Professional Documents
Culture Documents
State College School District High School Project: Proposal For Commissioning Services
State College School District High School Project: Proposal For Commissioning Services
Submitted by:
Air Balancing Engineers, Inc.
1175 North Vine Street
P.O. Box 311
Berwick, PA 18603
Table of Contents
3. Project Approach
Our team (Air Balancing Engineers / Borton-Lawson) brings to the table the insight
and understanding of a full staff of actively-practicing commissioning specialists,
testing, adjusting and balancing technicians, architects and professional
engineers with the wealth of experience gained in the successful completion of
hundreds of balancing and commissioning assignments. Our personnel are
specialists in mechanical system design and optimization, electrical systems,
HVAC control systems, operations and maintenance, project management, retro
commissioning and training.
As you review this qualification package, please consider the Air Balancing
Engineers advantage and value:
• People – Our commissioning team contains former facilities directors,
licensed master electricians, professional engineers, former HVAC controls
subcontractors and licensed TAB technicians. This cohesive team brings
extensive knowledge of building design, construction, operation and
maintenance to the commissioning process. Our people use their skills to
apply sound inspection and judgment to the commissioned systems for
the benefit of the client.
• Experience – Our team has extensive experience in the operation and
troubleshooting of HVAC systems, energy management control systems
and lighting control systems. Our people have the “boots on the ground”
experience required for a good commissioning agent. We understand the
commissioning is less the creation of fancy checklists and more the
targeted application of defined skillsets to a new project.
• Stewards – Air Balancing Engineers is committed to the furthering of
commissioning in the industry by working with peer groups, societies, etc.
to explain and educate clients about commissioning. We have LEED AP,
membership in the USGBC and commissioning certifications through the
BCA and NEBB.
Thank you for providing us the opportunity to present this proposal. If you have
any questions regarding our materials or if you would like additional information
please contact me.
Sincerely,
o Air Balancing Engineers – Working in the field setting up systems allows us to understand how the
newest technologies are functioning.
o Borton-Lawson – Being architects / engineers allows us to ensure the latest advances in building
envelope and MEP system design are being correctly commissioned.
o Together – Our common sense approach and positive team attitude with the design and
construction teams during the commissioning process assures the Owner a quality installation with
the building fully functional for its occupants on Day One.
As will be seen later in this proposal, Air Balancing Engineers and Borton-Lawson have been working hand-
in-hand together for the last 6+ years to provide quality commissioning services to clients just like the State
College Area School District.
Background:
• 20+ years hands-on experience with commissioning and validation of sophisticated environmental
control and building automation systems, much of it in K-12 and higher education schools.
• 45+ years Testing, Adjusting and Balancing experience in a wide range of projects such as K-12,
higher education, healthcare, pharmaceutical, general office, science buildings, clean rooms,
manufacturing, etc.
• Member of ASHRAE
• Hands-on experience with the field work required to successfully implement the TAB and
commissioning processes.
Background:
• 16+ years hands-on experience with commissioning and validation of sophisticated environmental
control and building automation systems
• Commissioning Team Leader and Mechanical Discipline Manager to lead design and quality
processes
• Project Manager and lead engineer for the design, installation, testing and documentation of a
Building Automation System (BAS) for a new animal building at a leading pharmaceutical
manufacturer. The BAS design included the control/monitoring of the HVAC System and its
associated appurtenances including central station air handlers, exhaust fans, room differential
pressure controls, alarming and all devices on the BAS including all hardware, software, control
equipment, and instrumentation associated with the building’s cGMP (current good
manufacturing practices) and non-cGMP areas.
Mr. Ed Poprik
Director of Physical Plant
State College Area SD
In addition, State College SD will have full access to the experience, capabilities and
knowledge of the entire professional staff of both Air Balancing Engineers and Borton-
Lawson in order to make the project a success.
Joseph Niznik
Plumbing / Fire Protection Commissioning Specialist
Borton-Lawson I 21 Years Consulting Experience
EDUCATION: Associate of Science – Mechanical Engineering Technology, Penn State University
EXPERIENCE: Mr. Joseph J. Niznik, Senior Mechanical Designer, has 21 years of experience in all
aspects of mechanical systems design. He is well-versed in the design/construction process, including
field investigation, design and layout, cost estimating, computer-aided drafting, specification writing,
shop drawing review and construction inspection. Through field experience, he documents existing
conditions and generates plans to include HVAC, Plumbing and Fire Protection piping system layouts
where existing plans do not exist or are not up-to-date. Design experience includes heating/cooling
load calculations, equipment selection, duct sizing and layout, flow calculations, pipe sizing and layout
and coordination of systems layout with those of other disciplines. Mr. Niznik’s experience includes
systems design for new construction, additions and renovations of large and small commercial,
industrial, institutional, residential and government projects.
Our commissioning standards place emphasis on the operations and maintenance of the facilities and
equipment to ensure the client is satisfied long after the construction is complete. We are especially
experienced with LEED certified projects and have the knowledge of the process to ensure all required
commissioning points are achieved.
Size of Project:
184,000 SF
LEED Rating:
Silver
Commissioning Scope:
LEED Fundamental
The Air Balancing Engineers / Borton-Lawson commissioning team provided fundamental and
enhanced commissioning services for the new, LEED Silver, $85 million, Medical Sciences Building for
The Commonwealth Medical College (TCMC). The new medical sciences facility, home of TCMC’s
academic and research programs, consists of two wings connected by a 2-story link containing a
lobby and café. The 4-story West Wing contains approximately 65,000 S.F. with a 20 table gross
anatomy lab, state of the art clinical skills and simulation suites and research labs. The 4-story, 119,000
S.F., East Wing contains a 250 seat auditorium, two 190 seat lecture halls, Library, eight student
community/study suites, teaching labs, small group rooms, as well as administration and support.
This project included 1160 tons of cooling, 19,000MBH of hot water heating capacity, 10,000pph of
steam heating, approximately 200 VAV boxes, 235,000CFM of central station AHU’s, exhaust fans, and
misc. supporting equipment for classroom and laboratory space.
Size of Project:
192,500 SF
LEED Rating:
Gold
Commissioning Scope:
LEED Enhanced
The ABE/BL team provided fundamental and enhanced commissioning services for the additions and
renovation project to the Midd-West High School in Middleburg, PA. The LEED Gold, $33.5 million project
included 169,609 square feet of additions and 22,883 square feet of renovations to an existing high
school designed to accommodate 800 students. The building is a two-story, secondary education
center with a water source heat pump mechanical system, lighting occupancy controls, increased
building insulation and daylighting all used to reduce yearly energy consumption. Commissioned
systems included of all the HVAC, building automation controls, water source heat pump equipment
(rooftop units, classroom units, etc.), condenser water systems (cooling towers, pumps), hot water
systems (boilers, pumps), welding shop exhaust fans, exhaust fans, heat recovery system, auditoriums
and Life-safety interlocks, fire alarm shutdown sequences, failure mode testing and variable frequency
drives (VFD’s). We performed LEED Fundamental and Enhanced Commissioning Services for this
project.
