Professional Documents
Culture Documents
Ene Getenet G+8 BOQ
Ene Getenet G+8 BOQ
Ene Getenet G+8 BOQ
A- Sub Structure
1 19.89 1 Excavation & Earth Work 1
24.08 478.95 1.1 Site clearing
35.77 1
- 17.885
16.285
478.95 total
1.2 bulk excavation 1
18.9 avg depth=120cm
23.1 2
1.2 523.18 total
trench excavation 1
2 22.08 axis A&E
0.90 33.912 1
1.20 47.69
2
2 5.00 axis A 0
0.90 7.45
1.20 10.80
0 14.35
0.9
1.20 -
1
54.16
58.49 total 2
excavation for retaining shear wall
1 34.79 L=7.9+8.61=16.51m
1
0.90 15.14 0
1.20 37.57 total
1.4 excavation for mat depth upto
150cm(d=1.5-1.2=0.3m)
1 9.35 MF-1
10.14 9.35
0.30 28.44 10.14
0 6.50 MF-2
2.50 9.95
0.30 - 10.45 2
28.44 total 2
1.5 excavation for mat depth exceeding
350cm(d=3.5-1.5=2m)
1 9.35 MF-1
3
10.14 4
2.00 189.62
0 6.50 MF-2
2.50 9.95 6
2.00 - 10.45
189.62 total
1
- 1
15.95
50.96 total
1.5 excavation for footing depth exceeding
350cm(d=3.5-1.5=2m)
1 4.80 F1 1pcs
4.80
2.00 46.08 1
2 4.60 F2 2pcs
4.60
2.00 84.64 1
1 6.9 CF-1 1pcs
2.60
2.00 35.88 1
1 3.50 F3 1pcs
3.50
2.00 24.50 1
1 4.10 F4 1pcs
4.10
2.00 33.62 1
2 3.90 F5 2pcs
4.00
2.00 62.40 3
1 3.5 F6 1pcs
3.6
2 25.20 2
1 3.7 F7 1pcs
3.7
2 27.38 2
5
4
6
2
12
20
16
0
2
339.70 total 24
Back fill
a..footing pad 2
1 18.20 F1
0.25 18.2 4
1.15 5.23 2.3
above pad around foundation column 16
1 22.62 C1
1.15 26.01 A=4.6*4.6-0.6*0.6=20.8m2 2
d=3.5-1.2-0.95=1.35m
2 17.4 F2 4
0.25 17.40
1.05 9.14 20.74 4
above pad around foundation column
2 20.74 C2
1.25 51.85 A=4.1*4.1-0.6*0.5=16.51m2
d=3.5-1.2-0.85=1.45m 8
1 13 F3 1pcs
0.25 13 1
0.75 2.44 11.83
above mat around foundation column 1
1 11.83 C3
1.55 18.34 A=4*45-0.6*0.4=15.76m2 2
d=3.5-1.2-0.85=1.45m
1 15.4 F4 2pcs
0.25 15.4
0.95 3.66 16.39
above mat around foundation column
1 16.39 C4 8
1.35 22.13 A=3.1*3.1-3.14*0.5*0.5/4=9.41m2 6
d=3.5-1.2-0.65=1.65m
2 14.8 F5 6pcs
0.25 14.8
0.85 6.29 15.18
2 15.18 C6&C8 1
1.45 44.02 A=2.5*2.5-0.5*0.3=6.1m2
d=3.5-1.2-0.55=1.75m
1 13 F6 1
0.25 13
0.85 2.76 12.18
above mat around foundation column-C3&C5
1 12.18 A=6.5*2.5-0.6*0.4-0.5*0.4=15.81m2
1.45 17.66 d=3.5-1.2-1.15=1.15m 1
1.15
1 13.8 F7
0.25 13.8 0
0.85 2.93 13.27
above strap footing-C2&C7
1 13.27 A=2.9*3+2.5*2.9-2*0.6*0.5=15.35m2
1.45 19.24 d=3.5-1.2-0.85=1.45m
1.45
1 37.58 MF-1 7
0.25 37.58
0.75 7.05 91.09 1
above strap footing-C1&C7
1 91.09 A=2.5*2.7+2.5*2.5-2*0.6*0.5=12.4m2
1.05 95.64 d=3.5-1.2-0.75=1.55m 1
1.45
12.4
1 18 CF-1 1
0.25 18
1.45 6.52
1 17.1 17.10
0.85 14.53
10
1
2
12
1
355.45 total
b.under hard core
1 10.81 d=1.2-0.35=0.85m
1.83 22.61
0.85 16.81 11.31 1
1 11.15 10.81
17.9 1.83
0.85 169.65 11.15
0.5 1.29 17.90
4.76 1.29 0
0.85 2.61 4.76
1 2.36 5.21
6.39 2.61 0
0.85 12.82 225.02
1 4.54 2.36
6.75 6.39
0.85 26.05 9.57
1 8.29 4.79
0.82 4.54
0.85 5.78 6.75
0.5 8.88 16.58
0.82 8.29 1
0.85 3.09
-
236.81 total 1
c.around massonry & shear wall
2 54.16 Lmw=25.9m
0.25 1
1.2 32.50
1 16.51 Lsw=34.79m 2
4.00 Davg=3.6m
0.50 33.02 Wavg=0.5m 1
65.52 total
478.95 cart away
0.2 95.79
523.18
58.49
37.57
28.44
189.62
50.96
339.70
1,323.75 total
236.81 25cm thick well rolled hard core
0.85 278.60
278.60 total
B.SUPER STRUCTURE
4.concrete work
C-25 concrete for
elevation column
sec A1-A1
5 4
0.6 5.6
0.6 7.20 1C1,2C2,3C3&3C4
sec C-C
4 4
0.6
0.6 5.76 0.0490625
