Page 1
Takeoff Sheet
Project :- Residence (G+1)
Location :- AKSUM-
Client:- Timnit G/senbet kahsay
Consultant :- G4 Engineering PLC
T.G L*W*H Squ Unit Description T.G L*W*H Squ Unit Description
1.5. Back Fill 1 4.51
1 179.375 m³ Detto as pie Excavation 0.7 3.16 m² along axis-2
1 107.45 m³ Detto as Bulk Excavation 1 3.81
1 80.87 m³ Detto as Trench Excavation 0.7 2.67 m² along axis-3
Deduction 1 1.35
23.376 m³ Total volume of concrete for footing pad 0.7 0.95 m² along axis-3'
2.21 m³ Total volume of concrete for footing columen 1 1.6
40.97 m³ Total volume of Masonry wall 0.7 1.12 m² along axis-4
301.139 m³ Total Volume of Backfill 1 3.61
246.81 m³ 1.6 cartaway 0.7 2.53 m² along axis-4'
2.concrete work 1 1.98
2.1 lean concrete 0.7 1.39 m² along -4'
7 2 A. under footing pad 74.86 m² Total
2 28 m² F1 2.2 C-25 concrete
1 1.4 A for pad
1.4 1.96 m² F2 7 2
2 1.8 2
1.8 6.48 m² LF1 0.5 14 m³ F1
3 1.2 1 1.4
1.2 4.32 m² LF2 1.4
1 1.2 0.4 0.784 m³ F2
1.2 1.44 m² LF3 2 1.8
1 1 1.8
1 1 m² LF4 0.7 4.536 m³ LF1
1 6.51 3 1.2
B. under masonry 1.2
1 6.51 0.6 2.592 m³ LF2
0.7 4.557 m² along axis-D 1 1.2
1 7.48 1.2
0.7 5.236 m² along axis-C' 0.6 0.864 m³ LF3
1 1.13 1 1
0.7 0.791 m² along axis-C 1
1 3.33 0.6 0.6 m³ LF4
0.7 2.331 m² along axis-B 23.376 m³ Total
1 5.93 B for foundetion column
0.7 4.151 m² along axis-A 3 0.2
1 3.99 0.4
0.7 2.793 m² along axis-1 2 0.48 m³ F1-C1
Page 2
Takeoff Sheet
Project :- Residence (G+1)
Location :- AKSUM-
Client:- Timnit G/senbet kahsay
Consultant :- G4 Engineering PLC
T.G L*W*H Squ Unit Description T.G L*W*H Squ Unit Description
1 0.2 1 5.13 Along axis-A
0.4 0.25
2 0.16 m³ F1-C3 0.4 0.513 m³ GFB7
3 0.3 1 6.29 Along axis-1
0.3 0.25
2 0.54 m³ F1-C6 0.4 0.629 m³ GFB8
1 0.2 1 11.11 Along axis-2
0.4 0.25
1 2.1 0.17 m³ F2-C1 0.4 1.11 m³ GFB9
0.2 1 10.86 Along axis-3
0.4 0.25
1.7 0.14 m³ LF1-C1 0.4 1.09 m³ GFB10
1 0.3 2 2.45 Along axis-3'
0.3 0.25
1.7 0.15 m³ LF1-C2 0.4 0.49 m³ GFB11
1 0.4 1 5.025 Along axis-4
0.4 0.25
1.8 0.29 m³ LF2-C8 0.4 0.5025 m³ GFB12
2 0.2 1 4.135 Along axis-4'
0.4 0.25
1.8 0.29 m³ LF2-C4 0.4 0.4135 m³ GFB13
2.21 m³ Total 9.16 m³ Total
2.3 Ground floor beam concrete work 2.4 Ground floor slab concrete
1 14.01 Along axis-D Total area of the ground floor
0.25 131.883 slab 131.883 m²
0.4 1.40 m³ GFB1 0.10 13.19 m³ Total
1 9.005 Along axis-C' 3 form work
0.25 A. forfooting pad
0.4 0.90 m³ GFB2 7 8.1
1 5.255 Along axis-C 0.5 28.35 m² F1
0.25 1 5.7
0.4 0.53 m³ GFB3 0.4 2.28 m² F2
1 10.93 Along axis-B 2 3.78
0.25 0.7 5.292 m² LF1
0.4 1.09 m³ GFB5 3 4.9
1 3.305 Along axis-B-C 0.6 8.82 m² LF2
