Y O UR P A R T N ER I N F OOT WEA R T EC H N OL OGY

SS26 OUTSOLE AUTOMATION


INTRODUCTION FOR VENDORS

PRODUCTION AUTOMATION
2023 12 27
BRIEF (PRODUCT INTRO.)

SPINE STUDS

BASE ILUSTRATION ONLY (SS18 Reff.)

Actual Pattern is still Confidential


CONCEPT / SCOPE
SS26 PREDATOR TOP SHOE
FULL AUTOMATION CONCEPT (BASE & SPINE)

ITEMS 1. STUDS 2. BASE 3. SPINE NOTE


BASE SPINE
Take-out, Pick Up, PickUp,
Sorting, Inserting, Inserting,
Process Condensing Take-Out, Take-out,
Placing Cutting,
Placing.
(1) Robot (1) Robot (1) Robot
(2) EoAT, (2) EoAT, (2) EoAT,
Tool/Device/Equipment (3) Condenser (3) JIG STUDS (3) JIG (Cutting)
(Automation) Box (4) JIG BASE (4) SI
(5) System (Conveyor)
Integration
Master Batch STUDS, & BASE, &
Material Master Batch Master Batch

Cell 1 Cell 2 & 3 (Integrated)

Cell Volume 4 4 4

CELL ITEMS IN CHARGE


Ilustration
1. STUDS : Framas Team
2. BASE & 3. SPINE : Framas Team & Vendors
INDONESIA Cell Layout P0/P1

4
INDONESIA Concept P0/P1
No Equipment No Scope Picture
1 Stud Transfer 1 Worker Insert Stud
Table to Jig
BASE SPINE

1.1 Robot pick up


Studs, put runner
to container
2 5-Axis Robot + 2 Robot Insert Studs,
EoAT Base pick up Base and
runner

3 Base Transfer 3 Robot put base to


Table Transfer Table,
2 Table Flip base and
4 Move to other side

4.1 Robot pick up Base


and put FG to
1.1 conveyor
3 3.1

4 5-Axis Robot + 4 Robot Pick up FG


EoAT Spine and insert Base

1
5

5 Prodution Table 5 Worker QC &


Packing FG
5
TIMELINE
We are Here

MODEL CELL PHASE @ 1 (6 Mo.) DUPLICATION CELL PHASE @ 3 (12 Mo.)

Dec-Jan Dec-Jan
2023-2024 2024-2025

Apr 24 June 24 Sep 24 Apr 25 June 25

1 Roboter 6 Roboter Purchase & Delivery


Mass
Purchase & Delivery ( 8 Months)
Concepting Production
(3 Months) 3 Integration Conv.
& Inquiry
(1 month) Purchase & Delivery
1 Integration Conv.
(5 Months)*
Purchase & Delivery
(4 Months)* 6 EoAT & 9 JIG x 20 Sizes**
Purchase & Delivery
2 EoAT & 3 JIG
Purchase & Delivery (6 Months)
(3 Months)
Latest Duplication
Kick-off
Note:
* Confirmed further by vendor
** Confirmed further by Managers Up

Milestone :
June 2024 : Sample Cell (1) Run
May – June 2025 : Full Cells (4) Mass Production Start
ACTION PLAN
1. fIN Team: Duration/DD File
1. Brief Intro 1. W4, Dec’23 Current
2. Roboter Requirements 2. W4, Dec’23 RBT Requirement

3. Process Design (Flow Process, I/O Qty. , etc) 3. W4, Dec’23 Process Design

4. 3D Layout Rough Design 4. W4, Dec’23


5. … 5. …

2. Roboter Vendor Team:


1. …
1. Quotation (Spec, Price, Lead Time, Warrant, Payment Term, Volume Discount, etc.)
2. …
2. …
3. …
3. …

3. Sistem Integration (SI) Vendor Team:


1. Quotation (Spec, Price, Lead Time, Warrant, Payment Term, Volume Discount, etc.) … 1. …
2. … 2. …
3. … 3. …
THANK YOU