Professional Documents
Culture Documents
Lightning Transients
Lightning Transients
Lightning Transients
DIgSILENT PowerFactory *
This example provides an introduction to lightning Lightning transients are atmospheric discharges. For
transients analysis with PowerFactory. Detailed power systems, generally discharges between thun-
models for overhead lines, substations and light- derclouds and overhead lines are of interest. Ac-
ning impulses are presented and explained. cording to Figure 1 lightning transients can be distin-
Based on the simulation model fast front lightning guished in two categories:
overvoltages are investigated in various study
cases. Both shielding failure and back-flashover • Shielding failure lightning transient: the light-
lightning transients are considered. ning flash bypasses the shielding of the over-
head line and strikes a phase conductor directly.
The following topics are included in the applica- • Back-flashover lightning transient: the light-
tion example: ning flash terminates on the tower or shield-
• Power system modelling for fast front tran- ing wire. The lightning strike is followed by a
sients flashover from the tower cross arm to the phase
conductor via the insulator.
• Lightning transients assessment
Both shielding failure and back-flashover lightning
• Fast front overvoltages (FFO) transients can cause severe overvoltages in nearby
substation and outages of the subjected overhead
• Statistical analysis line. Both overvoltages and the outage rate can be
assessed with a detailed simulation model of the cor-
responding overhead line and substation.
Substation
• Detailed model of 7 132 kV overhead line spans • Substation equipment such as transformers,
and final termination span surge arresters, circuit breakers, switches, CTs,
VTs etc.
• Detailed model of the 132 kV substation busbar
system The simulation model is described in detailed in the
subsequent subsections.
• Simplified model of 132 kV substation equipment
Substation
Figure 2: Application example: 132 kV overhead line and 132/33 kV substation of a hydro power plant
2.1 Overhead Line The geometry of the overhead line that is used in this
application example is shown in Figure 3 and includes
The analysis of lightning transients requires a detailed three phase wires (PW) A, B and C and one shielding /
model of the overhead line. The following input data is ground wire (GW). The X-Y coordinates of the conduc-
necessary for such a model: tors can be derived from Figure 3. The transmission
line insulator length is assumed to be 2 m. The corre-
• X-Y coordinates of each conductor and shield sponding coordinates of each conductor at the tower
wire are documented in Table 1.
Rev.1 2
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
The sag for the 132 kV is assumed as follows: Table 1: X-Y coordinates of multiphase system at the
tower
• Phase conductors: 6 m
20 m
26 m
Rev.1 3
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
2.2 EMT Line Model PowerFactory provides different line models for EMT
simulations. The following models are available:
The multiphase line model for EMT simulations in • Lumped PI-model
PowerFactory is based on the above input parameters
and created using the following elements and types: • Distributed Constant Parameter, also known as
Bergeron model
• ElmLne to represent the 3-phase line and single
phase shielding wire • Distributed Frequency Dependent Parameter
Modal Domain model, also known as J. Marti
• TypCon to define the phase conductor and model
shielding wire
• Distributed Frequency Dependent Phase Do-
• TypTow to define the tower geometry and spe- main model, also known as universal line model
cific earth resistivity (ULM)
• ElmTow to define the multiphase coupled sys- The lumped PI model is not suitable for lightning tran-
tem sients due to its limitations with regard to distributed
line parameters.
Based on the above input parameters, internal rou-
tines in PowerFactory calculate the frequency depen- In this application example, the Distributed Frequency
dent impedance and admittance matrix for the com- Dependent Modal Domain Parameter line model is
plete multiphase system according to Figure 6. used.
Rev.1 4
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
2.3 Overhead Line Tower tion 3. The equation is based in the height of the major
tower section ℎ𝑀 𝐴𝑇 𝑆 and the speed of light 𝑐.
For lightning transients studies, transmission line tow-
ers are included in the simulation model as well. The
towers are represented by several line sections and ℎ
𝜏𝑀 𝐴𝑇 𝑆 = 𝑀 𝐴𝑇 𝑆 (3)
circuit elements, according to the tower structure. 0.85 · 𝑐
The tower model that is used in this application exam- The height of the major tower section and the equiva-
ple is shown in Figure 7 and includes: lent radius are assumed as follows:
• Major tower section (MATS) from ground to first
• ℎ𝑀 𝐴𝑇 𝑆 = 20 𝑚
cross arm
• 𝑟𝑀 𝐴𝑇 𝑆 = 5 𝑚
• Minor tower sections (MITS) representing the
short tower sections and cross arms Thus, the surge impedance of the tower is 140 Ω and
the propagation speed is 78.4 ns.