0.25 1 4.9
0.4 0.33 m³ GFB4 0.6 2.94 m² LF3
1 5.8 Along axis-A 1 4.1
0.25 0.7 2.87 m² LF4
0.4 0.58 m³ GFB6 50.55 m² Total
Prepared By:___________________ Checked By:____________________
Page 3
Date & Sign:___________________ Date & Sign:____________________
Takeoff Sheet
Project :- Residence (G+1)
Location :- AKSUM-
Client:- Timnit G/senbet kahsay
Consultant :- G4 Engineering PLC
T.G L*W*H Squ Unit Description T.G L*W*H Squ Unit Description
B for foundetion column 1 4.8
3 1.3 0.4 1.92 m² along axis-3'
2 7.80 m² F1-C1 1 8.7
1 1.3 0.4 3.48 m² along axis-4
2 2.6 m² F1-C3 1 13.82
3 1.3 0.4 5.53 m² along axis-4'
2 7.8 m² F1-C6 69.31 m² Total
1 1.3 4.Hard Core
2.1 2.73 m² F2 1 129.676 Total area of hard core
1 1.3 0.25 32.42 m³ Total volme of hard core
1.7 2.21 m² LF1-C1 5. Masonry work
1 1.3 1 0.75 Along Axis -D
1.7 2.21 m² LF1-C2 8.01 6.01 m²
1 1.7 1 0.75 Along axis -C'
1.8 3.06 m² LF2-C8 5.78 4.34 m²
2 1.3 1 0.75 Along Axis-C
1.8 4.68 m² LF2-C4 2.13 1.60 m²
1 1.3 1 0.75 Along axis-B
1.8 2.34 m² LF3-C1 4.83 3.62 m²
1 1.7 1 0.75 Along Axis-A
1.8 3.06 m² LF4-C8 6.93 5.20 m²
35.43 m² Total 1 0.75 Along Axis-B&C
1 C form work for grade beeam 2.18 1.64 m²
26.97 1 0.75 Along Axis -1
1 0.4 10.79 m² along axis -D 4.44 3.33 m²
17.86 1 0.75 Along Axis-2
1 0.4 7.14 m² Along axis -c' 6.01 4.51 m²
9.535 1 0.75 Along Axis -3
1 0.4 3.81 m² Along-c 3.91 2.93 m²
20.16 1 0.75 Along Axis-3'
1 0.4 8.06 m² Along axis-B 1.6 1.20 m²
5.935 1 0.75 Along Axis-4
1 0.4 2.37 m² Along axis-B-C 2.1 1.58 m²
21.96 1 0.75 Along Axis-4'
1 0.4 8.784 m² Along axis-A 6.71 5.03
13.23 40.97 m² Total
1 0.4 5.292 m² Along axis-1
22.195
1 0.4 8.878 m² Along axis-2
21.92
0.4 8.77 m² Along axis-3
Prepared By:___________________ Checked By:____________________
Page 4
Date & Sign:___________________ Date & Sign:____________________
Takeoff Sheet
Project :- Residence (G+1)
Location :- AKSUM-
Client:- Timnit G/senbet kahsay
Consultant :- G4 Engineering PLC
T.G L*W*H Squ Unit Description T.G L*W*H Squ Unit Description
B SUPER STRUCTURE 1 12.03
1.CONCRETE WORK 0.3
1.2 Concrete work for column 0.3 1.0827 m³ FB4-Along axis-Along axis-B
10 0.2 1 11.16
0.4 0.275
2.76 2.21 m³ C1 0.55 1.68795 m³ FB5'' Along axis-A
2 0.3 1 5.33
0.3 0.3
2.76 0.50 m³ C2 0.3 0.48 m³ VERENDA
3 0.2 1 3.5
0.4 0.6
2.76 0.66 m³ C3 0.3 0.63 m³ FB6 Along axis-1
3 0.2 1 10.86
0.35 0.6
2.76 0.58 m³ C4 0.3 1.95 m³ FB7 Along axis-2
1 0.3 1 6.9
0.3 0.3
2.76 0.25 m³ C5 0.3 0.62 m³ FB7' Along axis-1-2
10 0.3 1 2.5
0.3 0.3
2.76 2.484 m³ C6 0.3 0.22 m³ FB8' Along axis-2-3
2 0.3 1 11.7
