Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

F E A T U R E A R T I C L E

Turbine Generator Rotor and Stator


Winding Hipot Testing
Key words: insulation testing, rotor winding, stator winding, turbine generator, hipot test

Introduction Relu Ilie


An important component of synchronous machines is the
electrical insulation that is used in both the stator and the rotor
Israel Electric Corporation, Israel
windings to insulate the copper conductors from ground. The G. C. Stone
stator winding insulation is exposed to continuous high ac volt-
ages of many kilovolts in service, whereas the rotor windings Qualitrol-Iris Power, Canada
(sometimes called field windings) in synchronous machines
operate under dc voltage, at voltages that are usually around
a few hundred volts. If the stator winding ground insulation is
punctured, the machine is automatically removed from service This article reviews the literature
by protective relaying. If the ground insulation fails in a rotor
winding, most commonly the machine is tripped, although it is
and international and national stan-
possible under some circumstances for the machine to continue dards concerned with factory and
to operate with a ground fault, but at great risk of catastrophic maintenance hipot testing of turbine
damage if a second fault were to develop. Thus, machine opera-
tors need assurance that the rotor and stator winding insulation generators, although much of the ar-
will not fail in service. ticle is also applicable to hydrogen-
One of the most common tests to ensure insulation reliabil-
ity is the insulation resistance test, where a relatively low dc
erators and synchronous motors.
voltage is applied to the insulation [1]. The insulation resistance
test ensures there are no shorts in the insulation, but it can miss
significant flaws that have not yet completely bridged the insula-
tion. For more than 100 years, the method used to detect incipi-
ent faults and weaknesses has been to temporarily apply a higher There is a considerable amount of literature available on hipot
than operating voltage to stator and rotor windings. The purpose testing machines, including how to do the test, the test voltage,
is to assure motor and generator operators that the main ground risks associated with hipot testing, as well as surveys of machine
insulation in those windings can be placed in service with lit- manufacturers and machine owners about test levels and under
tle risk of a failure. This most fundamental of insulation tests what circumstances they perform hipot testing [2]–[52]. In ad-
goes by various names, including high-potential testing (often dition, as discussed below, international and national standards
colloquially referred to as hipot testing), overvoltage testing, organizations have published many test guides and standards
withstand testing, or proof testing. The principle is that if the concerned with hipot testing. Most of this literature has focused
insulation can withstand a temporarily applied voltage higher on hipot testing of stator winding insulation. Often rotor wind-
than occurs in service, then an in-service failure during the fore- ing hipot testing receives minor or even no attention. The result
seeable future is unlikely. The hipot test is often performed after is that operators of machines have inconsistent or little guidance
critical winding manufacturing steps, just before the winding is on hipot testing of the rotor windings that have been in service.
first placed into operation, and sometimes during periodic shut- In this article, we review the literature and standards con-
downs of the motor or generator. Hipot testing is done using cerned with rotating machine hipot testing. First hipot testing
power frequency (50/60 Hz), dc or 0.1 Hz (very low frequency) after machine manufacture (factory hipot testing) is discussed.
voltage. Then we review the situations for testing once the machine has

March/April — Vol. 28, No. 2 0883-7554/12/$31/©2012/IEEE 29


seen service, usually called maintenance hipot testing, and af- “[generator] field windings are subjected to higher mechanical
ter a winding repair. Although the focus is on rotor windings, and thermal stresses.” The NEMA standard [4] is also
for completeness this review contrasts the situation with stator inconsequent, indicating this lower test value for brushless
winding hipot testing. Because the rotor winding is often sup- exciters of synchronous motors.
plied from a dc “exciter,” the following also makes reference to
the hipot voltages performed on exciter windings. Most of the History and Practices
following discussion is concerned with high-speed turbine (tur- From a review of the literature, it seems the hipot test volt-
bo) generators larger than 10 MVA, with stator voltages of 6 kV age levels have been established empirically and set by a trial-
or higher, and rotors rated above 100 V. However, the discussion and-error process according to manufacturing and maintenance
is also relevant to hydrogenerators and synchronous motors. experience.
Stator. In the United States, the one-minute ac insulation test on
finished machines was standardized 110 years ago. Initially, the
Factory Proof Hipot stator was tested at twice the rated voltage; later on, other values
were tried [6], [7]. Similarly, the 2 UsN test voltage was initially
Origin and Purpose
used in Europe based on old German and British standards [8].
This is a factory acceptance test, unanimously required by
Beginning in 1914, the American standards all stipulated the test
all standards for any new machine windings, and is intended
level given by equation (1) [7]. The seventh edition (1969) of
to prove manufacturing quality control. The final hipot test is
IEC 34-1 mentioned UsT = 2 UsN + 3 kV. From 1983 (eighth
normally preceded by higher voltage hipot tests, performed dur-
edition), the same level as equation (1) was adopted by IEC.
ing the manufacturing process, and for which no standards are
Figure 1 shows the historical changes in stator hipot levels.
available. These are not discussed here, but a survey of what
Standard ANSI C50.10 has allowed a dc hipot as an alternate
manufacturers use is presented in [36].
test since 1965, whereas IEC 60034-1 permitted dc beginning in
Current Standards its edition 10.2 (1999).
The traditional high-potential tests as specified by standards Rotor. According to old American standards, the rotor was tested
are performed with ac voltages (50/60 Hz) for 1 minute, on both at 1,500 Vac if UrN ≤ 400 V and at 2,000 Vac if rated higher [6].
stator and rotor, even though the rotor winding is operated under In 1913, [8] mentioned testing at 3 times the rated voltage in
dc voltage. the UK and Germany, with a minimum of 1,000 to 1,500 Vac.
Stator. According to standards IEC 60034-1 [2] and IEEE/ANSI In 1914, the USA testing level was changed to 10 UrN but not
C50.13 [3], the stator hipot ac voltage UsT shall be less than 1,500 Vac nor more than 3,500 Vac [7]. Standard ANSI
C50.10 (1965) stipulated the 10 UrN value without any upper
UsT = 2 UsN + 1 kVac, (1) limit. The seventh edition of IEC 34-1 and earlier required the
10 UrN factor but a 3,500 Vac maximum level. From 1977 [9],
where UsN is the stator rated line-to-line ac voltage (in kV rms)
using IEC terminology. In the IEEE standards, UsN is referred
to as E. By these standards, for windings rated 6 kV or above
(“when ac equipment is not available” [2]), an alternative dc
hipot may be agreed instead, at 1.7 times the ac value in equa-
tion (1).
Rotor. By the same standards IEC 60034-1 [2] and IEEE C50.13
[3], the rotor hipot ac voltage UrT shall be

