordance with manufacturer's instructions to:

H Plastered walls and concrete surfaces. M2

Prepare and apply one undercoat and two finishing coats of gloss
oil paint in accordance with manufacturer's instructions to:

J Grilled metal surfaces (balustrade) M2

ELEMENT NO. 8
INTERNAL FINISHINGS

BILL NO.2

ELEMENT NO. 9

EXTERNAL FINISHINGS

20mm thick rendering in Cement and Sand (1:4) mortar; as per


Architect's details; on:

A Walls M2

Prepare and apply approved weatherguard emulsion paint in


accordance with manufacturer's instructions to:

C Rendered surfaces M2

Water proofing the floor and roof slabs

A 4mm thick APP - modified bitumen torch - on horizontal membrane layed


with 50mm side and 75mm end laps on concrete surface by an approved
specialist as recommended by the manufacturer M2

B Ditto but 300mm high along the skirting M

B Parapet Walls M
CLIENT: VEGAS BAR DATE: Friday, April 5, 2024
PROJECT:COMPLETION OF THE PROPOSED COMMERCIAL BUILDING IN KAWEMPE DIVISION, KCCA CALC BY: IB

B Coping M

Cement and sand (1:3) screed as described


in:-

25mm thick paving (laid to falls) finished wood float to membrane


(measured separately)

Quarry Tiles

Selected "Kajjansi" Quarry Tiles laid and bedded in cement and Sand
(1:3) mortar including pointing.

