DBM-BC Rfi

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

Submission Inspection Location Spot /

S No. RFI Description of Activity From CH: To CH: Length Side


Service Road/MCWItem Status
Date Date Portion
784 KHPL/TK/NH-66/HWY/760 1-Sep-2023 2-Sep-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 379+500 379+840 340 LHS S/R Prime Coat Work Done

785 KHPL/TK/NH-66/HWY/761 1-Sep-2023 2-Sep-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 379+550 379+860 310 RHS S/R Prime Coat Work Done

786 KHPL/TK/NH-66/HWY/762 1-Sep-2023 2-Sep-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 379+180 379+410 230 RHS S/R Prime Coat Not Done
Trail Patch
800 KHPL/TK/NH-66/HWY/776 7-Oct-2023 8-Oct-2023 Trail Patch of Tack coat & BC (Service Road) 379+550 379+600 50 RHS S/R Work Done
BC
802 KHPL/TK/NH-66/HWY/778 13-Oct-2023 13-Oct-2023 Spraying of tack coat, laying & Level Checking of BC (service Road) 379+550 379+850 300 RHS S/R BC Spot RFI Work Done

803 KHPL/TK/NH-66/HWY/779 13-Oct-2023 13-Oct-2023 Spraying of tack coat, laying & Level Checking of BC (service Road) 379+500 379+830 330 LHS S/R BC Spot RFI Work Done

804 KHPL/TK/NH-66/HWY/780 13-Oct-2023 13-Oct-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 377+150 377+420 270 LHS S/R Prime Coat Spot RFI Work Done

805 KHPL/TK/NH-66/HWY/781 13-Oct-2023 13-Oct-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 377+150 377+460 310 RHS S/R Prime Coat Spot RFI Work Done

806 KHPL/TK/NH-66/HWY/782 13-Oct-2023 14-Oct-2023 Spraying of tack coat, laying & level checking of BC (service Road) 377+150 377+420 270 LHS S/R BC Not Done

807 KHPL/TK/NH-66/HWY/783 13-Oct-2023 14-Oct-2023 Spraying of tack coat, laying & level checking of BC (service Road) 377+150 377+460 310 RHS S/R BC Not Done

823 KHPL/TK/NH-66/HWY/799 14-Oct-2023 15-Oct-2023 Spraying of Prime Coat over WMM Top Layer (MCW) 377+150 377+440 290 LHS MCW Prime Coat Work Done

824 KHPL/TK/NH-66/HWY/800 14-Oct-2023 15-Oct-2023 Spraying of Prime Coat over WMM Top Layer (MCW) 377+150 377+440 290 RHS MCW Prime Coat Work Done
Trail Patch
839 KHPL/TK/NH-66/HWY/815 18-Oct-2023 19-Oct-2023 Trail Patch of Tack coat & DBM (MCW) 377+150 377+200 50 RHS MCW Work Done
DBM
840 KHPL/TK/NH-66/HWY/816 18-Oct-2023 19-Oct-2023 Spraying of tack coat, laying & level checking of DBM (MCW) 377+163 377+420 257 LHS MCW DBM Work Done

841 KHPL/TK/NH-66/HWY/817 18-Oct-2023 19-Oct-2023 Spraying of tack coat, laying & level checking of DBM (MCW) 377+165 377+420 255 RHS MCW DBM Work Done

846 KHPL/TK/NH-66/HWY/822 19-Oct-2023 20-Oct-2023 Spraying of Prime Coat over WMM Top Layer (MCW) 370+500 370+730 230 LHS MCW Prime Coat Work Done

850 KHPL/TK/NH-66/HWY/826 21-Oct-2023 21-Oct-2023 Spraying of tack coat, laying & level checking of DBM (MCW) 370+500 370+720 220 LHS MCW DBM Spot RFI Work Done

852 KHPL/TK/NH-66/HWY/828 21-Oct-2023 22-Oct-2023 Spraying of tack coat, laying & level checking of BC (service Road) 377+165 377+400 235 LHS S/R BC Work Done