ì10 U rN , at least 1,500 Vac if U rN £ 500 Vdc


ï
U rT = ï
í (2)
ï
ï
î 2 U rN + 4, 000 Vac if U rN > 500 Vdc,

where UrN is the field rated dc voltage (in V, at rated load). Inter-
estingly enough, in spite of the rotor winding operating under dc
voltage, these standards do not allow an alternative dc hipot test
for rotor windings.
Exciter. The IEC standard [2] recognizes that exciters connected
to the rotor winding shall be tested at the same voltage as the
rotor described in equation (2); NEMA MG 1 [4] has identical
requirements for generator brushless exciters (MG 1 does not
cover generators above 5 MVA, being cited here regarding
exciters only). Contrarily, by IEEE 421.3 [5], the exciter test
level is 2 UrN + 2,800 V if UrN > 350 V, because “experience Figure 1. Historical evolution of factory hipot level for stator
indicates that higher test voltages are not necessary” and windings.

30 IEEE Electrical Insulation Magazine


equation (2) was adopted by ANSI C50.10 and from 1983 by 0.8 UsT or 0.8 UrT. (4)
IEC too. Figure 2 shows the historical changes in rotor hipot
levels. Some utilities are specifying that new rotors be hipot According to [5], the exciter initial test is done at only 75%
tested both standing and running [10]; this complicates the test of the factory hipot level, and the same value is mentioned by
procedure, especially for brushless exciters [9]. NEMA MG 1 [4].

Initial Site Hipot History and Practices


About 80 years ago, British standards mentioned an initial
Origin and Purpose site acceptance test at 75% of the factory test voltage, whereas
Today, most turbine generators are completely assembled and [11] recommended the 85% value. Up to the publication of [3]
tested in the factory. Subsequent to the factory tests, the machine in 2006, a hipot test was specified in the United States (ANSI
is packed, shipped, and installed in the power plant; during this C50.13, ANSI C50.15) for each generator not completely as-
process, hidden damages may occasionally occur. Thus, it is sembled in the factory, but apparently it was a factory-level test
necessary to perform an additional high-potential test at the gen- performed in the field. Standard ANSI C50.10-1990 indicated
erating station on turbine generators before the initial startup. that if a test is made after installation in the generating station,
Often this hipot is called a field acceptance test or initial site its level should be 85% of equations (1) or (2). All of the above
hipot. Most believe that a hipot test has no effect on insulation ANSI standards have been withdrawn. An EPRI publication in
life as long as the insulation passed [36]. However, because the 1987 suggested hipot tests after installation be made at 75 or
generator may have been subjected to moisture or other con- 85% of the factory value, depending on the type, output, and
taminants, many believe that initial hipot at the generating sta- voltage rating of the generator [12].
tion should be somewhat less severe than that in the factory.
Note that because hydrogenerators are normally assembled for Repaired Winding Hipot
the first time at the generating station, the factory hipot and the
initial site hipot are the same. Origin and Purpose
This hipot test is intended to check the quality of a stator or ro-
Current Standards tor winding repair to some part of the insulation system or where
The initial site hipot test on the stator and rotor windings is the insulation may have been at risk due to some other interven-
recommended by IEEE [3] at the ac voltage tion (for example by a retaining ring replacement). Sometimes
it is also prudent to perform a hipot before a significant repair is
0.85 UsT or 0.85 UrT. (3) started. The purpose is to determine whether the insulation to be
repaired is weak in other areas. This enables the repair contrac-
The IEC standard [2] mentions the initial site test on a stator tor and the machine owner to ensure that the “good parts” of
or rotor as an optional purchaser request, done at the winding are truly in good enough condition to pass a hipot
after the repair. If such a before-repair hipot is not done and a
failure occurs after repair, then the owner is not sure whether the
contractor initiated other problems or the original winding had
other problems. For example, a retaining ring replacement may
include a hipot before the old retaining rings are removed, in ad-
dition to the final one after the new rings are mounted.

Current Standards
By IEC [2], completely rewound rotor and stator windings
(including all new insulation components) shall be tested at the
full ac test voltage as new machines, i.e., at

1.0 UsT or 1.0 UrT. (5)

When the contractor and user have agreed, [2] recommends


testing partially rewound windings at

0.75 UsT or 0.75 UrT. (6)

The standard IEC 60034-23 deals with refurbishing rotating


machines (including rewinding), whereas for the hipot test, it re-
fers to other standards such as [2]. In contrast, IEEE 1665-2009,
which deals with synchronous generator rewind, is more specif-
Figure 2. Historical evolution of factory hipot level for rotor ic by particularly emphasizing complete rewinds and citing test
windings. levels (as per new machines) from other standards, such as [3].