Ditto but 150mm high skirting finished flush

ELEMENT NO. 9
EXTERNAL FINISHINGS

BILL NO.2

ELEMENT NO. 10

FITTINGS

A Alow a provisional sum of Ushs. 18,000,000 for fittings

Allow a sum of Five million to provide a shelter above the staircase


Friday, April 5, 2024
IB
PURPOSE: ESTIMATES
QTY

13.36
0.20
13.56

7.60
7.60

2.27
0.48
2.76

89.60
89.60

8.08
8.08

8.91
8.91

241.40
241.40

241.40
241.40

1,140.75
2,034.00
413.83
3,360.00
303.00
9,052.50
334.13
16,638.20

330.80
330.80
Friday, April 5, 2024
IB

101.40
101.40

142.48
2.16
144.64

52.50
52.50

6.40
6.40

9.10
9.10

7.29
7.29

28.60
28.60

17.60
17.60

14.00
14.00

104.00
104.00

267.30

- 10.80
- 11.34
- 14.40
- 14.70
- 13.23
- 15.00
- 17.34
- 13.50
- 9.00
147.99

9.60
7.20
8.10
24.90
Friday, April 5, 2024
IB

13.23
15.00
17.34
13.50
59.07

333.30

- 11.52
- 2.16
- 14.40
- 3.12
- 6.24
295.86

27.00

- 7.68
19.32

6.60
1.20
7.50
1.60
1.50
18.40

4.40
4.40

3
Friday, April 5, 2024
IB

21.60
22.68
28.80
73.08

19.20
5.70
30.00
6.10
61.00

22.40
22.40

4.80
0.90
6.00
1.30
13.00

3.20
3.20

64.00
11.40
60.00
12.20
75.40

44.00
4.80
30.00
6.40
85.20

1.00

10.00

1.00

1.00

5.00

5.00

1.50
15.00
1.50
1.50
7.50
7.50
34.50
Friday, April 5, 2024
IB

1.00
1.00
-
5.00
-
7.00

10.00
10.00

1.00
10.00
1.00
1.00
5.00
5.00
23.00

2.00
20.00
2.00
10.00
22.00

2.00
10.00
12.00

2.00
20.00
2.00
2.00
10.00
10.00
46.00

10.00
10.00

1.00
1.00

1.00
1.00

1.00
1.00

6.00
6.00

2.40
0.27
1.80
0.39
4.86

4.09
36.55
4.09
1.94
20.43
7.52
74.61

99.60
Friday, April 5, 2024
IB
99.60

160.60
160.60

83.40
83.40

235.80

0.18
0.96
0.48
0.18
0.08
0.90
0.30
238.88

62.60
62.60

7.29
7.29

28.60
28.60

28.60
28.60

14.00
14.00

0.40
0.40

165.80
165.80

235.80
235.80

163.90
163.90

62.60
62.60
Friday, April 5, 2024
IB

7.29
7.29

28.60
28.60

28.60
28.60

24.90
24.90

0.40
0.40

70.60
70.60

251.34

- 23.04
- 10.80
217.50

147.99
630.36

7.68
7.20
5.28
2.18
2.08
2.20
2.36
2.10
1.80
6.72
1.14
6.00
1.22
2.44
3.36
832.11

246.04

217.50

67.20
38.40
105.60

52.50
241.40
6.40
Friday, April 5, 2024
IB
300.30

8.91

9.10

255.83

7.00
7.00

7.00
14.10
21.10

34.60
34.60

300.30

8.91

9.10

255.83

832.11

23.15

341.91

341.91

355.00

86.21
Friday, April 5, 2024
IB
86.21

86.21

355.00

355.00

86.21

18,000,000

5,000,000
Item Unit Qty Rate Amount
USHS USHS

BILL NO.2

ROOF TERRACE

ELEMENT NO. 2

SUPERSTRUCTURE

The prices for the following concrete are to include for


filling into formwork, well vibrating and packing around
rod reinforcement (formwork and reinforcement
measured separately)

Reinforced Insitu concrete grade 25 in:-

A Roof beams including lintels M3 10 Err:509 Err:509

B Columns M3 6 Err:509 Err:509

C 150mm suspended solid roof slab M2 37 Err:509 Err:509

C 100mm thick vertical concrete sun shades M2 43 Err:509 Err:509

Reinforcement

High tensile steel bar reinforcement to BS 4449 as described;


including all bends, hooks, tying wire, distance blocks, spacers
and the like

D Assorted rebar up to 16mm diameter. Kg 2586 Err:509 Err:509

Sawn Formwork as described to:-

E Sides of Columns M2 106 Err:509 Err:509

F Sides and Soffites of roof beams M2 121 Err:509 Err:509

G Soffites of a suspended solid roof slab M2 40 Err:509 Err:509

H Sides of vertical concrete sun shades M2 115 Err:509 Err:509

J Edge of roof slabs; 150mm wide. M 30 Err:509 Err:509

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS Err:509
ELEMENT NO. 2
RC SUPERSTRUCTURE 2/2/2
Item Unit Qty Rate Amount
USHS USHS

BILL NO.2

ROOF TERRACE

ELEMENT NO. 3

ROOFING

ROOF COVERINGS AND CONSTRUCTION

PERGOLA

Provisional quantities

Roof Coverings

A 6mm thick clear sheet polycarbonate with a protective UV layer on the


outer side; including fixing brackets. M2 74 150,000 11,100,000

METAL WORK

Welded metalwork to Structural Engineer's details

Unframed steel works

B Columns; 150x150x4mm SHS M 58 183,000 10,614,000

C Pergola members; 100x150X3mm RHS M 250 114,000 28,500,000

D Purlins; 40x25x2mm RHS M 123 19,600 2,410,800

Sundries

Holding down assemblies

E 16mm Diameter Holding down rawl bolts, 250mm long complete with
nuts and washers; bolting to concrete. No. 96 25,000 2,400,000

Two undercoats : and one coat gloss oil paint or equal and
approved : on metal : to

G Structural steel work; M2 175 10,000 1,750,000

Outdoor patio umbrellas

H Pergola members; 50x200mm RHS unnydaze Outdoor


Cantilever Offset Patio Umbrella - Outside Waterproof Polyester
Shade Steel Pole - Air Vent Cross Base and Crank - Deck
Backyard and Pool - 3000mm diameter; colour to client's
choice.
No. 13 1,050,000 13,650,000

