Professional Documents
Culture Documents
Switching Transients
Switching Transients
DIgSILENT PowerFactory *
is connected to the substation through a high voltage range which may vary from DC to several MHz
cable system.
• Distributed parameter line models
• Non-linear saturation characteristics of induc-
2 Simulation Model tances
• Stray inductances and capacitances
The investigation of electromagnetic transients re- • Electric arcing models for switches and insula-
quires an accurate representation of relevant power tors
system components. Depending on the transient be-
ing analysed the network model should include: The following subsections describe the models of the
power system components of the transmission system
• Valid representation of the model for a frequency shown in Figure 1.
~
Voltage Levels SG SYM
C Bank
8
400 kV
110 kV -2
TRF
33 kV
27 kV Load NE
PP400-1 SS Central
NE-400
PP400-2
CAB-NPP1 CAB-NPP2
SS North
N400-1
Load N
SR CE-1.1
SS West N400-2
0
Load E-1
CE-1.2
E110-1
0
OHL-WN OHL-NC
CE-2.1
TRF1
Load E-2
TRF2
CE-2.2
0
E110-2
Slack
OHL-WC1.1 OHL-WC1.2 OHL-WC1.3
WF-110 WF-33.1
TRF2
5
WTG1
W400-1 W400-2
WTG2
Rev.2 2
SWITCHING TRANSIENTS APPLICATION EXAMPLE
IS.R0.2
C110-B1-..
Bay01
IS.R0.1 CB.R0
IS4.3
Bay1
IS.R6.3 IS4.2 CB4 IS4.1 CE-1.1
IS.R3.3
Bay02
IS.R6.2 CB.R6 IS.R6.1
Bay07
OHL-NC
IS.R3.1 IS.R3.2 OHL-CN.. IS7.2 CB7 IS7.1 CE-1.2
IS.R5.2 CB.R5 IS.R5.1
Bay2
IS7.3
Bay03
OHL-CN..
C400-B2..
IS.R5.3
C110-B2-..
IS.R1.3
IS6.3
Bay04
IS.R1.2 CB.R1 IS.R1.1
Bay6
SR
IS.R4.1 IS6.1 CB6
C110-B3-..
C400-3-B8_CB IS.R4.2 IS6.2
Bay08
IS.R4.3 TRF1 IS3.3
C400-B8-SA1
Bay3
C110-B6-SA1
IS3.2 CB3 IS3.1 CE-2.2
CBS1
CBS2
CWC1_comp
C110-B7-SA1
IS.L2.3 IS2.2 CB2 IS2.1 CE-2.1
C400-B5-SA1
C400-1-B9_CB
Bay09
Bay4
IS.L2.1 IS.L2.2 IS2.3
OHL-WC1.3
TRF2
IS5.1 CB5 IS5.2
C110-B4-..
C400-B9..
Bay7
IS5.3
Bay05
IS.L3.3
C400-B1..
IS1.3
Bay5
IS1.2 CB1 IS1.1
Bay10
CE-3
IS.L1.3
IS0.2
C110-B5..
CWC-2_comp IS.L0.2
Bay8
CB0 IS0.1
Bay06
IS.L0.1 CB.L0
C110.. C110..
C400-1 C400-2
Overhead Lines
Overhead lines can be modelled based on their ge- Figure 3: 400 kV double circuit overhead line structure
ometry and material characteristics of the conductors
and earth return path in PowerFactory.
The Y-values which are entered in PowerFactory cor-
The geometry is entered in PowerFactory using the respond to the average height of the conductor and
X-Y coordinates of the phase conductors and ground ground wire along the line. The average height in-
wires as shown in Figure 3. The graph shows the ge- cludes the sag and is calculated as follows:
ometry of the 400 kV and 110 kV double circuit over-
head line being used in the network model (Figure 1).
Rev.2 3
SWITCHING TRANSIENTS APPLICATION EXAMPLE
Transposition
Rev.2 4
SWITCHING TRANSIENTS APPLICATION EXAMPLE
resistivity, relative permittivity and permeability is en- the generator’s 27 kV terminal with the 400 kV terminal
tered in PowerFactory. of the transmission grid.
The cables are layed directly in ground in flat formation Furthermore two YNd5 50 MVA transformers are in-
with a distance of 0.7 m apart. Two cable systems con- stalled in the wind farm and connect the 33 kV substa-
nect the substation North with the Power Plant (see tion of the wind farm with the 110 kV terminal of the
Figure 1). They are laid in parallel. The layout of sub-transmission system.
the complete cable system is shown in Figure 6. The
earth resistivity is assumed to be 100 Ωm. Saturation Model
2.2 Transformers
Transformer Types
Rev.2 5
SWITCHING TRANSIENTS APPLICATION EXAMPLE
The residual flux of the transformer is taken into con- • Substation Central
sideration by defining the initial flux in the transformer
element. The residual flux is defined in the phase do- • Substation Power Plant
main. • Substation Wind Farm
2.3 Generator
N400-1
EMT simulation.
IS1.2 IS3.2
N400-2
Bay1 Bay2
2.4 Loads
OH..
OHL-WN
The loads are modelled as constant impedance loads.
The network model comprises 5 substations: The substation layout includes two-breaker and 1 1/2-
breaker configuration. The two-breaker configuration
• Substation West is shown in Figure 2. In this case the circuit breaker,
branch disconnector and instrumental transformer are
• Substation North
duplicated in each branch. Busbar interchange and
Rev.2 6
SWITCHING TRANSIENTS APPLICATION EXAMPLE
isolation of one busbar for maintenance is possible. versus time under the influence of blast pressure,
One branch breaker can be taken out for maintenance arc length and arcing time as evaluated form circuit
at any time without interrupting operation. breaker tests.
The 1 1/2-breaker design is applied in Figure 9. Fewer For Transient Recovery Voltage (TRV) studies, the
breakers are needed here for the same flexibility as breaker capability curve is modelled according to
above. Isolation without interruption is possible. All IEC 62271-100 with a 2-parameter or 4-parameter
breakers are normally closed. Uninterrupted supply is curve depending on the voltage level and circuit
thus maintained even if one busbar fails. breaker rating.
Circuit breakers (CB) are modelled as ideal switches Surge arresters are used to protect electrical equip-
for most transients. ment in substations, such as transformers, circuit
breakers and bushings, against the effects of over-
For some transients, also the influence of the electri- voltages caused by incoming surges. Such overvolt-
cal arc needs to be considered. In example that is rep- ages can be caused by a direct or nearby lightning
resented in section 4.4, the electrical arc is modelled strike and other electromagnetic transients such as
according to [3] and represented three arms, one for e.g. switching operation in the power supply system.
each phase.
Surge arresters present a nonlinear resistor and are
Each arm is represented by two parallel switches and characterised by a highly non-linear U-I curve. During
a series resistance according to Figure 10. During the normal operating voltages surge arresters have an ex-
switching transient, the switch on the right side is ini- tremely high resistance and a relatively low resistance
tially opened (at execution time). The current is com- during transient overvoltages.
mutated then to the other path of the arm. The electri-
cal arc is represented by the resistance in the parallel Metal oxide arresters (MOA) are usually used for
branch (ElmSind) and the current is interrupted at the surge arresters and in most cases are connected from
next zero-crossing. phase to ground. The charactersitic U-I curve of an
surge arrester which is necessary for an EMT study
is usually provided in the vendor datasheet and is en-
tered in PowerFactory in tabular form.