March/April — Vol. 28, No. 2 31


The recommended practice for rotating apparatus repair devel-
Table 2. Hipot Test Examples for Rotor Rewinding.1
oped by the Electrical Apparatus Service Association (EASA)
AR100 [13] mentions for reconditioned windings a hipot test at Partial
Full rewinding
65% of new winding test value; for machines with windings that rewinding
are not reconditioned, only insulation resistance measurement SI: Old and new SI: New SI: New
should be done. This standard does not clearly define the term
“recondition.” C/CI: Old and C/CI: Old
C/CI: New
Item new and new
History and Practices Before retaining ring
Testing at full voltages per equation (5) is a common practice removal
0.7 UrT — —
for complete rewinds with all new insulation materials. How-
ever, in cases of partial rewinds or if old insulation parts are Individual new coils in slot 1.3 UrT 1.3 UrT 1.3 UrT
reused, the final test should be done at values from equation (6) After coil assembly and
0.65 UrT (0.9–1.0) UrT (1.1–1.2) UrT
or as agreed between contractor and user according to the exact clamp
work extent; these levels are normally in the range of 60 to 85%
Final: After retaining ring
of the test voltages in equations (1) or (2) for new machines. One installation
0.6 UrT 0.8 UrT 1.0 UrT
practical example for related repairs requiring winding hipot is
testing at 1.3 to 1.5 UsN before stator rewedging, and following 1
SI = slot insulation; C/CI = collector/connections insulation.
repairs with a test value of 0.l UsN lower [14].
Table 1 exemplifies test sequences performed during stator
rewinds [15]. Table 2 presents examples of hipot tests related Stator. Power frequency overvoltages may appear as a result
to full or partial rotor rewind, based on manufacturers’ recom- of ground faults in the power system. On high-impedance
mendations. grounded systems typical of utility generators, the neutral
displacement may reach the phase voltage, and in the healthy
Periodic Maintenance Hipot phases, the voltage to ground may rise to 1.0 UsN. If a weakness
is present, the first ground may initiate a second ground fault
Origin and Purpose (in the stator winding or elsewhere in the connected equipment,
This hipot test is used periodically during the life of the ma-
e.g., a voltage transformer). This will create a phase-to-phase
chine to verify its suitability for further operation. The test repro-
fault and high damaging currents that flow as long as enough
duces, in a controlled way, for one minute, the overvoltages to
field current still exists (typically 5 seconds to decay to 30%
ground that may occur in service. It searches out incipient flaws
of initial field current [16] or even a longer time in the case of
during a planned outage at a convenient time, risking less col-
brushless excitation systems).
lateral damage than would occur by an in-service failure caused
Apart from ground faults, other operation contingencies may
by a similar transient. If the winding survives the hipot test, it is
lead to ac overvoltages commensurable with the hipot level:
unlikely to fail in operation (at least for a few more years). The
load rejection (may cause self-excitation if the reactive power
maintenance hipot is also useful if visual inspection indicates a
generated by unloaded lines exceeds generator reactive absorp-
machine is in questionable condition or if it has been subjected
tion capability), ferro-resonance (e.g., paralleling of generator
to severe electrical, mechanical, or thermal stress (e.g., system
capacitance and voltage transformer if the neutral resistor is dis-
short circuit, bad synchronization, asynchronous operation, pro-
connected), faulty voltage regulator or voltage transformer, or
longed field ceiling, and so on).
high to low voltage windings faults in the step-up transformer.
Additional stresses may occur from the generator breakers, if
one phase fails to open or close in synchronism with the other
two phases [17], [18].
Table 1. Hipot Test Examples for Stator Rewinding. The stator hipot does check the phase-to-phase insulation at
Full a slightly higher voltage than the rated one, because the hipot
Partial rewinding rewinding is performed on each phase with the others grounded. Surge ar-
resters or capacitors on the machine terminals will not protect
Replacement
bars: Repaired Replacement Replacement
against power frequency overvoltages.
Item or reused bars: New bars: New Rotor. The rotor winding is usually floating with respect to
Spare bars in the
the rotor body. Thus in a healthy ungrounded rotor winding,
factory
— 1.3 UsT 1.3 UsT the voltages to ground are balanced and equal to half the field
voltage. When a ground fault occurs to the rotor body, in the
Spare bars after storage — 1.2 UsT 1.2 UsT most onerous condition (e.g., if the ground fault protection is
Bars installed in slots (1.4–1.65) UsN 1.1 UsT 1.1 UsT connected to one slip ring), full field voltage may appear at the
other winding end. This increases the probability of a second
Final: Complete winding ground fault, in the rotor winding or in other field circuit
(1.25–1.5) UsN (1.25–1.5) UsN 1.0 UsT
installed
elements (such as the “D leads” in the shaft bore of a turbine

