Professional Documents
Culture Documents
Method Statement of Potable Water and Firefighting Network Construction
Method Statement of Potable Water and Firefighting Network Construction
From : Branch of China Harbour Engineering Co Ltd. To : East Consulting Engineering Center
Specification Reference :
Subject : Method Statement of Potable Water and Firefighting Network Construction (Phase 3&4)
ENGINEER'S COMMENTS :
1 Risk assessment for the Method statement shall be mentioned.
2. Detailed Quality Control Inspection and Testing to be incorporate.
3. Incorporate types of tests carry for irrigation network.
DOCUMENTS ATTACHED
SR.# DOCUMENT NAME DESCRIPTION 1 NOTES/REMARKS In PMWeb Viewer
00103_CHE_MST_MEC_000004_R00 Method 00103_CHE_MST_MEC_000004_R00 Method Statement of
1 Statement of Potable Water and Firefighting Potable Water and Firefighting Network Construction (Phase Nil
Network Construction (Phase 3&4).pdf 3&4)
Signature : Signature :
00103-CHE-MST-MEC-000004
Rev. 01
Jan.21, 2024
per specifications, procedures, and HSE requirements. This method statement specifies
the technical requirements to be followed and also acts as a reference to clearly establish
Moreover, this document shall provide guidelines to check that specified materials are
installed and agreed procedures are implemented during the execution of work.
2. Scope
2.1. Objective
This scheme is based on the IFC drawings of the potable water and firefighting
networks system. The main reference specifications are the British standard, American
standard and local Saudi standard. The manpower, equipment and materials are
The purpose of this method statement is to outline the method of storage, handling and
Trench Excavation
Bedding
Pipe Installation
Pipe Test
Backfilling
Valve Construction
installation of HDPE pipe, DI pipe and relevant pipe fittings, connection to the existing
lines, set warning tape, value chamber construction, installation of fire hydrants, house
connection.
Ensure that drawings used for installation are the latest revision approved & all material
has been inspected by the consultant. Discuss method statement/risk assessment with
all concerned parties. Installation area is to be free from storage items or debris. The
work place shall be clean and safe to proceed with the installation.
6. Resources
6.1. Human Resources
No. Personnel Qty
1 Site Manager 1
2 Construction Manger 1
3 Site engineer Variable
4 Quality control Variable
5 Foreman Variable
6 Skilled labor Variable
7 Labor Variable
8 Surveyor Variable
9 Electrician Variable
10 Driver Variable
11 Operator Variable
6.2. Material and Approvals
The Installation of permanent materials shall proceed only after the approval by the
Consultant engineer. Material shall be brought to site along with proper documents such
as delivery note and test certificate. Material to be supplied to site as per site
requirement. The Material Inspection Request (MIR) shall be submitted to Engineer for
Specification. All the received materials and approved materials shall be in compliance
recommendations.
6.2.1. List of Materials
Valves
Bitumen coating
Water Meter
6.2.2. Tools, equipment and machines
Measuring Tape
Test Equipment
Fusion Machine
Surveying Instruments
Roller, brush
Drill machine
Grinder Machine
Water Tanker.
Chain Cutter
Check and ensure all drawings used for installation are approved for construction.
Necessary approval has been obtained for the earthworks and material to be used. All
materials must be approved prior to work start. The excavation shall be as per the exact
coordinates of approved shop drawings. The workplace shall be clean and safe to
proceed.
7.2. Surveying and Pipeline Axis Setting Out
With reference to the drawings, the central benchmark of the pipeline will be set by
GPS surveying; the locations of bends, fire hydrants and valve chambers are marked
and staked with GPS and level according to benchmarks. The central axis of the pipeline
in a portion of a straight line is marked with lime. Where obstacles are found above or
underground within the site, they shall be marked and removed or be provided with
All potable water pipelines shall be laid accurately to the lines, and levels gradients
calibration. Only the instruments and equipment acquired the calibration then we can
Excavation and Trenching will be done in accordance with detail drawings. Trench
excavation is carried out with excavators. We will determine the form of excavation
The area that shall be excavated needs to be barricaded and all safety warnings
shall be provided as required by the Safety Engineer. The equipment that shall be
used for excavation must be on/in a stable area. The required safety personnel shall
Excavation shall be carried out to the lines and levels as shown on the drawings.
Lines, levels and profiles shall be measured by optical instruments, which are
specified but shall nevertheless provide sufficient room for the safe laying, jointing,
and testing of pipework and utilities. The bottom of the excavation shall be always
Location of fire hydrants and valve chambers shall be prepared in the same
scrap and rubbish including builders work debris, or arising from escarpment
cleaning, or contains particle sizes greater than 100 mm shall be placed in spoil
areas.