Figure 10: Detailed circuit breaker arcing model Figure 11: Surge arrester 𝑈 − 𝐼 characteristic
Rev.2 7
SWITCHING TRANSIENTS APPLICATION EXAMPLE
A capacitor bank is installed at the substation North- When a completely demagnetised transformer is en-
East with a rated reactive power of 50 Mvar per step. ergised the flux Ψ in the iron core is zero at the instant
It is also switchable and has 10 steps. of switching. The instantaneous voltage in Figure 12
is zero at this instance. Due to the 90∘ phase shift
between the flux Ψ and the voltage, the flux ought to
be at its peak in steady state operation. However, due
3 Switching Transients to the initial condition (Ψ equals zero) the flux starts at
zero. As a result the curve of the flux Ψ is shifted by
Switching in electrical power systems re-configures Ψ𝑚 upwards in the first cycle of the transient. Thus,
the network topology for the following purposes: the flux starts at zero and then reaches a maximum of
2Ψ𝑚 in the first cycle as indicated in Figure 12 [1].
• Isolation and Earthing
Taking into account a residual flux of Ψ𝑅 in the iron
• Busbar-Transfer Switching core, the curve is shifted upwards even further as in-
dicated in Figure 12 and reaches a maximum peak
• Load Switching
value of Ψ𝑅 + 2Ψ𝑚 . The magnetization curve is now
• Fault-Clearing operating in the saturated region and the relationship
between the flux Ψ𝑚 and the current 𝑖 are no longer
The following switching transients are analysed in this governed by a linear relationship. This causes high
application example: and distorted inrush currents as shown in the graph.
• Transformer Energisation
ψ ψ, B
• Overhead Line Energisation ψR + 2 ψm
2 ∙ ψm
• Inductive Load Switching
ψR
• Fault-Current Interruption Switching
H, i
3.1 Saturation
For simulating electromagnetic transients such as Figure 12: Saturation and inrush current
transformer inrush currents or ferro-resonance, reac-
tor / transformer core saturation needs to be included
in the model of the transformer. The non-linear be-
haviour of a typical transformer iron core is shown in
3.2 Travelling Waves
Figure 12 [1].
When investigating transient and high-frequency
The solid lines represent the steady state voltage and steady-state phenomena, it is necessary to account
flux and current relationship when no saturation oc- for the distributed-parameter nature of conductors
curs. The dashed lines represent the behaviour dur- such as overhead lines, cables and in the case of high
ing a transient, when the core is being saturated (e.g. frequency transients, even of busbars.
during transformer energisation).
Typically, for low frequency steady-state analysis, lines
The magnetic flux Ψ, representing the time-integral of and cables are modelled using the well-known lumped
the voltage, lags in steady state the sinusoidal wave- parameter equivalent circuit, thus neglecting the dis-
form of the voltage by 90∘ . Being still in the linear tributed nature without loosing too much accuracy in
part of the saturation characteristic, the current is si- the results. In reality, a current in a conductor having
nusoidal as well. Thus, the current is proportional to even a very short length, needs a certain time to travel
the voltage. from its sending end to the remote end [1].
Rev.2 8
SWITCHING TRANSIENTS APPLICATION EXAMPLE
When an overhead line or cable is energised from frequency-dependent parameters for overhead lines,
the grid as shown in Figure 13, a voltage and current PowerFactory uses the approach proposed by J.Marti
surge are injected into the line. Before the breaker is [5]. For cable systems the Universal Line Model is
closed, the voltage at both ends of the line is zero. available and offers a high accuracy and a phase-
Upon breaker closing at the sending end of the line, domain formulation [6].
the voltage changes instantaneously from zero to the
supply voltage 𝑢𝑆 .
𝑢𝑆 𝑢𝑅
At the receiving end of the line, the voltage 𝑢𝑅 is still
zero since the surge needs a certain time to travel
from the sending to the receiving end of the line. The 𝑢𝑆 𝑢𝑅
surge propagates with the speed 𝑣 along the line and
arrives at the sending end of the line with a delay equal
with the propagation time 𝜏 .
𝑢𝑆 𝑢𝑅
The propagation speed 𝑣 is a function of the line in-
ductance 𝐿′ and capacitance 𝐶𝐿′′ . For a lossless line
the propagation speed 𝑣 is calculated by the following
equation [1]: Figure 13: Voltage surge line energisation
1
𝑣=√ During the transient, the surge is travelling back and
𝐿′ · 𝐶 ′ forward until damping and attenuation will eventually
result in a steady state condition. At each electri-
The propagation time constant 𝜏 is dependent on the cal boundary the surge is reflected and refracted as
propagation speed v and the line length indicated in Figure 13. Electrical boundaries arise
when the surge impedance of the network compo-
𝑙 √︀ nents change, e.g. at an overhead line - cable tran-
𝜏 = = 𝑙 · 𝐿′ · 𝐶 ′ sition or at the open end of a line.
𝑣
Rev.2 9
SWITCHING TRANSIENTS APPLICATION EXAMPLE
𝑢2 2 · 𝑍2
=
𝑢1 𝑍1 + 𝑍2
Switching Contacts start Arc extinction in last pole Contacts fully
command to separate Current interruption separated
𝑍 − 𝑍1
𝑢𝑟 = 2 arcing time
𝑍1 + 𝑍2 Total break time
𝑖1 2 · 𝑍1
=
𝑖2 𝑍1 + 𝑍2 Figure 15: Circuit breaker operation switching off
𝑍 − 𝑍2
𝑖𝑟 = 1
𝑍1 + 𝑍2 Upon contact separation, an arc is formed in the in-
terruption chamber of each pole. The actual current
Typical surge impedances for common power system interruption must wait for the zero crossing of the cur-
components are: rent. Depending on the type of circuit-breaker, the de-
vice may not be ready to interrupt at the first occurring
• Overhead lines: 200 Ω to 500 Ω current zero after contact separation.
• Cable systems: 40 Ω to 70 Ω
For SF6 circuit breakers, it takes a certain minimum
• Transformers: 1 kΩ to 10 kΩ arcing time before the electric arc extinguishes in the
circuit breaker because sufficient cooling pressure of
the extinction medium must be available and sufficient
3.3 Transient Recovery Voltage (TRV) contact distance must be reached. For vacuum circuit
breakers sufficient contact distance has to be reached
in order to extinguish the electric arc [2].
Transient recovery voltages (TRV) arise both at fault
interruption and load switching. In both cases a circuit
𝐿𝑆
breaker is switching off. The circuit breaker opening
procedure is explained in Figure 15. The switching
command is usually initiated automatically by a relay
𝐶𝑆 𝑢𝑆 𝑢𝐿 𝐶𝐿
that detects a fault in the system or a switching com- 𝐿𝐿
mand from the control center to trigger a change in the
operation scenario of the network.
Rev.2 10
SWITCHING TRANSIENTS APPLICATION EXAMPLE
The frequency of the transient part of the voltage is shunt reactor switching, terminal fault, short line fault
calculated by the following formula: interruption) the TRV contains multiple oscillation fre-
quencies which superimpose.
1 1 The exemplary TRV for a single phase circuit is shown
𝑓𝑆 = · √︀
2𝜋 𝐿𝑆 · 𝐶𝑆 in Figure 17 assuming the following values:
1 1 The plot shows that the TRV starts from zero at current
𝑓𝑅 = · √︀
2𝜋 𝐿𝐿 · 𝐶𝐿 zero, makes an excursion to the momentary power-
frequency voltage, overshoots in a damped oscillatory
The Transient Recovery Voltage (TRV) is the voltage manner and continues to oscillate until a steady-state
across the open circuit-breaker contacts which arises condition is reached. The frequency of the load side
immediately after current interruption. It is the differ- oscillation is 𝑓𝐿 = 3558.8 Hz and of the source side
ence between the voltage-to-earth at the source side 𝑓𝑆 = 73.9 Hz. Important parameters in a TRV study
𝑢𝑆 and load side 𝑢𝐿 : are the maximum transient recovery voltage 𝑈𝐶 and
the rate of rise of recovery voltage (RRRV). Both pa-
rameters are required for circuit breaker design stud-
𝑢TRV = 𝑢𝑆 − 𝑢𝐿 ies.