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS 70,424,800
ELEMENT NO. 2
RC SUPERSTRUCTURE 2/2/2
Item Unit Qty Rate Amount
USHS USHS

BILL NO.2

ELEMENT NO. 4

EXTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties set
in horizontal alternate courses:

A 200mm thick M2 217 Err:509 Err:509

B Ditto parapet walls M2 93 Err:509 Err:509

Pre cast concrete grade 25 in:-

F 250mm wide x 120mm thick average weathered coping bedded in


cement and sand 1:4 mortar M 103 25,000 2,575,000

Reinforced Insitu concrete grade 25 in:-

C Moulded concrete window Sill; Section size 250 x 85 x 50mm;


weathered and throated; all as per Architect's details M 20 Err:509 Err:509

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS Err:509
ELEMENT NO. 4
EXTERNAL WALING 2/4/1
Item Unit Qty Rate Amount
USHS USHS
BILL NO.2

ELEMENT NO. 5

INTERNAL WALLS

Brickwork in approved well burnt clay bricks built in cement


mortar (1:4) reinforced with 20 Gauge × 20mm Hoop iron ties set
in horizontal alternate courses:

A 200mm thick Wall M2 24 Err:509 Err:509

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS Err:509
ELEMENT NO. 4
INTERNAL WALING 2/5/1
Item Unit Qty Rate Amount
USHS USHS
BILL NO.2

ELEMENT NO. 6

WINDOWS AND SCREENS

Mild steel casement windows and fly screens

Provide and fix purpose made mild steel casement windows and
window 5mm thick transluscent glass, glazing beads, wash
leather strips, sealing, burglar proofing, fly mesh all ironmongery
and accessories; fixing to blockwork or concrete; all as per
Architect's drawings in:

A Sliding window type W1; Size 2000mm wide x 1800mm high. No. 2 900,000 1,800,000

A Top hung window type W2; Size 600mm wide x 1800mm high. No. 6 432,000 2,592,000

B Louvered window type W3; Size 450mm wide x 1500mm high. No. 5 168,750 843,750

Glass and glazing; fixed to steel with approved silicone sealant

C 5mm thick clear sheet glass and glazing to steel with putty M2 12 80,000 960,000

D Ditto obscure sheet glass diito M2 4 85,000 340,000

Prepare and apply one undercoat and two finishing coats of


gloss oil paint in accordance with manufacturer's instructions to:

F Metal surfaces (Measured flat both sides) M2 35 12,000 420,000

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS 6,955,750
ELEMENT NO. 6
WINDOWS 2/6/1
Item Unit Qty Rate Amount
USHS USHS

BILL NO.2

ELEMENT NO. 7

DOORS

Door frames, linings and mouldings in wrought mahogany as


described to Architect's details:-

A 250mm x 50mm rebated frame; plugging M 52 75,000 3,900,000

B 250mm x 50mm rebated transome M 8 75,000 600,000

C 25 x 50 mm; moulded bevelled architrave M 103 15,000 1,545,000

D 25 x 25 mm; moulded glazing beads. M 44 10,000 440,000

Provide and fix the following standard wrought hardwood solid


panelled door ; all as per Architect's details

E 45mm thick; Size 900mm x 2100 mm high - D2 No 9 750,000 6,750,000

Suppy and Fix the following "ASSA ABLOY UNION" or equal


approved Ironmongery

F 102mm x 76mm Pressed steel butt hinges Prs. 14 25,000 350,000

G Three lever mortice lock complete with furniture No 3 350,000 1,050,000

H Bathroom locks with indicator bolts. No 6 100,000 600,000

J 25mm diameter rubber door stop No 9 25,000 225,000

K Stainless steel kick plates 800mm long x 100mm high No 18 140,000 2,520,000

L Stainless steel push/pulll plates size 100mm wide x 300mm long No 18 85,000 1,530,000

