Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 10

R.A. BILL NO.

UKT CONSTRUCTIONS
Project : UNDRI CITI CENTER ,UNDRI, PUNE.
Name of Contractor: M/s. Tejaswini Transport
RA Bill No: 2
Date : 4/3/2016
SUMMARY

Amount
Sr.No. Item No Description
Upto Last Bill This Bill Uptodate

1 Running Account Bill Total (Commercial Bldg) 2340058 2571847 4911905

2 Extra Work 0.00 0.00 0.00

3 TOTAL = (1+2) 2340058 2571847.00 4911905.00

4 Add Service Tax @ 14.5% 327608 372918 700525.94

5 TOTAL = (3+4). 2667666 2944765 5612431.00

6 Deductions
T.D.S 2% (3) 46801 51437 98238.10
Debit Amount 0.00 0.00 0.00

7 TOTAL OF DEDUCTIONS 46801 51437 0.00

8 NET AMOUNT (5-7) 2667666 2893328 5612431

(Rupees: Twenty Eight Lakh Ninety Three Thousand Three Hundred Twenty Eight Rupees Only)
UKT CONSTRUCTIONS
CONTRACTOR : M/s. Tejaswini Transport
ABSTRACT SHEET
PROJECT: UNDRI CITI CENTER (PHASE - II)
R.A.Bill No : 2 Date - 3/4/2016

Sr. No. Item Unit Rate Qty. Amount


Upto last This Upto date Upto last This Upto date
A. ITEM RATE WORK
1 EXCAVATION IN SOIL & MURUM. (WITHIN 4 KM) CUM. 65 0 777.00 777.00 0 50505 50505
900000
2 EXCAVATION IN SOIL & MURUM. (WITHIN 10KM) CUM. 100 0 0.00 0.00 0 0 0

3 EXCAVATION IN SOFT ROCK (WITHIN 4KM) CUM. 270 0 416.42 416.42 0 112434 112434

4 EXCAVATION IN SOFT ROCK (WITHIN 10KM) CUM. 320 0 0.00 0.00 0 0 0

5 EXCAVATION IN HARD ROCK (WITHIN 4KM) CUM. 400 0 6022.27 6022.27 0 2408908 2408908

6 EXCAVATION IN HARD ROCK (WITHIN 10KM) CUM. 450 0 0.00 0.00 0 0 0

7 FILLING & LEVELLING OF MURUM CUM. 60 0 0.00 0.00 0 0 0

B. SUPPLY WORK
1 SUPPLY OF J.C.B. HOUR 650 0 0.00 0.00 0 0 0

2 SUPPLY OF DUMPER DAY 3000 0 0.00 0.00 0 0 0

3 SUPPLY OF TRACTOR DAY 1300 0 0 0.00 0 0 0

4 SUPPLY OF POCLAIN - BUCKET HOUR 1400 0 0 0.00 0 0 0

5 SUPPLY OF POCLAIN - BREAKER HOUR 2000 0 0 0.00 0 0 0

Total 0 2571847 2571847


Project : UNDRI CITI CENTER

Contractor : M/s. Tejaswini Transport

MEASUREMENT SHEET

R.A.Bill No : 2
Sr. Item Unit No. L B
No.

A EXCAVATION IN SOIL & MURUM. (WITHIN 4 KM)


A.1 FOR R.M.C PLANT AREA CU.M 1 42.000 16.000
A.2 MAIN ENTRANCE GATE ROAD SIDE TO DR. PLOT SIDE RET. WALL CU.M 1 30.000 5.000

B EXCAVATION IN SOFT ROCK (WITHIN 4KM)


B.1 LOW. PARK AREA RAMP TO R.M.C PLANT AREA TO LIFT NO-2 CU.M 1 18.500 7.500
B.2 PART C - (Shop 28) Cu.m 1 15.500 11.000

C EXCAVATION IN HARD ROCK (WITHIN 4KM)


C.1 PART A - ( Shop 1 to 14) Cu.m 1 49.300 11.500
C.2 PART B - (Shop 14 to 27) Cu.m 1 46.130 11.500
C.3 PART C - (Shop 28) Cu.m 1 15.500 11.000
C.4 PART D - (Lower Park) Cu.m 1 1193.570
C.5 STAIRCASE (2) AREA - BASEMENT PARKING Cu.m 1 5.800 4.20
C.6 LIFT NO-1 Cu.m 1 4.800 4.50
C.7 LIFT NO-2 Cu.m 1 4.800 9.50
C.8 LIFT NO-3 Cu.m 1 4.800 5.20
Project : UNDRI CITI CENTER

Contractor : M/s. Tejaswini Transport

MEASUREMENT SHEET

R.A.Bill No : 2
Sr. Item Unit No. L B H
No.