The TRV always consists of at least two oscillatory Current chopping may need be considered as well in
components, the source-side and load-side frequency the TRV study for some types of circuit breakers or
component. Depending on the switching action (e.g. switching transients.
200,00
100,00
0,00
-100,00
-200,00
-300,00
0,00 2,00 4,00 6,00 8,00 [ms] 10,00
Source: Phase Voltage SP in kV
200,00
100,00
0,00
-100,00
-200,00
-300,00
0,00 2,00 4,00 6,00 8,00 [ms] 10,00
Load: Phase Voltage SP in kV
200,00 40,00
100,00 30,00
0,00 20,00
-100,00 10,00
-200,00 0,00
-300,00 -10,00
0,00 2,00 4,00 6,00 8,00 [ms] 10,00
Circuit Breaker: Voltage Difference in kV Circuit Breaker: Phase Current/Terminal i in A
Source: Power Frequency Voltage
Figure 17: Source side, load side and transient recovery voltage (TRV)
Rev.2 11
SWITCHING TRANSIENTS APPLICATION EXAMPLE
Rev.2 12
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.1 Steady State Load Flow The external grid serves as slack and is supplying
Analysis 1900 MW for active power balancing and a reactive
power of 60 Mvar. The voltages of all busbars in
the transmission system and sub-transmission sys-
The load flow calculation is based on algorithms for
tem, are in the range of 0.99 to 1.03 p.u. in the steady
the unbalanced load flow taking into account unbal-
state load flow calculation. The loading of lines and
ances resulting from non-perfect line transposition of
transformers varies between 14% and 50%.
the multi-phase network and unsymmetrical loads and
generation. The active power control in the load flow The steady state load flow calculation results are the
calculation is based on the dispatch of generators and basis for the calculation of the initial conditions and
loads. The difference between load and generation is thus the starting point of the EMT simulation.
balanced by the reference machine.
Figure 19 shows the steady state EMT simulation re-
The external grid connected to substation West rep- sults. The plots contain the instantaneous voltage of
resents the transmission system in the West is used phase A, B and C at the substation Central, West and
as reference machine (slack). It controls the voltage North, as well as the RMS voltage of phase A. The
to 1 p.u. at substation West. The power plant con- RMS voltage is derived from the time domain signal
nected to substation North is set to dispatch 750 MW. using a DSL model.
A station controller is used to regulate the voltage at
the HV-side of the Power Plant to 1.02 p.u. The wind
farm connected to the 110 kV sub-transmission sys-
[deg]
tem is set to dispatch 30 MW at a power factor of 0.95
overexcited. 6,00
5,00
Large loads are connected to substation North and 4,00
North-East, each with a consumption of 1200 MW and 3,00
a power factor of 0.9 and 0.98 respectively. For reac- 2,00
tive power compensation the capacitor bank at sub-
1,00
station North-East is supplying 400 Mvar (tap 8). The
shunt reactor at substation Central is tapped to zero -240, -210, -180, -150, -120, -90,0 -60,0 -30,0 30,0 60,0 90,0 120, 150, 180, [kV]
-1,00
and thus not consuming any active power.
-2,00
-3,00
The load flow calculation is configured with automatic
-4,00
tap adjustment of transformers at substation Central
-5,00
and at the wind farm. The load flow calculation will
-6,00
determine the active and reactive power flows for all
-7,00
branches, and the voltage magnitude and phase for
-8,00
all nodes. Executing the load flow results in the phase
West 1: Line-Ground Voltage
voltages displayed in Figure 18. The voltage at sub- North 1: Line-Ground Voltage
C4_1.1: Line-Ground Voltage
North-East: Line-Ground Voltage
station West is the reference voltage with an angle of
∘ ∘
0 and a symmetrical phase shift of 120 for each
phase respectively. Figure 18: Phase voltages of the transmission system
Rev.2 13
SWITCHING TRANSIENTS APPLICATION EXAMPLE
600 600
[kV] [kV]
400 400
200 200
0 0
-200 -200
-400 -400
0 10 20 30 40 [ms] 50 0 10 20 30 40 [ms] 50
W400-1: Phase Voltage A W400-1: Phase Voltage B
N400-1: Phase Voltage A N400-1: Phase Voltage B
C400-3: Phase Voltage A C400-3: Phase Voltage B
250 600
[-] [kV]
200 400
150 200
100 0
50 -200
0 -400
0 10 20 30 40 [ms] 50 0 10 20 30 40 [ms] 50
C400-3_RMS-Voltage: UA W400-1: Phase Voltage C
N400-1_RMS-Voltage: UA N400-1: Phase Voltage C
W400-1_RMS-Voltage: UA C400-3: Phase Voltage C
Figure 19: Instantaneous and RMS phase voltages in the transmission system at steady state
Rev.2 14
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.2 Short Circuit 1ph with the highest share coming from the overhead line.
12
[kA]
8
-4
-8
0,0 20,0 40,0 60,0 80,0 [ms] 100,0
10
[kA]
5
-10
-15
0,0 20,0 40,0 60,0 80,0 [ms] 100,0
20
[kA]
10
-20
-30
0,0 20,0 40,0 60,0 80,0 [ms] 100,0
Figure 20: Phase currents in circuit breaker N400-B1-CB2, N400-B1-CB3 and overhead line OHL-WN during
single phase to ground fault
Rev.2 15
SWITCHING TRANSIENTS APPLICATION EXAMPLE
500
[kV]
250
-500
-750
0 20 40 60 80 [ms] 100
60
[kA]
40
-20
-40
0 20 40 60 80 [ms] 100
Figure 21: Phase voltage and short circuit current at terminal N-400_T1 during single phase to ground fault
Rev.2 16
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.3 Short Circuit 3ph line OHL-NC. The peak short circuit current is 27 kA
with the highest share coming from the overhead line.
A three phase fault in substation North is investigated
The voltage at the fault terminal and the overall short
in this study case.
circuit current are shown in Figure 23. After approxi-
Initially, the system is in steady state. All overhead mately 40 ms a new steady state conditions is reached
lines and cable systems are modelled with distributed and after 50 ms the fault is cleared. The peak voltage
parameter line models in order to account for travelling during the transient is 411 kV which corresponds to
wave effects. 1.25 p.u.
During the simulation, a three phase fault is applied in The simulation sequence is as follows:
substation North at the incomer of overhead line OHL- • 𝑡 = −20𝑚𝑠:
NC. It is assumed that the fault is cleared by three- start simulation
phase circuit breaker action by isolating the faulted
part of the network. • 𝑡 = 0 𝑚𝑠:
Single Phase to ground Fault in substation North
The simulation results are shown in Figure 22 for at Bay 1
the branches connected to the faulted terminal. The
fault current is supplied by the two circuit breakers • 𝑡 = 50𝑚𝑠:
N400-B1-CB2 and N400-B1-CB3 and the overhead Fault clearing
30
20
10
-10
-20
0 20 40 60 80 [ms] 100
OHL-WN: Phase Current A/Terminal i in kA
OHL-WN: Phase Current B/Terminal i in kA
OHL-WN: Phase Current C/Terminal i in kA
-4
-8
-12
0 20 40 60 80 [ms] 100
N400-B1-CB2: Phase Current A/Terminal i in kA
N400-B1-CB2: Phase Current B/Terminal i in kA
N400-B1-CB2: Phase Current C/Terminal i in kA
-4
-8
-12
0 20 40 60 80 [ms] 100
N400-B1-CB3: Phase Current A/Terminal i in kA
N400-B1-CB3: Phase Current B/Terminal i in kA
N400-B1-CB3: Phase Current C/Terminal i in kA
Figure 22: Phase currents in circuit breaker N400-B1-CB2, N400-B1-CB3 and overhead line OHL-WN during
single phase to ground fault
Rev.2 17
SWITCHING TRANSIENTS APPLICATION EXAMPLE
500
[kV]
250
-250
-500
-750
0 20 40 60 80 [ms] 100
N-400-1: Phase Voltage A
N-400-1: Phase Voltage B
N-400-1: Phase Voltage C
40
[kA]
20
-20
-40
-60
0 20 40 60 80 [ms] 100
N-400-1: Short-Circuit Current A
N-400-1: Short-Circuit Current B
N-400-1: Short-Circuit Current C
Figure 23: Phase voltage and short circuit current at terminal N-400_T1 during three phase fault
Rev.2 18
SWITCHING TRANSIENTS APPLICATION EXAMPLE
Rev.2 19
SWITCHING TRANSIENTS APPLICATION EXAMPLE
3 3 3
2 2 2
1 1 1
0 0 0
-1 -1 -1
-2 -2 -2
0 10 20 30 40 [ms] 50 0 10 20 30 40 [ms] 50 0 10 20 30 40 [ms] 50
WF-110: Phase Voltage A WF-110: Phase Voltage B WF-110: Phase Voltage C
TRF1: Magnetising Flux A TRF1: Magnetising Flux B TRF1: Mag. Flux c C
2 800 3,00
[p.u.] [A]
[p.u.]
