All bidders must bid on the manufacturers listed in the specifications. Failure to provide a bid that is based on the
manufacturers listed may result in deeming this proposal to be non-responsive.
Bidders are encouraged to bid alternative manufacturers by separately listing manufacturer. model and total cost
differential in the Bidders Alternates.
______________________________________________________________________________________________________
M/s SHASTRI ASSOCIATES 2 APPROVED MAKES
PROPOSED CONSTRUCTION OF UNIVERSAL SCHOOL OF ADMINISTRATION
_____________________________________________________________________________________________
28 Sealant 3M
NOTE:
1. The Contractor shall produce samples before procurement of the material for approval of the Architect for all
materials required for Works. The material of the makes out of the above as approved by the Architect shall
be used on the work
2. In respect of materials for which approved makes are not specified as above, the same shall be decided by
the Architect and shall be as per sample got approved from the Architect before procurement.
3. The Contractor shall submit samples of all materials in advance for approval.
______________________________________________________________________________________________________
M/s SHASTRI ASSOCIATES 3 APPROVED MAKES