′ 1
𝐶 = = 0.028 𝜇𝐹/𝑘𝑚 (4)
𝑍𝐶 · (ℎ /𝜏 )
𝑀𝑇 𝑆 𝑀𝑇 𝑆
′ 𝑍𝐶
𝐿 = = 0.55𝑚𝐻/𝑘𝑚 (5)
ℎ /𝜏
𝑀𝑇 𝑆 𝑀𝑇 𝑆
MITS
The inductance and capacitance can be defined in the
MATS
TypTow by selecting the Input Mode "Electrical Param-
eter" and defining the L’ and C’ on the Load Flow page.
The major tower section (MATS) is modelled as a 2.4 Transmission Line Insulators
lossless single phase distributed parameter line. The
surge impedance of the tower is calculated according
to equation 2, [1]. For lightning transient studies, the insulators are rep-
resented by voltage-dependent switches in parallel
with capacitances according to Figure 8. In steady
state operation of the overhead line, the voltage-
√ ℎ
𝑍𝑀 𝐴𝑇 𝑆 = 60 · (𝑙𝑛(2 · 2 · ( 𝑀 𝐴𝑇 𝑆 )) − 1) (2) dependent switch is open and the insulator is repre-
𝑟𝑀 𝐴𝑇 𝑆 sented by the lumped capacitance only.
Rev.1 5
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
10 pF to 100 pF. In this application example, a capaci- model. It closes the switch if the voltage exceeds the
tance of 20 pF is assumed [4]. dielectric strength of the line insulator. According to
Figure 9, the dielectric strength of the insulator is not
During the lightning transient, the voltage-dependent only a function of the overvoltage magnitude, but also
switch is controlled and triggered by a flashover waveform and duration.
Insulator Model
Lumped Dynamic
capacitance Flashover Model
Flashover Trigger
Rev.1 6
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
voltage across the insulator is continuously compared difference across the insulator exceeds the streamer
to the time dependent withstand voltage of the insu- inception voltage.
lator. If the voltage across the switch exceeds the
withstand voltage during the simulation, the switch is The streamer phase can generally be neglected. The
closed, modelling the flashover. propagation of the leader is described in terms of the
instantaneous values of its velocity. The leader veloc-
The time-dependent withstand voltage is a function of ity can be calculated according to the following expres-
the insulator length and is calculated according to the sion [1]:
following equations [4]:
[︂ ]︂
𝑑𝑙 𝑢(𝑡)
= 𝑣 = 𝑘 · 𝑢(𝑡) · − 𝐸50
𝐾 𝑑𝑡 𝑑𝑔 − 𝑙𝑙 (𝑡)
𝑈𝑓 = 𝐾1 + 2 (6)
𝑡0.75
where
𝐾1 = 400 · 𝐿 (7) 𝑑𝑔 is the gap length (length of the insulator)
𝑙𝑙 (𝑡) is the leader length
𝐾2 = 710 · 𝐿 (8) 𝑢(𝑡) is the actual (absolute value) voltage in the gap
𝐸50 average field at the critical flashover voltage CFO
The model is based on the streamer and leader propa- All three models for transmission line insulators are
gation physics during the transient. Initially, a streamer available in PowerFactory. In this application exam-
propagates along the insulator string when the voltage ple, the leader progression model (LPM) is used.
∆𝑢
Flashover Trigger
Rev.1 7
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
Resistance / Ω
be modelled either with a simple constant resistance
25
or a non-linear model:
20
Power Frequency Resistance Model: 15
The grounding system is simply a constant resistance
10
which corresponds to the power frequency resistance
of the tower. 5
0
Impedance Model with Soil Ionisation: 0 50 100 150 200
The injection of large currents into the ground results Discharge current / kA
in ionisation effects that cause a reduction of the ef-
fective grounding resistance during the transient. Figure 11: Transient resistance of the grounding sys-
tem
The non-linear grounding resistance as a function of
the current injected into the grounding system can be
calculated according to the following equation [1]:
2.6 Simulation Model Overhead Line
Figure 11 shows the high current transient resistance The lightning impulses ElmImpulse that are used to
of an overhead line tower grounding system as a simulate a shielding and back-flashover transient are
function of the discharged current injected for various connected at tower T04 and have to be triggered by a
power frequency resistances 𝑅0 . parameter event during the simulation.