Size of Project:
105,000 SF
LEED Rating:
Gold
Commissioning Scope:
LEED Enhanced
The ABE/BL team provided fundamental and enhanced commissioning services for the additions and
renovation project to the Midd-West Elementary School in Middleburg, PA. The LEED Gold, $18.5 million
project included 55,000SF of additions and 50,000SF of renovations. Commissioned systems included of
all the HVAC, building automation controls, water source heat pump equipment (rooftop units,
classroom units, etc.), energy recovery units, condenser water systems (cooling towers, pumps), hot
water systems (boilers, pumps) and exhaust fans.
Size of Project:
District Wide
LEED Rating:
none
Commissioning Scope:
Retro-Commissioning
Retro-Commissioning (RCx) is a systematic process for investigating, analyzing, and optimizing the
performance of building systems through operational and maintenance improvement measures and
help to confirm their continued performance over time. Goals of retro-commissioning may include
verification that a facility and its systems meet the owner’s requirements, improvement of building
performance by saving energy and reducing operational costs, identification and resolution of
building system operation, control and maintenance problems. The Air Balancing Engineers / Borton-
Lawson commissioning team met with the school district personnel to determine trouble spots,
performed air balancing checks of the areas with trouble spots, and worked with the district’s BAS
controls contractor to bring the systems back to an original specification state. The next phase of the
project consisted of the Cx team reviewing the existing documentation and the creation of a retro-
commissioning plan. Lastly, the Cx team will perform functional performance tests on all of the
existing equipment to identify issues and bring the equipment back to its original state.
Commissioned systems include of all the HVAC (air handling units), building automation controls, DX
cooling systems, hot water systems (boilers, pumps), exhaust fans, auditoriums and life-safety
interlocks, fire alarm shutdown sequences, failure mode testing and variable frequency drives
(VFD’s). Our team discovered, documented and corrected over 120 construction / controls issues.
Size of Project:
300,000 SF
LEED Rating:
Silver
Commissioning Scope:
K-12 Schools LEED Enhanced
Size of Project:
86,000 SF
LEED Rating:
none
Commissioning Scope:
LEED Fundamental
The Air Balancing Engineers / Borton-Lawson commissioning team provided functional preformance
testing services for the renovated Trevorton Elementary School in Trevorton, PA. The building is an
existing 86,000 S.F. K-6 elementary school. The project consisted of major upgrades to existig
classroom and facility spaces. The main heating and cooling was accomplished via a new
geothermal heating system.
the Iron Forge Elementary School Additions and Renovations project and
We are also currently engaged for the commissioning services for the new
West Berwick Elementary School project.
Size of Project:
Site Wide
LEED Rating:
none
Commissioning Scope:
Retro-Commissioning
Retro-Commissioning (RCx) is a systematic process for investigating, analyzing, and optimizing the
performance of building systems through operational and maintenance improvement measures and
help to confirm their continued performance over time. Goals of retro-commissioning may include
verification that a facility and its systems meet the owner’s requirements, improvement of building
performance by saving energy and reducing operational costs, identification and resolution of building
system operation, control and maintenance problems. ABE/BL is currently performing a retro-
commissioning on the comfort and process chilled water system at a 91,000sf facility at Tobyhanna
Army Depot (TYAD) that houses three major shop/production areas.
Size of Project:
Site Wide
LEED Rating:
none
Commissioning Scope:
BAS Optimization
Size of Project:
30,300 SF
LEED Rating:
Certified (achieved)
Commissioning Scope:
LEED Enhanced
The ABE / BL commissioning team provided fundamental and enhanced commissioning services for the
new LEED Certified, Bruce Weschler Residence Hall at Elwyn’s campus in Media, PA. The building is a
single story Intermediate Care Facility consisting of two “wings” with 18 resident rooms each for a total
of 36 single occupant resident rooms with private bathing facilities. The commissioning team performed
pre-functional inspections and functional testing of equipment and systems and provided the final
commissioning documentation for the project. Commissioned systems included of all the HVAC,
building automation controls, DX cooling systems, electric heating systems, exhaust fans and Life-safety
interlocks, fire alarm shutdown sequences, failure mode testing. The Owner’s representative for the
project was Praxis Building Solutions (Max Zahniser).
Size of Project:
31,500 SF
LEED Rating:
Silver (anticipated)
Commissioning Scope:
LEED Fundamental
Size of Project:
151,590 SF
LEED Rating:
Silver
Commissioning Scope:
LEED Fundamental
ABE/BL was selected to provide LEED Fundamental commissioning services on a new, LEED Silver, $35
million, office facility consisting of office space; administrative support space; sensitive compartmented
information facilities (SCIFs); storage space; an information processing and analysis center; and support
spaces. Commissioning services focused on the HVAC, plumbing, domestic hot water, electrical
infrastructure and Building Automation Controls systems including performing pre-functional inspections
and functional testing of equipment and systems, managed the deficiency database and reporting,
and provided the final commissioning documentation for the project.
Size of Project:
17,000 SF
LEED Rating:
Silver
Commissioning Scope:
LEED Fundamental
Geisinger’s new LEED Silver, 17,000 SF facility will house multiple physicians, including pediatrics, general
practice and specialists with an exam room compliment of 27. The one story facility also includes an
on-site pharmacy, X-ray facility, lab and support spaces. Air Balancing Engineers/Borton-Lawson
provided LEED Fundamental Commissioning services for the energy-related systems including the
variable refrigerant fan coil units, energy recovery ventilator, domestic hot water and the building
automation system. The major HVAC systems included an energy recovery ventilation unit for the
outside air requirements and a variable refrigerant fan coil system for the occupied spaces.
Size of Project:
315,000 SF
LEED Rating:
None
Commissioning Scope:
HVAC, controls, electrical
ABE/BL was selected to provide commissioning services on a new, $110 million, production facility.
Commissioning services will focus on the HVAC, plumbing, domestic hot water, electrical infrastructure
and Building Automation Controls systems. ABE/BL’s deep understanding of manufacturing equipment,
systems and controls will help provide the client with the confidence that the systems are being fully
checked out to a high standard.
Size of Project:
100,000 SF
LEED Rating:
Silver
Commissioning
Commissioning Scope:
HVAC, controls, electrical
Air Balancing Engineers provided fundamental commissioning services for the new LEED Silver,
Advanced Technology Center (ATC) at Montgomery County Community College in Blue Bell, PA. The
project was designed to accommodate the Humanities, Social Science, Math/Science/Advanced
Technologies, Information Technology and Business/Computer Science divisions. The four-story building
provides a collaborative learning environment where the humanities and sciences are brought
together within a facility that promotes an interdisciplinary approach to education. Adaptable for use
as a reception hall, the atrium features a coffee bar and interactive reception area with a touchscreen
and plasma monitor for directing visitors.