1 4 sec K-K
1 0.3316625
0.33 1.32
1 4 sec R-R 1
1
0.28 1.12 0.2826 1
1 4 sec M1-M1
1
0.28 1.12 4
2 4 sec N1-N1
1
0.28 2.24
1 4 sec U-U
1
0.2 0.80 0.19625
4 2.5 sec A2-A2
0.6 C6
0.6 3.60
20 2.5 C1,C3,C3'&C5
0.5
0.5 12.50
10 2.5 C1,C3,C3'&C5
0.45
0.45 5.06
5 2.6 C1,C3,C3'&C5
0.4
0.4 2.08
4 2.6 C1,C3&C3'
0.4
0.4 1.66
4 2.5 sec A3-A3
0.55 C6
0.55 3.03
8 2.5 C6
0.5
0.5 5.00
8 2.5 C6
0.45
0.45 4.05
8 2.6 C6
0.4
0.4 3.33
4 2.5 C2,C4&C8
1 0.2826
0.28 2.80
5 2.5 C2,C4,C8&C9
1 0.2374625
0.24 3.00
9 2.5 C2,C4,C8&C9
1 0.19625
0.2 4.50
13 2.5 C2,C4,C7,C8&C9
1 0.1589625
0.16 5.20
6 2.6 C2,C4,C7,C8&C9
1 0.1256
0.13 2.03
3 2.6 C2,C8&C9
1 0.1256
0.13 1.01
4 2.5 C7&C9
1 0.1256
0.13 1.30
80.98
79.71 total
intermidiate beam-1st floor
1 17.8 FFB-1
0.25 17.8
0.5 2.23
1 15.57 FFB-2
0.25 15.57
0.5 1.95
1 13.44 FFB-3
0.25 13.44
0.5 1.68
1 11.84 FFB-4
0.25 11.84
0.5 1.48
2 19.73 FFB-5
0.25 19.72
0.5 4.93
2 7
0.25 11.2
0.1 0.35 7.92
1 8.15 FFB-6
0.25 8.15
0.6 1.22
1 11.15
0.25 11.15
0.5 1.39
1 8.57 FFB-7
0.25 8.57
0.6 1.29
1 13.77
0.25 13.77
0.5 1.72
1 4.5 FFB-8
0.25
0.4 0.45
intermidiate beam-2nd floor to 8th floor
8 20.67 FB-1
0.25 20.67
0.5 20.67
8 16.04 FB-2
0.25 16.04
0.5 16.04
8 15.33 FB-3
0.25 15.33
0.5 15.33
8 13.04 FB-4
0.25 13.04
0.5 13.04 7.92
16 8.61 FB-5
0.25 8.61
0.6 20.66
16 12.7 12.7
0.25 7.44
0.5 25.40
8 9.15 FB-6
0.25 9.15
0.6 10.98
8 11.15
0.25 11.15
0.5 11.15
8 9.06 FB-7
0.25 9.06
0.6 10.87
8 13.36
0.25 13.36
0.5 13.36
8 4.63 EB-1
0.2
0.4 2.96
1,433.25
179.16 total intermidiate beam
roof beam
1 20.67 RB-1
0.25 20.67
0.4 2.07 236.23
1 15.57 RB-2
0.25 15.57
0.4 1.56 4.48
1 11.9 RB-3
0.25 11.9
0.4 1.19 74.72
2 14.63 RB-4
0.25 14.63
0.4 2.93
1 15.17 RB-5
0.25 15.17
0.4 1.52
1 8.69 RB-6
0.25 8.69
0.4 0.87
1 10.63 EB-2
0.25 10.63
0.4 1.06
1 5.65 EB-3
0.25 10.63
0.4 0.57
101.80
117.54 1
11.75 total
suspended slab 1
1 10.78 first floor slab
1.83 19.73 11.26
1 11.15 5.63
11.51 128.34 10.78
1 7.73 1.83
6.39 49.39 11.15
1 3.16 11.51
2.1 6.64 7.73
0.5 1.29 6.39
4.76 3.07 1.29
1 2.61 16.2
6.39 16.68 8.10
1 5.22 7.85
4 20.88 1.03
1 7.85 cantilever
1.03 8.09
0.5 7.85 cantilever
1.03 4.04
2 1.2 4.76
0.33 0.79
32
1
2
13
27.83 total
form work to
a.elevation column
36 4 1
0.6 86.40 5.6
1 4
2.04 8.16
4 4
1.88 30.08
1 4
1.57 6.28 1.57
16 2.5
0.6 24.00 10
112 2.5
0.5 140.00
72 2.5
0.45 81.00
68 2.6
0.4 70.72
16 2.6
0.55 22.88
4 2.5
1.88 18.80 1.884
5 2.5
1.73 21.63 1.73
9 2.5
1.57 35.33 1.57
13 2.5
1.41 45.82 1.41
9 2.6
1.26 29.48 1.26
4 2.5
1.26 12.60
633.18 total
b.intermediate beam
L(25x40cm)=710.7m
2 1,433.25 827.51
0.4 1,146.60
1 1,433.25 22
0.25 358.31 4
0 89.29 L(60x15cm)=81.84m
0.15 - 89.29
0 89.29
0.6 -
26
2
1.05 3
18
3
1,504.91 total 5
toptie beam 7
L=84.11m 10
2 117.54 4
0.4 94.03 7
7
1 117.54 12
0.25 29.39 8
9
6
7
7
123.42 total
365.44 total
15cm thick suspended slab & tanker slab
2,917.55 total
2.43
-
total
form work to
peregola beam
1
- total
1
1
Glazing work
4 1.5 1
1.5 9.00
2 1.52 1
2.7 8.21
1
1 1.47 1
2.7 3.97
1
1
2
4
1.25
1.5 1.88 4
3 0.8
0.5 1.20 2
1.2
1
20
20
20
1.5 1.80
2.85 20
1.5 4.28
10
10
0.7
1.5 1.05
1.45
1.5 2.18
0.8
1.5 1.20
34.75 total
plastering work
3coats of plastering to external wall
2
#REF! total external wall 2
3coats of plastering to internal wall
#REF!