0.3 0.6
2.76 0.50 m³ C7 0.3 2.11 m³ FB8' Along axis-3
2 0.4 1 5.16
0.4 0.6
2.76 0.88 m³ C8 0.3 0.93 m³ FB9 Along axis-4
8.06 m³ Total 1 4.4
1.3 beam concrete work 0.6
1 5.07 0.3 0.79 m³ FB10 Along axis-4
0.3 1 4.4
0.3 0.46 m³ FB1 along axis-D 0.6
1 5.33 0.3 0.792 m³ FB10 along axis-4'
0.3 1 5.46
0.3 0.48 m³ fb1' along axis-D 0.3
1 9.28 0.2 0.3276 m³ FB9' Along axis-4'
0.3 13.88 m³ Total
0.3 0.84 m³ FB2 along axis-C' 1.4 Edge beam
1 5.33 1 3.6
0.3 0.2
0.3 0.48 m³ FB3-Along axis-C 0.3 0.22 m³ Along axis-2-3
1 2.18
Prepared By:___________________ Checked By:____________________
Page 5
Date & Sign:___________________ Date & Sign:____________________
Takeoff Sheet
Project :- Residence (G+1)
Location :- AKSUM-
Client:- Timnit G/senbet kahsay
Consultant :- G4 Engineering PLC
T.G L*W*H Squ Unit Description T.G L*W*H Squ Unit Description
0.2 1 4.525 RB-10 Along axis -4'
0.3 0.13 m³ Along axis-1-2 0.25
1 4.383 0.35 0.40 m³
0.2 1 5.535 RB-11 Along axis -4-4'
0.3 0.26298 m³ Along axis-3-4 0.25
0.61 m³ Total 0.35 0.4843125 m³
1.5 For Top Tile Beam 2 4.34 RB-12 above +11.12
2 5.23 RB-1 Along axis-D&C 0.25
0.25 0.35 0.7595 m³
0.35 0.91525 m³ 2 2.4 RB-13 above +11.12
1 7.3 RB-2 Along axis -C' 0.25
0.25 0.35 0.42 m³
0.35 0.64 m³ 9.38 m³ Total
1 12.03 RB-3 Along axis-B 1 1.6 First Floor Slab
0.25 68.15
0.35 1.05 m³ 0.15 10.2225 m³ Total volume of floor slab
1 10.67 RB-4Along axis-A 1.7 Roof Slab
0.25 9.43
0.35 0.93 m³ 0.15 1.4145 m³ Total volume of Roof slab at +8.18
1 4.295 RB-5 Along axis-A 11.64 m³ Total
0.25 1.8 Stair Case
0.35 0.375813 m³ Landing Beam
1 8.363 RB-6 Along axis -2 1 2.5 SCB-1 Along axis -4
0.25 0.25
0.35 0.73 m³ 0.4 0.25 m³ Total
1 4.1 RB-6' Along axis -1&2 1 2.5 landing
0.25 0.74
0.35 0.36 m³ 0.17 0.3145 m³ Total
1 4.035 RB-7 Along axis -2-3 bottom flight
0.25 1 3.08
0.35 0.353063 m³ 1.2
1 10.11 RB-8 Along axis -3 0.17 0.62832 m³ along section 1-1&2-2
0.25 0.62832 m³ Total
0.35 0.884625 m³ steps
1 12.26 RB-9 Along axis -4 9 0.023
0.25 1.2 0.2484 m³ section 1-1
0.35 1.07275 m³
Prepared By:___________________ Checked By:____________________
Page 6
Date & Sign:___________________ Date & Sign:____________________
Takeoff Sheet
Project :- Residence (G+1)
Location :- AKSUM-
Client:- Timnit G/senbet kahsay
Consultant :- G4 Engineering PLC
T.G L*W*H Squ Unit Description T.G L*W*H Squ Unit Description
9 0.023 2 1.3
1.2 0.2484 m³ section 2-2 2.7 7.02 m² C7
0.4968 m³ Total 2 1.7
1.9.Gutter 2.76 9.384 m² C8
1 5.23 Along Axis-D 114.036 m² Total
0.14 0.72 m³ B for intermidet beam
1 7.05 Along Axis-C' 1 13.16 FB -1