Traditional TAB:
45 years’ exp.
with over 50%
repeat clients
Total
Commissioning,
Design and
Testing Services
Our commissioning process integrates construction and operational features to facilitate overall project
success by addressing details that may be overlooked in the typical construction process. This enhances
the quality of the project and results in better operational characteristics for long term use long after
construction is completed.
During construction, we will verify the details are built according to the contract documents, and
concerns will be discussed with your project construction team for resolution. When complete, we will
functionally test not just the respective systems but also the system components to observe they are
operating properly. Discovered issues will be brought to the attention of the construction team for
resolution.
Air Balancing Engineers fully understands the commissioning process as it is applied to LEED projects. We
have knowledge into the reasons behind why LEED commissioning requires certain tasks. We understand
why pre-functional checks, performance checks, design reviews and post occupancy reviews are
important to a building owner.
Engineering Firm:
• Up to date with latest advances in the craft
• Value during the design review process
• Expertise on development of construction documents
Together:
Architectural • Depth and breadth of the team members with a
and
Engineering passion for the work.
Firm
Proposal |State College Area SD – High School Project Commissioning Prepared for|
Project Approach
The State College School District fully appreciates the importance of commissioning to verify that all
commissioned systems are installed and operating as intended by the professional. The objective of
commissioning is to confirm and systematically document that a facility fulfills the functional and
performance requirements of the building owner, occupants and operators.
To reach this goal, it is necessary for the commissioning process to establish and document the owner’s
criteria for system function, performance and maintainability; as well as, to verify and document
compliance with these criteria throughout construction, start-up and the initial period of operation. In
addition, complete operation and maintenance (O&M) manuals, as well as training on system operation,
should be provided to the building operators to ensure the building continues to operate as intended.
To achieve these commissioning goals, Air Balancing Engineers assigns a Project Manager to be a point of
contact for the owner during the course of the construction project. The PM coordinates all
commissioning activities with the client and project team and also creates the “in-house” commissioning
team consisting of the following key personnel:
In order to functionally test the various equipment and systems, we heavily employ the use of the Central
Building Automation System (BAS). Using our team’s past BAS experience, our process is:
• Take the engineer’s approved BAS sequence of operation and create functional
performance test plans specific for each piece of equipment, control sequence and
control mode on the project.
• The system/equipment specific functional performance checklists are broken down to test
all modes: occupied, unoccupied, morning warm-up, alarms/safeties, etc. to ensure the
Owner’s Project Requirements are realized in the final operation of the systems.
• For field testing, we always place one technician at the tested piece of equipment and a
second technician sitting with the BAS subcontractor at the front end workstation. By doing
this, we not only ensure that the physical equipment operates as required, but also that the
BAS graphics are shown correctly. This will greatly assist the Owner’s Facilities Staff for
routine maintenance and troubleshooting issues.
• Each functional test mode of operation is simulated at the BAS terminal and the resulting
response (both graphically at the BAS front end workstation and physically at the
equipment) in the field is documented.
• Any discrepancies in expected outcome vs. actual outcome are recorded and
documented on the Commissioning Action List. This list serves as a living document to help
guide and provide a final record of the commissioning process from design, to construction
and finally in testing/acceptance.
Often times, buildings with large or sophisticated HVAC, electric or BAS systems will experience small
changes or modifications during the course of everyday operation. A potential method to check and
return these pieces of equipment/systems to a baseline condition is re-commissioning by the Owner. In re-
commissioning, the Owner’s facilities staff re-test the energy consuming equipment (HVAC, lighting
controls, domestic hot water, etc.) using the original commissioning forms. Therefore, Air Balancing
Engineers creates all of the commissioning documents and test plans electronically to assist an Owner with
future re-commissioning tasks.
Completion of a
Successful
•Identify issues early in the process Commissioning
•Enhanced document awareness Project
Cost Reduction
Date
Issue Date Responsible Issue Resolution Resolution
Issue Issue Description Contractor Action(s) Taken
Number Identified Contractor(s) (Open / Closed) Date
Notified
Site Visit #1 - Construction Inspection - January xx, 2011 - Attendees: BR, AS, SC, AC
Site Visit #2 - Pre-Functional Testing - March xx, 2011 - Attendees: BR, AS, SC, AC
Commissioning Plan
Revision 1
July 31, 2013
Table of Contents
1. COMMISSIONING PLAN OVERVIEW ........................................................................................................ 4
1.1. ABBREVIATIONS .............................................................................................................................. 4
1.2. DEFINITIONS ................................................................................................................................... 5
2. PURPOSE OF COMMISSIONING ............................................................................................................... 6
3. COMMISSIONING ROLES AND RESPONSIBILITIES..................................................................................... 6
3.1. TEAM MEMBERS ........................................................................................................................................ 6
3.2. DESCRIPTION OF ROLES / RESPONSIBILITIES ..................................................................................... 7
3.2.1. GENERAL (TYPICAL TO ALL MEMBERS OF THE COMMISSIONING TEAM) ................................................................ 7
3.2.2. OWNER/OPERATOR RESPONSIBILITIES ........................................................................................................... 8
3.2.3. OWNER RESPONSIBILITIES ............................................................................................................................ 9
3.2.4. ARCHITECT/ENGINEER RESPONSIBILITIES ........................................................................................................ 9
3.2.5. SUBCONTRACTOR'S RESPONSIBILITIES .......................................................................................................... 10
3.2.6. CXA RESPONSIBILITIES ............................................................................................................................... 11
3.3. FACILITY STAFF PARTICIPATION ......................................................................................................12
4. COMMISSIONING PROCESS OVERVIEW ..................................................................................................12
5. PRE-DESIGN PHASE ...............................................................................................................................14
5.1. COMMISSIONING SCOPING MEETING .............................................................................................14
5.2. OWNERS PROJECT REQUIREMENTS (OPR) .......................................................................................14
5.3. COMMISSIONING ISSUES LOG ........................................................................................................14
5.4. SYSTEMS MANUAL REQUIREMENTS ................................................................................................14
6. DESIGN PHASE ......................................................................................................................................15
6.1. COMMISSIONING PLAN ..................................................................................................................15
6.2. BASIS OF DESIGN ...........................................................................................................................15
6.3. DEVELOPMENT OF COMMISSIONING SPECIFICATIONS .....................................................................15
6.4. GENERAL REVIEW OF DRAWINGS AND SPECIFICATIONS ...................................................................15
6.5. TRAINING REQUIREMENTS .............................................................................................................16
7. CONSTRUCTION PHASE .........................................................................................................................16
7.1. SUBMITTALS ..................................................................................................................................16
7.2. SITE OBSERVATION ........................................................................................................................16
7.3. CHECKLIST DEVELOPMENT .............................................................................................................17
7.3.1. PRE-FUNCTIONAL TESTS ............................................................................................................................ 17
7.3.2. BAS CONTROLS CHECKLIST......................................................................................................................... 17
7.3.3. TAB CHECKOUT PLAN ............................................................................................................................... 17
7.3.4. SUBCONTRACTOR / MANUFACTURER EQUIPMENT START-UP PLAN .................................................................. 18
7.3.5. EXECUTION OF PRE-FUNCTIONAL CHECKLISTS................................................................................................ 18
1.1. Abbreviations
The following are common abbreviations used in this document and throughout the
commissioning process documentation:
A/E Architect/Design Engineer
BAS Building Automation System
CxA Commissioning Authority
Cx Commissioning
Cx Plan Commissioning Plan document
CM Construction Manager
CxT Commissioning Team
EC Electrical contractor
GC General Contractor
LEED Leadership in Energy and Environmental Design
MC Mechanical contractor
Subs Subcontractors to GC/CM
TAB Test and balance contractor
BOD Basis of Design
OPR Owner’s Project Requirements
O/O Owner/Operator
PFT Pre-Functional Test
FPT Functional Performance Test
1.2. Definitions
The following are common definitions used in this document and throughout the commissioning
process:
Acceptable Performance: A component or system being able to meet specified design
parameters under actual load including satisfactory documented completion of all functional
performance tests, control system trending and resolution of outstanding issues.