853 KHPL/TK/NH-66/HWY/829 21-Oct-2023 22-Oct-2023 Spraying of tack coat, laying & level checking of BC (service Road) 377+160 377+210 50 RHS S/R BC Work Done

896 KHPL/TK/NH-66/HWY/872 7-Nov-2023 7-Nov-2023 Spraying of tack coat, laying & level checking of BC (service Road) 377+210 377+460 250 RHS S/R BC Spot Work Done

909 KHPL/TK/NH-66/HWY/885 8-Nov-2023 9-Nov-2023 Spraying of Prime Coat over WMM Top Layer (MCW) 370+500 370+710 210 RHS MCW Prime Coat Work Done

920 KHPL/TK/NH-66/HWY/896 12-Nov-2023 13-Nov-2023 Spraying of tack coat, laying & level checking of DBM (MCW) 370+500 370+710 210 RHS MCW DBM Work Done

991 KHPL/TK/NH-66/HWY/967 19-Nov-2023 19-Nov-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 370+500 370+720 220 LHS S/R Prime Coat Spot Work Done

992 KHPL/TK/NH-66/HWY/968 19-Nov-2023 19-Nov-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 370+550 370+690 140 RHS S/R Prime Coat Spot Work Done

994 KHPL/TK/NH-66/HWY/970 19-Nov-2023 20-Nov-2023 Spraying of tack coat, laying & level checking of BC (service Road) 370+500 370+720 220 LHS S/R BC Work Done

995 KHPL/TK/NH-66/HWY/971 19-Nov-2023 20-Nov-2023 Spraying of tack coat, laying & level checking of BC (service Road) 370+550 370+690 140 RHS S/R BC Work Done

1010 KHPL/TK/NH-66/HWY/986 22-Nov-2023 23-Nov-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 393+850 393+990 140 LHS S/R Prime Coat Work Done

1015 KHPL/TK/NH-66/HWY/991 24-Nov-2023 25-Nov-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 370+250 370+430 180 LHS S/R Prime Coat Work Done

1016 KHPL/TK/NH-66/HWY/992 24-Nov-2023 25-Nov-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 370+080 370+190 110 LHS S/R Prime Coat Work Done

1019 KHPL/TK/NH-66/HWY/995 25-Nov-2023 25-Nov-2023 Spraying of tack coat, laying & level checking of BC (service Road) 393+850 393+990 140 LHS S/R BC Spot Work Done
Submission Inspection Location Spot /
S No. RFI Description of Activity From CH: To CH: Length Side
Service Road/MCWItem Status
Date Date Portion
1034 KHPL/TK/NH-66/HWY/1010 27-Nov-2023 28-Nov-2023 Spraying of tack coat, laying & level checking of BC (service Road) 370+250 370+430 180 LHS S/R BC Work Done

1035 KHPL/TK/NH-66/HWY/1011 27-Nov-2023 28-Nov-2023 Spraying of tack coat, laying & level checking of BC (service Road) 370+100 370+190 90 LHS S/R BC Work Done

1121 KHPL/TK/NH-66/HWY/1097 10-Dec-2023 11-Dec-2023 Spraying of Prime Coat over WMM Top Layer (MCW) 370+410 370+500 90 LHS MCW Prime Coat Work Done

1127 KHPL/TK/NH-66/HWY/1103 11-Dec-2023 12-Dec-2023 Spraying of tack coat, laying & level checking of DBM (MCW) 370+415 370+500 85 LHS MCW DBM Not Done

1131 KHPL/TK/NH-66/HWY/1107 12-Dec-2023 13-Dec-2023 Spraying of tack coat, laying & level checking of DBM (MCW) 370+415 370+500 85 LHS MCW DBM Work Done

1172 KHPL/TK/NH-66/HWY/1148 19-Dec-2023 19-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 369+700 370+000 300 LHS S/R Prime Coat Spot Work Done

1175 KHPL/TK/NH-66/HWY/1151 19-Dec-2023 20-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 369+710 369+970 260 LHS S/R BC Work Done

1188 KHPL/TK/NH-66/HWY/1164 21-Dec-2023 22-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 369+660 369+950 290 RHS S/R Prime Coat Work Done

