Professional Documents
Culture Documents
SOW - NEW REAGENT STORAGE WAREHOUSE STRUCTURAL STEEL WORKS - Steel Only
SOW - NEW REAGENT STORAGE WAREHOUSE STRUCTURAL STEEL WORKS - Steel Only
SCOPE OF SERVICES
23 January 2023
SCOPE OF SERVICES
Mutanda Mining has been in care & maintenance for the last 2 years and has since commenced with the restart of the
Phase 2 circuit. In line with the future production plans for Mutanda Mining, we will require additional streams within
the plant to be operational.
The Supply Chain Management (SCM) constructed 6528 sqm of Concrete slab & Base plinth Foundation for the new
Sulphur acid & reagent Lime storage due to the increase in the reagent demand to improve their internal product
management. The Structure & steel works of the new storage warehouse will be erected on the existing Concrete slab
built at the lime area next to the Mining and Project office.
These works under this Contract include, but are not limited to, the following:
4.1 General
Scope of Services
The rates and prices contained in the Contract Price Breakdown will be deemed to be fully inclusive prices for
the prescribed Services to meet design, overheads, drawings, specifications, and requirements, inclusive of all
provisional items:
4.2 Invoicing
Draft invoice format, supporting documents (like completion certificates, etc.), and required
date of receipt
Invoice to be approved in 15 days,
Invoice to be paid in 30 days from date of approval,
The following table provides a summary of typical evaluation criteria and weightings, subject to the
Category of Supply and Risk profile of that category:
The SCM department requested erecting the Steel Works and Electrical on the existing Concrete Slab (sqm
6528 ) at the Lime area next to the Mining Project. The project office approached the SCM to do the
warehouse's design development and construction management. This document will establish the
engineering and construction scope of work and general standard project development practices.
The site Location from the map is Shown in the picture below. The site coordinates are -10° 46’37” S, and 25°
48’46” E.
The Scope of the services to be performed shall include, but not be limited, the following:
I. Steel works: The contractor shall provide equipment, fully qualified and experienced personnel, and
high-quality work per Company Standards to construct the new reagent storage facility on the
Existing lime area, as requested by the project owner.
a) Supply and install the main structure & the secondary structure steel (UB Column 254x146x37kg/m
of 10.140 m - UB Column 254x146x37kg/m of 6.616 m - UB Column 254x146x37kg/m of 4.500 m)
b) Supply and install the Roof Frame Beam long of 40 m in the Middle and 24 m on the extreme
(406*140*39kg/m UB & 305*102*25kg/m UB)
c) Supply and install Knee bracing of 50*50*L –Lip Channel of 750*75*20*2 mm
d) Supply and install the wall and Roof Bracing of 50*50*5
e) Supply and Install the Roof sheeting IBR Galva 0.40 mm. Ensure to use 10 o slope
f) Supply and install all the following accessories where required as per BOQ and Drawing
a) Prepare and build concrete at 30 MPa upon a slab of 5000 mm wide and 150 mm thick with mesh reference
395 shall be installed around the building to keep water away (the contactor shall install a DPM -375 and use a
green sheet or similar on topsoil poisoned mattress before casting concrete
b) Construction of stormwater concrete drains that will be covered by heavy-duty gratings
1. Miscellaneous:
a. The contractor shall ensure that his personnel are trained, competent, and hold the relevant
certifications
b. The contractor shall coordinate with the engineer on the service delivery schedules
c. The contractor shall ensure that the services are performed and completed in accordance with the
agreed service delivery schedule
d. The contractor’s working hours shall be that of MUMI’s working hours unless discussed and agreed
otherwise between MUMI and the contractor
Scope of Services
e. Daily housekeeping and proper barricading are compulsory to secure the site
f. All rubble shall be disposed of as per MUMI environmental policies
g. The contractor shall abide by MUMI’s requirements with regard to safety, permits, inductions, SOP,
etc.
h. A detailed risk assessment (RA) report and mitigation measures are to be provided to MUMI within 7
days of signing a contract. This RA will be maintained, and appropriate actions must be implemented
throughout the project’s life and reviewed weekly at the construction progress meetings. Updates
must be provided daily at 8 am without fail.
i. All contractor personnel presence on site or attendance in the progress meetings shall be recorded
on daily diaries, verified, and signed off by the Engineer or his representative daily.
j. The contractor shall follow the Covid-19 safety protocol as per MUMI standards.
k. The contractor is to erect site signage in accordance with the code of practice that will clearly display
the project and the contractor’s information. MUMI to provide details of the signage board
Contractor to follow MUMI Site compliance standards for all related matters
Include Program of Services with Key Dates
All works to be completed before July 2023.
o BS-British Standards
o EN- European Standards
o IBC-International Building Codes
o ISO-International Organization for Standardization
o ASTM (International)
o American Society for Testing Materials
o SANS-South Africa African Standard
Other recognized international standards are accepted if the requirements specified in this scope of work are
met. The Contractor must clearly indicate in the technical documentation which codes, Standard and Services,
in compliance with the builder’s Quality Assurance Certificate, will be presented for the goods or materials to
be used on the project.