Gantt (Proposed Mercado Road)
Gantt (Proposed Mercado Road)
Gantt (Proposed Mercado Road)
Mobilization 100%
1 1 3 1
Project Billboard 100%
1 1 1 1
Occupational Safety and Health Program 30%
1 145 2 145
Removal of Existing Concrete
20 18 10 18
Aggregate Base Course 50%
19 35 26 35
Portland Cement Concrete Pavement
4 91 4 6
Demobilization 0%
146 1 146 1
Notes:
First pouring Feb.17 As of March 07, 2024 - the total accomplisments are 49.5%.