QA-ACT-PM-ITP-INT-GLZ-R0
0 First issue
QA-ACT-PM-ITP-INT-GLZ-R0 Page 1 of 6
Project (PROJECT NAME)
Inspection Verification
Submission / Inspection / ACT In
# Method Frequency Acceptance Criteria Record (register,
Test details ACT CO IP CL Charge
inspection, test)
1 DOCUMENTATION REVIEW
2 SAMPLE APPROVAL
Sample board /
Sample approval
In accordance to contract specs, Design
1-4 weeks form
Sample Submittals and material Submit to requirement, drawings, and approved
2a H H W before start PM/CM QA-ACT-PM-ISP--
approvals CM make
of works SAM-_____
To be procure from approved vendors Manufactures data
sheet
3 INSPECTION OF INCOMING MATERIALS.
QA-ACT-PM-ITP-INT-GLZ-R0 Page 2 of 6
Inspection Verification
Submission / Inspection / ACT In
Method Frequency Acceptance Criteria Record (register,
# Test details Charge
ACT CO IP CL inspection, test)
QA-ACT-PM-ITP-INT-GLZ-R0 Page 3 of 6
grooves to be made as per instructions of the
manufacturer of glazing compound.
Inspection Verification
Submission / Inspection / ACT In
Method Frequency Acceptance Criteria Record (register,
# Test details Charge
ACT CO IP CL inspection, test)
Rebates or grooves should be
Check for preparation of Rebates
sealed with an alkali resisting sealer and
5d and grooves in stone, concrete, Visual W H All works QE
allowed to dry before glazing. The compound
brick or other materials,
shall be metal-casement putty.
To be as per approved details as
5e Check on fixing of glazings Visual W H All works QE
Glazing with compound / glazing with bead
Sufficient compound should be applied to the
rebate so that, when the glass has been
pressed into the rebate, a bed of the
Check on glazing with compound Visual / compound (known as back putty) not less
5f W H All works QE
on rebates Mmnt than 1.5 mm thick will remain between the
glass and rebate; there shall be a surplus of
compound squeezed out above the rebate
which would be stripped at an angle
The glass should be pressed into the glazing
compounds previously placed in the groove. QA-ACT-PM-ISP-
Check on glazing with Compound The space between the glass and sides of the
5g Visual W H All works QE INT-GLZ-_____
into Grooves groove to be filled with the compound which
should then be stopped at an angle and not
undercut
Beads should be secured to the wooden frame
with either panel pins or screws and to metal
frames in the way provide a for in the-frame.
Check on securing of beads to the
5h Visual W H All works QE In securing wooden frames, an adequate
frame.
number of pins or screws for fixing the beads
should be used as to prevent flexing or
movement of beads.
Sufficient compound should be applied to the
rebate so that when the glass has been
Check on glazing with Beads along Visual / pressed into the rebate, a bed of compound
5i W H All works QE
with Compound Mmnt (known as back putty) not less than
1.5 mm thick will remain between the glass
and the rebate.
6 POST WORK INSPECTION
Non-Conformance
NCR and Inspection after
7 Refer to NCR Procedure in case of non compliance of tender/contract conditions. Report
Rectification of Defects
QA-ACT-PM-NCR
QA-ACT-PM-ITP-INT-GLZ-R0 Page 4 of 6
QA-ACT-PM-ITP-INT-GLZ-R0 Page 5 of 6
Project PROJECT NAME
INSPECTION RECORD
INSTALLATION
DOOR Inspection QA-ACT-PM-ISP-INT-
ITP Location
WINDOW No. GLZ-_____
Prepared
Applicable Drawing
by
Glazings
Item of work Spec: Ref: #
Type
Sign
# Description Result Date Contract
ACT
or
4 PRE WORKS INSPECTION
4b Check on materials
4c Check on openings
6a Cleaning
COMMENTS
CONTRACTOR ARCHETYPE
Date Sign Date Sign
QA-ACT-PM-ITP-INT-GLZ-R0 Page 6 of 6