Rev.1 8
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
T04
GW Strike PW Strike
Grid
V
~
OHGW_T01-T02 OHGW_T02-T03 OHGW_T03-T04 OHGW_T04-T05 OHGW_T05-T06 OHGW_T06-T07 OHGW_T07-T08 OHGW_Termination
_Lightning_StatisticalAnalysis
Figure 12: 132 kV overhead line model for lightning transient analysis
2.7 Substation Model The busbars are tubular pipes with specifications ac-
cording to Table 5. The busbar pipes are modelled
The 132/11 kV substation of the hydro power plant in- with TypCon.
cludes the following equipment:
For simplicity, elbows, bending etc. of the busbar sys-
• Busbars tem are not considered in this example.
This application example includes most of the above Table 5: 132 kV busbar specifications
components. The PowerFactory model is shown in
Figure 14 and explain in the following sections. Parameter Value
Conductor Type Tubular
Busbar System:
The AIS busbar system is modelled with a geometric DC-Resistance 0.005 Ω/km
line model using distributed line parameters. The gen- GMR 59.26 mm
eral layout of the busbar system is shown in Figure
13. Outer Diameter 60.0 mm
Inner Diameter 50.0 mm
2.8 m
Transformers:
2.8 m Transformers are modelled with the main electrical
parameters, such as MVA rating, rated voltages,
impedances and losses. The non-linear saturation
5.0 m
characteristic of the magnetising branch is not relevant
for lightning transients and can therefore be ignored.
Rev.1 9
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
• Inter-Winding capacitances HV-LV: 3 nF The values are based on [4] and assumed as follows:
The capacitances are modelled as lumped capaci- • Line-to-ground capacitance per side: 50 pF
tances at the HV and LV side of the transformer ter-
minals and as lumped capacitances between the HV • Line-to-Line capacitance: 5 pF
and LV terminals. The stray capacitances are defined
directly in the transformer element [9]. Instrument Transformers:
Instrument transformers such as voltage transformers,
Circuit Breaker and Switches: current transformers and power transformers are mod-
Circuit breakers and switches are modelled with elled with lumped elements. In this application exam-
lumped elements. In this application example, the cir- ple, it is assumed that power transformers (PT) are
cuit breaker and disconnecter line-to-line and line-to- installed at CB1, CB2 and CB3. The line-to-ground
ground stray capacitances are included only partially. capacitance is assumed th be 500 pF.
AIS_2.6
Bay4_AIS_2.2
DS4.2 Bay4_AIS_1.2
AIS_1.6
CB4
Bay4_AIS_2.1
DS4.1 Bay4_AIS_1.1
AIS_2.5
SA-TRF1 HV
DS_3.2
SA-TRF1 MV
Bay3_AIS_3.2 Bay3_AIS_4.2
AIS_1.5
TRF1
Bay3_AIS_1
CB3 Bay3_AIS_2
AIS_2.4
SG
G1
~
Bay3_AIS_3.1
DS_3.1 Bay3_AIS_4.1
CVT3
AIS_1.4
AIS_2.3
Bay1_AIS_4.2
DS1.2 Bay1_AIS_3.2
Bay1_AIS_2
CB1 Bay1_AIS_1
OHL-Substation
AIS_1.3
Bay1_AIS_4.1
DS1.1 Bay1_AIS_3.1
AIS_2.2
CVT1
CVT2
Bay2_AIS_3.2
DS_2.2 Bay2_AIS_4.2
AIS_1.2
TRF2
Bay2_AIS_1
CB2 Bay2_AIS_2
SG
G2
~
DS_2.1
AIS_2.1
SA-TRF2 MV
Bay2_AIS_3.1 Bay2_AIS_4.1
SA-TRF2 HV
AIS_1.1
Surge arresters are selected based on the maximum • Protective characteristic for switching impulses (
continuous operating voltage 𝑈𝑐 and expected tempo- 30/60𝜇𝑠) and lightning impulses (8/20𝜇𝑠)
rary overvoltages (TOV) in the system and defined by
the following parameters: For the analysis of lightning transient overvoltages,
the protective characteristic for the lightning impulse
Rev.1 10
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
time in s
0 0,2 0,4 0,6 0,8 1
In addition to the protective characteristic, the stray in- 0
-10
ductances of the connection leads have to be included
current in kA
-20
in the model and can be assumed with a typical value
-30
of 1 𝜇𝐻/𝑚. -40
-50
-60
-70
2.8 Lightning Flash
Figure 17: Lightning flash with several strokes [11]
35
most relevant for lightning transient analysis. 30
25
20
Lightning flashes usually comprise multiple strokes 15
10
(first stroke, subsequent and possibly continuous 5
strokes). The sequence of a typical lightning strike is 0
Rev.1 11
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
Lightning transient studies therefore have to be based quency fault current. The short circuit has to
on statistical parameters. be interrupted by tripping the line. The conse-
quence is an outage of the line and reduction of
The waveform is modelled according the recommen- the overhead line performance.