32 IEEE Electrical Insulation Magazine


generator rotor, collector rings, exciter windings, rectifiers, and Current Standards
so on). The second ground may unbalance the air-gap flux and
Stator. In general, according to the IEEE 62.2 [27], a stator
produce disastrous vibrations and substantial currents in the
winding maintenance ac hipot test is made in the range of
winding and rotor body.
Other causes of rotor winding overvoltages are also pos-
1.25 to 1.5 UsN (7)
sible. Although the rotor is normally operating on dc volt-
age, many overvoltage contingencies have ac superimposed
(this approximately equals 60 to 75% UsT). However, test levels
components, which tends to justify the rotor ac hipot testing.
only slightly above UsN, as low as
During field breaker opening of the high rotor inductance,
overvoltages appear, which are supposed to be limited by the
1.1 UsN, (8)
protective discharge resistance (higher in large machines on
ceiling excitation) [10], [19]. Abnormal voltages may also be
can be used to validate insulation with a known weakness, if a
caused by field forcing used to improve the system stability
rewinding is expected in the near future [27]. Standard IEEE
during short circuits. These may reach 50% of the factory hi-
115-2009 [28] points at a 1987 EPRI report that mentions that
pot level for high rated voltages and high ceiling rates [10]. In
“some machine standards refer to maintenance hipot levels as
static excitation systems, the spiky rotor voltage contains large
0.65 or 0.7 times the factory test level [12]. Manufacturers rec-
ac components. According to [10], the thyristor’s commutation
ommend 1.25–1.5 UsN for suitability to continued service tests.
may lead to maximum rotor voltages of up to 5 UrN (on high
Certain utilities may use 1.1–1.2 UsN for older, more mature
field forcing), while the voltage to ground at ceiling excita-
generators; their reasoning is that it is unnecessary to stress the
tion may reach 50% of the factory test level (and even more if
whole winding at 1.25–1.5 UsN when the coils near the neutral
reflections occur when long cables are used [20]). Moreover,
will never be subjected to such high voltage even for a phase-
in a shunt excitation system, overvoltages can result from a
to-ground fault.”
defective excitation transformer or may be transferred from its
Standard IEC 60034-1 [2] recommends that, if the user and
high voltage side.
contractor have agreed, an overhauled machine is subjected to
If a pole-slipping event takes place, an ac voltage at slip fre-
a test at
quency is induced on top of the rotor normal dc voltage. Pole-
slipping can also occur in the event of a field breaker opening,
1.5 UsN, (9)
leaving the generator in asynchronous operation. Large ac com-
ponents tend to reverse the excitation current on each negative
but without a clear definition of the term “overhaul.” The as-
peak, and these negative currents actually can flow in the case of
sumption is that overhaul work includes cleaning and drying
dc generator exciters. However, for excitation fed through recti-
with minimal disassembly.
fiers, these negative currents are blocked, thus a high voltage
appears across the rotor winding [10]. Some tests have measured Rotor. Although periodic hipot tests are well documented
slip voltages up to 3 to 4 UrN [21]. According to [22], conven- for stator windings, the literature is ambiguous about rotors.
tional equivalent machine models exaggerate the overvoltages. According to the recommendations of IEC 60034-1, if user and
Using a different model, it was found that calculated field volt- contractor have agreed, an overhauled machine is subjected to
ages are 4 to 5 UrN for asynchronous events. a test of
During a short circuit at the generator terminals, the rotor cur-
rent comprises the initial field current and superimposed dc and 1.5 UrN, at least 1,000 V. (10)
ac decaying components. According to tests, the field voltages
can attain 4 to 5 UrN [23]. During system short circuits, the rotor As mentioned before, “overhaul” is not totally clear, but the
current may become negative; worst cases are line-to-line short 1,000 Vac value may be used as a minimum periodic hipot level,
circuits (include a double frequency ac component), especially when no better references are available. The IEEE 62.2 deals
those occurring at leading power factor and cleared at unfavor- in detail with site hipot testing of armature only [27]. The ro-
able times [24], [25], when the rotor overvoltages may reach 4 tor maintenance hipot is not mentioned in IEEE 56-1997, but
to 5 UrN [22]. the IEEE 432-1992 (for smaller machines) indicates that such
If a unit is synchronized beyond standard reactive power vec- tests are made also on ground insulation of the rotor winding,
tor limits, a large current surge will flow in the stator windings, yet specifying test values for armature only. The two last-named
which is then reflected in the rotor. Reference [26] calculated standards have been withdrawn, and a merged revision is being
during negative field currents peak voltages of 9 to 14 UrN for developed.
mismatches of 12° in phase displacement and 12% in voltage. According to [22] and [25], salient-pole machines (especially
By [24] and [25], a phase opposition (180°) faulty synchroniza- motors or hydrogenerators in pump mode) may be subjected in
tion may lead to overvoltages as high as 4 to 5 UrN. service to larger rotor overvoltages than turbo-generators. How-
In general, larger rotor overvoltages may occur in smaller ever, the standards do not recognize such differences for factory
turbo-generators or those without suitable damper (amortisseur) nor for periodic hipot tests.
windings. Methods intended to protect the rotor against overvol- Exciter. According to IEEE 421.3 [5], the exciter’s hipot level
tages are discharge resistors or electronic devices. shall not exceed 65% of the factory test voltage.