M Coat hooks No 6 25,000 150,000

P Approved PVC Symbol- Gents washrooms No 1 75,000 75,000

Q Approved PVC Symbol- Ladies washrooms No 1 75,000 75,000

S Approved PVC Symbol- Kitchen No 1 75,000 75,000

Glass and glazing

T 5mm clear sheet glass in panes fixed to timber frame with glazing
beads (measured separately) M2 2 80,000 194,400

Prepare and apply one undercoat and two finishing coats of


polyurethane varnish in accordance with manufacturer's
instructions to:

D Wood general surfaces. M2 37 80,000 2,960,000

E Ditto not exceeding 100mm girth M 60 8,000 480,000

F Priming back of the door frames before fixing; 200 -300mm girth M 143 24,000 3,432,000

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS 26,951,400
ELEMENT NO. 7
DOORS 2/7/2
Item Unit Qty Rate Amount
USHS USHS

BILL NO.2

ELEMENT NO. 8

INTERNAL FINISHINGS

Floor screed; Cement and sand (1:4); wood floated finish:

A 40mm thick; to receive floor tile finish (measured separately) M2 60 25,000 1,500,000

C Ditto; to receive skirting; 100mm high ditto M 93 2,500 232,500

Supply and Fix approved ceramic tiles; non-slip; laid in an


approved pattern; bedded in approved adhesive cement and
pointed with an approved tile grout

D Size 450 x 450 x 10 mm thick to floors M2 60 85,000 5,100,000

E to skirtings; 100 mm wide M 131 8,500 1,113,500

SUNDRIES

Accessories

A Edge trim; aluminium strip; quarter round; setting at edges of wall tile
and terrazzo finish M 6 5,000 30,000

Wall Tile backing

Screed backing to wall; Cement and sand (1:4); wood floated


finish:

C 12mm thick; to receive ceramic wall tiles (measured separately) M2 132 16,000 2,112,000

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm second


coat of cement and lime putty (1:10); steel trowelled to:

D Walls M2 265 17,000 4,505,000

E Concrete surfaces (exposed beam and column surfaces) M2 155 17,000 2,635,000

Supply and fix approved glazed ceramic wall tiles; 300mm x


200mm x 6mm thick; approved colour; bedding and jointing on
screed (measured separately) with approved water proof
adhesive; flush pointing in approved coloured grout to:

F Walls M2 132 65,000 8,580,000

To collection 25,808,000
ELEMENT NO. 8
INTERNAL FINISHINGS 2/8/1
Item Unit Qty Rate Amount
USHS USHS
SUNDRIES

Accessories

G Edge trim; plastic; quarter round; setting at edges of wall tile finish M 88 4,500 396,000

Plaster; 12 mm first coat of cement and sand (1:6); 3 mm second


coat of cement and lime putty (1:10); steel trowelled to:

G Concrete ceiling soffites. M2 154 Err:509 Err:509

K Moulded Ceiling cornice as per Architect's detail M 101 Err:509 Err:509

Prepare and apply one undercoat and two finishing coats of matt
emulsion paint in accordance with manufacturer's instructions
to:

B Concrete ceiling soffites. M2 154 12,000 1,848,000

E Moulded Ceiling cornice as per Architect's detail M 101 3,600 363,600

Prepare and apply one undercoat and two finishing coats of silk
vinyl paint in accordance with manufacturer's instructions to:

H Plastered walls and concrete surfaces. M2 420 12,000 5,040,000

Mild steel Staircase balustrade; welded construction; shop


primed with red oxide

Fabricate, deliver to site, and install mild steel handrail 200mm high
overall; including 50mm diameter x 2mm thick handrail; 25x3mm CHS
vertical balustrades at a spacing of 600mm cast in concrete coping
complete with one coat of redoxide primer before delivery; all fixed as
per Architects design and satisfaction to ramp. M 103 55,000 5,665,000