1189 KHPL/TK/NH-66/HWY/1165 21-Dec-2023 22-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 370+140 370+350 210 RHS S/R Prime Coat Work Done

1197 KHPL/TK/NH-66/HWY/1173 23-Dec-2023 24-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 369+660 369+950 290 RHS S/R BC Work Done

1198 KHPL/TK/NH-66/HWY/1174 23-Dec-2023 24-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 370+140 370+350 210 RHS S/R BC Work Done

1199 KHPL/TK/NH-66/HWY/1175 23-Dec-2023 24-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 370+190 370+250 60 LHS S/R Prime Coat Work Done

1210 KHPL/TK/NH-66/HWY/1186 25-Dec-2023 26-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 369+970 370+000 30 LHS S/R BC Work Done

1211 KHPL/TK/NH-66/HWY/1187 25-Dec-2023 26-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 370+190 370+250 60 LHS S/R BC Work Done

1212 KHPL/TK/NH-66/HWY/1188 25-Dec-2023 26-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 370+080 370+100 20 LHS S/R BC Work Done

1215 KHPL/TK/NH-66/HWY/1191 25-Dec-2023 26-Dec-2023 Spraying of Prime Coat over WMM Top Layer (MCW) 375+230 375+400 170 RHS MCW Prime Coat Work Done

1244 KHPL/TK/NH-66/HWY/1220 26-Dec-2023 27-Dec-2023 Spraying of tack coat, laying & level checking of DBM (MCW) 375+230 375+400 170 RHS MCW DBM Work Done

1264 KHPL/TK/NH-66/HWY/1240 26-Dec-2023 27-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 370+430 370+500 70 LHS S/R Prime Coat Dummy Not Done

1265 KHPL/TK/NH-66/HWY/1241 26-Dec-2023 27-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 379+350 379+390 40 RHS S/R Prime Coat Dummy Not Done

1298 KHPL/TK/NH-66/HWY/1274 27-Dec-2023 28-Dec-2023 Spraying of Prime Coat over WMM Top Layer (MCW) 375+160 375+230 70 RHS MCW Prime Coat Dummy Work Done

1309 KHPL/TK/NH-66/HWY/1285 27-Dec-2023 28-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 370+430 370+500 70 LHS S/R BC Dummy Not Done

1312 KHPL/TK/NH-66/HWY/1288 27-Dec-2023 28-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 379+170 379+500 330 LHS S/R Prime Coat Dummy Not Done

1317 KHPL/TK/NH-66/HWY/1293 27-Dec-2023 28-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 379+180 379+350 170 RHS S/R Prime Coat Dummy Not Done

1321 KHPL/TK/NH-66/HWY/1297 27-Dec-2023 28-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 392+020 392+160 140 RHS S/R Prime Coat Dummy Work Done

1324 KHPL/TK/NH-66/HWY/1300 27-Dec-2023 28-Dec-2023 Spraying of Prime Coat over WMM Top Layer (MCW) 375+160 375+230 70 RHS MCW Prime Coat Dummy Repeated

1330 KHPL/TK/NH-66/HWY/1306 27-Dec-2023 28-Dec-2023 Spraying of Prime Coat over WMM Top Layer (MCW) 379+970 380+080 110 RHS MCW Prime Coat Dummy Work Done

1352 KHPL/TK/NH-66/HWY/1328 28-Dec-2023 29-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 370+430 370+500 70 LHS S/R BC Dummy Repeated

1353 KHPL/TK/NH-66/HWY/1329 28-Dec-2023 29-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 379+350 379+390 40 RHS S/R BC Dummy Not Done

1359 KHPL/TK/NH-66/HWY/1335 28-Dec-2023 29-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 375+110 375+420 310 RHS S/R Prime Coat Dummy Not Done

1363 KHPL/TK/NH-66/HWY/1339 28-Dec-2023 29-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 379+180 379+350 170 RHS S/R BC Dummy Not Done
Submission Inspection Location Spot /
S No. RFI Description of Activity From CH: To CH: Length Side
Service Road/MCWItem Status
Date Date Portion
1364 KHPL/TK/NH-66/HWY/1340 28-Dec-2023 29-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 392+020 392+160 140 RHS S/R BC Dummy Work Done