Material defined as hazardous shall be removed from the site and taken to an
collapse after excavation and delaying the work progress, pipe installation is executed
compacted 95% of Maximum Dry Density in accordance with standard details of IFC,
the Contractor shall issue a formal notice to the Engineer that the trench formation is
In bedding granular material shall be used below and above the pipes. The back fill
material shall be free of stones. The bedding material should be red sand paving
150mm in soil.
Depth of bedding material below the bottom of pipes shall not be less than one
quarter the diameter of the pipe for the entire length of the pipe.
Bedding to be shaped to fit around pipe joint protrusions, manholes or hand holds.
7.5. Pipe Installation
The pipes shall be installed in accordance with Project Specification and as per
The HDPE/DI Pipes and Fitting shall be as per Material Submittal approved by
Engineer.
All primary potable piping shall be buried to the depths as shown on the approved
drawings.
Verify location and elevation of all underground utility lines prior to starting trench
excavation work.
The work shall comply with all aspects of local AR Riyadh or Kingdom of Saudi
The pipes being installed shall be approved through MIR prior to installation.
The Level of the pipe would be as per the approved shop drawing and survey report.
The Joints for HPDE Pipes shall heat or electric fusion and the valves connection
Setting out of fire hydrants and valves chambers shall be done as per the approved
shop drawings, excavation will be carried out along with the pipeline trenches.
Install the valves along with pipeline to the approved invert level, with concrete
support.
Protective polyethylene sleeves shall be used with all DI pipes and fittings to be
installed in buried condition and shall be in accordance with BS 6076 or DIN EN
14628 or AWWA C105. The minimum nominal thickness of the sleeve shall be
Once the pipe fittings and valves are installed it shall be ensured that the area is
It shall be ensured that all the pipe and joints are visible with clean bedding area
The pipe joining is a process in which two ends of the pipes to be heated and welded
Face the pipe ends to establish clean, parallel surfaces and perpendicular to the
center line.
Join the two pipe ends together by applying the proper fusion force.
Scrape off the oxide layer at the welding joint of the pipe.
recommendations.
All trenches with pipe installed shall be immediately backfilled with preliminary
bedding and backfill sufficient to prevent arching or slipping under pressure, but,
all joints, fittings and connections are to remain exposed until successful
test plug and the pressure gauge with valve accessories for test. All the pressure
The Water is filled from the lower end to the higher end to the pumps limiting the
flow rate. Removal of the air from the main is essential. Check for the functioning
of the air valves, check the valves at the base of the air valve is open use the wash
During testing the pipes, joints and all accessories installed shall be carefully
Pressure gauges shall be dual reading in bar and PSI units. Calibration shall be such
After the main pipeline has been completely filled, the pressure shall be steadily
and gradually increased until the specified test pressure has been reached. Pressure
test shall be made at 1.5 times of the normal working pressure. Duration of pressure
and leakage tests shall be 2 hours. Allowable leakage is 0.02 liter/mm diameter/km
The water should be gradually discharged after the completion of the Hydro-Test
and ARV should be open position allowing the air to release and the end caps &
other accessories should be securely dismantled, cleaned and ready for the use of
next test.
7.8. Anchor Thrust Blocks
Anchor thrust blocks shall be made in accordance with Project Specification and as per
approved shop drawings. Anchor and thrust blocks shall be provided at all tees, bends,
valves and hydrants. The concrete shall be made with type V cement, manufacturer
Wet-Barrel Fire Hydrants shall be in accordance with AWWA C503, one DN 100
and two DN 65 outlets, DN 150 threaded or flanged inlet, and base section with
(minimum) fusion bonded epoxy. Hydrant shall have 16 bars minimum working
pressure design.
Outlet two 65 mm male thread to BS336 fire couplings for hose connection and
one 100 mm male thread outlet to BS336 fire coupling for pumper connection used
Each hydrant shall be equipped with, a buried gate valve with a surface box and
extension tube, and a horizontal ductile iron pipe connected to the main pipe. All
Set each hydrant on a slab of stone or concrete not less than 100 mm thick and 375
mm square. The service line to the hydrant, between the tee and the shoe of the
hydrant, shall be fully restrained. Set bases in not less than 0.4 cubic meter of
Each fire hydrants have 4 steel bollards 150mm diameter (Ref: Standard details of
Potable water) shall be required to protect the fire hydrant against traffic.
Installation of Steel bollards & its excavation at presence of surveyor and approved
formation level should be 95%. Install the steel bollards and make sure its straight
at 90-degree angle from surface. Then start layer by layer back filling with
complete compaction.