Prepare and apply one undercoat and two finishing coats of


gloss oil paint in accordance with manufacturer's instructions to:

J Grilled metal surfaces (balustrade) M2 62 12,000 744,000

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS Err:509
ELEMENT NO. 8
INTERNAL FINISHINGS 2/8/2

BILL NO.2
Item Unit Qty Rate Amount
USHS USHS

ELEMENT NO. 9

EXTERNAL FINISHINGS

Water proofing the floor and roof slabs

A 4mm thick APP - modified bitumen torch - on horizontal membrane


layed with 50mm side and 75mm end laps on concrete surface by an
approved specialist as recommended by the manufacturer M2 381 75,000 28,575,000

B Ditto but 300mm high along the skirting M 200 22,500 4,500,000

Cement and sand (1:3) screed as described


in:-

C 25mm thick paving (laid to falls) finished wood float to membrane


(measured separately) M2 381 25,000 9,525,000

Quarry Tiles

D Selected "Kajjansi" Quarry Tiles laid and bedded in cement and Sand
(1:3) mortar including pointing. M2 381 70,000 26,670,000

E Ditto but 150mm high skirting finished flush M 200 10,500 2,100,000

20mm thick rendering in Cement and Sand (1:4) mortar; as per


Architect's details; on:

F Walls including parapet walls M2 403 16,000 6,448,000

G Concrete surfaces (beam soffites and exposed columns) M2 30 16,000 480,000

H Edge of the slab; 150mm wide M 104 1,600 166,400

Prepare and apply approved weatherguard emulsion paint in


accordance with manufacturer's instructions to:

J Rendered surfaces M2 433 12,000 5,196,000

K Edge of the slab; 150mm wide M 104 1,200 124,800

Roof access

Galvanised Steel CAT ladders

L Welded Cat ladder 600mm wide and 6000mm long overall to tank
room flat roof anchored to block/ concrete work including painting as
per Architect's details No. 2 550,000 1,100,000

TOTAL CARRIED TO SUMMARY AT THE END


OF ELEMENTS 84,885,200
2/9/1
ELEMENT NO. 9
EXTERNAL FINISHINGS

BILL NO.2
Item Unit Qty Rate Amount
USHS USHS

ELEMENT NO. 10

FITTINGS

A Alow a provisional sum of Ushs. 10,000,000 for fittings Sum 18,000,000

TOTAL CARRIED TO SUMMARY AT THE


END OF ELEMENTS 18,000,000
2/10/1
ELEMENT NO.10
FITTINGS
Item Unit Qty Rate Amount
USHS USHS

Err:509

Err:509

BILL NO.2

THIRD FLOOR

SUMMARY OF ELEMENTS

Element No. 2: R.C. Superstructure Err:509

Element No. 3: Roofing 70,424,800

Element No. 4: External Walls Err:509

Element No. 5: Internal Walls Err:509

Element No. 6: Windows and screens 6,955,750

Element No. 7: Doors 26,951,400

Element No. 8: Internal Finishings Err:509

Element No. 9: External Finishings 84,885,200

Element No. 10: Fittings 18,000,000

TOTAL CARRIED TO GENERAL SUMMARY Shs. Err:509


2/S/E
BILL NO.3: ELECTRICAL
INSTALLATIONS
BILL NO.4: MECHANICAL
INSTALLATIONS
BILL NO.5: DAYWORKS
Item Description Unit Qty. Rate (Ushs) Amount (Ushs)

PROPOSED CLASSROOM AND MULTIPURPOSE HALL BLOCK


TO BE BUILT AT KISINGA TOWN COUNCIL, KASESE DISTRICT

Ms KAGANDA SCHOOL OF NURSING AND WIFERY, KAGANDO


RURAL DEVELOPMENT CENTRE PRIVATE BAY KASESE

BILL NO.6

DAY WORKS

(ALL PROVISIONAL)