14
16
2 - -
12 0.25
2.7 8.10
6 0.5 2
2.7 8.10 2
4 8.01 4
0.35 11.21 4
2 8.01 2
0.3 4.81 2
2
2
4 7.25 2
0.35 10.15 2
2 7.25
0.3 4.35
#REF! total internal wall 2
plastering to suspended slab&stair case
0.87 2
365.44
366.31 total 2
2 1.25 anti rust
1.5 3.75 1
8 1.5
0.1 1.20
4 1.52
0.1 0.61
2 1.47
0.1 0.29
2 0.8
1.5 2.40
8.25 total
2 1.25 varnish paint
2.7 6.75
16 0.8
2.7 34.56
2 0.65
2.7 3.51
. 44.82 total
false column
4 2.85
0.1
0.2 0.23 total
8 2.85 formwork to false column
0.1 2.28
8 2.85
0.2 4.56
6.84 total
1
14
15
15
2
1
4
3
1
1
1
2
1
sl&70
48
4
0
52
4
1
1
1
Sheet
214.24 total
2.3-C-25R.c.c for
2.2-12 CM R.C.C.ground floor slab
278.60 total
2.4 footing pad, lift shaft pad & mat foundation
4.3 F1
4.3 0.9
1.1 20.34
4.10 F2
4.10
1 33.62
3 F3
3 0.9
0.7 6.30
3.60 F4
3.60
0.9 11.66
3.4 F5
3.5 0.9
0.8 19.04
3.00 F6
3.10
0.8 7.44
3.2 F7
3.2
0.8 8.19
8.65 MF-1
9.64
0.7 58.37
33.38 mat beam
0.8 33.38
0.5 13.35 8.04
7.73 mat beam
0.4 7.73
0.5 1.55
6.4 CF-1
2.1
1.4 18.82
2
2
0.7 -
2.12 strap beam
0.5
0.8 -
4 strap beam
0.5 3.69
0.1 -
2.6 LF-1
2.6
0.6 -
198.68 total
basement column
2.1 C1-sec B-B
0.6
0.6 1.51
2.6 C2-sec C-C
0.6
0.5 1.56
2.6 C3-sec I-I
0.6
0.4 1.87
2.6 C4-sec M-M
1 A=3.14*0.5*0.5/4=0.19m2
0.19 0.99
2.6 C5&C7-sec P-P
0.5
0.4 2.08
2.6 C6&C8-sec Q-Q
0.5
0.3 2.34 0.19625
10.35 total
15cm thick suspended ground slab
9.95 13.85
7.7 76.62 3.41
9.4 9.95
7.45 70.03 7.7
5 7.7
7.7 38.50 4.75
4.75 9.4
3.71 17.62 7.45
0.36 cantilever
7.75 5.58 3.71
208.35 total area of 15cm thick suspended ground slab
208.35
0.15 31.25 total
239.60 total
foundation column
2.15 sec A-A
0.65 h=3.5-0.4-0.95=2.15m
0.65 4.54 2.15
2.15 sec B-B
0.65 h=3.5-0.4-0.75=2.35m
0.65 3.63 2.35
2.15 sec J-J
1 h=3.5-0.4-0.85=2.25m
0.38 0.82 0.38465
2.15 sec L-L
1 h=3.5-0.4-0.85=2.25m
0.33 0.71 0.3316625
2.15 sec M-M
1 h=3.5-0.4-1.15=1.95m
0.33 0.71 1.95
2.15 sec N-N
1 h=3.5-0.4-0.65=2.45m
0.33 1.42 A=3.14*0.5*0.5/4=0.19m2
2.15 sec O-O
1 h=3.5-0.4-1.15=1.95m
0.24 0.52 0.2374625
2.55 C6 on F5-sec T-T
0.5 h=3.5-0.4-0.55=2.55m
0.3 - 2.55
2.35 C7 on SF-1 & SF-2-sec O-O
0.5 h=3.5-0.4-0.75=2.35m
0.4 - 2.25
2.55 C8 on F5-sec T-T
0.5 h=3.5-0.4-0.55=2.55m
0.3 - 2.55
0.19625
12.35 total
ground floor beam
17.8 GFB-1
0.25 17.8
0.4 1.78
15.57 GFB-2
0.25 15.57
0.4 1.56 155.70
5.9 GFB-3
0.25 5.9
0.4 0.59
7.79 GFB-3'
0.25 7.79
0.4 0.78
11.84 GFB-4
0.25 11.84
0.4 1.18
6.75 GFB-5
0.25
0.4 2.03
6.39 GFB-5'
0.25 6.39
0.4 1.28
6.59 GFB-5''
0.25 6.59
0.4 1.32 15.15
11.15 GFB-6
0.25 11.15
0.4 1.12
7.11 GFB-7
0.25 7.11
0.4 0.71
13.49 GFB-7'
0.25 13.49
0.4 1.35
7.45 FB-7 on axis 2&3
0.6 7.45
0.15 -
15.63 FB-3' on axis C
0.3
0.5 -
7.95 DB-1 on axis 2&3
0.7
0.9 -
4.1 FB-1' on axis 2&3
0.25
0.4 -
4.1 FB-2' on axis 2&3
0.25
0.4 - 136.86
13.69 total
Basement beam
15.64 BB1 on axis A,B,C,D&E
0.25 5.06
0.4 7.82
15.15 BB2 on axis 1,2,3&4
0.25 15.15
0.4 6.06 138.80
13.88 total
e.form work to
a.footing pad,lift-shaft pad & mat foundation
4.3 F1
1.1 18.92
4.1 F2
1 32.80
3 F3
0.7 8.40
3.6 F4
0.9 12.96
6.9 F5
0.8 22.08 6.9
6.1 F6
0.8 9.76 6.1
3.2 F7
0.8 10.24 9.8
18.29 MF-1
0.7 25.61 18.29
33.38
0.5 33.38
7.73
0.5 7.73
8.5 CF-1
1.4 23.80 8.5
2.12
0.8 -
4
0.1 - 17.15
2.6 LF-1
0.6 - 11.95
205.68 total
basement column
2.1 C1-sec B-B
0.6 10.08
2.6 C2-sec C-C
1.1 11.44
2.6 C3-sec I-I
1 15.60
2.6 C4-sec M-M
1.57 8.16 circimfrance=3.14*0.5=1.57m2
2.6 C5&C7-sec P-P
0.9 18.72
2.6 C6&C8-sec Q-Q
0.8 24.96
88.96 1.57
b.foundation column
2.15 C1 on F-1-sec A-A
0.65 27.95 h=3.5-0.4-0.95=2.15m
2.15 C1 on SF-2-sec A-A
0.65 22.36 h=3.5-0.4-0.75=2.35m
2.15 C2 on F2 & SF-1-sec G-G
2.2 4.73 h=3.5-0.4-0.85=2.25m
2.15 C3 on F3-sec H-H
2.04 17.54 h=3.5-0.4-0.85=2.25m
2.15 C3 on MF-2-sec H-H
1.73 3.72 h=3.5-0.4-1.15=1.95m
2.45 C4 on F-4-sec L-L
1.57 - circumfrance=3.14*0.5=1.57m
1.95 C5 on MF-2-sec O-O
0.9 - h=3.5-0.4-1.15=1.95m
2.55 C6 on F5-sec T-T
0.8 - h=3.5-0.4-0.55=2.55m
2.35 C7 on SF-1 & SF-2-sec O-O
0.9 - h=3.5-0.4-0.75=2.35m
2.55 C8 on F5-sec T-T
0.8 - h=3.5-0.4-0.55=2.55m
76.30 total
basement beam
138.8 L=138.8m
0.4 111.04 total
ground floor beam
138.80
0.4 111.04
116.81
0.25 -
7.45
0.6 -
15.63
0.3 -
15.9 15.9
0.75 -
15.9
0.7 -
111.04 total
20cm thick lift shaft shear wall
7.14 2.25
2.25 32.13 7.14
6.3
3 -
32.13 total
25cm thick shear wall & shear pad
16.51
0.6 19.81
1.2
0.6 1.44
16.51
4.5 148.59
0.2
4.5 1.80
171.64 total
15cm thick suspended stair case & landing
1.4 sec A-A & sec C-C
0.16 5.38
1.4 bottom of slanted surface
4.04 11.31
4.04 edge of slanted surface
0.3 4.85
1.5 sec B-B
0.15 3.60
1.5 bottom of slanted surface
