MST-06029 - 0D - Method Statement Cement Treated Base Mixture-Word
MST-06029 - 0D - Method Statement Cement Treated Base Mixture-Word
MST-06029 - 0D - Method Statement Cement Treated Base Mixture-Word
CONTRACTOR:
Project name:
2 0 8 9 1 3 E G C MM A R C O N M S T 0 6 0 2 9 0 D A4
Document title:
1 / 36
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
TABLE OF CONTENT
1. INTRODUCTION ................................................................................................................................................... 4
1.1 PROJECT OVERVIEW.................................................................................................................................................. 4
2. PURPOSE OF THE DOCUMENT ............................................................................................................................. 5
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
LIST OF FIGURES
Figure 1: Freetown Location ............................................................................................................................................... 4
Figure 2: Queen Elizabeth Quay - Site Location .................................................................................................................. 4
Figure 3: General Layout ..................................................................................................................................................... 5
Figure 4: Circulation Plan .................................................................................................................................................... 9
Figure 5: Pavement structure ........................................................................................................................................... 10
Figure 6: Results on CBMG ............................................................................................................................................... 10
Figure 7: Progression of works ......................................................................................................................................... 11
Figure 8: Example of layout point grid .............................................................................................................................. 12
Figure 9: Layer of 0-100m graded crushed rocks.............................................................................................................. 13
Figure 10: Extract from the design of concrete pavement and supplementary report.................................................... 13
Figure 11: Extract from the structural design of Heavy duty pavements for ports and other industries ........................ 14
Figure 12: 2D Laser ........................................................................................................................................................... 15
Figure 13: Example of layout paint grid ............................................................................................................................ 15
Figure 14: plate Test being performed ............................................................................................................................. 16
Figure 15: Additional compaction of subgrade layer ........................................................................................................ 17
Figure 16: Surveyors controlling of 0/40mm layer ........................................................................................................... 18
Figure 17 : Spreading of cement on site ........................................................................................................................... 18
Figure 18: Cement spread on top of the 0/40mm ............................................................................................................ 19
- Figure 19: Mixing with the grader ............................................................................................................................ 20
Figure 20: Grader .............................................................................................................................................................. 21
Figure 20: Drum compactor .............................................................................................................................................. 21
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
1. INTRODUCTION
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
The aim of the PROJECT is to provide greater berthing capacity with the construction of a new berthing structure. The
new structure will include:
Main berth wall of approximate 230m, to accommodate a maximum size vessel of 225m (Panamax);
Dredging of berth to a depth of -13mCD;
Onshore mooring blocks, to moor the mentioned vessel;
Land reclamation, to increase the landside area available for use by the Client; and
Pavement and drainage to remove surface and subsurface water.
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
3. REFERENCE DOCUMENT
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
4. RESSOURCES
Weigth : 12T
- Grader Length of grader blade
3.66m
Weigth : 22T
- Drum compactor Vibration Frequency :
29/35 hz
- Water Bowser
- Total station
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
- Automatic level
5. WORKFORCE
The following table indicates the resources that will be employed by EIFFAGE Genie Civil Marine SL per shift
The access on the cofferdam will be done from the final access of the project (trucks, front loader, mobil crane, exca-
vator, pick-up...). and also from the access on the Eat bund,
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
The following figure indicates the circulation plan that will be respected.
Hinterland
All the platform will be cover of crushed rocks (0-100mm) on top of the reclamation sand in order to guarantee circu-
lation of tire equipment (trucks, trailer, crane…).
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
The following pavement structure for the whole platform had been choose :
This method statement only focuses on road base layer completion activities.
Road base layer is a cement treated material for which EIFFAGE Génie Civil has selected the following materials:
You will found below the results at seven days of the test done on the CBMG with 6%
Water is added to the crush rocks material, water content is done before on the crush rock 0/40mm before the spread
of cement. Following these results, we add water to the mix, and an other water content is done on the mix.
On site the cement content will be increase in order to compensate the loose on the bag and external elements.
A water curing is done after to avoid any problem of shrinkage.
Additional test will be done on site to demonstrate that our methods on site give good results also.
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
Cement treated base mixture will start after soil improvement activities completion and by plot. Progression of works
is shown on the following figure:
Zone 1
Zone 2
- Zone 2: East part, the work will be completed from the West to the East side
In the same time, the installation of paving blocks can start in the zone 1
The mixing is done in function of the gride, the length of the grader blade is not taken in account in the calculation
6. WORK PHASES
As stated before cement treated material will be completed in three layers (18 cm thick each). Several work phases are
required to complete this structure:
1. Control of subgrade layer (land reclamation)
For the following steps there will there two methods :
a. Laying of material
b. Cement spreading
c. Mixing with the grader
d. Compaction and grading
e. Curing
After the completion of the vibro compaction, the plateform will be clean from any soft peat on top of the sand.