In accordance with Clause 53 of the Conditions


of Contract, the Contractor will be paid day work rates
for extra work that cannot properly be measured and
valued, and the Contractor is to insert in the space
provided below the basic rates and costs of labour,
materials and plant as described hereunder:-

LABOUR

A WALLER hours 100 2,000 200,000

B CARPENTER hours 100 1,800 180,000

C SCAFFOLDER hours 100 2,000 200,000

D JOINER hours 100 1,800 180,000

E PLUMBER hours 100 1,500 150,000

F ELECTRICIAN hours 100 2,000 200,000

G PLASTERER hours 100 1,500 150,000

H PAINTER hours 100 1,500 150,000

J LABOURER hours 100 800 80,000

USHS. 1,490,000

To the basic net rates of labour used for work carried


out on dayworks, an addition 25% percent which is to
include for task work and incentive schemes, tools,
standing, scaffolding, supervision, insurace, transport
profit and overheads. 25% USHS. 372,500

To collection of Day works USHS. 1,862,500


6/1

MATERIALS

A Cement Per Tonne 1 600,000 600,000

BILL NO.6 - DAYWORKS SECTION


Item Description Unit Qty. Rate (Ushs) Amount (Ushs)

B Lime Per Tonne 1 1,000,000 1,000,000

C Sand Per Tonne 1 45,000 45,000

D Aggregate (grade 25 - 5mm) Per Tonne 1 140,000 140,000

E Hardcore Per Tonne 1 25,000 25,000

F Steel reinforcement

(i) Mild steel bar Kg 1 4,000 4,000

(ii) High tensile bar Kg 1 4,000 4,000

G BRC A 142 Fabric Mesh Steel Reinforcement 2.4 x 48M Per Roll 1 628,800 628,800

H Wrot timber (Mahogany) Per C.M 1 4,224,000 4,224,000

K Timber formwork Per SQ.M 1 12,500 12,500

K Approved Anti-termite treatment Per 4 Litres 1 475,500 475,500

L Paint, Gloss Per 4 Litres 1 35,000 35,000

N Paint, Emulsion Per 4 Litres 1 52,000 52,000

O Mahogany Varnish Per 4 Litres 1 48,000 48,000

P 200mm diameter uPVC rainwater downpipe 6M Per Each 1 269,200 269,200

Q Ditto bends Per Each 1 58,000 58,000

R Ditto offsets Per Each 1 58,000 58,000

S Ditto watershoe Per Each 1 58,000 58,000

T Fixing brackets Per Each 1 2,000 2,000

U Fixing screws Per Packet 1 5,000 5,000

V 75mm thick x 375mm wide weather/throated cills Per M 1 25,000 25,000

W 4 mm Clear sheet glass Per SQ.M. 1 55,000 55,000

X 5mm clear sheet glass Per SQ.M. 1 65,000 65,000

To collection of Day works USHS. 7,889,000


6/2

A 6mm clear sheet glass Per SQ.M. 1 70,000 70,000

B 4mm Translucent glass Per SQ.M. 1 60,000 60,000

C 5mm Translucent glass Per SQ.M. 1 70,000 70,000

BILL NO.6 - DAYWORKS SECTION


Item Description Unit Qty. Rate (Ushs) Amount (Ushs)
D 6mm Translucent glass Per SQ.M. 1 75,000 75,000