2.32 6.96
2.32 edge of slanted surface
0.3 2.78
1.4 landing
2.1 11.76
46.64 total
entrance stair
4.75
0.16 6.08
4.75
1.18 5.60
4.75 bottom of slanted surface
2.35 11.16
2.35 edge of slanted surface
0.3 1.41
24.26 total
expansion joint
14.7 117.60
15.15 90.90
-
-
208.50 total
25cm thick retaining shear wall
16.51 a.shear pad
0.6 L=34.79m
1.25 12.38 33.85
16.51 shear wall
0.2 Davg=3.6m
4.5 14.86
27.24 total
20cm thick lift-shaft shear wall
7.14 L=2*2+2*1.6=7.2m
0.2 H=3.5-0.65=2.85m
2.25 3.21 2.85
6.3 L=2+2*0.55+2*1.6=6.3m
0.2 H=3m
3 - 7.2
3.21 total
15cm thick suspendedstair case & ramp
at main entrance
3.5 Atr&rsr=0.5*0.3*0.16=0.02m2
0.02 0.49 0.024
3.5 landing
1
0.15 0.53
3.5 slanted surface
2.35 Ls.s.=2.35m
0.15 1.23 6.112
6.11 15cm thick R.C.C. ramp
1 A=4.02*1.1+1.3*1.3=6.11m2
0.2 1.22 9.45
3.47 total
15cm thick suspendedstair case & landing
1.4 sec A-A & sec C-C
0.02 0.28
1.4 Ls.s.=2*2.02=4.04m
4.04
0.15 0.85
1.5 sec B-B
0.02 0.21
1.5 Ls.s.=2.32m
2.32
0.15 0.52
5.8 landing beam
0.25 L=2*1.4+2*1.5=5.8m
0.4 0.58
1.4 landing
2.1
0.15 0.88
3.32 total
form work to
15cm thick suspended stair case & landing
1.4 riser
0.15 2.52
1.5
0.15 1.80
1.4 landing
2.1 5.88
1.4 bottom of slanted surface
4.04 5.66
4.04 edge of slanted surface
0.3 2.42
1.5 bottom of slanted surface
2.32 3.48
2.32 edge of slanted surface
0.3 1.39 5.8
5.8 landing beam
0.22 3.83 L=2*1.4+2*1.5=5.8m
26.98 total
3.Massonry work
54.16 a.below NGL
0.4
1.2 26.00 total
b.above NGL
L=1*21.7+2*7.45=36.6m
54.16 d=0.5m
0.4 -30.38
0.5 10.83 total
c.massonry steps
stone massonry steps
10.09 L=1.69+2+2*1.46+2*1.74=10.09m
0.25 0.87165
0.2 -
1.49 landing
1.17
0.5 -
- total
wooden door price per meter square=1284.86BIRR
HCB work
20cm HCB wall
ground&1st
43.16 axis 1,1'&3
2.8 120.85 43.16
6.77
38.96
266.29 0
ddn for door & window
2
2.75 33.00
1.2
2.1 5.04
0.9
2.75 4.95
0.7
2.75 1.92
1.2
1.75 8.40
1
1.75 1.75
0.7
1.75 1.22
0.5
0.6 0.60
56.89 total ddn
209.40 total 20cm HCB wall
brick wall
4.85
- total
dressed stone wall
- total
15cm HCB wall
16.7 axis 2,2'&3
2.8 46.76 16.7
21.24 axis A'&C'
2.8 59.47 21.24
106.23
0.9 ddn for door & window
2.1 7.56
7.56 total ddn
98.67 total 15cm HCB wall
internal plastering
370.39
16
6.42
34.668
41.5 glazing
1.75 72.63 total
73.14 total
gutter
17.34 17.34 8.6
8.6 8.60 17.34
25.94 total
j bolt
0.75 24.00
2.47 kgpermeter
59.28 total
Dia.12x12x5mm CHS elevation column
2.7 21.60 total
Dia.15x15x5mm CHS elevation column
4.2 4.20 total
3.14 10x10x5mm RHS top tie beam
5.4 33.91
5.3 42.40
76.31 total
steel truss
180x180x8mm upper & lower members
18.82 94.10 L1=18.82m
14.25 85.50 spacing =1.5m
179.60 11.87
bracing members
9.45 103.95 L=9.45
plate
9.31 65.17 5.16666666666667
1.54
21 32.34
6.54
2.37 15.50
9.64
11.3 108.93
7.5
14.4 108.00
1,525.78 total
2.6
0.3
0.3 3.04
sec H-H
2.6
0.35
0.35 0.32
sec E-E
2.61
0.3
0.3 2.35
4.76666666666667
5.55555555555556
19.8441
43.45
43.16
carpentry & joinery
a.dia.10-12cm equalyptus upper&lower main members
Llower=5m,Lupper=5.14m Ltotal=10.14
spacing=0.9m
10.14 223.08 No. of truss=2*(8.5/0.9)+1=22
8.74 34.96 Llower=4.29m,Lupper=4.45m Ltotal=8.74
No. of truss=(2/0.9)+1=4
258.04 total
b.dia.8-10cm equalyptus vertical&diagonal members
L=1*(1.2+1+0.8+0.6+0.4)+1*(1.1+
0.9+0.7+0.5+0.3)=7.5m
7.5 195.00 total
5X7 roof purlin
Lpurlin=12.01m, Lp=10.62
43.16 86.32 spacing=0.9m
43.45 130.35 No. of purlin=1*(5/0.9)+1=7
216.67 total
4X5cm chipwood ceiling purlin
spacing=0.6m
1 18.00 3.05
10 30.00 5.08333333333333
3.23 16.15 2.49
2 14.00 1.245
1.25 12.50
5.17 20.68
3.05 21.35
3.6 25.20
3.93 47.16
6.44 51.52
2.55 22.95
4.72 28.32
3.05 21.35
3.45 24.15
353.33 total
1 8mm chipwood ceiling
10 10.00
3.23
2 6.46
1.25
5.17 6.46
3.05
3.6 10.98
3.93
6.44 25.31
2.55
4.72 12.04
3.05
3.45 10.52
-
-
total
81.77 total
Finishing work
3cm cement screed
basement floo
15.41 cement tile
12.84 197.86
15.01
3.74 56.14 4.98
5.14 ground floor
2.42 12.44 terrazzo tile
5.16 verendah
2.52 13.00 3.93
5
2.99 14.95
7.93 24.3165
1.41 11.18 2.5389
2 corridor
8.04 16.08 6.14
5.02 corridor
1 5.02
1.41 landing
2.29 6.46
6.45
6.14 79.21 4.9
4.9
1.72 8.43
2.17 toilet
1.17 2.54
3.9 kitchen
1.52 11.86
3.15 corridor
1 6.30
2.97 toilet
1.17 6.95
4.94 M.bed rooms & children's bed rooms
2.65 26.18
4.8 first floor
2.8 13.44 verendah
2.94 M.bed rooms & children's bed rooms
2.65 31.16
3.15 corridor
1 12.60
2.97 toilet
1.17 13.90
3.9 kitchen
1.52 23.71
6.45
6.14 79.21
4.9
1.72 8.43
2 corridor
8.04 16.08 6.14
5.02 corridor
1 5.02
1.41 landing
2.29 6.46
4.8 second, third ,fourth & fifth floors