0 400
2,00
-2 0
1,00
-4 -400
0,00
-6 -800
-1,00
-8 -1200
0 10 20 30 40 [ms] 50 0 10 20 30 40 [ms] 50
TRF1: Magnetising Current, Phase a TRF1: Phase Current A/HV-Side -2,00
TRF1: Magnetising Current, Phase b TRF1: Phase Current B/HV-Side -6 -4 -2 0 2 [p.u.] 4
TRF1: Magnetising Current, Phase c TRF1: Phase Current C/HV-Side
Figure 24: Transformer HV side voltage, magnetic flux in the core, magnetising current
1,04
[-]
1,02
WF_PCC_RMS-Voltage: UA
1,00
WF_PCC_RMS-Voltage: UB
WF_PCC_RMS-Voltage: UC
0,98
0,96
0,94
0 200 400 600 800 [ms] 1000
800
[A]
400
TRF1: Phase A
0
TRF1: Phase B
TRF1: Phase C
-400
-800
-1200
0 200 400 600 800 [ms] 1000
400
300
TRF1: Phase A
200
TRF1: Phase B
TRF1: Phase C
100
-100
0,00 50,0 100, 150, 200, 250, 300, 350, 400, 450, 500,
Figure 25: RMS voltage dip at PCC, inrush currents and their harmonic distortion (FFT)
Rev.2 20
SWITCHING TRANSIENTS APPLICATION EXAMPLE
3 3 3
2 2 2
1 1 1
0 0 0
-1 -1 -1
-2 -2 -2
0 10 20 30 40 [ms] 50 0 10 20 30 40 [ms] 50 0 10 20 30 40 [ms] 50
WF-110: Phase Voltage A WF-110: Phase Voltage B WF-110: Phase Voltage C
TRF1: Magnetising Flux A TRF1: Magnetising Flux B TRF1: Mag. Flux c C
6 3000 4,00
[p.u.] [A]
[p.u.]
3 2000
2,00
0 1000
0,00
-3 0
-2,00
-6 -1000
-4,00
-9 -2000
0 10 20 30 40 [ms] 50 0 10 20 30 40 [ms] 50
TRF1: Magnetising Current, Phase a TRF1: Phase Current A/HV-Side -6,00
TRF1: Magnetising Current, Phase b TRF1: Phase Current B/HV-Side -5,0 -2,5 0,0 2,5 5,0 [p.u.] 7,5
TRF1: Magnetising Current, Phase c TRF1: Phase Current C/HV-Side
Figure 26: Transformer HV side voltage, magnetic flux in the core, magnetising current
Rev.2 21
SWITCHING TRANSIENTS APPLICATION EXAMPLE
1,04
[-]
1,00
WF_PCC_RMS-Voltage: UA
0,96
WF_PCC_RMS-Voltage: UB
WF_PCC_RMS-Voltage: UC
0,92
0,88
0,84
0 200 400 600 800 [ms] 1000
4000
[A]
3000
TRF1: Phase A
2000
TRF1: Phase B
TRF1: Phase C
1000
-1000
0 200 400 600 800 [ms] 1000
1000
750
TRF1: Phase A
500
TRF1: Phase B
TRF1: Phase C
250
-250
0,00 50,0 100, 150, 200, 250, 300, 350, 400, 450, 500,
Figure 27: RMS voltage dip at PCC, inrush currents and their harmonic distortion (FFT)
Rev.2 22
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.6 Transformer Energisation III The analysis of the sympathetic inrush phenomena is
evaluated in this section and shown in Figure 28.
Parallel Transformer Energisation with
The simulation sequence is as follows:
Sympathetic Inrush
• 𝑡 = −50𝑚𝑠:
Start simulation. Transformer TRF2 is already
The energisation of a transformer that is connected to energised and operated under no load condition
one or several parallel transformers that are already
energised and operated under no load condition may • 𝑡 = 0 𝑚𝑠:
give rise to a phenomena that is called sympathetic Energisation of transformer TRF1 by closing
inrush. The inrush currents associated with this tran- switch CB4 in Bay2 of substation WindFarm.
sient have a relatively long duration and may pose a
threat to the reliability and security of the system. The simulations plots show the transformer inrush cur-
rents in TRF1 and the the sympathetic inrush currents
During the energisation of parallel transformers, the in transformer TRF2 as well as the source currents
transformer that is already energised may experience supplying the windfarm.
an unexpected saturation during the inrush transient
of the other transformer. This saturation is a result of The inrush current in TRF2 is caused due to the sat-
an asymmetrical voltage drop across the system resis- uration of the corresponding transformer. The satura-
tance caused by the inrush current of the transformer tion is due to the an offset of the magnetising currents
which is being energised and results in an offset of the in this transformer that results from the asymmetrical
magnetising currents in the already energised trans- voltage drop of the inrush currents from TRF1.
former.
3000
[A]
2000
TRF1: Phase A
1000
TRF1: Phase B
TRF1: Phase C
0
-1000
-2000
0 1000 2000 3000 4000 [ms] 5000
1200
[A]
800
TRF2: Phase A
400
TRF2: Phase B
TRF2: Phase C
0
-400
-800
0 1000 2000 3000 4000 [ms] 5000
3000
[A]
2000
-1000
-2000
0 1000 2000 3000 4000 [ms] 5000
Figure 28: Inrush currents of transformer TRF 1 and sympathetic inrush current of transformer TRF2 was
already energised
Rev.2 23
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.7 Transformer Energisation IV scripts library of this project. In each simulation, the
circuit breaker closing time and optionally (depending
Statistical Analysis: on settings) the pole scatter between the phases is
changed according to the configuration in the script.
The inrush currents and voltage dips during the trans-
For the following analysis, the residual flux in the trans-
former energisation transient depends on the circuit
former core is assumed to be zero at the time when
breaker closing time.
the transformer is energised.
The circuit breaker closing time is of random nature in
The simulation results for the transformer energisation
reality and therefore all points on the wave (PoW) are
are shown in Figure 29 when pole scatter between the
possible during the switching transient (unless con-
phases is neglected. As can be seen, the inrush peak
trolled switching is applied).
current and RMS voltage drop are a function of the
In order to account for all potential circuit breaker clos- circuit breaker closing time.
ing times, statistical switching studies are required. In
Figure 30 shows the maximum inrush peak current
this study case, a Python script is used to run more
and minimum RMS voltage for the transformer ener-
than 100 EMT simulations (depending on the configu-
gisation when a pole scatter is considered. The pole
ration of closing events and pole scatter).
scatter is considered with a normal distribution. The
The script for the statistical analysis is stored in the standard deviation 𝜇 is assumed to be 0.5.
