FIREPROOFING MATERIAL : LIGHT WEIGHT CEMENTITIOUS NOTES :

CL CL CL

NOTE 11
1. FOR NOTES, REFER TO DB-000-13302-0001,
CL

(TYP)
"GENERAL NOTES FOR STEEL STRUCTURE".
A A
2. PHILOSOPHY AND EXTENT OF PASSIVE FIREPROOFING SHALL BE IN
ACCORDANCE WITH SS-000-12413-0001.
01
3. SECTION DETAILS OF FIREPROOFING SHALL BE REFERED TO
STANDARD DWG FIREPROOFING DB-000-13302-0007-002.

4. THE MINIMUM THICKNESS OF FIREPROOFING MATERIALS FOR


STRUCTURAL MEMBERS SHALL BE INSTALLED WITH A THICKNESS
NOTE 3 NOTE 3 TO PROVIDE A MINIMUM FIRE-RESISTANCE RATING OF 30 MINUTES
B 01 01
FOR LFP-30 AND 90 MINUTES FOR LFP-90 WHEN SUBJECTED TO A B
FP IS NOT APPLIED SPECIFIED EL OF TOP OF FP TEST FURNACE ENVIRONMENT IN ACCORDANCE WITH UL 1709 OR AN
EQUIVALENT FIRE EXPOSURE TEST PROCEDURE ACCEPTED BY
PURCHASER.
NOTE 9 (TYP)
5. FIREPROOFING MATERIAL TYPE SHALL BE LIGHTWEIGHT
CEMENTITIOUS.

6. FOR THE DETAIL OF EXPANSION JOINT, SEE STANDARD DWG


DB-000-13302-0025, DB-000-13302-0125
C FP IS NOT APPLIED FP IS NOT APPLIED
01 C
7. FIREPROOFING SHALL NOT BE PROVIDED AROUND STEEL
FP IS NOT APPLIED STRUCTURE CONNECTION WITH SLOT HOLES.

8. FOR MORE DETAILS, REFER TO DB-000-12413-0001,


"TYPICAL FIREPROOFING EXTENT DRAWING FOR EQUIPMENT AND
STRUCTURE".

9. IN ACCORDANCE WITH SS-000-13A00-0001, STRUCTURAL STEEL AND


FP IS NOT APPLIED ACCESSORIES SHALL BE PAINTED AS BELOW;
D =NON FIREPROOFING MATERIAL - Modify 1b D
FP IS NOT APPLIED FP IS NOT APPLIED =FIREPROOFING MATERIAL - Modify 1e
GUSSET PLATE FOR NON FIREPROOFING CONNECTING MEMBER
SHALL BE PAINTED AS PER Modify 1b.

10. THICKNESS OF FIREPROOFING SHALL BE MEASURED FROM THE TOP


OF BOLT HEAD.

11. FOR THE DETAIL OF TOP OF COLUMN,SEE STANDARD DWG.


DB-000-13302-0009-001, DB-000-13302-0109-001
E NOTE 10 E
FP IS NOT APPLIED
(TYP) 01

A
-
FP IS NOT APPLIED

F F
BRACING CONNECTION BEAM TO BEAM CONNECTION A SEC
-
(ELEVATION) (PLAN)

FP IS NOT APPLIED
G G
FP IS NOT APPLIED

FP IS NOT APPLIED
01
DB-000-13302-0007-004 STANDARD DRAWING FOR FIREPROOFING (4)
DB-000-13302-0007-003 STANDARD DRAWING FOR FIREPROOFING (3)
DB-000-13302-0007-002 STANDARD DRAWING FOR FIREPROOFING (2)
FP IS NOT APPLIED
DWG NO. TITLE

H REFERENCE DRAWINGS H

COLUMN BASE POST BASE PLATE AND BEAM TO BEAM CONNECTION


HANGER GUSSET PLATE BRACING
(ELEVATION) (PLAN)
01 25-Aug-21 ISSUED FOR CONSTRUCTION K.N T.T Y.Y
00 10-Jun-21 ISSUED FOR REVIEW K.N T.T Y.Y
CL CL CL REV DATE ISSUE PURPOSE PREP'D CHK'D APP'D
I REVISIONS
I

NOTE 10
(TYP)
SOUTH REFINERIES COMPANY

BASRAH REFINERY UPGRADING PROJECT


J CONTRACTOR JOB CODE J
0-8494-20-0000
STANDARD DRAWING
FOR
FIREPROOFING (1)
COLUMN SPLICE

DOCUMENT CLASS SIZE SCALE


K X A1 NONE K
CONTRACT NO.

EXPANSION JOINT (NOTE 6) 5360/B/2020


COLUMN AND BEAM PROJECT DWG NO. REV.
DB-000-13302-0007-001 01

D M S1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
-
J Sep-
06-
2 0 2
D This document and any attachment is confidential and is the property of JGC HOLDINGS CORPORATION and/or its affiliated undertakings. If you are not an authorized person by written permission of JGC HOLDINGS CORPORATION and/or its affiliated undertakings, you should not copy, trace, photograph, reproduce or use it for any purpose nor disclose its contents to any other person. 1/1
RINTE
ED WHEN P
ROLL
NCONT

You might also like