TAILING MINE FILTRATION PROJECT


Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Date : April 6th, 2023

DAILY PROGRESS REPORT


0. DAILY PROGRESS & MANPOWER Construction Phase
MANPOWER WORK HOURS RAINFALL RECORD
PLAN ACTUAL ACTUAL ACTUAL
DISCIPLINE/ACTIVITY
Night Night Night
Day Shift Overtime Day Shift Overtime Day Shift Overtime Start End Total Hours Remarks
Shift Shift Shift
Direct Labor * 7 5 55
Skilled Worker (Source : Jakarta) 7 5 55
Rebarman 1 1 11
Mason 1
Carpenter 1 1 11
HDPE Piping 2 1 11
Fitter 1 1 11
Pipe Fitter
Boilermaker 1 1 11
Welder Steel (SMAW+GTAW)
Painter
OTHER CONDITION
Unskilled Worker (Source : Jakarta)
Start End Total Hours Remarks
Helper
Skilled Worker (Source : Local)

Unskilled Worker (Source : Local)

Indirect * 24 24 264
Construction Manager Total Hours :
Deputy Constraction Manager 1 1 11 Note :
Planner 1 1 11
Surveyor 1 1 11
Field Engineer/Project Engineer 1 1 11
HR Staff 2 2 22 EQUIPMENT ON SITE QTY
Civil Foreman 1 1 11
Civil Supervisor 1 1 11 Roughter Crane 50 Ton 1
Civil QC Engineer 1 1 11 Roughter Crane 90 Ton 1
Civil Superintendent Boomtruck 15 Ton 1
QC Staff Concrete Pump 1
Mechanical Mixer Truck 09 1
SMP Foreman 1 1 11 Mixer Truck 10 1
SMP Supervisor 1 1 11 Telehandler 1
SMP QC Engineer (WI qualification) Tractor Head 6X6 1
Scaffolding Inspector Total Equipment 8
Scaffolder
HSE Supervisor 1 1 11
Safety Officer 1 1 11
Logistic and Warehouse 1 1 11
Rigger 1 1 11
Driver 2 2 22
Electrician 2 2 22
Operator Crane 2 2 22
Operator Telehandler 1 1 11
Operator Manlift
Operator Boom Truck 1 1 11
Operator Trailer 1 1 11
Operator Concrete Pump
Operator Mixer Truck

TOTAL 31 29 319

2. MAJOR HIGHLIGHT
Thursday, 06 April 2023 Friday, 07 April 2023
ACTIVITY UNIT QTY ACTIVITY UNIT QTY
A. Civil A. Civil
Set Up Office Lay out & Containers Create site office base concrete
Prepare support pad Produce support pad
Prepare concrete decking Produce concrete decking
B. Structure : B. Structure :

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

E. Logistic : E. Logistic :

F. Scaffold : F. Scaffold :

G. Others G. Others
Continue online HSE induction Continue online HSE induction
Preparing mobilisation equipment. Continue preparing mobilisation equipment.
Concern :

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


Page 2 of 2

MILLING CAPACITY EXPANSION PROJECT


Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : April 6th, 2023

DAILY PHOTOGRAPH

PHOTOGRAPH

GENERAL ACTIVITIES

EMK TMF Site Familiarisation Continue Online & Offline training

Continue Online & Offline training

CIVIL

Continue Prepare Concrete Decking & Pad Produce Concrete Pad

Produce Concrete Decking