66
[pu]
65
64
63
62
61
0 4 8 12 16 20
x-Axis: WF_PCC_RMS-Voltage: Switch time in ms
WF_PCC_RMS-Voltage: Min. RMS voltage phase A
WF_PCC_RMS-Voltage: Min. RMS voltage phase B
WF_PCC_RMS-Voltage: Min. RMS voltage phase C
1200
[A]
900
600
300
-300
1 5 9 13 17 21
x-Axis: TRF1: Switch time in ms
TRF1: Peak Current Phase A
TRF1: Peak Current Phase B
TRF1: Peak Current Phase C
Figure 29: Statistical analysis of transformer energisation without the consideration of pole scatter.
Rev.2 24
SWITCHING TRANSIENTS APPLICATION EXAMPLE
65
[pu]
64
63
62
61
60
0 4 8 12 16 20
x-Axis: WF_PCC_RMS-Voltage: Switch time in ms
WF_PCC_RMS-Voltage: Min. RMS voltage phase A
WF_PCC_RMS-Voltage: Min. RMS voltage phase B
WF_PCC_RMS-Voltage: Min. RMS voltage phase C
1600
[A]
1200
800
400
-400
0 4 8 12 16 20
x-Axis: TRF1: Switch time in ms
TRF1: Peak Current Phase A
TRF1: Peak Current Phase B
TRF1: Peak Current Phase C
Figure 30: Statistical analysis of transformer energisation with the consideration of pole scatter.
Rev.2 25
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.8 Overhead Line Energisation I line models is based on the corresponding energisa-
tion frequency for each line and ranges from 350 Hz to
Energisation without Surge Arresters 3000 Hz.
Rev.2 26
SWITCHING TRANSIENTS APPLICATION EXAMPLE
750
Max. =575,898 kV
500
250
-250
-500
0 4 8 12 16 [ms] 20
C-400_Bay09: Phase Voltage A in kV
W400-2_Bay01: Phase Voltage A in kV
500
250
-250
-750
0 4 8 12 16 [ms] 20
C-400_Bay09: Phase Voltage B in kV
W400-2_Bay01: Phase Voltage B in kV
500
250
-250
Min. =-365,616 kV
-500
-750
0 4 8 12 16 [ms] 20
C-400_Bay09: Phase Voltage C in kV
W400-2_Bay01: Phase Voltage C in kV
Figure 31: Transient phase-to-ground voltages at the sending and receiving end during the energisation of
OHL WC-1
Energisation
1200
[A]
800
-400
-800
0 300 600 900 1200 [us] 1500
Energisation
1200
[A]
800
-400
-800
0 300 600 900 1200 [us] 1500
Energisation
300
[A]
0
-900
-1200
0 300 600 900 1200 [us] 1500
Figure 32: Transient phase currents during the energisation of OHL WC-1
Rev.2 27
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.9 Overhead Line Energisation II re-energisation sequence are shown in Figure 33. Ini-
tially, the system is in steady state and the load current
Re-Energisation without Surge Arresters is below 1 kA. During the fault, the currents reach sev-
eral kAs and become zero after fault clearing.
In this study case, re-energisation transients are in-
The transient voltages during the re-energisation are
vestigated. Initially, the system is in steady state. All
shown in Figure 34. Initially, the system represents a
overhead lines and cable systems are modelled with
balanced system with a voltage in the range of 1 p.u.
distributed parameter line models in order to account
After fault clearing, the voltage in the faulted phase is
for travelling wave effects.
zero while in the healthy phases, the trapped charge
The constant frequency / Bergeron line model is used sustains. During the re-energisation, overvoltages
in this study case. The modal transformation of the with very high magnitudes occur in the in the system.
line models is based on the corresponding energisa- The peak line-to-earth voltage is 850 kV.
tion frequency for each line and ranges from 350 Hz to
In this study case, the surge arresters are set out of
3000 Hz.
service. The simulation sequence is as follows:
The frequency for travel time estimation / modal trans- • 𝑡 = − 150𝑚𝑠:
formation can be calculated based on the following start simulation
equation:
• 𝑡 = −50 𝑚𝑠:
Single Phase to ground Fault at terminal N400-
𝑣 1 B2-3
𝑓𝜏 = =
4·𝑙 4·𝜏
• 𝑡 = − 0𝑚𝑠:
More advanced distributed parameter line models are Line tripping → opening of circuit breakers
available in PowerFactory. Further information is avail- N400-B2-CB3, N400-B2-CB2 and C400-B2-
able in the technical reference [5]. CB1. The current is interrupted in the next zero-
crossing of each phase.
During the simulation, a single phase to ground fault is
applied in substation North at the incomer of overhead • 𝑡 = 0 𝑚𝑠:
line OHL-NC. It is assumed that the fault is cleared by Fault clearing → removing the fault at terminal
three-phase auto-reclosure. First, the faulted line is N400-B2-3
tripped by opening the corresponding circuit breakers. • 𝑡 = 197 𝑚𝑠:
Re-energisation → closing the circuit breaker
As a result of the circuit breaker action, the voltage in
N400-B2-CB3
the healthy phases is trapped (trapped charge) while
the voltage in the faulted phase is zero. The trapped • 𝑡 = 203 𝑚𝑠: Re-energisation → closing the cir-
charge significantly impacts the transient overvoltages cuit breaker N400-B2-CB2
during the re-energisation.
• 𝑡 = 205 𝑚𝑠: Re-energisation → closing the cir-
The currents through the circuit breakers during the cuit breaker C400-B2-CB1
Rev.2 28
SWITCHING TRANSIENTS APPLICATION EXAMPLE
20
10
-10
-20
-30
0 100 200 300 400 [ms] 500
C400-B2-CB1: Phase Current A/Terminal i in kA
N400-B2-CB2: Phase Current A/Terminal i in kA
N400-B2-CB3: Phase Current A/Terminal i in kA
-2
-4
-6
0 100 200 300 400 [ms] 500
C400-B2-CB1: Phase Current B/Terminal i in kA
N400-B2-CB2: Phase Current B/Terminal i in kA
N400-B2-CB3: Phase Current B/Terminal i in kA
-2
-4
-6
0 100 200 300 400 [ms] 500
C400-B2-CB1: Phase Current C/Terminal i in kA
N400-B2-CB2: Phase Current C/Terminal i in kA
N400-B2-CB3: Phase Current C/Terminal i in kA
1000 600
Max. =850,942 kV
[kV] [kV]
500 300
0 0
-500 -300
-1000 -600
-1500 -900
0 100 200 300 400 [ms] 500 0 100 200 300 400 [ms] 500
C400-3-B2-1: Phase Voltage A N400-2: Phase Voltage A
C400-3-B2-1: Phase Voltage B N400-2: Phase Voltage B
C400-3-B2-1: Phase Voltage C N400-2: Phase Voltage C
Rev.2 29
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.10 Overhead Line Energisation III The currents through the circuit breakers during the
re-energisation sequence are shown in Figure 35. Ini-
Re-Energisation with Surge Arresters tially, the system is in steady state and the load current
is below 1 kA. During the fault, the currents reach sev-
In this study case, re-energisation transients are in- eral kAs and become zero after fault clearing.
vestigated. Initially, the system is in steady state. All
During the re-energisation, the overvoltages are lim-
overhead lines and cable systems are modelled with
ited by the surge arrester that are connected in substa-
distributed parameter line models in order to account
tion North and Central. The peak line-to-earth voltage
for travelling wave effects.
is 700 kV. The currents absorbed currents and energy
The constant frequency / Bergeron line model is used of the surge arrester in substation Central are shown
in this study case. The modal transformation of the in Figure 36.
line models is based on the corresponding energisa-
The simulation sequence is as follows:
tion frequency for each line and ranges from 350 Hz to
3000 Hz. • 𝑡 = − 150𝑚𝑠:
start simulation
The frequency for travel time estimation / modal trans-
formation can be calculated based on the following • 𝑡 = −50 𝑚𝑠:
equation: Single Phase to ground Fault at terminal N400-
B2-3
𝑣 1 • 𝑡 = − 0𝑚𝑠:
𝑓𝜏 = =
4·𝑙 4·𝜏 Line tripping → opening of circuit breakers
N400-B2-CB3, N400-B2-CB2 and C400-B2-
More advanced distributed parameter line models are CB1. The current is interrupted in the next zero-
available in PowerFactory. Further information is avail- crossing of each phase.
able in the technical reference [5].