dation by for example CIGRE, IEC and IEEE. Figure
19 shows an example of a lightning flash with an am- Shielding Failure Lightning Transient
plitude of 31 kA and a front time of 5 𝜇𝑠 modelled ac- Overhead line phase conductors are usually protected
cording to the IEC waveform and CIGRE waveform. from lightning strikes by shielding / ground wires.
However, lightning flashes with small amplitudes can
Detailed information about lightning strike parameters penetrate the shielding of the overhead line and strike
and their modelling approach can be found in [3] and a phase conductor directly.
in [2].
The maximum amplitude 𝐼𝑚𝑎𝑥 that is able to penetrate
40 the shielding can be calculated based on the strik-
[kA] ing distance 𝑟𝐿𝐹 of the lightning flash, using electro-
30 geometric-models (EGM). The protective area of the
shielding wire increases with increasing amplitude of
the lightning flash amplitude due to an increase of the
20
striking distance with increasing amplitude.
-10
0 10 20 30 40 [us] 50
IEC (Heidler): Phase Current A
CIGRE: Phase Current A
0.75
𝑟𝐿𝐹 = 7.1 · 𝐼𝑚𝑎𝑥 (11)
Figure 19: Lightning flash with several strokes
3 Lightning Transients
The maximum lightning shielding failure lightning cur-
rent 𝐼𝑆𝐹 𝐼 that can penetrate the shielding of the over-
Lightning transients are associated with several prob-
head line can be calculated by the following equation
lems in power systems that include:
[10]:
• Fast Front Overvoltages
Lightning transients can cause fast front over-
voltages (FFO) that exceed the insulation
strength of substation equipment and other
equipment such as cables.
These overvoltages can result in an insulation ℎ+𝑦
1
failure and damage of the equipment. Lightning 𝐼𝑆𝐹 𝐼 = [ 2 ] 0.75 (12)
0.71 · (1 − 𝑠𝑖𝑛(𝛼))
overvoltages are especially relevant for system
with a voltage level below 300 kV.
• Overhead Line Outages
Lightning transients cause often a flashover
across the insulator. The flashover is an elec-
Depending on the overhead line geometry, the max-
tric arc between the phase conductor and tower
imum shielding failure current ranges from 10 kA to
cross arm. The electric arc provides a low ohmic
30 kA.
path between the ground (tower cross arm) and
phase conductor. Shielding failure lightning transients are usually only
The low ohmic path corresponds to a phase-to- investigated for lightning currents with amplitudes up
ground fault and will be followed by a power fre- to the maximum shielding failure current 𝐼𝑆𝐹 𝐼 .
Rev.1 12
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
100µ𝑠
Rev.1 13
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
and overvoltages in the substation. Considera- The active power control in the load flow calculation is
tion of surge arresters (see section 4.3); based on the dispatch of generators and loads. The
difference between load and generation is balanced
• “Back-Flashover Lightning I”: by the reference machine. The substation and over-
Simulation of a lightning strike to shield wire at head line are modelled as unloaded system for the
tower T04. Investigation back-flashover mecha- lightning transient analysis. The dispatch of the gen-
nism, travelling effects and overvoltages in the erators in the hydro power plant is P = 0 MW and Q =
substation (see section 4.4); 0 Mvar.