1365 KHPL/TK/NH-66/HWY/1341 28-Dec-2023 29-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 390+370 390+510 140 RHS S/R Prime Coat Dummy Work Done

1366 KHPL/TK/NH-66/HWY/1342 28-Dec-2023 29-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 390+520 390+640 120 RHS S/R Prime Coat Dummy Work Done

1370 KHPL/TK/NH-66/HWY/1346 28-Dec-2023 29-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 393+290 393+380 90 RHS S/R Prime Coat Dummy Work Done

1374 KHPL/TK/NH-66/HWY/1350 28-Dec-2023 29-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 379+030 379+150 120 LHS S/R Prime Coat Dummy Not Done

1375 KHPL/TK/NH-66/HWY/1351 28-Dec-2023 29-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 379+170 379+500 330 LHS S/R BC Dummy Not Done

1386 KHPL/TK/NH-66/HWY/1362 28-Dec-2023 29-Dec-2023 Spraying of tack coat, laying & level checking of DBM (MCW) 375+160 375+230 70 RHS MCW DBM Dummy Work Done

1387 KHPL/TK/NH-66/HWY/1363 28-Dec-2023 29-Dec-2023 Spraying of tack coat, laying & level checking of DBM (MCW) 379+970 380+080 110 RHS MCW DBM Dummy Work Done

1406 KHPL/TK/NH-66/HWY/1382 29-Dec-2023 30-Dec-2023 Spraying of Prime Coat over WMM Top Layer (MCW) 380+130 380+240 110 LHS MCW Prime Coat Dummy Work Done

1416 KHPL/TK/NH-66/HWY/1392 29-Dec-2023 30-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 369+950 369+990 40 RHS S/R Prime Coat Dummy Work Done

1419 KHPL/TK/NH-66/HWY/1395 29-Dec-2023 30-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 375+110 375+420 310 RHS S/R BC Dummy Not Done

1420 KHPL/TK/NH-66/HWY/1396 29-Dec-2023 30-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 375+420 375+600 180 RHS S/R Prime Coat Dummy Not Done

1423 KHPL/TK/NH-66/HWY/1399 29-Dec-2023 30-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 379+030 379+140 110 LHS S/R BC Dummy Not Done

1425 KHPL/TK/NH-66/HWY/1401 29-Dec-2023 30-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 390+370 390+510 140 RHS S/R BC Dummy Work Done

1426 KHPL/TK/NH-66/HWY/1402 29-Dec-2023 30-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 390+520 390+640 120 RHS S/R BC Dummy Work Done

1427 KHPL/TK/NH-66/HWY/1403 29-Dec-2023 30-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 390+710 390+760 50 RHS S/R Prime Coat Dummy Work Done

1428 KHPL/TK/NH-66/HWY/1404 29-Dec-2023 30-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 390+770 390+850 80 RHS S/R Prime Coat Dummy Work Done

1430 KHPL/TK/NH-66/HWY/1406 29-Dec-2023 30-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 392+830 392+940 110 RHS S/R Prime Coat Dummy Work Done

1431 KHPL/TK/NH-66/HWY/1407 29-Dec-2023 30-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 393+290 393+380 90 RHS S/R BC Dummy Work Done

1445 KHPL/TK/NH-66/HWY/1421 29-Dec-2023 30-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 369+950 369+990 40 RHS S/R Prime Coat Repeated

1448 KHPL/TK/NH-66/HWY/1424 29-Dec-2023 30-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 375+110 375+420 310 RHS S/R BC Repeated

1449 KHPL/TK/NH-66/HWY/1425 29-Dec-2023 30-Dec-2023 Spraying of Prime Coat over WMM Top Layer (Service Road) 375+420 375+600 180 RHS S/R Prime Coat Repeated

1452 KHPL/TK/NH-66/HWY/1428 29-Dec-2023 30-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 379+030 379+140 110 LHS S/R BC Repeated