Action Item: This is any issue that requires an action, response, work, etc. it can be an RFI,
a work directive, a clarification, to do item, an identified issue, etc.
Basis of Design (BOD): The Architect/Engineer’s Basis of Design is comprised of two
components: the Design Criteria and the Design Narrative, these documents record the
concepts, calculations, decisions, and product selections used to meet the Owner’s Project
Requirements (OPR) and to satisfy applicable regulatory requirements, standards, and
guidelines.
Building Automation System (BAS): The computer based temperature control or automation
system.
Calibrate: The act of comparing an instrument of unknown accuracy with a standard of
known accuracy to detect, correlate, report, or eliminate by adjustment any variation in the
accuracy of the tested instrument.
Checklists: Lists of data or inspections that should be verified to ensure proper system or
component installation, operation or function. Verification checklists are developed and used
during all phases of the commissioning process to verify that the Owner’s Project
Requirements (OPR) is being achieved.
Commissioning Plan: A document that outlines the scope and defines responsibilities,
processes, schedules, and the documentation requirements of the Commissioning Process.
Commissioning Process: A quality focused process for enhancing the delivery of a project.
The process focuses upon verifying and documenting that the facility and all of its systems,
components, and assemblies are planned, designed, tested, can be operated, and
maintained to meet the Owner’s Project Requirements (OPR), Basis of Design (BOD) and
Contract Documents (CD).
Commissioning Report: The final document which presents the commissioning process
results for the project. Commissioning reports include an executive summary, the
commissioning plan, issue log, correspondence, and all appropriate check sheets and test
forms.
Commissioning Team: Individual team members whose coordinated actions are responsible
for implementing the Commissioning Process.
Contract Documents (CD): Contract documents include design and construction contracts,
price agreements and procedure agreements. Contract Documents also include all final and
complete drawings, specifications, and all applicable contract modifications or supplements.
Functional Performance Testing: That full range of checks and tests carried out to
determine if all building components, sub-systems, systems and interfaces between systems
function in accordance with the Contract Documents. In this context, “function” includes all
modes and sequences of control operation, all interlocks and conditional control responses
and all specified responses to abnormal emergency conditions. The functional performance
2. Purpose of Commissioning
The basic purpose of commissioning is to provide documented confirmation that building
systems function in compliance with criteria set forth in the Owner’s Project Requirements
(OPR), Basis of Design (BOD) and project Contract Documents to satisfy the owner's
operational needs. This definition is based on the critical understanding that the owner must
have some means of verifying that their functional needs are rigorously addressed during the
pre-design/design, construction, acceptance and warranty phases.
This project is also registered with the U.S. Green Building Council (USGBC) for their LEED
Certification program. This rating system represents the most comprehensive, sustainable
building guideline available and the Owner requested that the project be designed and built to
meet a Gold LEED rating. Commissioning is an integral part of the LEED rating system and is
considered a prerequisite to attain any LEED certification. For further information on the LEED
rating system, please refer to the LEED Reference Guide available from the USGBC website.
• Read and respond to Owner's and CxA's comments and questions in a timely
fashion.
• Incorporate commissioning specifications and edit the appropriate sections of the
construction specifications to include commissioning. Specify design goals and
approved methods of testing the equipment and systems.
B. Construction Phase
• Issue necessary changes in construction and provide a copy to CxA.
• Issue clarifications or interpretations of Design Intent as required.
• Maintain a record set of shop drawings, product data, warrantees, test reports,
balance reports, start up certifications, etc. as required by contract.
• Review O&M manuals and incorporate CxA's comments in a mark up or
approval.
C. Acceptance Phase
• Witness key tests and verifications.
• Consult on and resolve any design related issues/problems that arise during this
phase.
• Participate in the systems level training program for the operators as required.
D. Warranty Phase
• Consult with Owner as necessary to convey and maintain design intent and
respond to any identified deficiencies.
The commissioning process is intended to assist with the coordination of traditionally separate
functions of system documentation, equipment startup, control system checkout and
performance testing. The Cx Plan is the document that outlines the organization, schedule,
allocation of resources and documentation requirements of the Cx Process. The Cx Plan is the
key means for the CxA to inform all parties as to how each system functions independently and
with respect to other systems. The plan shall be updated as necessary and redistributed to the
commissioning team for review and comment.
The entire Commissioning Team is encouraged to provide feedback to the CxA at any time
during the CX process. This feedback will enable the commissioning to be adjusted according
to the project specifics and will help stream line the entire Commissioning process.
See below for the Commissioning Process and Document Flowchart for further description of
the Commissioning Process.
BOD Written
Bidding Documents
Cx Plan Created
and Kickoff Meeting
Equipment Submittals,
Project Phase: Construction Procurement and Installation
Cx Phase: Construction
Pre-Functional &
System Readiness
Checklists Created
Equipment Start-Ups
Functional
Performance Testing
Equipment Turnover
Project Phase: Startup/Testing to Owner
Cx Phase: Acceptance
Preparation of Final
Turnover Package
Owner Training
Deferred/Seasonal
Testing
Project Phase: Warranty
Cx Phase: Warranty Project Complete
Commissioning Plan Page 13 of 22
Revision 1 – July 31, 2013
Commissioning for Middleburg Elementary School
Midd-West School District
5. Pre-Design Phase
The Pre-Design Phase is the starting point for the commissioning process. Its main objectives
are to review and document the Owner’s Project Requirements (OPR) and to begin the
development of the commissioning plan.
6. Design Phase
The main objectives of Design Phase commissioning are to verify the Owner’s Project
Requirements are incorporated into the design documents, creation of a Basis of Design
document and the updating of the Cx Plan.