• “Back-Flashover Lightning II”: The voltage source at end of the termination sec-
Simulation of a lightning strike to shield wire at tion is used as reference machine (slack). It controls
tower T04. Investigation back-flashover mecha- the voltage to 1 p.u. at terminal Termination_PHW.
nism, travelling effects and overvoltages in the The unloaded overhead line generates approximately
substation. Consideration of surge arresters 2.4 Mvar of reactive power that is absorbed by the volt-
(see section 4.5); age source.
Rev.1 14
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
200
[kV]
107.921 kV
100
-53.999 kV
-100
-200
-300
0 3 6 9 12 [ms] 15
T04_PHW: Phase Voltage A
T04_PHW: Phase Voltage B
T04_PHW: Phase Voltage C
Figure 23: Instantaneous phase-to-earth voltage at 𝑡 = 0𝑠 (time instance for lighnting strike injection for the
upcoming simulations)
Rev.1 15
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
rent surge along the overhead line towards the sub- The transient voltages at transformer TRF-2 reach ap-
station from tower T04. The travel time along the span proximately 1500 kV and at circuit breaker CB3 al-
is approximately 𝜏 = 0.83 𝜇𝑠. most 2000 kV. These overvoltages exceed the dielec-
tric strength of the equipment by far and will result in
The fast front overvoltages (FFO) at the 132 kV level of insulation failures and thus damage of the equipment.
the substation are shown in Figure 27 . The transient
voltages are documented both for the transformer HV Based on the assessment of shielding failure light-
terminal (TRF-2 HV) at the open end of circuit breaker ning transients, surge arresters have to be installed in
CB3 as phase-to-earth and phase-to-phase voltages. the substation in order to protect the equipment from
shielding failure lightning transients.
20 1000
[kA] [kV]
15 0
10 -1000
20 1000
[kA] [kV]
5 -2000
15 0
0 -3000
10 -1000
-5 -4000
5 0 1 2 3 4 [us] 5 -2000 0 1 2 3 4 [us] 5
PW Strike: Phase Current T04_INS_SW-PHA: Voltage Difference
T04_INS_SW-PHB: Voltage Difference
0 -3000 T04_INS_SW-PHC: Voltage Difference
4 4
-5 -4000
[-] 0 Figure
1 24:
2 Lightning
3 strike and5 flashover
4 [us] [kA] 0mechanism
1 at 2tower T04
3 4 [us] 5
PW Strike: Phase Current T04_INS_SW-PHA: Voltage Difference
3 0
T04_INS_SW-PHB: Voltage Difference
T04_INS_SW-PHC: Voltage Difference
2 -4
4 4
[-] [kA]
1 -8
3 0
0 -12
2 -4
-1 -16
1 0 1 2 3 4 [us] 5 -8 0 1 2 3 4 [us] 5
T04_FOM_LPM-PHA: ll T04_INS_SW-PHA: Phase Current A/Terminal i
T04_FOM_LPM-PHB: ll
0 T04_FOM_LPM-PHC: ll -12
-1 -16
0 1 2 3 4 [us] 5 0 1 2 3 4 [us] 5
T04_FOM_LPM-PHA: ll T04_INS_SW-PHA: Phase Current A/Terminal i
T04_FOM_LPM-PHB: ll
T04_FOM_LPM-PHC: ll
Rev.1 16
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
8,00
[kA]
6,00
4,00
2,00
0,00
-2,00
0,00 2,00 4,00 6,00 8,00 [us] 10,00
OHPW_T01-T02: Phase Current A/Terminal j
OHPW_T02-T03: Phase Current A/Terminal j
OHPW_T03-T04: Phase Current A/Terminal j
2000 4000
[kV] [kV]
1500 3000
1000 2000
500 1000
0 0
-500 -1000
0 10 20 30 40 [us] 50 0 10 20 30 40 [us] 50
TRF-2 HV: Phase Voltage A Bay3_T5.1: Phase Voltage A
TRF-2 HV: Phase Voltage B Bay3_T5.1: Phase Voltage B
TRF-2 HV: Phase Voltage C Bay3_T5.1: Phase Voltage C
3000 3000
[kV] [kV]
2000 2000
1000 1000
0 0
-1000 -1000
-2000 -2000
0 10 20 30 40 [us] 50 0 10 20 30 40 [us] 50
TRF-2 HV: Line to Line Voltage A Bay3_T5.1: Line to Line Voltage A
TRF-2 HV: Line to Line Voltage B Bay3_T5.1: Line to Line Voltage B
TRF-2 HV: Line to Line Voltage C Bay3_T5.1: Line to Line Voltage C
Rev.1 17
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
The simulation setup and simulation sequence is iden- The phase currents and absorbed energy of surge ar-
tical to the previous study case (4.2). In contrast to the rester SA-TRF2 are documented in Figure 34. The
previous example however, the surge arresters in the peak current exceeds the nominal current of 10 kA.
substation are in service. The absorbed energy is relatively low.
