Buffing of Exterior sq.m 984.99 984.99 Not Started Plastering of Exterior sq.m - - Not Started Buffing of Interior sq.m 1236.89 1236.89 Not Started Plastering of Interior sq.m - - Not Started Painting of Gate I-Beam ln.m 18.38 0.00 Finished Installation of Access Door @Gate lot 1.00 1.00 Not Started Painting of Office Flooring (Elastormeric Paint sq.m 23.63 23.63 In Progress Plumbing and Water Supply of CR lot 1.00 1.00 Finished Concreting of Driveway cu.m 5.79 5.79 Not Started Installation of Chicken Wire @Roof Monitor lot 1.00 1.00 Not Started Installation of End Face @Roof Monitor lot 1.00 1.00 Not Started Installation of Flashing Tape ln.m 8.38 8.38 Not Started Water Proofing of Walls sq.m 984.99 984.99 Not Started Painting of Downspout ln.m 122.00 122.00 Not Started Installation of Wall Flashing @Canopy ln.m 8.38 8.38 Not Started Electrical Works lot 1.00 1.00 Finished Tiling @ CR sq.m 4.00 4.00 Not Started Warehouse 2 Units Prev. Bal Current Bal. Remarks Buffing of Exterior sq.m 560.00 560.00 Not Started Plastering of Exterior sq.m - - In Progress Buffing of Interior sq.m 589.10 589.10 Not Started Plastering of Interior sq.m - - In Progress Painting of Gate I-Beam ln.m 12.00 0.00 Finished Installation of Access Door @Gate lot 1.00 1.00 Not Started Painting of Office Flooring (Elastormeric Paint sq.m 23.63 23.63 Not Started Plumbing and Water Supply of CR lot 1.00 1.00 Finished Concreting of Driveway cu.m 6.03 6.03 Finished Installation of Chicken Wire @Roof Monitor lot 1.00 1.00 Not Started Installation of End Face @Roof Monitor lot 1.00 1.00 Not Started Installation of Flashing Tape lot 1.00 1.00 Not Started Water Proofing of Walls sq.m 560.00 560.00 Not Started Installation of Downspout ln.m 90.00 90.00 Not Started Painting of Downspout ln.m 90.00 90.00 Not Started Installation of Wall Flashing @Canopy ln.m 8.38 8.38 Not Started Electrical Works lot 1.00 1.00 Not Started Tiling @ CR sq.m 4.00 4.00 Not Started Installation of Precast pcs 32.00 16.00 Finished FaBrication of Precast pcs 12.00 0.00 Finished Installation of C-Channel Bars ln.m 64.10 33.00 Finished Concreting and Installation of of Stiffiner Column ln.m 198.00 45.00 In Progress Office Installation lot 1.00 1.00 Not Started Installation of Gate lot 1.00 1.00 In Progress Warehouse 3 Units Prev. Bal Current Bal. Remarks Buffing of Exterior sq.m 717.87 717.87 Not Started Plastering of Exterior sq.m - - In Progress Buffing of Interior sq.m 970.59 970.59 Not Started Plastering of Interior sq.m - - In Progress Painting of Gate I-Beam ln.m 10.20 2.80 Finished Installation of Access Door @Gate lot 1.00 1.00 Not Started Painting of Office Flooring (Elastormeric Paint sq.m 54.00 54.00 Finished Plumbing and Water Supply of CR lot 1.00 1.00 Finished Concreting of Driveway cu.m 2.916 0.87 In Progress Installation of Chicken Wire @Roof Monitor lot 1.00 1.00 Not Started Installation of End Face @Roof Monitor lot 1.00 1.00 Not Started Installation of Flashing Tape ln.m 10.20 10.20 Not Started Water Proofing of Walls sq.m 717.87 717.87 Not Started Painting of Downspout ln.m 90.00 90.00 Not Started Installation of Wall Flashing @Canopy ln.m 8.38 8.38 Not Started Electrical Works lot 1.00 1.00 Finished Tiling @ CR sq.m 4.00 4.00 Not Started Installation of Precast pcs 0.00 0.00 Finished FaBrication of Precast pcs 0.00 0.00 Finished Linitel Beams ln.m 0.00 0.00 Finished Concreting and Installation of of Stiffiner Column ln.m 72.00 49.00 In Progress Office Installation sq.m 54.00 10.80 In Progress Installation of Gate I-Beam lot 1.00 0.00 Finished Installation of Gate lot 1.00 1.00 Not Started Driveway Units Prev. Bal Current Bal. Remarks Container Van Installation lot 1.00 1.00 Finished Container Van, Masonry,Sanitary and Water Supply lot 1.00 1.00 In Progress (Masonry Works Done) Septic Tank Manhole Concreting pcs 3.00 0.00 Finished Catch Basin Conver Concreting pcs 38.00 38.00 Not Started Plumbing and Sanitary Lines lot 1.00 1.00 Not Started Driveway Preparation and Concreting sq.m 850.47 425.24 In Progress (Subgrade Preparation) Culvert Laying pcs 20.00 0.00 Finished Catch Basin Installation & Fabrication pcs 13.00 13.00 Not Started Sidewalk, Curb nd Gutter ln.m 151.07 90.00 Not Started Street Light Solar pcs - - Not Started Installation, Fabrication of Entrance Gate lot 1.00 1.00 Not Started Installation and Fabrication of Guard House lot 1.00 1.00 Not Started