The CxA is not responsible for design concept, design criteria or compliance with codes. The
CxA does not verify the designers’ calculations or proof schematics or layouts in detail. The
CxA uses his or her knowledge to provide input into the various systems. For example, the CxA
does not verify appropriate pipe or duct sizing, but may provide comments on unusually tight or
restrictive duct layouts and bends or a poor location of a static pressure sensor.
The CxA provides a copy of the review comments to the Owner. The A/E provides a written
response to the CxA and Owner.
7. Construction Phase
The construction phase includes commissioning tasks executed after the Design Phase has
been completed and prior to the Acceptance Phase. The main commissioning activities
performed during this phase are equipment submittal review, verification that the systems are
correctly installed and manufacturer / subcontractor equipment start-ups.
7.1. Submittals
The Owner will provide the CxA with a full set of approved equipment and system submittals for
review to ensure compliance to the OPR, BOD and Contract Documents. This equipment data
includes installation and start-up procedures, operation & maintenance (O&M) data,
performance data and BAS control drawings. The subcontractors, CM or A/E shall notify the
CxA of any new OPR or operating parameter changes, added control strategies and sequences
of operation, or other change orders that may affect commissioned systems.
Once there is an approved submittal, the respective subcontractor (MC, EC, BAS, etc.) will
submit information required for commissioning, including:
o Cutsheets and performance data (regular submittal data)
o Product description literature (general information)
o Installation Guide
o Start-up guide and checkout plan
o Test plans / reports (factory tests, start-up test, etc.)
o Operation and Maintenance (O&M) books
o Warranty and service contract information
o Control drawings and points list
o Control sequences and schedules
o Certifications (pressure, leaks, gas, government inspections, etc.)
Pre-Functional Tests are primarily installation verifications, static inspections and start-
up procedures to prepare the equipment or system for initial operation (e.g., oil levels
OK, fan belt tension, labels affixed, gauges in place, sensor calibration completed,
systems installed as per design documents and details, etc.). Examples of the static
inspections that the subcontractor must perform are hydrostatic testing of all piping
systems and pressure testing of all ducts for leakage. Completed static test inspection
sheets are to be submitted to the CxA.
Subcontractors typically already perform many of the PFT items that the CxA will
recommend. The CxA will perform and/or witness the PFT verification and document
the results.
This start-up test shall be in addition to the requirements for subcontractor tests, Code
official’s inspection tests, Authority Having Jurisdiction requirements and operating
instructions. The subcontractor shall supervise, conduct, and document the start-up
tests. Any adjustments and/or alterations which the start-up tests indicate as necessary
for the proper functioning of all equipment shall be completed before functional
performance testing can begin.
The subcontractor shall submit start-up procedures, data sheets and recording forms for
review a minimum of four weeks prior to execution of the start-up verification process.
It is the responsibility of the subcontractors and/or vendors to direct and execute all
startup activities. All System Readiness checklist items are to be completed during the
scheduled equipment/system start-up. The CxA or CM may observe selected startup
procedures of primary equipment.
The CxA is responsible for the execution of all pre-functional checklists. Pre-functional
checklists shall ensure that the equipment and systems are hooked up and operational.
The pre-functional testing for a given piece of equipment or system must be
successfully completed prior to formal Functional Performance Testing can begin.
8. Acceptance Phase
The acceptance phase includes commissioning tasks executed after the construction has been
completed, all site observations and static tests have been completed and all Pre-Functional
Tests have been completed and accepted. The main commissioning activities performed
during this phase are verification that the installed systems are functional as verified by
conducting Functional Performance Tests and Owner training.
Functional testing and verification may be achieved by manual testing (persons manipulate the
equipment and observe performance) or by monitoring the performance and analyzing the
results using the control system’s trend log capabilities or by stand-alone data loggers. The
CxA will follow the specifications and use judgment where needed to determine which method
is most appropriate.
The control system is tested before it is used to verify performance of other components or
systems. The air balancing and water balancing is completed and debugged before functional
testing of air-related or water-related equipment or systems. Testing proceeds from
components to subsystems to systems and finally to interlocks and connections between
systems.
See Appendix H of this document for the Functional Performance Tests to be used on this
project.
8.6. Sampling
Multiple identical pieces of non-life-safety or otherwise non-critical equipment may be
functionally tested using a sampling strategy.
Corrections of minor issues identified may be made during the tests at the discretion of the CxA
with the concurrence of the Owner. In such cases the issue and resolution will be documented
on the Issues Log. Every effort will be made to expedite the testing process and minimize
unnecessary delays, while not compromising the integrity of the procedures.
For all other issues, once an issue has been identified and a resolution has been decided, the
appropriate party corrects the issue and notifies the CxA that the equipment is ready to be
retested. The CxA reschedules the test and the test is repeated until satisfactory performance
is achieved.
The final commissioning report will include an overview or summary of the commissioning
process, major results of the process, the final commissioning issues log and resolutions,
commissioning progress and field reports, a deferred testing log, an unresolved issues log, a
lessons-learned evaluation, and concluding with a recommendation to accept the process as
complete.
For each piece of commissioned equipment, the report should contain the disposition of the
CxA regarding the adequacy of the equipment, documentation and training meeting the
contract documents in the following areas:
Appendices shall contain acquired sequence documentation, logs, meeting minutes, progress
reports, deficiency lists, site visit reports, findings, unresolved issues, communications, etc.
Pre-Functional tests, functional performance tests, monitoring data and analysis will be
provided in a separate labeled binder.
9. Warranty Phase
The warranty phase includes commissioning efforts executed after a project has been
completed and accepted by the Owner. The commissioning tasks include follow-up on
verification of system performance, measurement and verification tasks and assistance in
identifying warranty issues and enforcing warranty provisions of the construction contract.
10. Schedule
The CxA works with the Owner in order to incorporate the commissioning tasks into the overall
project schedule in order to allow the subcontractors to perform commissioning in the normal
flow of a project.
General Mode
Unoccupied Mode
Start/Stop Test
Results
Trigger for Test: Expected Outcome: Comment #
(pass/fail)
Boiler and Pump (P-3) de-energizes
Hot water mixing valve indexed closed to
boiler
Index heat pump water system into unoccupied Combustion air dampers close
mode Cooling tower de-energizes
Cooling tower bypass valve indexed closed
to tower
Loop pumps (P-1 and P-2) de-energize
Occupied Mode
BAS Sequence of Operation for Occupied
Mode:
Comment Sheet
Comment # Description
Unoccupied Mode
The units supply fan is de-energized and the units outside air
damper shall be closed and return air damper opens. Any one of
BAS Sequence of Operation for Unoccupied the VAV box space temperature sensors shall cycle the fan,
Mode: electric heat and mechanical cooling as required to maintain
reduced night setback setpoint. The VAV dampers shall continue
to modulate to maintain night setback setting.