March/April — Vol. 28, No. 2 33


History and Practices resistance test. Also according to one book [37], stator windings
are much more likely to be subjected to maintenance hipots than
Stator. In the beginning of the 20th century, German standards
are rotors.
mentioned hipot tests at 130% of the rated voltage for 5 minutes
Reference [16] clarifies that “rotor windings operate at rela-
[8]. A few years later, [11] proposed to include in the American
tively low voltages, less than 750 V dc, and are generally de-
standard a test to ground at 1.25 UsN and also a test between
signed with creepage paths subjected to contamination.” As a
phases at 1.75 UsN. By [29], no really reliable nondestructive
result, a good test can be performed with megohmmeter, and
test was available for predicting the remaining life of rotating
routine hipot is generally not recommended.
machines in service, and consequently, if a failure in service
One large manufacturer recognizes in its instructions (pub-
were to be avoided, it was necessary to use hipot testing.
lished from 1979 through 2009) that the practice in most utili-
After an extensive survey, in 1945 a utility started a periodic
ties is to do much less hipot testing on the rotor than on stator,
testing program at 1.5 UsN, which they claimed proved
although the rotor insulation is also an important cause of forced
effective for eliminating winding failures in service with no ill
outages. It appreciates that this practice should be reevaluated,
effects on good insulation [29]. One hipot test voltage survey
applying more efforts in rotor and associated excitation test pro-
performed in the 1960s indicated testing between 1.0 and 1.5
grams [43]. On the other hand, manufacturers normally do not
UsN [30]. Manufacturers’ surveys from the 1970s indicated that
explicitly recommend hipot tests as standard maintenance prac-
maintenance hipot testing has proven necessary and useful to
tice on rotors. Power plant engineers are normally worried when
detect weak spots, particularly with aged insulation. If a bar fails
asked to perform rotor hipots, even at a minimum of 1,000 Vac.
a hipot test, the invariable reason is insulation damage. Based
on much experience, no service failure occurred within the two-
year period following a hipot test [31], [32]. Hipot Test Risk
CIGRÉ surveys [33], [34] from the 1980s concluded that “the When deciding to perform a hipot test, the two conflicting
most representative and most generally accepted method for as- alternatives are
sessing the good condition of insulation is application of a hipot
proof test. From the different methods, the 1 minute ac test at 1.5 • do the test when the machine is stopped for planned
UsN is the most widely recognized.” CIGRÉ checked this issue maintenance and risk a controlled insulation failure or
again in 1996 and deduced that routine hipot testing is a com- • do not perform a hipot test, but then accept the risk of a
mon method to ultimately check the dielectric strength of wind- forced outage during operation with the associated lost
ings (in 12 out of 17 countries); 9 countries perform ac tests at revenue and the possibility of much greater damage to
1.5 UsN, and others perform ac tests at slightly lower voltages or the machine.
dc tests [35]. By [36], in 2000 most utilities used a hipot level of
1.2 to 1.6 UsN, depending on machine history and criticality. One In the final analysis, this is a risk management decision that
book [37] mentions that nowadays the maintenance ac hipot is has to take into consideration many aspects including, among
more widespread in Asia and Europe than in North America. others, type and condition of insulation, equipment age, its his-
The newest and most comprehensive survey is the EPRI re- tory and importance to the power system, machine operating
port 1014908 from 2008 [38], which updated the previous work regime, desired service reliability, and system generation needs
[36]. It seems that fewer utilities used hipot maintenance tests in [36], [37].
2008 than in 2001; most respondents perform periodic hipots at The hipot test should be applied only when the machine is
60 to 80% of factory UsT [39]. By [38], the electrical withstand expected to be in good condition and its insulation resistance
of a stator winding should be at least 1.2 to 1.3 UsN based on and polarization index are deemed suitable as per IEEE 43 [1].
a ground fault event, plus a 10% voltage fluctuation and some During any off-line test, even when the winding is tested at nor-
(10–20%) safety margin. Even a 1.0 UsN test will give some mal service voltage, all coils/bars in the winding are at high po-
protection against service failure, although the margin may be tential. Thus, coils close to the neutral in a stator winding will
small in the event of a system disturbance; a test level of at least see much higher voltage than in service. Similarly, more voltage
1.2 UsN is preferable [16], and using lower hipot levels does not stress will occur across some of the groundwall insulation than
ensure long-term serviceability of the winding insulation [38]. would be experienced in service. Many feel that after any hipot
test, the insulation resistance test should be repeated.
Rotor. Much less information has been published for rotor
Before any maintenance hipot testing, it is recommended to
maintenance tests than for stator windings. One example of
check the ready availability of strategic spare components. For
utility practice is testing rotors rated 125 V at 1,000 V and those
instance, keeping in stock spare stator bars in suitable quantities
rated 250 V at 1,500 V (no value is mentioned for UrN ≥500 V)
and types [15] will permit relatively rapid stator winding repairs
[40]. According to the EPRI handbook [41], “test voltages of
(except in case of global VPI machines). Ideally, a complete
about 1,000 V are sometimes used for turbine generator rotor
spare rotor would enable the most comprehensive solution for
insulation which has seen service.” CIGRÉ surveys [33], [34]
rotor winding hipot failures. Major spares such as a complete
found that in only a few countries are hipot tests systematically
rotor are usually only justifiable if the spare can be used in a
performed on rotors and that substantially more attention is paid
number of generators that the utility operates.
to the stator winding. A newer CIGRÉ survey (1996) [42] does
High-potential tests are performed at lethal voltages and pose
not mention hipots on rotor windings except for the insulation
high safety dangers. Both test equipment operators and plant