Paint guard posts (Red and White 3mm thick paint) or as per Saudi standard
Locate valves for easy access and provide separate support where necessary. Install
valves in horizontal piping with stem at or above the center of the pipe.
sequencing bolt tightening to make initial contact of flanges and gaskets as flat and
parallel as possible. Tighten bolts gradually and uniformly using a torque wrench.
sides of extension.
Protection tubes: Either PVC-U. Shape, sizes and other constructional details are
Wrap buried valves, flanged joints, mechanical joints, flanged pipe spools with
thrust collars, and adapters with polyethylene material, complete the wrap prior to
construction.
7.11. Valve Chamber Construction
IUG-DWG-CP-080010).
The Contractor shall issue a formal notice to the Engineer for the inspection of
All dirt, chips, sawdust, nails, and other foreign materials shall be completely
removed from forms before any concrete is deposited therein. Forms previously
used shall be thoroughly cleaned of all dirt, mortar, and foreign material before
being reused. Before concrete is placed in forms, all inside surfaces of the forms
shall be thoroughly coated with commercial quality form oil or other equivalent
coating which will permit the ready release of the forms and will not discolor the
concrete. Forms may be removed at the convenience of the Contractor and with
the prior approval of the Engineer after the Concrete has hardened. The concrete
Backfilling shall be done immediately after finishing pipe installation and testing.
Provide warning tape located at 300 mm above the top of the pipe in all trenches.
Trench Backfilling (Within the Pipe Zone): Trench backfills shall contain no rocks or
stones larger than 50 mm in the greatest dimension and shall be free of vegetation, trash,
chunks of highly plastic clay, or other unsatisfactory- material. Backfill Material shall
Trench backfilling consists of two procedures: a) Backfilling prior to test. The trench
shall be hand tamped and backfilled with part of sand above the pipe and leave the pipe
joints clean. The gap between the bottom of the pipe and the trench bottom must be
tamped and no backfilling is allowed within 0.3m on each side of the connection for
further test observation. b) Massive backfilling after the pipe is approved qualified with
test. Backfilling is executed on both sides of the pipe simultaneously and the soil shall
POTABLE WATER LINE BELOW” for water mains, etc. Warning tape shall be laid
300 mm above the pipeline, the text on the tape shall be permanent ink bounded to resist
prolonged chemical attack by corrosive acids and alkaline with message repeated at a
a- Warning Tape
For all potable water mains, the tape shall be blue in color,
Tape shall be printed in Arabic and English alternately with the words
Tape shall be 300 mm in width, 100 microns nominal thickness and obtained
Ductile iron pipe for water shall be C-Class to BS EN 545 or equivalent unless
otherwise indicated in the Bill of Quantities or the Drawings and shall be suitable
for an allowable operating pressure (PFA) of [16] or [25] bars. Ductile ion pipes
could also be to AWWA C151 pressure class 350.Refer to the Potable Water
(Section 33 10 00) Clause 2.2.1 / A.
The ends of each pipe shall be plain and suitable for heat fusion. Pipe and fittings
shall be class minimum or 16 bars. Refer to the Potable Water (Section 33 10 00)
Clause 2.2.2 / A.
d- Joints for pipes and fittings shall be by heat fusion and in strict accordance with
mobilize .
width flange, and 660 mm diameter cover. Refer to the Specification for Valves
Frame: for roadways Class D400 heavy duty non-rock type for wheel loads up to
11.5 tons. Minimum test load 400 kN. Refer to the Specification for Valves and
Wet-Barrel Fire Hydrants: AWWA C503, one DN 100 and two DN 65 outlets,
DN 150 threaded or flanged inlet, and base section with DN 150 mechanical-joint
inlet.
Outlet two 65 mm male thread to BS336 fire couplings for hose connection and
one 100 mm male thread outlet to BS336 fire coupling for pumper connection
used by local fire department. Include cast-iron caps with steel chains.
Interior and exterior coating to be 180 microns (minimum) fusion bonded epoxy.
All bends, elbows, reducers and tees for buried pipes shall be from the same pipe
material.
Bends, elbows, reducers and tees to be installed inside valve chambers shall be
made of carbon steel, ductile iron, cast iron, bond strand or FRP.
Couplings: The nuts, bolts and washers shall be stainless steel 316.coating shall
be factory applied non toxic fusion bonded epoxy powder or a Nylon based
polyamide 11 coating system with normal dry film thickness (DFT) of 300
g- Air Valve
Air valves shall be suitable for the system maximum working pressures. Valves
shall be tested for leak tightness in steps of 200 KN/M2 up to the maximum
working pressures.
h- Gate Valve
ductile-iron body and bonnet; with bronze or ductile-iron gate, resilient seats,
Interior and exterior Coating: To be 300 microns fusion bonded epoxy coating.