Start/Stop Test
Results
Trigger for Test: Expected Outcome: Comment #
(pass/fail)
Supply fan de-energizes
Index unit into unoccupied mode Outside air damper closes
Return air fan opens
Verify all VAV box night heating setback
Setpoints are 65DegF
temperatures are 65DegF.
Supply fan energizes.
Check Heating Mode: Adjust a VAV box space
temperature setpoint above the current VAV Outside air damper remains closed and
box space temperature value. return air damper remains open.
Electric heat energizes
Verify all VAV box night cooling setback
Setpoints are 80DegF
temperatures are 80DegF.
Supply fan energizes.
Check Cooling Mode: Adjust a VAV box space
Outside air damper remains closed and
temperature setpoint below the current VAV
return air damper remains open.
box space temperature value.
Mechanical cooling energizes
Return all setpoints to as-found values. Setpoints returned to as-found values.
FPT - Variable Air Volume AHU Unit 1 of 4 FPT-AHU-5
Functional Performance Test (FPT) State College High School
(Variable Air Volume AHU Unit)
Warm-Up Mode
Unit will be indexed to the warm-up cycle when the average space
temperature is below the occupied heating temperature setpoint of
70DegF (adj.). The unit fan shall run continuously. Outside air
BAS Sequence of Operation for Warm-Up damper shall be closed, return air damper open and the VAV box
Mode: dampers shall be at a maximum setpoint position. When the
average space temperature is at the occupied setpoint, then the
morning warm-up cycle will be switched over to the occupied
mode.
Start/Stop Test
Results
Trigger for Test: Expected Outcome: Comment #
(pass/fail)
Supply fan energizes
Outside air damper closes
Return air damper opens
Index unit into warm-up mode Electric heat is energized
Mechanical cooling is locked-out
VAV box dampers at maximum setpoint
position
Cool-Down Mode
Unit will be indexed to the cool-down cycle when the average
space temperature is above the occupied cooling temperature
setpoint of 75DegF (adj.). The unit fan shall run continuously.
BAS Sequence of Operation for Cool-Down Outside air damper shall be closed, return air damper open and
Mode: the VAV box dampers shall be at a maximum setpoint position.
When the average space temperature is at the occupied setpoint,
then the morning cool-down cycle will be switched over to the
occupied mode.
Start/Stop Test
Results
Trigger for Test: Expected Outcome: Comment #
(pass/fail)
Supply fan energizes
Outside air damper closes
Return air damper opens
Index unit into cool-down mode Electric heat is de-energized
Mechanical cooling is energized
VAV box dampers at maximum setpoint
position
Occupied Mode
Upon the unit being indexed into occupied mode, the supply fan
shall run continuously and the outside air damper shall be opened
to minimum position. Based on the required space temperature
BAS Sequence of Operation for Occupied
setpoints, the units mechanical cooling, economizer dampers and
Mode:
electric heat shall be modulated in sequence to maintain a
discharge air temperature reset schedule between 55DegF and
120DegF.
FPT - Variable Air Volume AHU Unit 2 of 4 FPT-AHU-5
Functional Performance Test (FPT) State College High School
(Variable Air Volume AHU Unit)
Comment Sheet
Comment # Description
Note /
Description
Observation #
General Mode
Start/Stop Test
Results
Trigger for Test: Expected Outcome: Comment #
(pass/fail)
Verify the cooling tower, boiler, associated
Disconnects are pulled to the "off"
water loop pumps and 100%OA unit
position.
disconnects are "off".
Heat pump indexed to occupied mode of
control
Unoccupied Mode
Start/Stop Test
Results
Trigger for Test: Expected Outcome: Comment #
(pass/fail)
Supply fan de-energizes
Outside air damper closes
Index unit into unoccupied mode
Isolation valve closes
Compressor de-energizes
Results
Trigger for Test: Expected Outcome: Comment #
(pass/fail)
Supply fan energizes
Outside air damper remains closed
Index unit into morning warm-up mode
Isolation valve opens
Compressor energizes
Results
Trigger for Test: Expected Outcome: Comment #
(pass/fail)
Supply fan energizes
Outside air damper remains closed
Index unit into morning cool down mode Isolation valve opens
Reversing valve energizes
Compressor energizes
Occupied Mode
BAS Sequence of Operation for Occupied
Mode:
Start/Stop Test
Results
Trigger for Test: Expected Outcome: Comment #
(pass/fail)
Supply fan energizes
Index unit into occupied mode
Outside air damper opens to minimum
position
Adjust the space CO2 setpoint above the current Outside air damper modulates closed
space CO2 value. towards minimum setpoint
Environmental Index
BAS Sequence of Operation for Environmental
Index:
Readout Test
Results
Trigger for Test: Expected Outcome: Comment #
(pass/fail)
BAS calculates the space Environmental
Unit needs to be in occupied mode and BAS Index (0-100%)
controller is monitoring zone temperature and
CO2 readings Readout includes the percentage of time
since occupancy began that the
Enviromental Index was 70% or higher.
Comment Sheet
Comment # Description
1. Air Balancing Engineers proposes to provide Building Commissioning services to the State
College Area School District for the High School construction project based on the Scope of
Work described in Part B of the Request for Proposal and the Form of Agreement and its terms
and conditions attached to the Proposal, for a fixed fee of: $345,550
The above lump sum fee includes the necessary tasks to achieve both the LEED Fundamental
Commissioning of Building Energy Systems prerequisite and the LEED credit for Enhanced
Commissioning.
2. In addition to the above referenced services, an additional fee is proposed to complete the
Building Envelope Commissioning services, also described in Part B of the Request for Proposal as
follows: $134,650
a. Design Phase:
i. Fee: $41,500
ii. Hours: 354 hours
iii. Representative Tasks:
1. Design Review of Owner’s Project Requirements (OPR) and Basis of Design
(BOD)
2. Meeting related to LEED
3. Pre-bid design reviews of contract documents against the OPR/BOD at
60% and 90% completion
4. Create Commissioning Specifications for inclusion in the contract
documents
5. Attend 3-5 project design meetings (as required)
b. Construction Phase:
i. Phase 1 – New:
1. Fee: $67,380
2. Hours: 580 hours
ii. Phase 2 – New/Renovation:
1. Fee: $112,300
2. Hours: 960 hours
iii. Phase 3 – North Construction:
1. Fee: $44,900
2. Hours: 380 hours
iv. Representative Tasks (same for construction phases 1, 2 and 3):
1. Submittal review for compliance with OPR and BOD
2. Develop, prepare and implement Commissioning Plan
3. Jobsite installation inspections – pre-functional testing
4. Equipment startup verification
5. Functional Performance Testing
6. Commissioning / Construction Meetings
a. Design Phase:
i. Fee: $16,160
ii. Hours: 116 hours
iii. Representative Tasks:
1. Work with Design Team during development of building shell/envelope
detailing.