1471 KHPL/TK/NH-66/HWY/1447 30-Dec-2023 31-Dec-2023 Spraying of tack coat, laying & level checking of DBM (MCW) 380+130 380+240 110 LHS MCW DBM Work Done

1476 KHPL/TK/NH-66/HWY/1452 30-Dec-2023 31-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 369+950 369+990 40 RHS S/R BC Dummy Work Done

1478 KHPL/TK/NH-66/HWY/1454 30-Dec-2023 31-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 375+420 375+600 180 RHS S/R BC Dummy Not Done

1479 KHPL/TK/NH-66/HWY/1455 30-Dec-2023 31-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 390+710 390+760 50 RHS S/R BC Dummy Work Done

1480 KHPL/TK/NH-66/HWY/1456 30-Dec-2023 31-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 390+770 390+850 80 RHS S/R BC Dummy Work Done

1481 KHPL/TK/NH-66/HWY/1457 30-Dec-2023 31-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 392+830 392+940 110 RHS S/R BC Dummy Work Done

1491 KHPL/TK/NH-66/HWY/1467 30-Dec-2023 31-Dec-2023 Spraying of tack coat, laying & level checking of BC (service Road) 369+950 369+990 40 RHS S/R BC Repeated
Submission Inspection Location Spot /
S No. RFI Description of Activity From CH: To CH: Length Side
Service Road/MCWItem Status
Date Date Portion
1511 KHPL/TK/NH-66/HWY/1487 3-Jan-2024 4-Jan-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 369+670 369+780 110 RHS MCW Prime Coat Work Done

1512 KHPL/TK/NH-66/HWY/1488 3-Jan-2024 4-Jan-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 369+850 369+990 140 LHS MCW Prime Coat Not Done

1519 KHPL/TK/NH-66/HWY/1495 4-Jan-2024 5-Jan-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 369+670 369+780 110 RHS MCW DBM Work Done

1520 KHPL/TK/NH-66/HWY/1496 4-Jan-2024 5-Jan-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 369+850 369+990 140 LHS MCW DBM Not Done

1600 KHPL/TK/NH-66/HWY/1576 13-Jan-2024 14-Jan-2024 Spraying of Prime Coat over WMM Top Layer (Service Road) 379+100 379+550 450 RHS SR Prime Coat Dummy Work Done

1603 KHPL/TK/NH-66/HWY/1579 13-Jan-2024 14-Jan-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 375+570 375+660 90 LHS MCW Prime Coat Work Done

1606 KHPL/TK/NH-66/HWY/1582 14-Jan-2024 15-Jan-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 375+570 375+660 90 LHS MCW DBM Work Done

1633 KHPL/TK/NH-66/HWY/1609 16-Jan-2024 17-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 379+100 379+550 450 RHS SR BC Dummy Work Done

1637 KHPL/TK/NH-66/HWY/1613 17-Jan-2024 18-Jan-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 379+170 379+400 230 RHS MCW Prime Coat Work Done

1646 KHPL/TK/NH-66/HWY/1622 20-Jan-2024 21-Jan-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 379+200 379+390 190 RHS MCW DBM Work Done

1650 KHPL/TK/NH-66/HWY/1626 20-Jan-2024 21-Jan-2024 Spraying of Prime Coat over WMM Top Layer (Service Road) 370+000 370+080 80 LHS SR Prime Coat Dummy Work Done

1665 KHPL/TK/NH-66/HWY/1641 22-Jan-2024 23-Jan-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 370+000 370+410 410 LHS MCW Prime Coat Work Done

1672 KHPL/TK/NH-66/HWY/1648 23-Jan-2024 24-Jan-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 370+000 370+410 410 LHS MCW DBM Work Done

1687 KHPL/TK/NH-66/HWY/1663 24-Jan-2024 25-Jan-2024 Spraying of Prime Coat over WMM Top Layer (Service Road) 375+110 375+750 640 RHS SR Prime Coat Dummy Work Done