3.87 92.88 verendah
2.94 M.bed rooms & children's bed rooms
2.65 155.82
3.15 corridor
1 63.00
2.97 toilet
1.17 69.50
3.9 kitchen
1.52 118.56
6.45
6.14 396.03
4.9
1.72 42.14
2 corridor
8.04 80.40 6.14
5.02 corridor
1 25.10
1.41 landing
2.29 32.29
terace floor slab
139.07
6.46
roof floor slab & tanker slab
-
6.46
2.88
1,912.30 total
5cm thick cement tile ff
254.00 total
terrazzo tile ff
1,651.84 total
PVC tile ff
total
marble tile ff
1,912.30
-
-
- -
- -
1,912.30 total
stair case
1.1 terrazzo tread & riser
0.3 4.62
1.1 tread
0.15 2.64
7.26 total
13.35 kitchen
1.8 24.03 13.35
66.51
0.65 ddn for door & window
1.8 1.17
0.8
1.8 2.88
0.8
0.5 1.20
1.2
0.9 1.08
6.33
60.18 total
marble tread & riser
1.05 a.tread
0.28 4.12
1.05 b.riser
0.16 2.52
2.1 landing
1.18 2.48
9.11 total
0.28 4.20 skerting
1.18 2.36
2.1 2.10
8.66 total
8.66 total marble skerting
1.5 6.00 window sile
0.8 2.40
1.2 1.20
1.45 1.45
3.55 3.55
1.52 3.04
1.47 1.47
19.11 total
light pts
massive leueta
2nd to 5th floors
8 32.00
8 8.00 first floor
13 13.00 ground floor
0 - basement floor
53.00 total
G+7+ Terrace Appartement
A) under isolated & strap footing, lift shaft pad & mat foundation m2 214.24 113.36 24,285.79
B) under massonry & retaining shear wall foundation m2 35.58 113.36 4,033.35
Reinforced concrete, class c-25, 360kg cement/m3 filled and vibrated
around rod reinforcement steel & from work measured separately.
2.2
A) Isolated footin, strap footing, lift shaft pad & mat foundation m3 198.68 3868.34 768,558.70
B) foundation column m3 12.35 3868.34 47,759.98
D)Grade beam m3 13.69 3868.34 52,942.10
G) 20cm thick lift-shaft shear wall m3 3.21 3868.34 12,428.98
H)25cm thick shear wall & pad m3 27.24 3868.34 105,379.38
J) 15cm thick entrance stair & ramp m3 3.47 3868.34 13,426.04
2.3 K)10cm thick R.C.C. concrete floor slab c-20, 320kg cement/m .
3
m2 278.60 386.83 107,772.53
2.4 Provide, cut and fix in position sawn zigba form work.
A) Isolated footin, strap footing, lift shaft pad & mat foundation m2 205.68 312.48 64,269.64
B) foundation column m2 76.30 339.35 25,893.59
D)Grade beam m2 111.04 339.35 37,681.42
G) 20cm thick lift-shaft shear wall m2 32.13 332.58 10,685.80
H)25cm thick shear wall & pad m2 171.64 332.58 57,084.70
J) 15cm thick entrance stair & ramp m2 24.26 397.56 9,643.81
Steel reinforcement according to structural drawing. Price shall include
2.5 cutting, bending, placing in position & tying wires.
a) Diam.8mm deformed bars. Kg 3961.15 69.13 273,834.09
b) Diam.10mm deformed bars. Kg 3613.47 65.68 237,332.90
c) Diam.12mm deformed bars. Kg 724.79 65.68 47,603.92
d) Diam.14mm deformed bars. Kg 3552.67 65.68 233,339.29
e) Diam16mm deformed bars. Kg 5746.30 67.51 387,932.85
f) Diam,20mm deformed bars Kg ### 67.80 1,068,510.11
g) Diam.24mm deformed bars Kg 67.80 -
2.6 Supply & install 0.5cm thick & 10cm high styrofoam expansion joint ml 208.50 37.46 7,810.41
· Total Carried to Summary 3,598,209.37
3Masonry Work
50cm thick trench or equivalent stone masonry foundation wall below
3.1 NGL bedded in cement sand mortar1:3 m3 26.00 2065.97 53,708.61
3.2 50 cm thick stone massonary above N.G.L. m3 10.83 2208.67 23,924.31
3.3 stone masonory steps m3 2572.67 -
· Total Carried to Summary 77,632.92
B. Super Structure
4.1 4. Concrete Work
Reinforced concrete class C-25 360 kg cement/m3 of concrete, filled into
form work and vibrated around reinforcement rods. Reinforcement and
form work are measured separately.
a) In elevation columns m3 79.71 4101.73 326,955.05
b)intermidiate beam m3 179.16 4101.73 734,849.33
c) roof beam m3 11.75 4101.73 48,211.73
d) 20cm thick lift-shaft shear wall m3 36.90 4101.73 151,368.60
e)15cm thick susspended slab,roof slab & tanker slab m3 437.63 4101.73 1,795,051.55
f)15cm thick susspended stair case& landing m3 27.83 4101.73 114,134.74
4.2 C-20 lintel beam m3 22.55 3581.00 80,751.55
Provide, cut and fix in position sawn zigba wood form work or
4.3 equivalent form work
a) In elevation columns m2 633.18 379.64 240,380.08
b)intermidiate beam m2 1504.91 379.64 571,324.02
c) roof beam m2 123.42 379.64 46,854.03
d) 20cm thick lift-shaft shear wall m2 373.90 348.42 130,272.84
e)15cm thick susspended slab,roof slab & tanker slab m2 2917.55 348.42 1,016,533.45
f)15cm thick susspended stair case& landing m2 365.44 395.13 144,395.12
f)lintel beam m2 65.98 379.64 25,048.65
Steel reinforcement according to drawing cut bent and placed in
position. Unit price shall include in cutting, bending, placing in position
4.3 and typing wire.