• 𝑡 = 0 𝑚𝑠:
During the simulation, a single phase to ground fault is Fault clearing → removing the fault at terminal
applied in substation North at the incomer of overhead N400-B2-3
line OHL-NC. It is assumed that the fault is cleared by
three-phase auto-reclosure. First, the faulted line is • 𝑡 = 197 𝑚𝑠:
tripped by opening the corresponding circuit breakers. Re-energisation → closing the circuit breaker
N400-B2-CB3
As a result of the circuit breaker action, the voltage in
• 𝑡 = 203 𝑚𝑠: Re-energisation → closing the cir-
the healthy phases is trapped (trapped charge) while
cuit breaker N400-B2-CB2
the voltage in the faulted phase is zero. The trapped
charge significantly impacts the transient overvoltages • 𝑡 = 205 𝑚𝑠: Re-energisation → closing the cir-
during the re-energisation. cuit breaker C400-B2-CB1
Rev.2 30
SWITCHING TRANSIENTS APPLICATION EXAMPLE
20
10
-10
-20
-30
0 100 200 300 400 [ms] 500
C400-B2-CB1: Phase Current A/Terminal i in kA
N400-B2-CB2: Phase Current A/Terminal i in kA
N400-B2-CB3: Phase Current A/Terminal i in kA
-2
-4
-6
0 100 200 300 400 [ms] 500
C400-B2-CB1: Phase Current B/Terminal i in kA
N400-B2-CB2: Phase Current B/Terminal i in kA
N400-B2-CB3: Phase Current B/Terminal i in kA
-2
-4
-6
0 100 200 300 400 [ms] 500
C400-B2-CB1: Phase Current C/Terminal i in kA
N400-B2-CB2: Phase Current C/Terminal i in kA
N400-B2-CB3: Phase Current C/Terminal i in kA
1000 600
500 300
0 0
-500 -300
-1000 -600
-1500 -900
0 100 200 300 400 [ms] 500 0 100 200 300 400 [ms] 500
C400-3-B2-1: Phase Voltage A N400-2: Phase Voltage A
C400-3-B2-1: Phase Voltage B N400-2: Phase Voltage B
C400-3-B2-1: Phase Voltage C N400-2: Phase Voltage C
Rev.2 31
SWITCHING TRANSIENTS APPLICATION EXAMPLE
0,500 0,08
[kA] [MWs]
0,375 0,06
0,250 0,04
0,125 0,02
0,000 -0,00
-0,125 -0,02
200 210 220 230 240 [ms] 250 200 210 220 230 240 [ms] 250
C400-B2-SA1: MO Current A C400-B2-SA1: MO absorbed Energy
C400-B2-SA1: MO Current B C400-B2-SA1: MO absorbed Energy
C400-B2-SA1: MO Current C C400-B2-SA1: MO absorbed Energy
Rev.2 32
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.11 Overhead Line Energisation IV at the sending end of the line. The magnitude of the
injected surge depends mainly upon the voltage in-
Re-Energisation Statistical Analysis stantaneous value (point on the waveform) at which
the circuit-breaker contacts close electrically. Since
In this study case, re-energisation transients are in- the point on the waveform of the voltage depends on
vestigated. Initially, the system is in steady state. All the circuit breaker closing instant, statistical studies
overhead lines and cable systems are modelled with should usually be performed. As the circuit breaker
distributed parameter line models in order to account closing time is of random nature in reality, all potential
for travelling wave effects. breaker closing times and thus overvoltages should be
evaluated.
The constant frequency / Bergeron line model is used
in this study case. The modal transformation of the The randomness of the circuit breaker closing time
line models is based on the corresponding energisa- is modelled in PowerFactory by means of statistical
tion frequency for each line and ranges from 350 Hz to analysis. The statistical analysis tool in PowerFac-
3000 Hz. tory runs multiple simulations. In each simulation the
breaker closing time is varied randomly within a de-
The frequency for travel time estimation / modal trans- fined range. Additionally, breaker pole scattering can
formation can be calculated based on the following be included in the statistical analysis in order to ac-
equation: count for deviations in the closing time between the
three phases.
𝑣 1 An example of a statistical switching analysis is pro-
𝑓𝜏 = =
4·𝑙 4·𝜏 vided in this section. Figure 38 shows the maximum
overvoltages for the 𝑛 = 200 EMT simulations exe-
More advanced distributed parameter line models are cuted automatically by the statistical tool in PowerFac-
available in PowerFactory. Further information is avail- tory.
able in the technical reference [5].
Multipe Run Set-up:
In this study case, the surge arresters are set out of
service. The simulation sequence is as follows: • Execution of DPL script Stochastic Switching
Rev.2 33
SWITCHING TRANSIENTS APPLICATION EXAMPLE
1450,00
[kV]
1200,00
950,00
700,00
450,00
200,00
0,00 40,00 80,00 120,00 160,00 200,00
x-Axis: C400-3-B2-1: Simulation case
C400-3-B2-1: Voltage Phase A
C400-3-B2-1: Voltage Phase A
C400-3-B2-1: Voltage Phase A
Rev.2 34
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.12 Cable Energisation I The frequency for travel time estimation / modal trans-
formation can be calculated based on the following
Energisation Overvoltages equation:
600 600
[kV] [kV]
300 300
0 0
-300 -300
-600 -600
-900 -900
0 5 10 15 20 [ms] 25 0 5 10 15 20 [ms] 25
N400-2: Phase Voltage A PP400-B1-1: Phase Voltage A
N400-2: Phase Voltage B PP400-B1-1: Phase Voltage B
N400-2: Phase Voltage C PP400-B1-1: Phase Voltage C
Figure 39: Transient phase-to-ground voltages at the sending and receiving end during the energisation of the
cable system NPP-1
Rev.2 35
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.13 Cable Energisation II When the shunt compensation degree exceeds 50%,
meaning that the reactive power of the shunt reactor
Missing Zero-Crossing Phenomena compensates more than 50% of the cable charging
capacitive current, the DC current of the shunt reac-
The simultaneous energisation of a cable and its tor can exceed the combined AC current of the shunt
compensating shunt reactor may cause the so called reactor and cable. Under this circumstance, the zero
"zero-missing" phenomena. During the zero-missing missing phenomena can occur when the cable is en-
phenomena, the current through the circuit breaker ergised together with the shunt reactor.
does not cross zero for several cycles. During the
The zero missing phenomena is demonstrated in the
time of zero-missing it is difficult or impossible to open
following example. For that purpose, it is assumed that
the breaker if a fault occurs in the system. There-
the two 400 kV cables are compensated with shunt
fore, the system is more vulnerable and unprotected
reactors only at the substation and not at the power
against faults.
plant.
The zero-missing phenomenon can be explained with
Furthermore, it is assumed, that the compensating
the cable system with a shunt reactor according to Fig-
shunt reactors have each a reactive power rating of
ure 40. When the cable system and shunt reactor are
100 Mvar and are connected directly to the cable. The
energised together, the current of the reactor has two
reactive power of each HV cable is approximately
components, an AC-component and a decaying DC-
160 Mvar, corresponding to a shunt compensation de-
component.
gree that is approximately 60%.