2. Pre-bid design reviews of contract documents at 60% and 90%
completion. Areas of focus for the design reviews will be the water
barrier, air barrier, vapor barrier and thermal barrier.
3. Create Commissioning Specification for inclusion in the contract
documents
4. Attend 3-5 project design meetings (as required)
b. Construction Phase:
i. Phase 1 – New:
1. Fee: $26,250
2. Hours: 190 hours
ii. Phase 2 – New/Renovation:
1. Fee: $43,760
2. Hours: 315 hours
iii. Phase 3 – North Construction:
1. Fee: $17,500
2. Hours: 126 hours
iv. Representative Tasks (same for construction phases 1, 2 and 3):
1. Inspection based verification of the walls, footing & floors, windows &
doors and roofs.
2. Perform periodic site visits to observe the building envelope construction
3. Submittal review for compliance with specifications
4. Installation inspections at the following milestones:
a. Prior to air barrier installation
b. During air barrier and thermal barrier installation
c. At air barrier completion
d. At roof completion
e. At door and window trim installation
5. Develop, prepare and implement a Building Envelope Commissioning
Plan
6. Sample items to be reviewed during inspections:
a. Low spots without drains
b. Incorrect insulation
c. Flashing obstructing drainage
d. Commissioning / Construction Meetings as required
c. Warranty / Acceptance Phase:
i. Fee: $30,980
ii. Hours: 223 hours
iii. Representative Tasks:
Proposed Sampling Rates: In our experience, identifying a detailed equipment sampling plan is
difficult when the construction documents are only at a 30% completion stage. At this design
stage, full system interoperability is not fully defined and detailed. By implementing a sampling
plan now, some of these specific system to system or critical equipment testing could be
overlooked. The pricing above reflects 100% testing of equipment (no sampling). A sampling plan
could be created at a later drawing stage (e.g. 80% or 90%) once the final amounts and type of
equipment and systems are known.
4. Fee Schedule of Hourly Rates to be used for any Additional Services that may be required on the
project:
6. A sample agreement (EJCDC) for commissioning services is attached. We are open to either
using an agreement similar to this one or some other similar type for this project.
7. Assumptions / Exclusions:
a. While not included in the above scope of work, the owner can elect to perform more in-
depth envelope functional testing (such as ASTM): Whole building pressure test, assembly
water intrusion tests, roof water intrusion tests, thermal intrusion tests and adhesion pull tests.
b. The subcontractors will provide start-up reports and pre-functional checklists and data
forms for major equipment items and automatic controls. Air Balancing Engineers will
review the forms prior to completion.
c. Air Balancing Engineers will prepare test forms and direct the functional performance tests.
The subcontractors will provide the necessary staff (mechanical, controls, electrical,
equipment manufacturer, etc.) to operate the systems.
d. The commissioning agent shall not be responsible for reenergizing any electrical
equipment, machinery or systems that may default to off requiring manual restart during
any electrical circuit testing. The restart of said equipment shall be the responsibility of the
owner or an agent representing the owner or an on-site contractor responsible for the
installation of same.
We look forward to working with you and your team on this project
and providing solutions that will benefit the State College School District.
This proposal will be valid for 90 days from the date of the letter.
____________________________________("Owner")
and
________________________________________________________(“Engineer”).
Owner's Project, of which Engineer's services under this Agreement are a part, is generally identified as
follows:
_____ __________________(“Project").
___________________________
A. Engineer shall provide, or cause to be provided, the services set forth in this Agreement. If
authorized by Owner, or if required because of changes in the Project, Engineer shall furnish
services in addition to those set forth above. Owner shall pay Engineer for its services as set forth
in Paragraphs 7.01 and 7.02.
B. Engineer shall complete its services within a reasonable time, or within the following specific time
period: Commissioning services will follow the timeframe set out in the project construction
schedule.
C. If the Project includes construction-related professional services, then Engineer's time for
completion of services is conditioned on the time for Owner and its contractors to complete
construction not exceeding __ months. If the actual time to complete construction exceeds the
number of months indicated, then Engineer's period of service and its total compensation shall be
appropriately adjusted.
A. Invoices: Engineer shall prepare invoices in accordance with its standard invoicing practices and
submit the invoices to Owner on a monthly basis. Invoices are due and payable within 30 days of
EJCDC E-520 Short Form of Agreement Between Owner and Engineer for Professional Services.
Copyright ©2009 National Society of Professional Engineers for EJCDC. All rights reserved.
Page 1
receipt. If Owner fails to make any payment due Engineer for services and expenses within 30 days
after receipt of Engineer’s invoice, then the amounts due Engineer will be increased at the rate of
1.0% per month (or the maximum rate of interest permitted by law, if less) from said thirtieth day.
In addition, Engineer may, after giving seven days written notice to Owner, suspend services under
this Agreement until Engineer has been paid in full all amounts due for services, expenses, and
other related charges. Owner waives any and all claims against Engineer for any such suspension.
Payments will be credited first to interest and then to principal.
3.01 Termination
1. For cause,
a. By either party upon 30 days written notice in the event of substantial failure by the
other party to perform in accordance with the Agreement’s terms through no fault of
the terminating party. Failure to pay Engineer for its services is a substantial failure to
perform and a basis for termination.
b. By Engineer:
1) upon seven days written notice if Owner demands that Engineer furnish or perform
services contrary to Engineer’s responsibilities as a licensed professional; or
2) upon seven days written notice if the Engineer’s services for the Project are delayed
for more than 90 days for reasons beyond Engineer’s control.
2. For convenience, by Owner effective upon Engineer's receipt of written notice from
Owner.
B. The terminating party under Paragraph 3.01.A may set the effective date of termination at a time
up to 30 days later than otherwise provided to allow Engineer to complete tasks whose value
would otherwise be lost, to prepare notes as to the status of completed and uncompleted tasks, and
to assemble Project materials in orderly files.
EJCDC E-520 Short Form of Agreement Between Owner and Engineer for Professional Services.
Copyright ©2009 National Society of Professional Engineers for EJCDC. All rights reserved.
Page 2
C. In the event of any termination under Paragraph 3.01, Engineer will be entitled to invoice Owner
and to receive full payment for all services performed or furnished in accordance with this
Agreement and all reimbursable expenses incurred through the effective date of termination.
A. Owner and Engineer are hereby bound and the successors, executors, administrators, and legal
representatives of Owner and Engineer (and to the extent permitted by Paragraph 4.01.B the
assigns of Owner and Engineer) are hereby bound to the other party to this Agreement and to the
successors, executors, administrators, and legal representatives (and said assigns) of such other
party, in respect of all covenants, agreements, and obligations of this Agreement.
B. Neither Owner nor Engineer may assign, sublet, or transfer any rights under or interest (including,
but without limitation, moneys that are due or may become due) in this Agreement without the
written consent of the other, except to the extent that any assignment, subletting, or transfer is
mandated or restricted by law. Unless specifically stated to the contrary in any written consent to
an assignment, no assignment will release or discharge the assignor from any duty or responsibility
under this Agreement.