A EXCAVATION IN SOIL & MURUM. (WITHIN 4 KM)


A.1 FOR R.M.C PLANT AREA CU.M 1 42.000 16.000 1.000
A.2 MAIN ENTRANCE GATE ROAD SIDE TO DR. PLOT SIDE RET. WALL CU.M 1 30.000 5.000 0.700

QTY
B EXCAVATION IN SOFT ROCK (WITHIN 4KM)
B.1 LOW. PARK AREA RAMP TO R.M.C PLANT AREA TO LIFT NO-2 CU.M 1 18.500 7.500 1.200
B.2 PART C - (Shop 28) Cu.m 1 15.500 11.000 1.466

QTY

C EXCAVATION IN HARD ROCK (WITHIN 4KM)


C.1 PART A - ( Shop 1 to 14) Cu.m 1 49.300 11.500 4.054
C.2 PART B - (Shop 14 to 27) Cu.m 1 46.130 11.500 3.572
C.3 PART C - (Shop 28) Cu.m 1 15.500 11.000 2.015
C.4 PART D - (Lower Park) Cu.m 1 1193.570 1.072
C.5 STAIRCASE (2) AREA - BASEMENT PARKING Cu.m 1 5.800 4.20 3.350
C.6 LIFT NO-1 Cu.m 1 4.800 4.50 1.35
C.7 LIFT NO-2 Cu.m 1 4.800 9.50 1.35
C.8 LIFT NO-3 Cu.m 1 4.800 5.20 1.35

QTY
LEVEL SHEET OF EXCAVATION OF UKT CONSTRUCTIONS (PHASE-II)

Sr. Item Location Excavation level Avg. Rock Excavation level Avg. Rock Ht. of
( Hard Excavation
( Hard rock
No. / Point rock top level) Top Bottom level) Bottom (Rock)
C EXCAVATION IN HARD ROCK (WITHIN 4KM)
C.1 PART A - ( Shop 1 to 14) 1 88.800 88.656 85.423 84.602 4.054
PART A - ( BESIDE DR. PLOT) 2 88.820 85.173
3 88.690 84.973
4 88.830 84.323
5 88.580 84.333
6 88.520 84.613
7 88.570 84.583
8 88.580 84.273
9 88.600 84.323
10 88.900 84.373
11 88.930 84.343
12 88.725 84.333
13 88.730 84.303
14 88.745 84.553
15 88.570 84.583
16 88.620 84.403
17 88.580 84.333
18 88.530 84.373
19 88.630 84.183
20 88.580 84.423
21 88.570 84.583
22 88.730 84.673
23 88.720 84.923
24 88.740 84.823
25 88.560 84.573
26 88.460 84.563
27 88.550 84.723
28 88.790 84.873
29 88.580 84.973
30 88.450 85.123

C.2 PART B - (Shop 14 to 27) 46 89.050 88.745 84.668 85.173 3.572


PART B - (BESIDE MAIN ROAD SIDE AREA) 47 88.960 84.963
48 88.880 84.923
49 88.980 85.223
50 88.910 85.323
62 89.100 85.043
63 89.030 85.123
64 88.930 85.123
65 88.810 85.123
66 88.920 85.603
67 88.815 85.523
68 88.640 85.273
79 88.325 85.223
80 88.565 85.203
81 88.750 85.213
82 88.545 85.193
83 88.500 85.183
84 88.435 85.178
Sr. Item Location Excavation level Avg. Rock Excavation level Avg. Rock Ht. of
( Hard Excavation
( Hard rock
No. / Point rock top level) Top Bottom level) Bottom (Rock)
85 88.615 85.173
93 88.625 85.263
94 89.055 85.153
95 88.435 85.163
96 88.440 85.153
97 88.730 85.143
98 88.575 85.178

C.3 PART C - (NEW WEIGH BRIDGE SIDE AREA)


96 86.893 86.933 84.578 84.918 2.015
97 86.918 84.918
98 86.968 84.968
99 86.963 84.963
104 86.978 84.978
105 86.878 84.878
106 86.928 84.928
107 86.923 84.923
108 86.938 84.938
109 86.943 84.943
110 86.928 84.928
111 86.948 84.948
113 86.933 84.933
114 86.948 84.948
115 86.928 84.928
117 86.938 84.938
118 86.918 84.918
119 86.928 84.928
120 86.943 84.943
121 86.933 84.933
122 86.923 84.923