Figure 40: Circuit breaker operation switching off • 𝑡 = 430 𝑚𝑠: First zero-crossing in phase C
Rev.2 36
SWITCHING TRANSIENTS APPLICATION EXAMPLE
1200 3000
[kV] [A]
800 2000
400 1000
0 0
-400 -1000
-800 -2000
0 100 200 300 400 [ms] 500 0 100 200 300 400 [ms] 500
N400-2: Phase Voltage A CAB-NPP1: Phase Current A/Terminal i
N400-2: Phase Voltage B CAB-NPP1: Phase Current B/Terminal i
N400-2: Phase Voltage C CAB-NPP1: Phase Current C/Terminal i
500 3000
[A] [A]
250 2000
0 1000
-250 0
-500 -1000
-750 -2000
0 100 200 300 400 [ms] 500 0 100 200 300 400 [ms] 500
NNPS1_comp: Phase Current A N400-B1-CB2: Phase Current A/Terminal i
NNPS1_comp: Phase Current B N400-B1-CB2: Phase Current B/Terminal i
NNPS1_comp: Phase Current C N400-B1-CB2: Phase Current C/Terminal i
Figure 41: Energisation of cable system with a shunt reactor. The plots show the terminal voltage at the
sending end of the cable, the cable and shunt reactor current as well as the circuit breaker phase currents.
500 500
[kV] [kV]
250 250
0 0
-250 -250
-500 -500
-750 -750
0 10 20 30 40 [ms] 50 0 100 200 300 400 [ms] 500
N400-2: Phase Voltage A N400-2: Phase Voltage A
N400-2: Phase Voltage B
N400-2: Phase Voltage C
[A] [A]
2000 800
1000 400
0 0
-1000 -400
-2000 -800
0 100 200 300 400 [ms] 500 0 100 200 300 400 [ms] 500
N400-B1-CB2: Phase Current B/Terminal i N400-B1-CB2: Phase Current C/Terminal i
Figure 42: Energisation at 𝑡 = 8.2 𝑚𝑠 with voltage zero crossing in phase C, resulting in a Transient phase-to-
ground voltages at the sending and receiving end during the energisation of the cable system NPP-1
Rev.2 37
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.14 TRV Terminal Fault elled according to IEC 62271-100 with a 4-parameter
envelope curve. The parameters that define the di-
In this section the transient recovery voltages (TRV) electric strength for the specific circuit breaker are
across the breaker poles of the circuit breaker C400- listed in Table 2.
B9_CB in substation Central is analysed. The circuit
The envelope curve defines the maximum transient
breaker connected the overhead line OHL-WC1.3 to
voltages which are allowed after the fault interruption
the substation.
across the breaker poles and represents the dielectric
Following a terminal fault on the line side of the circuit strength of the breaker.
breaker, the protection relays will trigger the breaker.
The limits in Table 2 correspond to the short-circuit
For the purpose of this analysis C400-B9_CB is mod-
duty tests T100, T60 and T30. The duty test T100 cor-
elled as an ideal switch that is linked to the circuit
responds to a short circuit current equal to the short
breaker capability curve. The capability curve repre-
circuit rating of the CB. In the duty test T60 the short
sents the dielectric strength during the transient ac-
circuit current is only 60% of the short circuit rating of
cording and is in accordance with the IEC 62271-100.
the CB.
All lines are modelled with distributed parameters in Table 2: Parameters of TRV envelope of 420 kV circuit
this example. Lumped models could be used for most breakers; terminal faults (T)
lines as well and would speed up the simulation. How-
ever, for simplification, all lines were modelled with dis-
Curve 𝑢1 /kV 𝑡1 /𝜇s 𝑈𝐶 /kV 𝑡2 /𝜇s
tributed parameter line models.
T100 334 167 624 668
The simulation sequence is as follows: T60 334 11 669 666
• 𝑡 = −20𝑚𝑠: T30 - - 687 137
start simulation
• 𝑡 = 0 𝑚𝑠:
Three Phase to ground Fault at the incomer ofFigure 44 shows the short circuit current flowing from
OHL-WC1.3 in substation Central substation Central to the fault location at the beginning
of overhead line (OHL) WC-1.3. Initially the current
• 𝑡 = 40 𝑚𝑠: through the circuit breaker is in steady state. At time
Line tripping → opening of the corresponding 𝑡 = 0 s the fault is initiated with zero fault impedance
circuit breakers CC400-1-B9_CB, W400-1-B2_- (𝑅𝑓 𝑎𝑢𝑙𝑡 = 0 Ω and 𝑋𝑓 𝑎𝑢𝑙𝑡 = 0 Ω).
CB1 and W400-1-B2_CB2.
The current is interrupted in the next zero- The steady state load current changes into a signif-
crossing of each phase. icantly higher short circuit current in an oscillatory
manner as shown in Figure 44. After a few ms the
C400-B8-SA1
CWC1_comp
of the network is isolated.
IS.L2.3
C400-B5-SA1
C400-1-B9_CB
Bay09
OHL-WC1.3
IS.L2.1 IS.L2.2 During the short circuit transient, the terminal voltage
at substation Central drops from a peak line-to-earth
C400-B9..
IS.L3.3
Rev.2 38
SWITCHING TRANSIENTS APPLICATION EXAMPLE
[kA]
20
10
-10
-20
0 20 40 60 80 [ms] 100
IS.L2.3: Phase Current A/Terminal i
IS.L2.3: Phase Current B/Terminal i
IS.L2.3: Phase Current C/Terminal i
[kV]
300
-300
-600
-900
0 20 40 60 80 [ms] 100
C4_1.1: Phase Voltage A
C4_1.1: Phase Voltage B
C4_1.1: Phase Voltage C
Figure 44: Short circuit current through the CB.L2 during the transient and voltage at substation Central
Rev.2 39
SWITCHING TRANSIENTS APPLICATION EXAMPLE
800
400
-400
-800
-1200
41 44 47 50 53 [ms] 56
C400-1-B9_CB: Voltage Difference A in kV
C400-1-B09_CB.L2 Capability Curve: TRV_limit_A_neg
C400-1-B09_CB.L2 Capability Curve: TRV_limit_A_pos
800
400
-400
-800
-1200
41 44 47 50 53 [ms] 56
C400-1-B9_CB: Voltage Difference B in kV
C400-1-B09_CB.L2 Capability Curve: TRV_limit_B_neg
C400-1-B09_CB.L2 Capability Curve: TRV_limit_B_pos
800
400
-400
-800
-1200
41 44 47 50 53 [ms] 56
C400-1-B9_CB: Voltage Difference C in kV
C400-1-B09_CB.L2 Capability Curve: TRV_limit_C_neg
C400-1-B09_CB.L2 Capability Curve: TRV_limit_C_pos
Figure 45: Transient recovery voltage (TRV) and dielectric strength of circuit breaker
Rev.2 40
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.15 TRV Shunt Reactor Switching I The simulation results are shown in Figure 46 and
47. The first zero-crossing occurs in phase A after
For reactive power compensation a shunt reactor is the circuit breaker is triggered by a simulation event.
installed at substation Central as shown in Figure 2. At 𝑡 = 0.607 ms the current in phase A is zero and
The shunt reactor is a three-phase five-leg core type the breaker poles are opened in this phase. Then,
with a rated reactive power of 200 Mvar. The reac- 3.404 ms later at 𝑡 = 4.011 ms the current in phase C
tor is switchable and has 4 steps. Thus, it is able goes to zero and the poles are opened in this phase.
to consume 0 Mvar, 50 Mvar, 100 Mvar, 150 Mvar and In phase B the current is interrupted at 𝑡 = 7.314 ms.
200 Mvar. The reactor is connected directly to the
Following the current interruption in each phase, the
400 kV busbar via a 400 kV circuit breaker.