C. Unless expressly provided otherwise, nothing in this Agreement shall be construed to create,
impose, or give rise to any duty owed by Owner or Engineer to any contractor, subcontractor,
supplier, other individual or entity, or to any surety for or employee of any of them. All duties and
responsibilities undertaken pursuant to this Agreement will be for the sole and exclusive benefit of
Owner and Engineer and not for the benefit of any other party.
A. The standard of care for all professional engineering and related services performed or furnished
by Engineer under this Agreement will be the care and skill ordinarily used by members of the
subject profession practicing under similar circumstances at the same time and in the same locality.
Engineer makes no warranties, express or implied, under this Agreement or otherwise, in
connection with Engineer’s services. Subject to the foregoing standard of care, Engineer and its
consultants may use or rely upon design elements and information ordinarily or customarily
furnished by others, including, but not limited to, specialty contractors, manufacturers, suppliers,
and the publishers of technical standards.
B. Engineer shall not at any time supervise, direct, control, or have authority over any contractor's
work, nor shall Engineer have authority over or be responsible for the means, methods, techniques,
sequences, or procedures of construction selected or used by any contractor, or the safety
precautions and programs incident thereto, for security or safety at the Project site, nor for any
failure of a contractor to comply with laws and regulations applicable to such contractor's
furnishing and performing of its work.
C. This Agreement is to be governed by the law of the state or jurisdiction in which the Project is
located.
D. Engineer neither guarantees the performance of any contractor nor assumes responsibility for any
contractor’s failure to furnish and perform its work in accordance with the contract between Owner
EJCDC E-520 Short Form of Agreement Between Owner and Engineer for Professional Services.
Copyright ©2009 National Society of Professional Engineers for EJCDC. All rights reserved.
Page 3
and such contractor. Engineer is not responsible for variations between actual construction bids or
costs and Engineer's opinions or estimates regarding construction costs.
E. Engineer shall not be responsible for the acts or omissions of any contractor, subcontractor, or
supplier, or of any of their agents or employees or of any other persons (except Engineer’s own
employees) at the Project site or otherwise furnishing or performing any construction work; or for
any decision made regarding the construction contract requirements, or any application,
interpretation, or clarification of the construction contract other than those made by Engineer.
F. The general conditions for any construction contract documents prepared hereunder are to be the
“Standard General Conditions of the Construction Contract" as prepared by the Engineers Joint
Contract Documents Committee (EJCDC C-700, 2007 Edition) unless the parties agree otherwise.
G. All documents prepared or furnished by Engineer are instruments of service, and Engineer retains
an ownership and property interest (including the copyright and the right of reuse) in such
documents, whether or not the Project is completed. Owner shall have a limited license to use the
documents on the Project, extensions of the Project, and for related uses of the Owner, subject to
receipt by Engineer of full payment for all services relating to preparation of the documents and
subject to the following limitations: (1) Owner acknowledges that such documents are not
intended or represented to be suitable for use on the Project unless completed by Engineer, or for
use or reuse by Owner or others on extensions of the Project, on any other project, or for any other
use or purpose, without written verification or adaptation by Engineer; (2) any such use or reuse,
or any modification of the documents, without written verification, completion, or adaptation by
Engineer, as appropriate for the specific purpose intended, will be at Owner’s sole risk and without
liability or legal exposure to Engineer or to its officers, directors, members, partners, agents,
employees, and consultants; (3) Owner shall indemnify and hold harmless Engineer and its
officers, directors, members, partners, agents, employees, and consultants from all claims,
damages, losses, and expenses, including attorneys’ fees, arising out of or resulting from any use,
reuse, or modification of the documents without written verification, completion, or adaptation by
Engineer; and (4) such limited license to Owner shall not create any rights in third parties.
H. To the fullest extent permitted by law, Owner and Engineer (1) waive against each other, and the
other’s employees, officers, directors, agents, insurers, partners, and consultants, any and all claims
for or entitlement to special, incidental, indirect, or consequential damages arising out of, resulting
from, or in any way related to the Project, and (2) agree that Engineer’s total liability to Owner
under this Agreement shall be limited to the total amount of compensation received by Engineer,
whichever is greater.
I. The parties acknowledge that Engineer’s scope of services does not include any services related to
a Hazardous Environmental Condition (the presence of asbestos, PCBs, petroleum, hazardous
substances or waste as defined by the Comprehensive Environmental Response, Compensation and
Liability Act, 42 U.S.C. §§9601 et seq., or radioactive materials). If Engineer or any other party
encounters a Hazardous Environmental Condition, Engineer may, at its option and without liability
for consequential or any other damages, suspend performance of services on the portion of the
Project affected thereby until Owner: (1) retains appropriate specialist consultants or contractors to
identify and, as appropriate, abate, remediate, or remove the Hazardous Environmental Condition;
and (2) warrants that the Site is in full compliance with applicable Laws and Regulations.
EJCDC E-520 Short Form of Agreement Between Owner and Engineer for Professional Services.
Copyright ©2009 National Society of Professional Engineers for EJCDC. All rights reserved.
Page 4
J. Owner and Engineer agree to negotiate each dispute between them in good faith during the 30 days
after notice of dispute. If negotiations are unsuccessful in resolving the dispute, then the dispute
shall be mediated. If mediation is unsuccessful, then the parties may exercise their rights at law.
A. This Agreement (including any expressly incorporated attachments), constitutes the entire
agreement between Owner and Engineer and supersedes all prior written or oral understandings.
This Agreement may only be amended, supplemented, modified, or canceled by a duly executed
written instrument.
A. Using the procedures set forth in Paragraph 2.01, Owner shall pay Engineer as follows:
B. The portion of the compensation amount billed monthly for Engineer's services will be based upon
Engineer's estimate of the percentage of the total services actually completed during the billing
period.
7.02 Additional Services: For additional services of Engineer’s employees engaged directly on the
Project, Owner shall pay Engineer an amount equal to the cumulative hours charged to the Project
by each class of Engineer’s employees times standard hourly rates for each applicable billing class;
plus reimbursable expenses and Engineer’s consultants’ charges, if any. Engineer's standard
hourly rates are attached as Appendix 1.
EJCDC E-520 Short Form of Agreement Between Owner and Engineer for Professional Services.
Copyright ©2009 National Society of Professional Engineers for EJCDC. All rights reserved.
Page 5
Attachments: Appendix 1, Engineer's Standard Hourly Rates
IN WITNESS WHEREOF, the parties hereto have executed this Agreement, the Effective Date of
which is indicated on page 1.
OWNER: ENGINEER:
By: By:
Title: Title:
Date Signed: Date Signed:
EJCDC E-520 Short Form of Agreement Between Owner and Engineer for Professional Services.
Copyright ©2009 National Society of Professional Engineers for EJCDC. All rights reserved.
Page 6