The fast front overvoltages (FFO) at the 132 kV level of Based on the assessment of shielding failure lightning
the substation are shown in Figure 28 . The transient transients, the overvoltage protection concept is not
voltages are documented both for the transformer HV sufficient to protect the complete substation from over-
terminal (TRF-2 HV) at the open end of circuit breaker voltages.
CB3 as phase-to-earth and phase-to-phase voltages.
The installation of additional surge arresters, for ex-
The transient voltages at transformer TRF-2 are suffi- ample at the overhead line incomer bay, is required in
ciently limited by the HV surge arrester. However, the order to protect the complete substation from insula-
surge arrester can limit the overvoltages only within its tion failures due to lightning transients.
600 4000
[kV] [kV]
400 3000
200 2000
0 1000
-200 0
-400 -1000
0 10 20 30 40 [us] 50 0 10 20 30 40 [us] 50
TRF-2 HV: Phase Voltage A Bay3_T5.1: Phase Voltage A
TRF-2 HV: Phase Voltage B Bay3_T5.1: Phase Voltage B
TRF-2 HV: Phase Voltage C Bay3_T5.1: Phase Voltage C
600 3000
[kV] [kV]
300 2000
0 1000
-300 0
-600 -1000
-900 -2000
0 10 20 30 40 [us] 50 0 10 20 30 40 [us] 50
TRF-2 HV: Line to Line Voltage A Bay3_T5.1: Line to Line Voltage A
TRF-2 HV: Line to Line Voltage B Bay3_T5.1: Line to Line Voltage B
TRF-2 HV: Line to Line Voltage C Bay3_T5.1: Line to Line Voltage C
Rev.1 18
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
12 0,08
[kA] [MWs]
9 0,06
6 0,04
3 0,02
0 -0,00
-3 -0,02
0 10 20 30 40 [us] 50 0 10 20 30 40 [us] 50
SA-TRF2 HV: Phase Current A SA-TRF2 HV: MO absorbed Energy
SA-TRF2 HV: Phase Current B SA-TRF2 HV: MO absorbed Energy
SA-TRF2 HV: Phase Current C SA-TRF2 HV: MO absorbed Energy
Rev.1 19
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
4.4 Back-Flashover Lightning I the tower top and tower cross arms increase pro-
portionally to the lightning current amplitude, surge
impedance of the tower and grounding impedance.
This study case investigates the overvoltages in the
substation after a back flashover caused by a lightning According to Figure 30 the voltage at the tower ex-
strike into the ground wire of the overhead line. ceeds 2000 kV. The peak voltage difference across the
line insulator in phase A at tower T04 reaches approx-
The simulation is carried out for a lightning impulse
imately 2700 kV at 𝑡 = 2.2 𝜇𝑠. This voltage magni-
with the following parameters:
tude with its corresponding voltage waveform exceeds
• Front time: 3 𝜇𝑠 the dielectric strength of the insulator and results in a
back-flashover from the tower cross arm to the phase
• Tail time: 285 𝜇𝑠 conductor in phase A.
• 𝑡 = −10 𝜇𝑠: The fast front overvoltages (FFO) at the 132 kV level of
Integration step size event to reduce step size the substation are shown in Figure 32. The transient
from 100 𝜇𝑠 to 1 𝑛𝑠 voltages exceed the overvoltages from the shielding
failure lightning transits due to the steeper impinging
• 𝑡 = 0 𝜇𝑠: surges (short rise time compared to the direct strike).
Event to trigger the lightning flash
As for the shielding failure lightning transients, the
• 𝑡 = 50 𝜇𝑠: overvoltages in the substation exceed the dielectric
End of simulation strength of the equipment also for back-flashover light-
ning transients by far if surge arresters are not in-
The simulation results are shown in the plots below. stalled and will result in insulation failures and thus
damage of the equipment.
