Daily Report for Overhaul Activity UNIT-9

Date: 24.09.2017
Section: TM-660MW
Sr No. Location/Aux Period Work Carried out Remark
1 LP Vacuum Pump A&B 23.09.2017 HP Vacuum Pump A&B boroscopic inspection
To carried out; G/Box oil replaced; PHE cleaning
24.09.2017 done; R/C and Suction strainers cleaned and Work Complete
gasket replaced; Alignment checking &
correction done; Flex Coupling cleaning and
grease replaced
2 CEP C 23.09.2017 CEP C Suction Strainer Cleaning work done, Work Complete
gasket replaced.
3 TDBFP- A 23.09.2017 Suction Strainer Cleaning work done, Cover Work Complete
plate sealing O-Ring replaced
4 DMCW(TG) PHE #1 22.09.2017 Dismantling of PHE in progress Work in progres
To
28.09.2017
5 HPH’s Drip Control 23.09.2017 Drip Control Valves Gland replacement work Work completed
Valves to
24.09.2017
6 DMCW(SG) # 2 24.09.2017 Pump internal inspection done; suction Work in progres
to strainer cleaning done; Alignment checking in
25.09.2017 progress
7 CPP Pit Drain pumps 23.09.2017 CPP Drain pump A&B O/H work Work in progres
to
28.09.2017
8 TDBFP Drain Pit 23.09.2017 Drain pump A&B O/H work Work in progres
to
30.09.2017
9 ACW 22.09.2017 ACW Pump No.1 Strainer cleaning work Work completed
to
24.09.2017
10 Service Air Compressor 22.09.2017 Element replacement work Work in progres
No.3 to
28.09.2017