0.14 0.97 m³ 0.395 5.1982 m² Along axis-D
1 1.40 Along Axis-B 1 13.74 FB -1'
0.14 0.19 m³ 0.395 5.4273 m² Along axis-D
1 5.65 Along Axis-A 1 23.04 FB-2
0.14 0.77 m³ 0.65 14.976 m² Along axis-C
1 5.33 Along axis belo- A 1 12.89 FB-3
0.14 0.73 m³ 0.65 8.3785 m² Along axis-C
1 4.85 Along axis-1 1 31.09 FB-4
0.14 0.66 m³ 0.65 20.2085 m² Along axis-B
1 4.31 Along axis-2 1 5.33 FB-5'
0.14 0.59 m³ 0.395 2.10535 m² Along axis-A
1 4.40 Along axis-3 1 27.79 FB-5''
0.14 0.60 m³ 0.395 10.97705 m² Along axis-A
1 13.51 Along Axis -4' 1 10.7 FB-6
0.14 1.85 m³ 0.395 4.2265 m² Along axis-1
7.09 m³ Total 1 33.33 FB7
2 formwork 0.65 21.6645 m² Along axis-2
A for elvation column 1 21.53 FB7'
10 1.3 0.395 8.50435 m² Along axis-1-2
2.76 35.88 m² C1 1 36.93 FB-8
0.65 24.0045 m² Along axis-3
2 1.3 1 15.63 FB-9
2.76 5.52 m² C2 0.65 10.1595 m² Along axis-4
2 1.3 1 17.13 FB-9'
2.76 7.176 m² C3 0.395 6.76635 m² Along axis-4-4'
3 1.2 1 13 FB-10
2.76 9.936 m² C4 0.65 8.45 m² Along axis-4
1 1.2 1 14.1 FB-10'
2.7 3.24 m² C5 0.65 9.165 m² Along axis-4
10 1.3 160.2116 m² Total
2.76 35.88 m² C6 C.for edge beam
Page 7
Date & Sign:___________________ Date & Sign:____________________
Takeoff Sheet
Project :- Residence (G+1)
Location :- AKSUM-
Client:- Timnit G/senbet kahsay
Consultant :-G4 Engineering PLC
T.G L*W*H Squ Unit Description T.G L*W*H Squ Unit Description
1 10.83 EB-1 1 7 RB-13
0.395 4.27785 m² Along axis -2-3 0.85 5.95 m² Along axis-4
1 8.667 EB-2 272.9015 m² Total
0.395 3.423465 m² Along axis -1-2 E. form work for slab
1 12.346 EB-3 1 63.81 m² for slab
0.395 4.87667 m² Along axis-A-B 1 3.87 for slab of +8.18
12.57799 m² Total 2.6 10.062 m²
D.For Top Tile Beam 73.872 Total formwork of slab
1 14.565 RB-1 F. for stair case
1 14.565 m² Along axis-D For Landing Beam
1 21.957 RB-2 1 8.1 scB1
1 21.957 m² Along axis-c' 0.395 3.1995 m² Total
1 33.11 RB-3 Soffit form work
1 33.11 m² Along axis-B 1 2.5
1 13.965 RB-1 0.74 1.85 m² for landing
1 13.965 m² Along axis-C 2 3.1 For B.Flight along section 1-1 & 2-2
1 28.804 m² RB-4 1.2 7.44 m²
1 28.804 m² Along axis-A 9.29 m² Total
1 14.431 RB-5 For Steps
1 14.431 m² Along axis-blow-A Area of one Step=0.24 m²
1 25.105 RB-6 36 0.023 0.828 m² Along Section 1-1 & 2-2
1 25.105 m² Along axis-2 0.828 m² Total
1 12.03 RB-7 Side Form work for the flight
1 12.03 m² Along axis-b/n 2&3 4 3.1 Along section 1-1 and 2-2
1 36.67 RB-8 0.17 2.108 m² Total
1 36.67 m² Along axis-3 For Risers
1 36.78 RB-9 20 1.2 Along section 1-1 and 2-2
1 36.78 m² Along axis-4 0.15 3 m² Total
1 3.95 RB-10 G.formwork for gutter