34 IEEE Electrical Insulation Magazine


personnel must be fully trained and certified before performing ists for continued safe operation. This test also provides an easy-
these tests. No leads should be left unconnected or ungrounded to-interpret result that is either “go” or “no go” [38]. The hipot
during the test. The stator hipot test on generators is performed test does not damage or introduce any significant harm to the
on each phase separately (if possible), with the other two phases insulation [36], [38], [43], [45], [49]–[51]. The authors believe
grounded; all voltage transformers, lightning arrestors, capaci- that the hipot test should be specified and implemented as rec-
tors, and so on should be disconnected. During the rotor hipot ommended by standards on manufacturing, at the initial site, and
test, the diodes of an assembled brushless excitation system after repair and maintenance tests. To mitigate the managers’
should be short-circuited (not grounded). Excitation system and engineers’ reluctance on using this risky tool, the hipot test
components such as line-to-ground capacitors, shaft current sup- policy should be regulated by the utility’s internal procedures, as
pressors, voltage attenuators, and so on should be insulated from an integral component of the generator availability plan.
ground during the test. It is the authors’ opinion that stator winding maintenance hi-
pot tests will help utilities avoid in-service failures. In the au-
Maintenance Hipot Test Periodicity thors’ experience, any stator winding that failed a maintenance-
Only about 50% of utilities perform maintenance hipot tests level hipot had such extensive deterioration that the winding
[36], [39]. For utilities that do maintenance hipot testing, the would have failed in any case after the winding was returned
periodic maintenance hipot tests are usually performed as part to service. The stator winding hipot test should be done at least
of a scheduled major overhaul and inspection activities [27]. Ac- during major outages, or if deterioration is suspected following
cording to IEEE 67, the time between inspections is usually de- diagnostic tests or visual inspections, or as a decision aid for
termined by the manufacturer’s recommendations and the user’s future rewinds [14].
experience [44]. Consideration should be given to the opera- It seems it is common practice not to perform periodic main-
tion hours, number of starts, severe short circuits or other high tenance hipot tests on rotor windings. Instead, the rotor ground
transients experienced, outages for turbine repairs, conditions insulation is usually just given a low-voltage (perhaps 500 Vdc)
found in previous inspections, type of station (nuclear or fossil), insulation resistance test. Even the polarization index may not
unit size and duty, generator age, system demand, and insurance be applicable for nonencapsulated designs, according to IEEE
company implications. 43 clause 12.2.1 [1]. Service problems relating to rotor insula-
Until about 1980, American, Japanese, and European manu- tion failure are common, especially in turbine generators, due to
facturers normally recommended inspection and hipot after the contamination, fracture, migration and cut-through, as a result
first year of operation and subsequently at intervals of about 3 to of creepage surface design and high mechanical duties in opera-
5 years [32], [45]. At that time, utilities normally fulfilled these tion [9], [16], [37], [52]. These stresses are the main impetus for
recommendations, as shown in an old survey of utilities [30]. A high factory hipot levels. But these stresses seem to be almost
1987 CIGRÉ report found that stator hipots were done for diag- neglected for rotor winding maintenance, in contrast with the
nostic purposes every 4 to 6 years, and rotor hipots much less stator. In factory testing the hipot test level is relatively much
frequently (10 to 12 years or never) [46]. A 1996 CIGRÉ survey higher for rotors than for the stator. In contrast, the test level for
mentioned that major overhauls with extensive dielectric testing maintenance hipots is inverted, with the rotor tested only with an
were performed in intervals of 6 to 9 years [35]. An IEEE report insulation resistance test at or near operating voltage.
in 2001 found that the most frequent major outage intervals were Many circumstances were presented above to show that tem-
8 to 10 years [47]. porary high-voltage stress can be applied to the rotor winding
The current general tendency is to have less frequent outages, ground insulation during operation. To mitigate the risk of rotor
which consequently means the interval between maintenance hi- winding insulation failure by these transients, the authors sug-
pot tests is getting longer. This is presumably being driven by gest a maintenance rotor ac hipot of
the need to minimize outages and maximize revenue from the
generators. This trend has been accentuated by restructuring 0.5 UrT, at least 1,000 Vac (11)
of the power industry (deregulation, privatization). One large
manufacturer still recommends stator hipots for every minor (30 would be justifiable. This hipot level does not include a safety
months) and major (60 months) outage, whereas rotor hipots are margin, contrary to the 0.6 to 0.75 UsT ac hipot level used on
mentioned as optional. It is interesting that the major outage def- stators (equation 7). Nevertheless, this rotor maintenance hipot
inition has become wider to include either rotor-out or limited level seems much more appropriate than the present practice and
access robotic inspections [48]. may be used as a proposal toward further discussions. This ro-
tor winding maintenance hipot should only be performed if the
Conclusions insulation is clean and dry, that is, it has a high insulation resis-
Maintaining the integrity of the insulation system is essential tance level.
for generator reliability. The insulation may continue to perform
quite satisfactorily at service voltage but fail under overvoltages References
[1] IEEE Recommended Practice for Testing Insulation Resistance of Rotat-
occurring in operation. According to a wide survey of standards, ing Machinery, IEEE Standard 43-2000, reaffirmed Mar. 2006.
organizations, manufacturers, and user opinion, the maintenance [2] Rotating Electrical Machines—Part 1: Rating and Performance, IEC
hipot test is the most reliable test to verify the suitability of the Standard 60034-1, 12th edition, Feb. 2010.
insulation to perform its function and to prove that a margin ex- [3] IEEE Standard for Cylindrical-Rotor 50 Hz and 60 Hz Synchronous