1688 KHPL/TK/NH-66/HWY/1664 24-Jan-2024 25-Jan-2024 Spraying of Prime Coat over WMM Top Layer (Service Road) 370+430 370+500 70 LHS S/R Prime Coat Dummy Work Done

1689 KHPL/TK/NH-66/HWY/1665 24-Jan-2024 25-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 370+000 370+080 80 LHS S/R BC Dummy Work Done

1690 KHPL/TK/NH-66/HWY/1666 24-Jan-2024 25-Jan-2024 Spraying of Prime Coat over WMM Top Layer (Service Road) 370+060 370+140 80 RHS S/R Prime Coat Dummy Work Done

1703 KHPL/TK/NH-66/HWY/1679 24-Jan-2024 25-Jan-2024 Spraying of Prime Coat over WMM Top Layer (Service Road) 379+030 379+500 470 LHS S/R Prime Coat Dummy Work Done

1715 KHPL/TK/NH-66/HWY/1691 24-Jan-2024 25-Jan-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 379+170 379+400 230 RHS MCW Prime Coat Repeated

1726 KHPL/TK/NH-66/HWY/1702 25-Jan-2024 26-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 375+110 375+430 320 RHS S/R BC Dummy Work Done

1727 KHPL/TK/NH-66/HWY/1703 25-Jan-2024 26-Jan-2024 Spraying of Prime Coat over WMM Top Layer (Service Road) 375+580 375+800 220 LHS SR Prime Coat Dummy Work Done

1728 KHPL/TK/NH-66/HWY/1704 25-Jan-2024 26-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 370+430 370+500 70 LHS S/R BC Dummy Work Done

1729 KHPL/TK/NH-66/HWY/1705 25-Jan-2024 26-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 379+030 379+500 470 LHS S/R Prime Coat Dummy Work Done

1760 KHPL/TK/NH-66/HWY/1736 25-Jan-2024 26-Jan-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 379+170 379+400 230 RHS MCW Prime Coat Repeated

1765 KHPL/TK/NH-66/HWY/1741 26-Jan-2024 27-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 375+430 375+750 320 RHS S/R BC Dummy Work Done

1766 KHPL/TK/NH-66/HWY/1742 26-Jan-2024 27-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 370+060 370+140 80 RHS S/R BC Dummy Work Done

1796 KHPL/TK/NH-66/HWY/1772 27-Jan-2024 28-Jan-2024 Spraying of Prime Coat over WMM Top Layer (Service Road) 380+060 380+240 180 LHS S/R Prime Coat Dummy Work Done

1811 KHPL/TK/NH-66/HWY/1787 28-Jan-2024 29-Jan-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 372+060 372+260 200 RHS MCW Prime Coat Dummy Work Done

1812 KHPL/TK/NH-66/HWY/1788 28-Jan-2024 29-Jan-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 372+060 372+260 200 LHS MCW Prime Coat Dummy Work Done

1815 KHPL/TK/NH-66/HWY/1791 28-Jan-2024 29-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 375+580 375+800 220 LHS S/R BC Dummy Work Done
Submission Inspection Location Spot /
S No. RFI Description of Activity From CH: To CH: Length Side
Service Road/MCWItem Status
Date Date Portion
1824 KHPL/TK/NH-66/HWY/1800 29-Jan-2024 30-Jan-2024 Spraying of Prime Coat over WMM Top Layer (service Road) 374+330 374+530 200 LHS S/R Prime Coat Work Done

1829 KHPL/TK/NH-66/HWY/1804 29-Jan-2024 30-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 380+060 380+240 180 LHS S/R BC Dummy Work Done

1830 KHPL/TK/NH-66/HWY/1805 29-Jan-2024 30-Jan-2024 Spraying of Prime Coat over WMM Top Layer (service Road) 373+500 373+750 250 RHS S/R Prime Coat Dummy Work Done

1831 KHPL/TK/NH-66/HWY/1806 29-Jan-2024 30-Jan-2024 Spraying of Prime Coat over WMM Top Layer (service Road) 373+380 373+540 160 LHS S/R Prime Coat Dummy Work Done