Extension spindles for gate valves: steel to BS 2470 - M12, hot dip galvanized to
i- Butterfly Valve
Type: To BS EN 593, double flange with resilient seating, for horizontal use.
Protective coating is to be hot applied coal tar or bitumen and Thickness of coat
The flow meter shall be magnetic type and shall of robust construction, fully
specifications:
-IP 67.
-Operating Temperature: -10 to +60oC
-Power Supply: 24 VDC
-Output Signal: 4-20 Ma
-Accuracy: ± 0.5% of measured value.
-Repeatability: ± 0.5% of measured value.
Transducer with the following specifications:
-IP 68
-Operating Temperature: -10 to +60oC
-st.st. Diaphragm.
8.2. Quality Control Inspection and Testing
Formation levels shall be the true levels and compacted to at least 90% density, in
Install warning tape directly above utilities, (300 mm) below finished grade,
Air valves shall be installed at high points in pipe work to fulfill three functions.
Air Valves shall be tested for leak tightness in steps of 200 KN/M2 up to the
strength at 1.5 time maximum working pressure. Refer to the Specification for
Specification for Valves and Hydrants for water Utility service (331419) Clause
2.1 / 1 / B.
Fittings and joints: Permanently anchor fittings before testing and leave all joints
exposed for checking.
Maintain test pressure for specified test duration with pumping stopped.
Test pressure shall be 1.5 times the maximum sustained pressure. Refer to the
Test period shall be 2 hours and allowable leakage 0.02 liter/mm diameter/km
Mechanical test, hydrostatic test, leakage test; as per AWWA C503 Section 5.
The duration of the leakage test is one minute after all air has been exhausted.
The formwork shall be inspected by the Engineer after assembly on the work area
All reinforcement shall be free from dirt, mill scale, scaly rust, paint, grease, oil
All ready-mix concrete are delivered to the site with a batch ticket listing the
following:
- Truck number.
- Loading time.
- Slump
Concrete delivered at a temperature not less than 10°C not greater than 32°C.
Slump of concrete with admixture shall be in the range of 160mm to 200mm with
minimum or as per approved mix design. Refer to the Cast In-Place Concrete
At least six specimens shall be prepared per sample. Three of these shall be tested
at 7 days and three at 28 days. Refer to the Cast In-Place Concrete section
The free-drop height of concrete shall be not greater than 1.5m and the method of
The backfill shall be placed in uniform layers and each layer of material being
not less than 95% of maximum dry density complying with ASTM D1557 or
density of 90% of the maximum dry density complying with ASTM D1577 or
It is the general policy of CHEC to provide all employees, subcontractors and any other
All CHEC staff involved in field work should constantly remind themselves of these
requirements and be aware that each of them has a role to play in bringing this about
by the correct mental approach. In particular, the following should be given careful
consideration:
Plan and practice your escape routes and emergency procedures regularly;
9.2. Induction
Personnel on site shall undergo an initial site HSE induction from Contractor. Before
entry to the working areas are gained, this shall be site specific and details the hazards
most likely present within the site, the emergency procedures, and site-specific
restrictions.
9.3. Personal Protective Equipment
Appropriate PPE shall always be worn by personnel when on site and involved in
survey operations. This will include, but not be limited to, coveralls, safety helmet,
safety boots, and gloves if handling wire or equipment. Other items of PPE shall be
worn as applicable.
9.4. Environment Protection
During surface clearance CHEC shall dispose vegetation and relevant rubbish to
proper locations.
Upon slurry incurred during foundation excavation works, if not suitable for
During concrete casting CHEC shall strictly control the remaining concrete
CHEC shall checkup all machinery equipment on a daily basis to avoid oil
contamination.
Risk Matrix
b) Consequences
a) Likelihood
1. Minor 2. Medium 3. Major 4. Catastrophic
A. Frequent Medium Medium High High
B. Occasional Medium Medium High High
C. Probable Low Medium Medium High
D. Remote Low Low Medium High
E. Improbable Low Low Medium Medium
Risk Rating and Action criteria
Risk level Priority Action required
High 1st Immediate action is required to eliminate or reduce the risk level
Medium 2nd Implement control measures within specified time frame
Tolerable risk, no additional control measure is needed but continuous monitoring is required to ensure that
Low 3rd
the existing controls are maintained effectively.
INITIAL RISK RESIDUAL
RATING RISK RATING
TASK/OPERATIONAL BASIC CAUSE OF
HAZARD DESCRIPTION Control Measures Responsible Person
STEPS HAZARD
L C R L C R