March/April — Vol. 28, No. 2 35


Generators Rated 10 MVA and Above, IEEE Standard C50.13-2005, Feb. [29] L. F. Hunt and J. H. Vivian, “Routine insulation testing of synchronous
2006. machines,” presented at the AIEE Winter General Meeting, New York,
[4] Motors and Generators, NEMA Standard Publications MG 1-2009, Revi- NY, Jan. 1951.
sion 1-2010. [30] G. W. Armstrong Jr. and D. J. Kopaczynski, “Generator insulation testing
[5] IEEE Standard for High-Potential Test Requirements for Excitation Sys- (A review),” in Proceedings of the International Conference of Doble
tems for Synchronous Machines, IEEE Standard 421.3-1997, Dec. 1997, Clients, 1968.
reaffirmed Dec. 2004. [31] C. V. Maughan and A. F. Bristor, “Maintenance of large turbine-generator
[6] “Report of the Committee on Standardization,” in Transactions of the stator insulation systems,” in Proceedings of the International Conference
American Institute of Electrical Engineers, vol. XVI-XIX. New York, of Doble Clients, 1970.
NY: American Institute of Electrical Engineers, 1899–1902. [32] R. H. Schuler, “Experience with maintenance testing of water-cooled
[7] “Standardization rules of AIEE,” in Transactions of the American generator stator winding insulation,” in Proceedings of the International
Institute of Electrical Engineers, vol. XXVI- XXXVII. New York, NY: Conference of Doble Clients, 1971.
American Institute of Electrical Engineers, 1907–1918. [33] Working Group 07 of Study Committee No. 11 (Rotating machines),
[8] A. Fleming and R. Johnson, Insulation and Design of Electrical Wind- “Evaluation of the quality of the insulation of high voltage large rotating
ings. London, UK: Longmans, Green, and Co., 1913, pp. 183–188. machines,” Electra, no. 70, pp. 51–64, May 1980.
[9] G. W. Staats, “High potential test voltages of high voltage synchronous [34] R. H. Schuler, “Report on diagnosis and monitoring for evaluating the
machines—Proposed changes to ANSI C50 Standard,” presented at the condition of windings of rotating electrical machines,” Electra, no. 112,
IEEE PES Winter Meeting, New York, NY, Jan.-Feb. 1973. pp. 9–16, May 1987.
[10] P. Richardson, R. Hawley, and J. Wood, “Insulation levels for turbo- [35] A. Huber, “Report on stator winding integrity,” Electra, no. 169, pp.
generator rotors,” presented at the IEEE Winter Meeting, New York, NY, 34–41, Dec. 1996.
Jan.-Feb. 1972. [36] B. K. Gupta, G. C. Stone, and J. Stein, “Use of machine hipot testing
[11] C. M. Gilt and B. L. Barns, “Insulation tests of electrical machinery be- in electric utilities,” presented at the Electrical Insulation and Electrical
fore and after being placed in service,” presented at the Winter Conven- Manufacturing and Coil Winding Conference, Cincinnati, OH, Oct. 2001.
tion of the AIEE, New York, NY, Jan.-Feb. 1929. [37] G. C. Stone, E. A. Boulter, I. Culbert, and H. Dhirani, Electrical Insula-
[12] W. J. Sheets, “Electric generators,” in EPRI Power Plant Electrical tion for Rotating Machines. Piscataway, NJ: IEEE Press/John Wiley &
Reference Series, vol.1, Rep. EL-5036-V1. Palo Alto, CA: Electric Power Sons Inc., 2004, pp.243–248.
Research Institute, 1987. [38] G. C. Stone, and B. K. Gupta, Guide for Rotating Machine Stator
[13] Recommended Practice for the Repair of Rotating Electrical Apparatus, Winding Hipot Testing, Report 1014908, Palo Alto, CA: Electric Power
ANSI/EASA Standard AR100-2010, Oct. 2010. Research Institute, Mar. 2008.
[14] J. Timperley, “Power frequency overpotential tests on installed stator [39] B. K. Gupta, G. C. Stone, and J. Stein, “Stator winding hipot (high po-
windings of rotating electric machines,” Panel Session on “High voltage tential) testing,” presented at the IEEE Electrical Insulation Conference,
testing of rotating machines,” presented at the IEEE/PES Winter Meeting, Montreal, Canada, May-Jun. 2009.
New York, NY, Feb. 1997. [40] Testing Solid Insulation of Electrical Equipment, vol. 3-1. Denver, CO:
[15] R. Ilie and B. Moore, “Spare bar inventory decisions,” presented at the US Department of the Interior, Bureau of Reclamation, Facilities Engi-
EPRI European TGUG Meeting, Workshop and Vendor Exposition, neering Branch, Dec. 1991.
Madrid, Spain, Jun. 2009. [41] I. M. Culbert, H. Dhirani, and G. C. Stone, “Handbook to assess the
[16] C. V. Maughan, “Testing of large electric generators for suitability of ser- insulation condition of large rotating machines,” in EPRI Power Plant
vice,” presented at the Iris Rotating Machines Conference, San Antonio, Electrical Reference Series, vol. 16, Rep. EL-5036-V16. Palo Alto, CA:
TX, Jun. 2002. Electric Power Research Institute, 1987.
[17] E. P. Dick, B. K. Gupta, A. Greenwood, R. W. Cheung, H. Dhirani, and L. [42] J. M. Guillard, “Study of rotor winding integrity,” Electra, no. 169, pp.
Lishchyna, Surge Protection of Generators, Report EPRI-GS-6936. Palo 26–32, Dec. 1996.
Alto, CA: Electric Power Research Institute, Oct. 1990. [43] GEK 7613h, “Insulation testing of turbine-generator windings,” in GE
[18] D. J. Bornebroek, C. G. A. Koreman, P. T. Liljegren, T. J. M. Peters, and Power Systems, Jun. 2009.
C. Reynaud, Overvoltages and Overvoltage Protection in the Generator [44] IEEE Guide for Operation and Maintenance of Turbine Generators, IEEE
Main Electrical Circuit in Power Stations, Report 98, CIGRÉ, Aug. 1995. Standard 67-2005, Nov. 2005.
[19] H. Herzog and J. Deak, “Protecting the static excitation equipment and [45] J. S. Johnson, “Interpretation of maintenance overpotential test data and
rotor windings of synchronous machines against overvoltages,” Brown their effect on winding operation reliability,” in Proceedings of the Inter-
Boveri Rev., vol. 69, pp. 207–211, Jun. 1982. national Conference of Doble Clients, 1967.
[20] I. Nagy, P. Korondi, Z. Süto, T. Ruzsányi, and J. Móricz, “Voltage stress [46] J. G. Heard, Report on Large Turbine Generator Maintenance Practices,
of the rotor winding in turbine-generator furnished by thyristor exciter,” CIGRÉ Working Group 01 of Study Committee 11, 1987.
presented at CIGRÉ Session, Paris, France, Aug.–Sept. 1998. [47] IEEE/PES Task Force, “The present status of maintenance strategies and
[21] V. Easton, “Excitation of large turbogenerators,” Proc. IEE, vol. 111, no. the impact of maintenance on reliability,” IEEE Trans. Power Syst., vol.
5, pp. 1040–1048, May 1964. 16, no. 4, Nov. 2001.
[22] M. Canay, “Overvoltages in the field circuit of synchronous machines [48] GEK 103566g, “Creating an effective maintenance program,” GE En-
with rectifier excitation,” Brown Boveri Rev., vol. 61, pp. 217–227, May ergy, Nov. 2011.
1974. [49] J. E. Timperley and J. R. Michalec, “Estimating the remaining service
[23] H. J. Humphries and W. Fairney, “Excitation rectifier schemes for large life of asphalt-mica stator insulation,” presented at the IEEE/PES Winter
generators,” Proc. IEE, vol. 119, no. 6, pp. 661–671, Jun. 1972. Meeting, New York, NY, Jan.-Feb. 1994.
[24] I. M. Canay, “Investigation of the rotor overvoltage in synchronous ma- [50] H. G. Sedding, R. Schwabe, D. Levin, J. Stein, and B. K. Gupta, “The
chines with rectifier excitation,” Electric Machines and Electromechan- role of ac & dc hipot testing in stator winding ageing,” presented at the
ics, vol. 3, pp. 21–38, 1978. Electrical Insulation and Electrical Manufacturing and Coil Winding
[25] M. Canay and J. J. Simond, “Rotor overvoltages and interturn voltages in Conference, Indianapolis, IN, Sep. 2003.
the field winding of synchronous machines,” Brown Boveri Rev., vol. 67, [51] B. K. Gupta, H. G. Sedding, G. C. Stone, and J. Stein, “Do Hipot tests
pp. 516–523, Sep. 1980. damage rotating machine insulation?” presented at the International
[26] W. D. Humpage, J. R. Smith, and G. J. Rogers, “Induced field-system Symposium on Electrical Insulation (ISEI), San Diego, CA, Jun. 2010.
transients in synchronous generators having unidirectional forms of [52] C. V. Maughan, “A brief history of turbine-generator electrical insulation
excitation supply,” Proc. IEE, vol. 121, no. 7, pp. 647–652, Jul. 1974. and support systems,” presented at the 78th Annual International Doble
[27] IEEE Guide for Diagnostic Field Testing of Electric Power Apparatus— Client Conference, Boston, MA, 2011.
Electrical Machinery, IEEE Standard 62.2-2004, Dec. 2004.
[28] IEEE Guide for Test Procedures for Synchronous Machines, IEEE Stan-
dard 115-2009, May 2010.