a) Diam 6mm plain bar Kg 83.64 -
b) Diam.8mm deformed bars kg ### 70.05 1,199,742.93
c) Diam.10mm deformed bars kg ### 66.25 2,411,148.96
d) Diam.12mm deformed bars kg 6215.75 66.25 411,793.53
e) Diam.14mm deformed bars kg 3577.24 66.25 236,992.41
f) Diam.16mm deformed bars kg ### 68.09 942,096.25
g) Diam.20mm deformed bars kg ### 68.38 2,353,308.11
· Total Carried to Summary 12,981,212.95
5.Wall Work
5.1 20cm thick class B HCB wall bedded in cement mortar 1:4 m2 2689.00 475.18 1,277,759.02
5.2 15cm thick class B HCB wall bedded in cement mortar 1:4 m2 1928.89 440.39 849,463.87
5.3 10cm thick class B HCB wall bedded in cement mortar 1:4 m2 442.56 421.51 186,543.47
· Total Carried to Summary 2,313,766.35
6.Steel structre & Rroofing
Steel Stair emergency exit with all acsessories as follows: -
150x150x5mm plate according to the design (price shall include fixing
6.2 bolt & no) Pcs 16.00 125.00 2,000.00
180x1800x8mm SHS steel truss according to the structural
6.3 drawing (price shall include all the necessary works) -
Upper and lower main truss chords ml 179.60 225.00 40,410.00
6.4 120x120x5mm inclined & vertical bracing members ml 103.95 145.00 15,072.75
40x40x3mm angle iron welded on the steel truss in every 1.2m
for the connection of purlin & upper truss member price shall
6.5 include all the necessary works ml 22.35 85.00 1,899.75
6.6 100x100x4mm SHS purlin ml 165.79 120.00 19,895.04
6.7 Colovred flat metal sheet gutter according to the drawing dev ml 112.13 185.00 20,744.05
6.8 Ø110mm PVC down pipe fixed on column with metal strupps. ml 457.50 129.33 59,168.48
J-bolt Steel reinforcement according to drawing cut bent and placed in
position. Unit price shall include in cutting, bending, placing in position
6.9 and typing wire.
Diam.20mm deformed bars kg 59.28 68.38 4,053.57
6.10. Xyepex water proofing material or equivalent m2 139.07 12000.00 1,668,818.40
· Total Carried to Summary 1,832,062.03
7.Carpentary & Joinery Work
7.2 wooden door
D1 100x210cm No 24.00 6500.00 156,000.00
D2 80x210cm No 49.00 6350.00 311,150.00
D3 70x210cm No 52.00 6250.00 325,000.00
SD1-Sliding door size 80x210cm No 11.00 6400.00 70,400.00
· Total Carried to Summary 862,550.00
8. Aluminium Work
Aluminium windows and doors made of extrude profiles of 6060
standard of UNI3569 HB65 norms dimensional tolerance and thickness
of the aluminium to be of UNI3879 norm spacer for the glazing and
paneles with average from 10-42mm.Operable windows to be of
horixontal and vertical pivoting. Aluminium profile of bronze color with
8.1 brushed finish cut and assembeled to the size and shapes shown on the
schedule of windows and doors.Manufacturing of the door and windows
subject to approval of shop drawings to be provided by the Contractor.
2.1
Stops- 3
Operation- full collective/duplex control
Entrance- one side
Speed- 1.6m/s
Travel distance-38m
Power supply-380/221,50Hz
Drive-VVVF variable voltage & frequency
Cabin material- wall,car & landing door all stations steel
Floor cover -lined with wear resistance PVC, floor to floor height 3.5m
no of bars
item location Length
footing pad F1 6.2 60
101.3 F2 5.8 58
103.5 F3 4.1 50
6.44 F4 5.1 62
F5 4.7 31
4.8 30
F6 4.3 24
1.288 4.4 23
2.338 F7 4.5 52
CF1 17.8 19
9.2 55
MF-1 9.75 98
9.75 98
10.74 88
10.74 88
sec X-X 11.74 22
ST-1 3.7 98
sec Y-Y 10.75 22
ST-1 3.7 88
sec Z-Z 12.33 8
12.33 8
ST-2 2.8 103
foundation column sec A-A 4.7 22
25.5 ST-1 2.3 27
ST-1' 1.9 27
sec B-B 4.7 16
ST-1 2.3 27
ST-1' 1.9 27
sec J-J 4.7 26
ST-12 2 27
ST-12' 1.78 27
sec L-L 4.7 24
ST-5 1.85 27
ST-5' 1.62 27
sec M-M 4.7 18
ST-5 1.85 27
ST-5' 1.62 27
sec N-N 4.7 16
ST-5 1.85 27
ST-5' 1.62 27
sec O-O 4.7 14
ST-6 1.52 27
17.3333333333333 ST-6' 1.38 27
shear wall & shear pad RW-1 17.51 16
16.51 3.3 112
17.51 5.4 112
3.3 16.81 30
110.066666666667 RW-2 3.85 106
16.81 21.2 19
lift shaft-shear wall(L=7.88m) 1 4.86 54
7.88 14 2.25 72
52.5333333333333 9 3.6 70
21.12 2 11.1 160
17.5 4 1.95 96
7.5 5 1 4
4.2 12
ground slab all axis 10.81 9