C.4 PART D - (FRONT OF SITE OFFICE AREA) 31 88.720 88.668 87.606 87.596 1.07
32 88.660 87.566
33 88.970 87.626
34 89.010 87.616
35 89.030 87.826
36 88.830 87.726
37 88.550 87.626
38 88.570 87.476
39 88.690 87.536
40 88.500 87.566
41 88.720 87.571
42 88.720 87.531
43 88.950 87.641
51 88.640 87.736
52 88.570 87.701
53 88.820 87.616
54 88.960 87.631
55 88.760 87.646
56 88.720 87.526
57 88.500 87.531
58 88.700 87.546
59 88.900 87.541
Sr. Item Location Excavation level Avg. Rock Excavation level Avg. Rock Ht. of
( Hard Excavation
( Hard rock
No. / Point rock top level) Top Bottom level) Bottom (Rock)
60 88.890 87.551
61 88.860 87.751
62 89.100 87.536
63 89.030 87.516
69 88.435 87.486
70 88.425 87.616
71 88.765 87.631
72 88.720 87.651
73 88.390 87.641
74 88.385 87.676
75 88.675 87.626
76 88.695 87.576
77 88.640 87.556
78 88.665 87.536
85 88.615 87.536
86 88.640 87.531
87 88.590 87.561
88 88.600 87.626
89 88.715 87.576
90 88.310 87.536
91 88.055 87.631
92 88.420 87.576
99 88.280 87.536
100 88.710 87.526
101 89.010 87.576
102 88.400 87.676
103 88.555 87.726
104 88.790 87.476
112 88.260 87.586
116 88.610 87.576
LEVEL SHEET OF EXCAVATION OF UKT CONSTRUCTIONS (PHASE-II)

Sr. Item Location Excavation level Avg. Rock Excavation level Avg. Rock Ht. of
Excavation
( Soft Rock top ( Hard rock Top
No. / Point level) Top level) Bottom (Rock)
B EXCAVATION IN SOFT ROCK (WITHIN 4KM)
B.2 PART C - (NEW WEIGH BRIDGE SIDE AREA)
96 88.440 88.699 86.893 86.933 1.766
97 88.730 86.918
98 88.575 86.968
99 88.280 86.963
104 88.790 86.978
105 88.915 86.878
106 88.620 86.928
107 88.825 86.923
108 88.970 86.938
109 89.025 86.943
110 88.860 86.928
111 88.525 86.948
113 88.580 86.933
114 89.055 86.948
115 88.545 86.928
117 88.630 86.938
118 88.650 86.918
119 88.640 86.928
120 88.670 86.943
121 88.670 86.933
122 88.680 86.923
Project : UNDRI CITI CENTER

Contractor : M/s. Tejaswini Transport

SUB - ABSTRACT SHEET

Sr. Item Unit Rate R.A. BILL NO.1 R.A. BILL NO.2 R.A. BILL NO.3 TOTAL QTY. TOTAL AMT.

No. QTY. AMT. QTY. AMT. QTY. AMT.

A. ITEM RATE WORK


1 EXCAVATION IN SOIL & MURUM. (WITHIN 4 KM) CUM. 65 0 0 0 0 0.00

2 EXCAVATION IN SOIL & MURUM. (WITHIN 10KM) CUM. 100 0 0 0 0 0.00

3 EXCAVATION IN SOFT ROCK (WITHIN 4KM) CUM. 270 0 0 0 0 0.00

4 EXCAVATION IN SOFT ROCK (WITHIN 10KM) CUM. 320 0 0 0 0 0.00

5 EXCAVATION IN HARD ROCK (WITHIN 4KM) CUM. 450


0 0 0 0 0.00
6 EXCAVATION IN HARD ROCK (WITHIN 10KM) CUM. 400
0 0 0 0 0.00
7 FILLING & LEVELLING OF MURUM CUM. 60
0 0 0 0 0.00
B. SUPPLY WORK
1 SUPPLY OF J.C.B. HOUR 650 0 0 0 0 0.00

2 SUPPLY OF DUMPER DAY 3000 0 0 0 0 0.00

3 SUPPLY OF TRACTOR DAY 1300 0 0 0 0 0.00

4 SUPPLY OF POCLAIN - BUCKET HOUR 1400 0 0 0 0 0.00

5 SUPPLY OF POCLAIN - BREAKER HOUR 2000 0 0 0 0 0.00


Total

You might also like