1837 KHPL/TK/NH-66/HWY/1812 30-Jan-2024 31-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 373+500 373+750 250 RHS S/R BC Dummy Work Done

1838 KHPL/TK/NH-66/HWY/1813 30-Jan-2024 31-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 373+380 373+540 160 LHS S/R BC Dummy Work Done

1839 KHPL/TK/NH-66/HWY/1814 30-Jan-2024 31-Jan-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 372+060 372+260 200 RHS MCW DBM Dummy Work Done

1840 KHPL/TK/NH-66/HWY/1815 30-Jan-2024 31-Jan-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 372+060 372+260 200 LHS MCW DBM Dummy Work Done

1845 KHPL/TK/NH-66/HWY/1820 30-Jan-2024 31-Jan-2024 Spraying of tack coat, laying & level checking of BC (service Road) 374+330 374+530 200 LHS S/R BC Work Done

1935 KHPL/TK/NH-66/HWY/1909 7-Feb-2024 8-Feb-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 371+980 372+060 80 RHS MCW Prime Coat Work Done

1941 KHPL/TK/NH-66/HWY/1915 8-Feb-2024 9-Feb-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 375+400 375+550 150 RHS MCW Prime Coat Work Done

1942 KHPL/TK/NH-66/HWY/1916 8-Feb-2024 9-Feb-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 371+980 372+060 80 RHS MCW DBM Work Done

1952 KHPL/TK/NH-66/HWY/1926 9-Feb-2024 10-Feb-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 375+400 375+550 150 RHS MCW DBM Work Done

1976 KHPL/TK/NH-66/HWY/1950 11-Feb-2024 12-Feb-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 371+970 372+060 90 LHS MCW Prime Coat Work Done

1977 KHPL/TK/NH-66/HWY/1951 11-Feb-2024 12-Feb-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 375+660 375+770 110 LHS MCW Prime Coat Work Done

1989 KHPL/TK/NH-66/HWY/1963 12-Feb-2024 13-Feb-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 375+660 375+770 110 LHS MCW DBM Work Done

1996 KHPL/TK/NH-66/HWY/1970 13-Feb-2024 14-Feb-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 371+970 372+060 90 LHS MCW DBM Work Done

2068 KHPL/TK/NH-66/HWY/2042 20-Feb-2024 21-Feb-2024 Spraying of Prime Coat over WMM Top Layer (SR) 376+985 377+130 145 RHS S/R Prime Coat Work Done

2071 KHPL/TK/NH-66/HWY/2045 21-Feb-2024 22-Feb-2024 Spraying of tack coat, laying & level checking of BC (service Road) 376+985 377+100 115 RHS S/R BC Work Done

2116 KHPL/TK/NH-66/HWY/2090 23-Feb-2024 24-Feb-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 369+860 369+990 130 RHS MCW Prime Coat Work Done

2117 KHPL/TK/NH-66/HWY/2091 23-Feb-2024 24-Feb-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 369+860 369+990 130 LHS MCW Prime Coat Work Done

2118 KHPL/TK/NH-66/HWY/2092 23-Feb-2024 24-Feb-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 369+700 369+780 80 RHS MCW Prime Coat Work Done

2119 KHPL/TK/NH-66/HWY/2093 23-Feb-2024 24-Feb-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 369+700 369+780 80 LHS MCW Prime Coat Work Done

2145 KHPL/TK/NH-66/HWY/2119 25-Feb-2024 26-Feb-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 369+870 369+990 120 LHS MCW DBM Work Done

2146 KHPL/TK/NH-66/HWY/2120 25-Feb-2024 26-Feb-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 369+870 369+990 120 RHS MCW DBM Work Done

2147 KHPL/TK/NH-66/HWY/2121 25-Feb-2024 26-Feb-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 369+700 369+780 80 LHS MCW DBM Work Done

2148 KHPL/TK/NH-66/HWY/2122 25-Feb-2024 26-Feb-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 369+700 369+780 80 RHS MCW DBM Work Done

2186 KHPL/TK/NH-66/HWY/2160 26-Feb-2024 27-Feb-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 370+180 370+350 170 RHS MCW Prime Coat Work Done