0.82 1.83 45
3.28 11.15 73
17.9 46
1.29 21
4.76 7
2.36 27
6.39 11
4.54 28
6.75 20
8.29 5
0.82 35
8.88 5
0.82 37
ground floor beam GFB-1 38.9 3
GFB-2 33.64 3
GFB-3 12.8 3
GFB3' 16.58 3
GFB4 26.09 3
GFB5 15.5 3
GFB5' 14.78 3
GFB5'' 14.94 3
GFB6 26.4 3
GFB7 15.92 3
GFB7' 30.88 3
stirruup GFB GFB-1 1.2 120
13.49 GFB-2 1.2 105
89.9333333333333 GFB-3 1.2 41
599.555555555556 GFB3' 1.2 53
3997.03703703704 GFB4 1.2 80
8.2 GFB5 1.2 24
7.95 GFB5' 1.2 44
53 GFB5'' 1.2 45
GFB6 1.2 76
GFB7 1.2 49
GFB7' 1.2 91
Total length
unit weightkg/m
total weight
no of bars
item location Length
elevation column C1 12.9 16
8 7.6 16
11.84 11.4 14
7.68 3.18 12
11.05 C2 9.1 26
7.21 3.8 20
11.52 3.8 18
3.8 16
7.6 14
6.98 14
5.19 C3 5.3 22
7.6 20
3.8 16
7.6 14
3.8 12
6.98 10
C3' 9.1 16
7.6 14
11.4 14
6.98 12
C4 12.9 16
7.6 14
7.6 14
3.18 12
C5 12.9 16
3.8 16
7.6 14
6.98 12
C6 5.3 22
7.6 20
3.8 18
3.8 16
7.6 14
6.98 14
C7 12.9 14
3.8 12
7.6 12
3.8 10
3.18 8
C8 9.1 18
7.6 16
11.4 14
6.98 14
C9 5.3 22
3.8 20
3.8 16
11.4 14
3.8 14
6.98 12
FC 5.25 6
stirruup E.C. col-60x60
20 ST-10 2.3 36
13.3333333333333 ST-10* 1.9 36
col-60x60
3.33333333333333 ST-10 2.3 26
ST-10* 1.9 26
col-dia 65
ST-12 2 36
ST-12' 1.78 36
col-dia 60
ST-5 1.85 36
ST-5* 1.62 36
col-dia 60
ST-5 1.85 26
ST-5* 1.62 26
col-dia 55
ST-9 1.7 26
ST-9* 1.5 26
col-dia 50
ST-6 1.52 36
ST-6* 1.38 36
col-dia 50
ST-6 1.52 52
ST-6* 1.38 52
col-dia 45
ST-7 1.36 52
ST-7* 1.22 52
col-dia 45
ST-7 1.36 78
ST-7* 1.22 78
4 col-dia 40
ST-8 1.2 26
ST-8* 1.1 26
col-dia 40
ST-8 1.2 26
ST-8* 1.1 26
col-dia 40
ST-8 1.2 52
ST-8* 1.1 52
col-55x55
ST-1 2.1 26
ST-1' 1.74 26
col-50x50
ST-2 2 104
ST-2* 1.54 104
col-50x50
ST-2 2 52
ST-2* 1.54 52
col-45x45
ST-3 1.7 52
ST-3* 1.34 52
col-40x40
ST-4 1.5 26
ST-4* 1.22 26
col-40x40
ST-4 1.5 26
ST-4* 1.22 26
stair case sec A-A 4.09 13
3.28 15
2.81 11
3.8 6
1.02 48
sec B-B 5.57 14
4.37 16
4.57 11
3.8 8
1.02 72
sec C-C 4.81 13
3.74 15
3.7 11
3.8 6
1.02 48
intermidiate beam(FF) FFB-1 19.55 3
19.55 4
8.98 negative bar 10.29 2
11.05 negative bar 2.62 2
FFB-2 17.32 3
16.52 4
negative bar 9.63 2
negative bar 1.87 2
FFB-3 15.19 3
14.39 4
negative bar 6.41 2
negative bar 3.27 2
FFB-4 13.59 3
12.7 4
negative bar 9.04 2
FFB-5 23.37 3
15.94 5
7.32 5
negative bar 11.67 3
negative bar 4.54 2
FFB-6 22.58 3
16.32 5
5.61 5
negative bar 8.54 3
negative bar 6.86 2
FFB7 25.4 3
16.57 5
negative bar 17.45 3
intermidiate beam(SF to EF) FB-1 22.33 3
22.23 4
negative bar 15.59 2
FB-2 17.82 3
17.02 4
negative bar 6.41 2
negative bar 5.59 2
FB-3 16.99 3
16.09 4
negative bar 7.58 2
negative bar 4.2 2
FB-4 14.82 3
16.02 4
negative bar 9.82 2
FB-5 24.61 3
23.35 17.07 5
7.19 5
negative bar 17.44 3
FB-6 23.58 3
17.32 5
5.61 5
negative bar 9.54 3
negative bar 6.86 2
FB-7 25.73 3
17.56 5
negative bar 13.69 3
negative bar 4.07 2
EB-1 10.3 3
stirruup I.M-1st floor FFB-1 1.4 150
13.77 FFB-2 1.4 131
114.75 FFB-3 1.4 113
FFB-4 1.4 100
FFB-5 1.4 115
1.6 60
FFB-6 1.6 69
1.4 94
FFB-7 1.6 73
1.4 115
30 FFB-8 1.2 31
stirruup I.M-1st to 8th floors FB-1 1.4 174
13.36 FB-2 1.4 135
111.333333333333 FB-3 1.4 129
FB-4 1.4 110
FB-5 1.6 73
1.4 108
FB-6 1.6 78
1.4 94
FB-7 1.6 77
1.4 113
30.8666666666667 EB-1 1.1 32
Roof Beam RB-1 23.03 3
22.23 4
negative bar 15.28 3
RB-2 9.58 3
7.6 3
16.48 4
negative bar 3.88 3
negative bar 7.2 2
RB-3 13.5 3
12.81 4
negative bar 3.88 3
negative bar 4.86 2
RB-4 10.09 3
16.22 4
negative bar 11.55 3
RB-5 18.25 3
16.75 4
negative bar 12.09 3
RB-6 9.91 3
9.21 4
negative bar 7.47 3
EB-2 22.3 3
EB-3 12.4 3
stirruup roof beam (L=117.54m) all axis 1.2 785
117.54
783.6
suspended slab-1st floor all axis 1.89 30
2.33 18.17 74
13.55 11.66 37
18.49 8 74
9 37
6.87 83
1.95 17
2.28 120
18.49 13
17.85 20
19.3 69
18.49 18
suspended slab-2nd to 8th floors all axis 6.87 98
13.54 17.85 31
5 19.3 69
35.7142857142857 1.89 30
1.95 27
2.28 120
9.18 37
9.47 74
18.49 18
13.54 37
18.17 74
suspended slab-Terrace floor all axis 8.93 112
5.25 1.89 30
37.5 6.87 59
18.49 17.85 31
18.3 30
1.95 27