E 6mm one way reflective glass Per SQ.M. 1 180,000 180,000

F Three lever mortice lock Per Each 1 80,000 80,000

G 100mm Pressed steel butt hinge Per Each 1 12,500 12,500

H 100mm long Flush bolt Per Each 1 8,000 8,000

1 Coat Hooks Per Each 1 10,000 10,000

J Indicator Signage Per Each 1 55,000 55,000

K 25mm diameter rubber door stop Per Each 1 10,000 10,000

L Door closer Per Each 1 350,000 350,000

M Solid clay bricks Per 1000 1 300,000 300,000

N 450mm x 200mm x 100mm hollow concrete blocks Per 1000 1 2,700,000 2,700,000

O 450mm x 200mm x 100mm solid concrete block Per 1000 1 2,700,000 2,700,000

P 450mm x 200mm x 150 ditto Per 1000 1 3,000,000 3,000,000

Q 300mm x300mm x 8mm Porcelain floor tiles Per SQ.M. 1 60,000 60,000

R 150mm x 150mm x 6mm white glazed wall tiles Per SQ.M. 1 35,000 35,000

S 230mm x 150mm x 6mm white glazed wall tiles Per SQ.M. 1 35,000 35,000

T 300mm x 300mm x 300mm Maxpan block Per SQ.M 1 35,000 35,000

U 25mm x 3mm earth copper tape Per M 1 38,000 38,000

S 95mmsq bare copper cable Per M 1 43,000 43,000

T 35mmsq bare copper cable Per M 1 14,000 14,000

To collection 9,940,500
6/3

A 6mmsq bare copper cable Per M 1 2,500 2,500

B 2.5mmsq. TWE copper cable Per M 1 1,000 1,000

C 2.5mmsq. SC PVC-I copper cable Per M 1 1,000 1,000

D 4.0mmsq. SC PVC-I copper cable Per M 1 1,500 1,500

E 10.0mmsq. 3C PVC-SWA-PVC copper cable Per M 1 17,500 17,500

BILL NO.6 - DAYWORKS SECTION


Item Description Unit Qty. Rate (Ushs) Amount (Ushs)

F 2.5mmsq 3C PVC-SWA-PVC copper cable Per M 1 6,200 6,200

G 38W TC - DD compact fluorescent lamp Per Each 1 4,600 4,600

H 3 Compartment PVC trunking As crabtree CRABCL1 Per M 1 119,000 119,000

1 6.0mmsq. 4C PVC-SWA-PVC copper cable Per M 1 15,000 15,000

J 10.0mmsq SC PVC-I copper cable Per M 1 4,000 4,000

K 2.5mmsq. 4C PVC-SWA-PVC copper cable Per M 1 7,500 7,500

L 1.5mmsq SC PVC-I copper cable Per M 1 1,000 1,000

M 80mm diameter Galvanised mild steel pipes 6M Per M 1 144,900 144,900

N 100mm ditto bends Per Each 1 161,000 161,000

O 80mm ditto bends Per Each 1 138,000 138,000

P 80 x 80 x 65mm diito tees Per Each 1 158,700 158,700

Q 20mm diameter galvanised steel tubing 6M Per M 1 13,800 13,800

R 32mm diameter ditto Per M 1 32,200 32,200

S 65mm diameter ditto Per M 1 73,600 73,600

T 80mm diameter ditto Per M 1 144,900 144,900

U 15mm diameter galvanised steel bend Per Each 1 4,600 4,600

V 32mm diameter ditto Per Each 1 16,100 16,100

W 65mm diameter ditto Per Each 1 48,300 48,300

To collection 1,116,900
6/4

A 20mm diameter galvanised steel tee Per Each 1 4,600 4,600

B 32mm diameter ditto Per Each 1 11,500 11,500

C 65mm diameter ditto Per Each 1 27,600 27,600

D 20-15mm diameter reducer Per Each 1 2,300 2,300

E 40-25mm diameter ditto Per Each 1 11,500 11,500

F 80-32mm diameter ditto Per Each 1 41,400 41,400

BILL NO.6 - DAYWORKS SECTION


Item Description Unit Qty. Rate (Ushs) Amount (Ushs)
G 15mm diameter Unions Per Each 1 6,900 6,900