TRV, as described in section 3.3 arises across the
In this study case, the transient recovery voltage breaker poles. The TRV for each phase is depicted
(TRV) is analysed when the shunt reactor in substa- in Figure 47 together with the breaker capability curve
tion Central is switched off. Before disconnecting, the of the CB. According to IEC 62271-100 the TRV en-
shunt reactor is operated at step 2, supplying the grid velope is defined by a two-parameter curve. The input
with 200 Mvar of reactive power. The reactor is then parameters for the TRV envelope are based on the
disconnected by opening the CB. The objective of this maximum peak voltages 𝑢𝑐 and rate of rise of recovery
study case is to analyse the transients following the voltage 𝑅𝑅𝑅𝑉 . In this example the following parame-
reactor drop out. ters are assumed for the breaker capability curve:
Rev.2 41
SWITCHING TRANSIENTS APPLICATION EXAMPLE
600
[kV]
400
200
-200
-400
0 4 8 12 16 [ms] 20
C-400-XShunt: Phase Voltage A
C-400-XShunt: Phase Voltage B
C-400-XShunt: Phase Voltage C
200
[A]
100
-100
-200
-300
0 4 8 12 16 [ms] 20
C400-3-B8_CB: Phase Current A/Terminal i
C400-3-B8_CB: Phase Current B/Terminal i
C400-3-B8_CB: Phase Current C/Terminal i
Figure 46: Shunt reactor side phase voltages and phase currents in the circuit breaker C400-3-B8_CB
1000
500
-500
-1000
-1500
0 3 6 9 12 [ms] 15
C400-3-B8_CB: Voltage Difference A in kV
C400-2-B08_CB.L2 Capability Curve: TRV_limit_A_neg
C400-2-B08_CB.L2 Capability Curve: TRV_limit_A_pos
1000
500
-500
-1000
-1500
0 3 6 9 12 [ms] 15
C400-3-B8_CB: Voltage Difference B in kV
C400-2-B08_CB.L2 Capability Curve: TRV_limit_B_neg
C400-2-B08_CB.L2 Capability Curve: TRV_limit_B_pos
1000
500
-500
-1000
-1500
0 3 6 9 12 [ms] 15
C400-3-B8_CB: Voltage Difference C in kV
C400-2-B08_CB.L2 Capability Curve: TRV_limit_C_neg
C400-2-B08_CB.L2 Capability Curve: TRV_limit_C_pos
Figure 47: Transient recovery voltage (TRV) and dielectric strength of circuit breaker
Rev.2 42
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.16 TRV Shunt Reactor Switching II Following the current interruption in each phase, the
TRV, as described in section 3.3 arises across the
In this study case, the transient recovery voltage breaker poles. Compared to the previous case, the
(TRV) is analysed when the shunt reactor in substa- TRV is now higher due to the additional energy that is
tion Central is switched off. In comparison to the previ- stored in the inductance (current is not zero at current
ous study case, current chopping will be considered interruption).
for the switching transient.
The TRV for each phase is depicted in Figure 47 to-
The simulation sequence is as follows: gether with the breaker capability curve of the CB. Ac-
cording to IEC 62271-100 the TRV envelope is de-
• 𝑡 = −20𝑚𝑠: fined by a two-parameter curve. The input parame-
start simulation ters for the TRV envelope are based on the maximum
peak voltages 𝑢𝑐 and rate of rise of recovery voltage
• 𝑡 = 0 𝑚𝑠:
𝑅𝑅𝑅𝑉 . In this example the following parameters are
Switch event to open phase A circuit breaker
assumed for the breaker capability curve:
C400-3-B8_CB in substation Central at an mag-
nitude of 5 A • Peak TRV voltage 𝑢𝐶 : 787 kV
• 𝑡 = 4 𝑚𝑠: • Time to 𝑢𝐶 : 112 µs
Switch event to open phase B circuit breaker
C400-3-B8_CB in substation Central at an mag- The TRV exceeds the limits of the circuit breaker. The
nitude of 5 A following results are obtained:
• 𝑡 = 10 𝑚𝑠: • Phase A: 𝑢𝑐 = 626 kV; 𝑅𝑅𝑅𝑉 = 2.57 kV/𝜇s
Switch event to open circuit phase C breaker
C400-3-B8_CB in substation Central at an mag- • Phase B: 𝑢𝑐 = 625 kV; 𝑅𝑅𝑅𝑉 = 2.47 kV/𝜇s
nitude of 5 A
• Phase C: 𝑢𝑐 = 627 kV; 𝑅𝑅𝑅𝑉 = 2.53 kV/𝜇s
The simulation results are shown in Figure 48 and Fig-
It is therefore expected that re-ignition may occur dur-
ure 49. The first current chopping occurs in phase A
ing the switching transient.
after the circuit breaker is triggered by a simulation
event. The subsequent current chopping events can
be seen in the simulation plot.
Rev.2 43
SWITCHING TRANSIENTS APPLICATION EXAMPLE
800
[kV]
400
-400
-800
-1200
0 4 8 12 16 [ms] 20
C-400-XShunt: Phase Voltage A
C-400-XShunt: Phase Voltage B
C-400-XShunt: Phase Voltage C
200
[A]
100
-100
-200
-300
0 4 8 12 16 [ms] 20
C400-3-B8_CB: Phase Current A/Terminal i
C400-3-B8_CB: Phase Current B/Terminal i
C400-3-B8_CB: Phase Current C/Terminal i
Figure 48: Shunt reactor side phase voltages and phase currents in the circuit breaker C400-3-B8_CB
1000
500
-500
-1000
-1500
0 10 20 30 40 [ms] 50
C400-3-B8_CB: Voltage Difference A in kV
C400-3-B8_CB: CB TRV envelope positive A
C400-3-B8_CB: CB TRV envelope negative A
1000
500
-500
-1000
-1500
0 10 20 30 40 [ms] 50
C400-3-B8_CB: Voltage Difference B in kV
C400-3-B8_CB: CB TRV envelope positive B
C400-3-B8_CB: CB TRV envelope negative B
1000
500
-500
-1000
-1500
0 10 20 30 40 [ms] 50
C400-3-B8_CB: Voltage Difference C in kV
C400-3-B8_CB: CB TRV envelope positive C
C400-3-B8_CB: CB TRV envelope negative C
Figure 49: Transient recovery voltage (TRV) and dielectric strength of circuit breaker
Rev.2 44
SWITCHING TRANSIENTS APPLICATION EXAMPLE
4.17 Circuit Breaker SF6 Arcing Model Tripping of the generator by opening the follow-
ing circuit breakers:
In this example, the influence of the electrical arc in the CB_Phase-A.1, CB_Phase-B.1, CB_Phase-C.1
circuit breaker is investigated for a near-to-generator and opening CB0 and CB2
short circuit. The simulation plots in Figure 50 show the phase cur-
rents of the synchronous generator and the resistance
Such short circuit currents are characterised by rel-
of the electrical arc during the transients.
atively high DC-components and associated missing
zero crossing phenomena during the first few power Following the short circuit at terminal PP400-1, the cir-
frequency cycles. In order to model such kind of tran- cuit breakers that connect the generator to the fault
sients, the influence of the arc-conditions need to be are triggered to interrupt the current at the next zero
considered. The dynamic behaviour of the arc is mod- crossing (following the reaction time of the relays).
elled according to section 2.5.1 in this example.
Missing zero-crossings occur both in phase B and C
During the simulation, a three phase fault is applied in due to the high DC-component of the currents in these
substation North at the incomer of overhead line OHL- phases. The electrical arc in the circuit breaker damps
NC. The simulation sequence is as follows: the DC-component of the fault currents and thus en-
• 𝑡 = −20𝑚𝑠: ables a successful current interruption after two further
Start simulation power frequency cycles.
400
[kA]
200
-200
-400
-600
0 30 60 90 120 [ms] 150
SYM: Phase Current A
SYM: Phase Current B
SYM: Phase Current C
160
[-]
120
80
40
-40
0 30 60 90 120 [ms] 150
Arcing Model Phase A: Rout
Arcing Model Phase B: Rout
Arcing Model Phase C: Rout
Figure 50: Phase currents of the generator and arcing resistance in each phase of the SF6 circuit breaker
Rev.2 45
SWITCHING TRANSIENTS APPLICATION EXAMPLE