2.28 51
5.64 112
2.7 39
11.09 41
1.92 37
11.08 8
1.92 37
5.15 9
9.29 18
9.79 39
suspended slab-roof floor all axis 8.87 33
8.1 8 37
57.8571428571429 5.73 37
5.73 8.39 37
11.08 59
lift shaft-shear wall(L=7.2m) 1 48 124
140 3 2.8 32
446 3' 3.28 32
4 5.75 170
4 12.1 446
5 2.95 280
10 2 4
Total length
unit weightkg/m
total weight
sub st
no of members Diam in mm
8 10 12 14 16 20 24
1 372
2 672.8
1 205
1 316.2
2 291.4
2 288
1 103.2
1 101.2
1 234
1 338.2
1 506
1 955.5
1 955.5
1 945.12
1 945.12
2 516.56
4 1450.4
2 473
4 1302.4
2 197.28
2 197.28
4 1153.6
5 517
5 310.5
5 256.5
4 300.8
4 248.4
4 205.2
1 122.2
1 54
1 48.06
1 112.8
1 49.95
1 43.74
1 84.6
1 49.95
1 43.74
2 150.4
2 99.9
2 87.48
1 65.8
1 41.04
1 37.26
1 280.16
1 369.6
2 1209.6
2 1008.6
2 816.2
2 805.6
2 524.88
2 324
2 504
2 3552
2 374.4
2 8
1 50.4
1 97.29
1 82.35
1 813.95
1 823.4
1 27.09
1 33.32
1 63.72
1 70.29
1 127.12
1 135
1 41.45
1 28.7
1 44.4
1 30.34
1 116.7
1 100.92
1 38.4
1 49.74
1 78.27
3 139.5
2 88.68
2 89.64
1 79.2
1 47.76
1 92.64
1 144
1 126
1 49.2
1 63.6
1 96
3 86.4
2 105.6
2 108
1 91.2
1 58.8
1 109.2
super st
no of members Diam in mm
8 10 12 14 16 20
2 412.8
2 243.2
2 319.2
2 76.32
1 236.6
1 76
1 68.4
1 60.8
1 106.4
1 97.72
1 116.6
1 152
1 60.8
1 106.4
1 45.6
1 69.8
1 145.6
1 106.4
1 159.6
1 83.76
2 412.8
2 212.8
2 212.8
2 76.32
1 206.4
1 60.8
1 106.4
1 83.76
4 466.4
4 608
4 273.6
4 243.2
4 425.6
4 390.88
1 180.6
1 45.6
1 91.2
1 38
1 25.44
1 163.8
1 121.6
1 159.6
1 97.72
1 116.6
1 76
1 60.8
1 159.6
1 53.2
1 83.76
1 31.5
9 745.2
9 615.6
4 239.2
4 197.6
1 72
1 64.08
4 266.4
4 233.28
4 192.4
4 168.48
5 221
5 195
1 54.72
1 49.68
4 316.16
4 287.04
5 353.6
5 317.2
1 106.08
1 95.16
9 280.8
9 257.4
3 93.6
3 85.8
2 124.8
2 114.4
4 218.4
4 180.96
5 1040
5 800.8
4 416
4 320.32
9 795.6
9 627.12
9 351
9 285.48
8 312
8 253.76
7 372.19
7 344.4
7 216.37
7 159.6
7 342.72
7 545.86
7 489.44
7 351.89
7 212.8
7 514.08
7 437.71
7 392.7
7 284.9
7 159.6
7 342.72
1 58.65
1 78.2
1 20.58
1 5.24
1 51.96
1 66.08
1 19.26
1 3.74
1 45.57
1 57.56
1 12.82
1 6.54
1 40.77
1 50.8
1 18.08
2 140.22
2 159.4
2 73.2
2 70.02
2 18.16
1 67.74
1 81.6
1 28.05
1 25.62
1 13.72
1 76.2
1 82.85
1 52.35
8 535.92
8 711.36
8 249.44
8 427.68
8 544.64
8 102.56
8 89.44
8 407.76
8 514.88
8 121.28
8 67.2
8 355.68
8 512.64
8 157.12
16 1181.28
16 1365.6
16 575.2
16 837.12
8 565.92
8 692.8
8 224.4
8 228.96
8 109.76
8 617.52
8 702.4
8 328.56
8 65.12
8 247.2
1 210
1 183.4
1 158.2
1 140
2 322
2 192
1 110.4
1 131.6
1 116.8
1 161
1 37.2
8 1948.8
8 1512
8 1444.8
8 1232
16 1868.8
16 2419.2
8 998.4
8 1052.8
8 985.6
8 1265.6
8 281.6
1 69.09
1 88.92
1 45.84
1 28.74
1 22.8
1 65.92
1 11.64
1 14.4
1 40.5
1 51.24
1 11.64
1 9.72
2 60.54
2 129.76
2 69.3
1 54.75
1 67
1 36.27
1 29.73
1 36.84
1 22.41
1 66.9
1 37.2
1 942
1 56.7
1 1344.58
1 431.42
1 592
1 333
1 570.21
1 33.15
2 547.2
1 240.37
1 357
1 1331.7
1 332.82
8 5386.08
8 4426.8
8 10653.6
8 453.6
8 421.2
16 4377.6
8 2717.28
8 5606.24
8 2662.56
8 4007.84
8 10756.64
1 1000.16
1 56.7
1 405.33
1 553.35
1 549
1 52.65
2 232.56
1 631.68
1 105.3
1 454.69
1 71.04
1 88.64
1 71.04
1 46.35
1 167.22
1 381.81
1 292.71
1 296
1 212.01
1 310.43
1 653.72
1 5952
1 89.6
1 104.96
1 977.5
1 5396.6
1 826
10 80
0 43359.37 58986.55 6999.72 2956.4 8756.99 13933.26
0.222 0.395 0.617 0.888 1.21 1.58 2.47
0 17126.951 36394.701 6215.7514 3577.244 13836.044 34415.152
Take Off Sheet
A- Sub Structure
1 14 1 Excavation & Earth Work
5.55 77.70 1.1 Site clearing
138.846
- 91.5624
89.9624
77.70 total
1.2 bulk excavation
12.5 avg depth=120cm
3.05
3.5 133.44 total
trench excavation
1 28.50 axis A&E
0.50 L=2*10+2*3.6=27.2m
3.50 49.88 28.5
back fill under hard core
12.00
2.55
0.50 15.30
15cm thick shear wall
28.50
0.15
3.00 12.83
2 28.50
3.00 171.00
15cm thick suspended slab
12.00
12.55 150.6
ddn for manhole opening
0.60
0.6 0.36
150.24
150.24
0.15 22.54
0.90 15.14
1.20 - total
1.4 excavation for mat depth upto
150cm(d=1.5-1.2=0.3m)
0 8.50 MF-1
9.65
0.30 -
2 6.50 MF-2
2.50 9.95
0.30 9.75 10.45
-
Sheet