ID WBS Task Task Name Duration Start Finish Predecessors

Mode
1 1 2nd Floor mock up 97 days 26-03-24 16-07-24
2 1.13 Drawings 1 day 26-03-24 26-03-24
5 1.38 Approval & Vendor Onboarding 44 days 20-04-24 10-06-24
6 1.38.1 Submision of Sample for Approval 31 days 20-04-24 25-05-24
7 1.38.1.1 Civil items 26 days 20-04-24 20-05-24
8 1.38.1.1.71 Waterproofing material 1 day 20-04-24 20-04-24
9 1.38.1.1.72 Siporex blocks 7 days 25-04-24 02-05-24
10 1.38.1.1.73 Kadappa stone 1 day 20-04-24 20-04-24
11 1.38.1.1.75 Joining chemical 1 day 20-05-24 20-05-24
12 1.38.1.1.76 Window frames 1 day 15-05-24 15-05-24
13 1.38.1.1.77 Primer/Putty 1 day 20-04-24 20-04-24
14 1.38.1.1.78 Paints 1 day 20-04-24 20-04-24
15 1.38.1.1.79 Window Shutter 1 day 20-04-24 20-04-24
16 1.38.1.2 MEP items 31 days 20-04-24 25-05-24
17 1.38.1.2.67 Drain pipe 1 day 25-04-24 25-04-24
18 1.38.1.2.68 Point Wires witch switch socket1 day 25-04-24 25-04-24
19 1.38.1.2.69 Commode fittings 1 day 10-05-24 10-05-24
20 1.38.1.2.70 Light fixtures & ceiling fan 1 day 20-04-24 20-04-24
21 1.38.1.2.71 Copper pipe-Split AC 1 day 30-04-24 30-04-24
22 1.38.1.2.72 Split AC 1 day 18-05-24 18-05-24
23 1.38.1.2.73 FAPA & FFTG 1 day 15-05-24 15-05-24
24 1.38.1.2.74 Exhaust fan 1 day 25-05-24 25-05-24
25 1.38.6 Approval from PEPL 34 days 02-05-24 10-06-24
26 1.38.6.1 Civil items 34 days 02-05-24 10-06-24
27 1.38.6.1.53 Waterproofing material 1 day 25-05-24 25-05-24
28 1.38.6.1.54 Siporex blocks 1 day 06-05-24 06-05-24
29 1.38.6.1.55 Kadappa stone 1 day 10-05-24 10-05-24
30 1.38.6.1.56 Cement bags 1 day 02-05-24 02-05-24
31 1.38.6.1.57 Joining chemical 1 day 10-05-24 10-05-24
32 1.38.6.1.58 Window frames 1 day 25-05-24 25-05-24
33 1.38.6.1.59 Primer/Putty 1 day 30-05-24 30-05-24

Page 1
ID WBS Task Task Name Duration Start Finish Predecessors
Mode
34 1.38.6.1.60 Paints 1 day 30-05-24 30-05-24
35 1.38.6.1.61 Window Shutter 1 day 10-06-24 10-06-24
36 1.38.6.2 MEP items 34 days 02-05-24 10-06-24
37 1.38.6.2.51 Drain pipe 1 day 10-05-24 10-05-24
38 1.38.6.2.52 Point Wires witch switch socket1 day 20-05-24 20-05-24
39 1.38.6.2.53 Commode fittings 1 day 25-05-24 25-05-24
40 1.38.6.2.54 Light fixtures & ceiling fan 1 day 02-05-24 02-05-24
41 1.38.6.2.55 Copper pipe-Split AC 1 day 25-05-24 25-05-24
42 1.38.6.2.56 Split AC 1 day 01-06-24 01-06-24
43 1.38.6.2.57 FAPA & FFTG 1 day 01-06-24 01-06-24
44 1.38.6.2.58 Exhaust fan 1 day 10-06-24 10-06-24
45 1.38.6.3 Vendor On-boarding 1 day 15-05-24 15-05-24
46 1.38.6.3.1 Interior & Finishing 1 day 15-05-24 15-05-24
47 1.16 Procurement From IBC 41 days 04-05-24 20-06-24
67 1.41 Client Procured Materials 24 days 20-05-24 15-06-24
75 1.42 Finishing 43 days 22-05-24 10-07-24
101 1.43 Corridor Finishing 44 days 22-05-24 11-07-24
110 1.44 MEP 13 days 02-07-24 16-07-24
111 1.44.17 Point wiring 7 days 02-07-24 09-07-24 99FF+3 days
112 1.44.18 Cable laying/DB incomer 4 days 09-07-24 12-07-24 111FF+3 days
113 1.44.19 Switch box Installation 6 days 09-07-24 15-07-24 112FF+2 days
114 1.44.20 CP fittings & sanitary wares 7 days 06-07-24 13-07-24 99
115 1.44.21 FAPA 10 days 03-07-24 13-07-24 99FF+7 days
116 1.44.22 FFTG 8 days 08-07-24 16-07-24 115FF+2 days
117 1.44.23 Split AC copper piping & leak testing7 days 03-07-24 10-07-24 93,99FF+4 days
118 1.44.24 Split Ac indoor and outdoor Installation
11 days 03-07-24 15-07-24 99FF+8 days

Page 2
Resource Names April 2024 May 2024 June 2024 July 2024
12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20

Page 3
Resource Names April 2024 May 2024 June 2024 July 2024
12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20

Page 4
August 2024 September 2024 October 2024 November 2024 December 2024
20 25 30 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12

Page 5
August 2024 September 2024 October 2024 November 2024 December 2024
20 25 30 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12

Page 6