1 3.95 m² Along axis-4' 8.61 m² Along axis-D
1 16.58 RB-11 11.57 m² Along axis-C'
1 16.58 m² Along axis-4' 2.41 m² Along axis-B
1 12.26 RB-12 9.29 m² Along axis-A
0.85 10.421 m² Along axis-C 7.94 m² Along axis-1
1 12.36 RB-12 7.13 m² Along axis-2
0.85 10.506 m² Along axis-B 7.27 m² Along axis-3
1 7.05 RB-13 22.05 m² Along axis-4'
0.85 5.9925 m² Along axis-3 76.27 m² Total
Page 8
Date & Sign:___________________ Date & Sign:____________________
Takeoff Sheet
Takeoff Sheet
Project :- Residence (G+1)
Location :- AKSUM-
Client:- Timnit G/senbet kahsay
Consultant :- G4 Engineering PLC
3.Block Work 3.2.For the First Floor
3.1.For the Ground Floor i. 20 cm thick HCB
i. 20 cm thick HCB A.External
A.External 1 35.46
1 29.14 2.76 97.8696 m²
2.76 80.4264 m² B.Internal
B.Internal 1 25.13
1 16.72 2.76 69.3588 m²
2.76 46.1472 m² 167.2284 m² Total
126.5736 m² Deducation
Deduction for Door and Window 5 0.9
1 0.9 2.1 9.45 m² Door
2.1 1.89 m² Door 2 0.86
1 0.1 0.6 1.032 m² window
0.6 0.06 m² window 2 0.76
1 1.5 0.6 0.912 m² window
1.6 2.4 m² window 11.394 m² Total
4.35 m² Total 155.8344 m² Net Area of 20cm HCB
122.2236 m² Net Area of 20cm HCB ii. 15Cm thick HCB
ii. 15Cm thick HCB A.Internal
A.Internal 1 24.13
1 8.93 2.76 66.5988 m²
2.76 24.6468 m² Deducation
Deduction 3 2.1
3 0.9 0.9 5.67 m² door
2.1 5.67 m² Door 1 1.25
1 1.5 2.1 2.625 m² door
1.6 2.4 m² window 1 1.5
8.07 m² Total 1.6 2.4 m² window
16.5768 m² Net Area of 15cm HCB 10.695 m² Total
iii. 10cm thick 55.9038 m² Net Area of 15cm HCB
External iii. 10 Cm thick HCB
1 3.62 1 External
2.76 9.9912 m² 8.51
internal 2.76 23.4876 m² Total
1 5.85
2.76 16.146 m²
26.1372 m² Total
Page 9
Date & Sign:___________________ Date & Sign:____________________
Takeoff Sheet
Takeoff Sheet
Project :- Residence (G+1)
Location :- AKSUM-
Client:- Timnit G/senbet kahsay
Consultant :- G4 Engineering PLC
4. Roof work 12 3.75 45 ml Vertical for Right Side
A. Along the left direction to the 12 6.51 78.12 ml Diagonal for Right side
front elevation direction having 257.28 ml Total
1 99.04 m² 5cm overlap in both directions. C. zigba purlin with 90cm
B. Along the Right direction to the spacing
front elevation direction having 16 14.11 225.76 ml Total
1 101.981 m² 5cm overlap in both directions. D. 8cm thick chipwood
201.021 m² Total area of decra required 1 Axis (D,C&3,4)
4.2.Gutter 4.577
Along axis -D 8.9 40.7353 m²
1 5.228 ml 1 Axis (C',B&1,2)
Along axis- C' 1.15
1 7.05 ml 4.202 4.8323 m²
Along axis-B Axis (C',B&2,3)
1 1.4 ml 1 5.348
Along axis-A 4.202 22.472296 m²
1 5.65 ml Axis (C,B&3,3')