Then the reclamation sand will be spread on the top of the platform until the final level by layer of 20cm, using exca-
vator
The sand will be compacted by the simple drum compactor.
After completion of the layer, plate test will be done to verify if the CBR is higher than 5%.
Plate test will be done following a grid of 7m x 7m.
To verify the level of the platform, the altimetry will be check following the grid bellow:
After completion of the layer, plate test will be done to verify if the CBR is higher than 80%.
Plate test will be done following a grid of 7m x 7m.
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
And the same altimetry verification will be done on the top of the platform.
Subgrade layer is controlled after completion of land reclamation improvement and before starting cement treated
base mixture operations. Two items are controlled:
- Altimetry of subgrade
- Bearing capacity: a bearing capacity of EV2 ≥ 80 MPa is required according to calculation note and K ≤ 2.
For a Sand, with a CBR > 5%, is equivalent to an EV2 > 50 Mpa
Figure 10: Extract from the design of concrete pavement and supplementary report
For the sub-base material, regarding the structure we have, we are in the case of classe 2 sub-base material.
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
Following the extract bellow of the Heavy duty pavements for ports and other industries, we should have a test at 100
Mpa.
Figure 11: Extract from the structural design of Heavy duty pavements for ports and other industries
Altimetry control is performed by a team of surveyors. Two different methods can be employed in order to control:
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
- 2D laser
- Layout points grid
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
70%
60% S
éri
50% e2
40%
30%
20%
10%
0%
100 10 1 0,1 0,01
Size of Sieve in mm
A plate test is performed in order to check bearing capacity of subgrade layer. A team of laboratory technicians is re-
sponsible of performing this test.
The first layer of cement treated base mixture is made of a layer 0/40 mm material that will be laid on top of graded
crushed rock. Required thickness of 0/40mm layer will around 180 mm. Stockpile will be located on EIFFAGE Site instal-
lations and transported using front loader and grader.
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
The cement will be in bag, and open following a number of bag per square meters.
The grid will be a 2m x 1.42m, This can be adapted following the results on the crushing test.
On this grid two bags of 50kg will be spread.
The cement bag will be open on top of the previous 0/40mm graded.
After the spread of the cement, the mixing of material (with optional water spreading, depending of moisture content
of material) using the grader is done.
To spread the cement, we will create a gride on top of the 0-40mm, this grid will be calculate following the formula-
tion we have.
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
For the vertical joint, two vertical joints, from two different layers cannot be aligned.
The drum roller will pass on top the joint without vibration.
Cover between two passes of cement spreader will respect SETRA GTS prescriptions as shown hereinafter:
The mixing with the grader depends on the way you give the orientation of the grader blade.
The grader doesn’t only push the material, he is putting the material and the cement on the side of the grader,
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
The mixture is made by the passage of the cement and 0/40 in the blade.
After some passage the mix came homogeneous.
The remaining water will be added following the results of the water content on the 0/40mm.
Water content will taken during the mixing process to confirm the correct water content in the mix.
-
- Figure 19: Mixing with the grader
The mixing is done on the full heigh of the 0/40mm layer, 18cm.
The grader blade has to be oriented with an angle and in the way to remove the mix on the side of the grader.
A grader is employed to complete le level of the layer. When the grader have achieve le final level of the platform, the
compaction can start.
Compaction then starts using drum roller, EIFFAGE expects to need 8 passes in order to meet compaction requirements.
This will be confirmed during trial length.
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
Grading is controlled by a team surveyors. Tolerances regarding altimetry is ± 2 cm. for the two first layer.
The final layer will be graded +/- 5mm.
Density of material is controlled using sand-cone method (ASTM D1556 standard). Compaction requirement is q1 ac-
cording to GTR standard meaning 95% of controlled points must have 𝜌𝑑𝑚≥98%𝜌𝑑𝑂𝑃𝑀
The disclosure of this document by EIFFAGE GENIE CIVIL MARINE confers no proprietary rights on the reader or use
Any information contained hereto is the property of EIFFAGE GENIE CIVIL MARINE and shall not be disclosed and/or communicated to third parties without EIFFAGE GENIE CIVIL MARINE express consent.
NECTAR BULK TERMINAL BERTH EXTENSION Date : 25/01/23
In case of lack of density additional passes of tire roller are applied until requirements are fulfilled.
6.4.3 Curing
Water will be spread on the layer for 3 days using a water bowser. Frequency of water spreading will be adjusted ac-
cording to weather conditions.
The curing will be done until the CBMG achieved the 28 days strength.
A bituminous emulsion will be spread on top of the last layer of the CBMG.
6.5 SECOND LAYER AND THE THIRD LAYER OF CEMENT TREATED BASE MIXTURE
Second layer of cement treated is completed at least 3 days after completion of 1st layer to ensure curing. The same
operations described previously will be repeated.
Crushing test will be done to confirm that we have the results to continue the next steps.
From the test we have done, we see that at 7 days, we have the results expected.
7. APPENDIX