H 32mm diameter ditto Per Each 1 13,800 13,800

1 50mm diameter ditto Per Each 1 29,900 29,900

J 110mm diameter uPVC soil pipe 6M Per Each 1 138,000 138,000

K 50mm ditto waste pipe 6M Per Each 1 41,400 41,400

L 32mm ditto Per Each 1 27,600 27,600

M 50mm ditto sweep bend Per Each 1 4,600 4,600

N 32mm ditto Per Each 1 2,300 2,300

O 110mm ditto single branch access Per Each 1 20,700 20,700

P 50mm ditto sweep tee Per Each 1 4,600 4,600

Q 40mm ditto Per Each 1 2,300 2,300

R 110 x 50mm diameter trapped floor gully Per Each 1 57,500 57,500

S 110mm ditto floor gully inlet Per Each 1 57,500 57,500

T 110mm diito wc connector 'P' outlet Per Each 1 34,500 34,500

U 32mm ditto self-releasing bottle trap Per Each 1 75,000 75,000

V 40 x 32mm diameter socket reducer Per Each 1 2,300 2,300

W 50mm Bronze gate valves Per Each 1 264,500 264,500

X 'S' trap WC bowl to BS 3402 Per Each 1 615,000 615,000

To collection 1,497,300
6/5

A 32mm diameter back entry, low pressure flush valve Per Each 1 637,500 637,500

B Single bowl, single drainer stainless steel sink size 2000 x 600mm Per Each 1 1,035,000 1,035,000

C Toilet toll holder size 150 x 150mm Per Each 1 87,400 87,400

D liquid soap dispenser. Per Each 1 115,000 115,000

E Plane glass mirror size 610x 450mm Per Each 1 57,500 57,500

F 25mm diameter black Steel tubing Per M 1 11,500 11,500

G 65mm diameter ditto Per M 1 41,400 41,400

H 50mm ditto flanged tee Per Each 1 52,900 52,900

BILL NO.6 - DAYWORKS SECTION


Item Description Unit Qty. Rate (Ushs) Amount (Ushs)

1 50mm diameter ditto Per Each 1 52,900 52,900

J 150mm ditto bend Per Each 1 287,500 287,500

K 32mm ditto Per Each 1 16,100 16,100

To Collection 2,394,700

COLLECTION

Page 6/2 7,889,000

Page 6/3 9,940,500

Page 6/4 1,116,900

Page 6/5 1,497,300

Page 6/6 2,394,700

22,838,400

To the basic net rates of materials used for work carried


out on dayworks, an addition of 25% which is to
include for unloading and storing as necessary,
the use of hand plant, and machinery etc. available
on site, profit and overheads. 25% USHS. 5,709,600

To collection of Day works 28,548,000


6/6

PLANT

A Portable Compressor with 2 breakers or equivalent


with 1500 mm hoses and reels hours 150 50,000 7,500,000

B Damp Truck (0.75 tonne) hours 150 25,000 3,750,000

C Lorry seven tonne tipper hours 150 35,000 5,250,000

D Concrete Mixer (14/10) complete for weight batch


mixing hours 100 50,000 5,000,000

E 50 mm self priming centrifugal pump with hose and


ancillary equipment hours 20 30,000 600,000

F Concrete Vibrators hours 150 30,000 4,500,000

USHS. 26,600,000

BILL NO.6 - DAYWORKS SECTION


Item Description Unit Qty. Rate (Ushs) Amount (Ushs)
To the basic rates of plant used for work carried out
on dayworks, an addition of 25% per cent, which is
to include for driver and/or attendance, fuel and
consumable stores supervision, insurance, road licence,
profit and overheads. 25% USHS. 6,650,000

To collection of Day works USHS 33,250,000

COLLECTION
COLLECTION

LABOUR 1,862,500

MATERIALS 28,548,000

PLANT 33,250,000

TOTAL CARRIED TO GENERAL SUMMARY 63,660,500


6/6

BILL NO.6 - DAYWORKS SECTION