2187 KHPL/TK/NH-66/HWY/2161 26-Feb-2024 27-Feb-2024 Spraying of Prime Coat over WMM Top Layer (SR) 369+120 369+300 180 LHS SR Prime Coat Work Done

2188 KHPL/TK/NH-66/HWY/2162 26-Feb-2024 27-Feb-2024 Spraying of Prime Coat over WMM Top Layer (SR) 369+120 369+290 170 RHS SR Prime Coat Work Done
Submission Inspection Location Spot /
S No. RFI Description of Activity From CH: To CH: Length Side
Service Road/MCWItem Status
Date Date Portion
2218 KHPL/TK/NH-66/HWY/2192 28-Feb-2024 29-Feb-2024 Spraying of Prime Coat over WMM Top Layer (SR) 371+960 372+250 290 RHS SR Prime Coat Work Done

2220 KHPL/TK/NH-66/HWY/2194 28-Feb-2024 29-Feb-2024 Spraying of tack coat, laying & level checking of BC (service Road) 369+120 369+270 150 RHS S/R BC Work Done

2221 KHPL/TK/NH-66/HWY/2195 28-Feb-2024 29-Feb-2024 Spraying of tack coat, laying & level checking of BC (service Road) 369+120 369+300 180 LHS S/R BC Work Done

2222 KHPL/TK/NH-66/HWY/2196 28-Feb-2024 29-Feb-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 370+190 370+340 150 RHS MCW DBM Work Done

2225 KHPL/TK/NH-66/HWY/2199 28-Feb-2024 29-Feb-2024 Spraying of Prime Coat over WMM Top Layer (SR) 371+960 372+250 290 LHS SR Prime Coat Work Done

2231 KHPL/TK/NH-66/HWY/2205 29-Feb-2024 1-Mar-2024 Spraying of tack coat, laying & level checking of BC (service Road) 371+960 372+250 290 RHS S/R BC to be shift Work Done

2232 KHPL/TK/NH-66/HWY/2206 29-Feb-2024 1-Mar-2024 Spraying of tack coat, laying & level checking of BC (service Road) 371+960 372+240 280 LHS S/R BC to be shift Work Done

2235 KHPL/TK/NH-66/HWY/2209 29-Feb-2024 1-Mar-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 375+280 375+470 190 LHS MCW Prime Coat to be shift Work Done

2236 KHPL/TK/NH-66/HWY/2210 29-Feb-2024 1-Mar-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 371+900 371+980 80 RHS MCW Prime Coat Work Done

2237 KHPL/TK/NH-66/HWY/2211 29-Feb-2024 1-Mar-2024 Spraying of Prime Coat over WMM Top Layer (MCW) 371+870 371+970 100 LHS MCW Prime Coat Work Done

2247 KHPL/TK/NH-66/HWY/2221 1-Mar-2024 2-Mar-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 375+280 375+470 190 LHS MCW DBM to be shift Work Done

2248 KHPL/TK/NH-66/HWY/2222 1-Mar-2024 2-Mar-2024 Spraying of Prime Coat over WMM Top Layer (SR) 373+540 373+970 430 LHS SR Prime Coat to be shift Work Done

2249 KHPL/TK/NH-66/HWY/2223 1-Mar-2024 2-Mar-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 371+880 371+970 90 LHS MCW DBM to be shift Work Done

2250 KHPL/TK/NH-66/HWY/2224 1-Mar-2024 2-Mar-2024 Spraying of tack coat, laying & level checking of DBM (MCW) 371+900 371+970 70 RHS MCW DBM to be shift Work Done

2256 KHPL/TK/NH-66/HWY/2230 2-Mar-2024 3-Mar-2024 Spraying of tack coat, laying & level checking of BC (service Road) 373+540 373+970 430 LHS SR BC Repeated

2270 KHPL/TK/NH-66/HWY/2244 3-Mar-2024 4-Mar-2024 Spraying of tack coat, laying & level checking of BC (service Road) 373+540 373+970 430 LHS SR BC to be shift Work Done