Figure 30 shows the lightning strike impulse with a
peak amplitude of 100 kA. The lightning current prop- Based on the assessment of back-flashover lightning
agates through the steel tower into the grounding sys- transients, surge arresters have to be installed in
tem and from the grounding system into the earth. the substation in order to protect the equipment from
As result of the current propagation, the potential at shielding failure lightning transients.
Rev.1 20
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
120 4000
[kA] [kV]
90 3000
60 2000
30 1000
0 0
-30 -1000
0 1 2 3 4 [us] 5 0 1 2 3 4 [us] 5
GW Strike: Phase Current T04_INS_SW-PHA: Voltage Difference
T04_INS_SW-PHB: Voltage Difference
T04_INS_SW-PHC: Voltage Difference
4 10,0
[-] [kA]
3 7,5
2 5,0
1 2,5
0 0,0
-1 -2,5
0 1 2 3 4 [us] 5 0 1 2 3 4 [us] 5
T04_FOM_LPM-PHA: ll T04_INS_SW-PHA: Phase Current A/Terminal i
T04_FOM_LPM-PHB: ll
T04_FOM_LPM-PHC: ll
6,00
[kA]
4,00
2,00
0,00
-2,00
-4,00
0,00 2,00 4,00 6,00 8,00 [us] 10,00
OHPW_T01-T02: Phase Current A/Terminal j
OHPW_T02-T03: Phase Current A/Terminal j
OHPW_T03-T04: Phase Current A/Terminal j
Rev.1 21
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
1200 1500
[kV] [kV]
900 1000
600 500
300 0
0 -500
-300 -1000
0 10 20 30 40 [us] 50 0 10 20 30 40 [us] 50
TRF-2 HV: Phase Voltage A Bay3_T5.1: Phase Voltage A
TRF-2 HV: Phase Voltage B Bay3_T5.1: Phase Voltage B
TRF-2 HV: Phase Voltage C Bay3_T5.1: Phase Voltage C
1000 3000
[kV] [kV]
500 2000
0 1000
-500 0
-1000 -1000
-1500 -2000
0 10 20 30 40 [us] 50 0 10 20 30 40 [us] 50
TRF-2 HV: Line to Line Voltage A Bay3_T5.1: Line to Line Voltage A
TRF-2 HV: Line to Line Voltage B Bay3_T5.1: Line to Line Voltage B
TRF-2 HV: Line to Line Voltage C Bay3_T5.1: Line to Line Voltage C
Rev.1 22
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
600 1500
[kV] [kV]
400 1000
200 500
0 0
-200 -500
-400 -1000
0 5 10 15 20 [us] 25 0 5 10 15 20 [us] 25
TRF-2 HV: Phase Voltage A Bay3_T5.1: Phase Voltage A
TRF-2 HV: Phase Voltage B Bay3_T5.1: Phase Voltage B
TRF-2 HV: Phase Voltage C Bay3_T5.1: Phase Voltage C
600 3000
[kV] [kV]
300 2000
0 1000
-300 0
-600 -1000
-900 -2000
0 5 10 15 20 [us] 25 0 5 10 15 20 [us] 25
TRF-2 HV: Line to Line Voltage A Bay3_T5.1: Line to Line Voltage A
TRF-2 HV: Line to Line Voltage B Bay3_T5.1: Line to Line Voltage B
TRF-2 HV: Line to Line Voltage C Bay3_T5.1: Line to Line Voltage C
Rev.1 23
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
12 0,08
[kA] [MWs]
9 0,06
6 0,04
3 0,02
0 -0,00
-3 -0,02
0 10 20 30 40 [us] 50 0 10 20 30 40 [us] 50
SA-TRF2 HV: Phase Current A SA-TRF2 HV: MO absorbed Energy
SA-TRF2 HV: Phase Current B SA-TRF2 HV: MO absorbed Energy
SA-TRF2 HV: Phase Current C SA-TRF2 HV: MO absorbed Energy
Rev.1 24
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
4.6 Statistical Lightning Analysis I • Impulse amplitude range (minimum and maxi-
mum amplitude) for phase wire strikes (shield-
In reality, waveform and amplitude of lightning flashes ing failure transient) and tower strikes (Back-
are unique for each lightning flash event. Extensive flashover transients)
measurement campaigns have been carried out in the • Set of terminals to record overvoltages (line-to-
last decades in order to derive the probability distri- ground and line-to-line)
