Professional Documents
Culture Documents
Group 1 Earned Value Monitoring
Group 1 Earned Value Monitoring
AGUSTIN, MARVIN B.
DHARIWAL, PRINCE AJIT SINGH D.
LASAM, DANIEL A.
SANTIAGO, JOHARIKO A.
SALADINO, RIANNE ANGEL E.
SORIANO, JOHN MICHAEL ANGELO E.
TUNGPALAN, KENNETH M.
MARCH 2024
highlights
Group 1
EARNED VALUE MONITORING
what is earned value monitoring?
Group 1
EARNED VALUE MONITORING
Current project challenges
Group 1
EARNED VALUE MONITORING
earned value - overview
Group 1
EARNED VALUE MONITORING
earned value (why & what)
Group 1
EARNED VALUE MONITORING
earned value - benefits
Group 1
EARNED VALUE MONITORING
earned value - criticism
The time required for data measurement and manipulation can be considerable.
Qualifying/measuring work-in-progress (WIP) can be challenging.
Integration of financial expenditure information with schedule status.
adhere to project management best-practices
Baseline your schedule
Analyze variance from your expectations
Diligently update your schedule and expenditure
Understand work products produced by the project
Organize your estimation and schedule around work products
Group 1
EARNED VALUE MONITORING
earned value - definitions
Group 1
EARNED VALUE MONITORING
earned value monitoring, several key metrics are used:
Group 1
EARNED VALUE MONITORING
Group 1
EARNED VALUE MONITORING
earned value - ac, pv, ev
Group 1
EARNED VALUE MONITORING
earned value - cost/schedule + or -
Group 1
EARNED VALUE MONITORING
earned value - metrics
Group 1
EARNED VALUE MONITORING
cost metrics
Group 1
EARNED VALUE MONITORING
cost metrics
Group 1
EARNED VALUE MONITORING
earned value metrics
Group 1
EARNED VALUE MONITORING
earned value - Variance & management reserve
Group 1
EARNED VALUE MONITORING
variance - sv & cv illustration
Group 1
EARNED VALUE MONITORING
variance - do you know
What is the problem causing the variance?
What is the impact on other efforts, if any?
What corrective action is planned or under way?
What is the impact on time, cost & performance?
What are the expected results of the corrective action?
The padding added to a project for unexpected costs that are within
the project scope
1. NOT an allowance for changes to scope
2. NOT part of the cost estimate
Added by upper management, NOT the project manager.
Group 1
EARNED VALUE MONITORING
earned value - example
Group 1
EARNED VALUE MONITORING
example - budget, schedule, tasks
Group 1
EARNED VALUE MONITORING
comparison - pv, ac & ev
Group 1
EARNED VALUE MONITORING
cost performance indicators
Group 1
EARNED VALUE MONITORING
earned value - example (Utilizing Revised Estimates)
Group 1
EARNED VALUE MONITORING
example - latest revised estimate
Total budget (BAC) = $5,000
Work schedule (PV) = $2,000
Work accomplished (EV) = $1,800
Actual cost (AC) = $2,400
Latest Revised Estimate (LRE) = $5,600
TCPI (To Complete Cost Performance Index)
CPI = EV/AC ($1,800 / $2,400) = 0.75
TCPI (at BAC) = Work Remaining (BAC - EV)/ Budget Remaining (BAC - AC)
TCPI (at BAC) = ($5,000 - $1,800)/$5,000 - $2,400) = 1.23
TCPI (at LRE) + Work Remaining (BAC - EV)/Estimate Remaining (LRE-AC)
TCPI (at LRE) = $5,000 - $1,800)/$5,600-$2,400) = 1.00
Based on the LRE ($5,600), the project will come on budget (1.00) & revised estimate
appears reasonable.
Group 1
EARNED VALUE MONITORING
earned value - success criteria
Group 1
EARNED VALUE MONITORING
criteria
Group 1
EARNED VALUE MONITORING
”The three great essentials to achieve anything
worth while are, first, hard work; second,
stick-to-itiveness; third, common sense.”
- thomas edison
Group 1
EARNED VALUE MONITORING
THANK YOU FOR
LISTENING!