Along axis-Below A 1 3.896
1 5.33 ml 2.45 9.5452 m²
Along axis-1 Axis (B,A&2,3)
1 4.85 ml 1 5.098
Along axis-2 8.016 40.865568 m²
1 4.31 ml Axis (B,A&3,4)
Along axis-3 1 3.896
1 4.4 ml 4.008 15.615168 m²
Along axis-4' Axis (B,A)
1 13.51 ml 1 0.382
51.728 ml Total 4.008 1.531056 m²
4.3 down pipe Axis (A&3,3')
9 6.18 55.62 Total 1 4.278
5.Carpentry and Joinery work 2.4 10.2672 m²
5.1 Truss and stractural members 145.864088 m² Total
A. dia 10-12cm eucalyptus for a 6. Metal Work for hand rail and stair
12 7.009 84.108 ml total of trusses having 1200 mm 6.1 Alumium hand rail
12 7.228 86.736 spacing 1 10.464 10.464 m² Total
ml Total Inclined truss meember 6.2 for stair case
12 13.81 165.72 ml Total horizontal truss member 1 2.21
336.564 ml Total 0.88 1.9448 m² along section 1-1
B.dia 8-10 cm eucalyptus 1 2.21
Page 10
12 4.59 55.08 ml Vertical for Left Side 0.88 1.9448 m² along section 2-2
12 6.59 79.08 ml Diagonal for Left side 14.3536 m² Total
Page 11
Location :- AKSUM-
Client:- Timnit G/senbet kahsay
Consultant :- G4 Engineering PLC
Page 12
Prepared By:___________________ Checked By:____________________
Date & Sign:___________________ Date & Sign:____________________
Page 13
Page 14
(54.33)
#NAME?
Page 15
Bar Schedule
Project :- Residence (G+1)
Location:- AKSUM
Client:- Timnit G/senbet kahsay
:- Ephi Engineering
Consultant Consultant PLC PLC
:- Y G4 Engginering
Type of No of Total length
Item Location Dia No.bar T.Length Shape
stracture Element Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20
Bar Schedule
Project :- Residence (G+1)
Location :- AKSUM
Client:- Timnit G/senbet kahsay
G4 yalfal Engineering
Consultant :- Engineerig PLC PLC
Type of No of Total length
Item Location Dia No.bar T.Length Shape
stacture Element Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20
1 Gutter sec-3 1 12 31 1 2.75 85.25
2 2 12 31 1 8.5 263.50
3 sec-4' 1 12 91 1 2.75 250.25
4 2 12 91 1 8.5 773.50
BIRR
TOTAL (B)
TOTAL
BIRR
(A+B)
Summary
AMOUNT
46,050.86
52,661.74
85,236.38
28,680.75
8,032.47
220,662.19
100,032.14
88,523.58
280,427.93
49,711.62
53,647.64
27,177.82
10,494.92
152,462.39
90,739.84
26,087.69
1,295,146.02
1,515,808.22
For Septic tank
Takeoff Sheet
Project :- Residence (G+1)
Location :- Akusm
Client:- Tmnit G/Senbet
Consultant :- G4 Engineering PLC
T.G L*W*H Squ Unit Description
1.Excavation and Earth work
1 3.60 1.1. Pit Excavation
2.30
2.50 20.70 m³ For Septic tank
2. Concrete Work
2.1. C-5 Lean Concrete
1 3.10 C. Under septic tank
1.80 5.58 m²
2.2. C-25 Concrete
1 3.10 Bottom slab
1.80
0.20 1.12 m³