bution of the lightning flash parameters, mainly ampli-
tude, front time and tail time. • Set of surge arresters to record absorbed cur-
rents and energy during the simulation
In a simplified approach, the probability distribution of
the amplitude can be calculated according to equation The script executes a simulation for each lightning
13. The equation can be used to calculate the proba- strike amplitude in the define range. The front time
bility that the lightning amplitude will exceed a critical is calculated based on the amplitude for each run. Af-
current 𝐼𝑐 . The mean values of the amplitude distribu- ter each simulation, the maximum line-to-ground and
tion is 31 kA [2]. line-to-line voltage for each selected terminal and ab-
sorbed currents and energy for each selected surge
arrester are stored in an additional result object Sta-
1 tisticalAnalysis.ElmRes
𝑃 (𝐼 > 𝐼𝑐 ) = (13)
1 + ( 𝐼𝑐 )2.6 The simulation in each run is carried out with the fol-
31 𝑘𝐴
lowing parameters for the lightning flash in this exam-
ple:
The front time to reach the lightning flash amplitudes
𝐼𝐹 can be approximated depending on the amplitude • Front time: Statistical variation based on equa-
range as follows: tion 14 and 15
• 3 kA < 𝐼𝐹 < 20 kA: • Tail time: 285 𝜇𝑠
Rev.1 25
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
2000 2000
[kV] [kV]
1600 1600
1200 1200
800 800
400 400
0 0
0 40 80 120 160 200 0 40 80 120 160 200
x-Axis: TRF-2 HV: Strike current x-Axis: Bay3_T3: Strike current
TRF-2 HV: m:U:A Bay3_T3: m:U:A
TRF-2 HV: m:U:B Bay3_T3: m:U:B
TRF-2 HV: m:U:C Bay3_T3: m:U:C
Figure 35: Peak fast front overvoltages (phase-to-earth for phase A, B and C) at terminal TRF-2 HV and
Bay3_T3 for each simulation run (3 kA to 200 kA)
Rev.1 26
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
4.7 Statistical Lightning Analysis II The results of the multi-run simulation are shown
in Figure 36. The plot show the peak overvolt-
age (phase-to-earth) for each simulation run (1 kA to
200 kA) for terminal TRF-2 HV and Bay3_T3.
The simulation setup and simulation sequence is iden-
tical to the previous study case (4.6). In contrast to the Furthermore, Figure 37 documents the absorbed peak
previous example however, the surge arresters in the phase currents and cumulative energy of the surge ar-
substation are in service. rester SA-TRF2 HV for each simulation run.
500 2000
[kV] [kV]
400 1600
300 1200
200 800
100 400
0 0
0 40 80 120 160 200 0 40 80 120 160 200
x-Axis: TRF-2 HV: Strike current x-Axis: Bay3_T3: Strike current
TRF-2 HV: m:U:A Bay3_T3: m:U:A
TRF-2 HV: m:U:B Bay3_T3: m:U:B
TRF-2 HV: m:U:C Bay3_T3: m:U:C
Figure 36: Peak fast front overvoltages (phase-to-earth for phase A, B and C) at terminal TRF-2 HV and
Bay3_T3 for each simulation run (3 kA to 200 kA)
Rev.1 27
LIGHTNING TRANSIENTS APPLICATION EXAMPLE
16 100
[kA]
12 75
8 50
4 25
0 0
-4 -25
0 40 80 120 160 200 0 40 80 120 160 200
x-Axis: SA-TRF2 HV: Strike current x-Axis: SA-TRF2 HV: Strike current in kA
SA-TRF2 HV: m:I:bus1:A SA-TRF2 HV: s:Emov_a in p.u. (base: 0,00 kA)
SA-TRF2 HV: m:I:bus1:B SA-TRF2 HV: s:Emov_b in p.u. (base: 0,00 kA)
SA-TRF2 HV: m:I:bus1:C SA-TRF2 HV: s:Emov_c in p.u. (base: 0,00 kA)
Figure 37: Absorbed peak currents and cumulative energy of surge arrester SA-TRF2 HV for each simulation
Rev.1 28
LIGHTNING TRANSIENTS APPLICATION EXAMPLE