36 IEEE Electrical Insulation Magazine


Relu Ilie received the MS degree in elec- Greg Stone was a dielectrics engineer
trical engineering from the Technical Uni- with Ontario Hydro’s Research Division
versity of Iaşi, Romania. He is in charge of from 1975 to 1990. Since 1990, Dr. Stone
power plant electrical systems and equip- has been employed at Iris Power in Toron-
ment for the Israel Electric Corporation. to, Canada, a rotating machine diagnostic
Relu Ilie has 29 years of experience in the instrument manufacturing company he
generation and transmission field, mostly helped to form. He is a past-president of
dedicated to electrical machines issues: de- the IEEE Dielectrics and Electrical Insu-
sign and failure analysis, maintenance and lation Society and continues to be active
inspections, monitoring and testing, technical specifications, life on many IEEE and IEC standards working groups. He has pub-
extension, condition assessment, and so on (e-mail: reluilie@ lished two books and many papers concerned with rotating ma-
iec.co.il). chine insulation. Greg Stone has a PhD in electrical engineering
from the University of Waterloo (Canada), is a Fellow of the
IEEE, a Fellow of the Engineering Institute of Canada, and is a
registered professional engineer in Ontario, Canada.

037-Gb IEEE No Boundaries HALF 12/1/05 11:28 Page 1

YO U K N O W YO U R S T U D E N T S N E E D I E E E I N F O R M AT I O N .
N O W T H E Y C A N H AV E I T . A N D Y O U C A N A F F O R D I T .

IEEE RECOGNIZES THE SPECIAL NEEDS OF SMALLER COLLEGES,

and wants students to have access to the information that will


put them on the path to career success. Now, smaller colleges can
subscribe to the same IEEE collections that large universities
receive, but at a lower price, based on your full-time enrollment
and degree programs.
Find out more–visit www.ieee.org/learning

March/April — Vol. 28, No. 2 37

You might also like