North-South Commuter Railway Extension

(NSCR-EX) Project
General Consultant Services

Reference No.: NSCR-GCR-N03-ZWD-TRL-DC-000709


05 April 2024

DOCUMENT TRANSMITTAL FORM


GCR Consortium

Usec. Jeremy S. Regino


Undersecretary for Railways
Department of Transportation (DOTr)
12th Floor Primex Tower, EDSA Corner,
Connecticut Street, San Juan City,
1503 Metro Manila

We transmit herewith the following document/(s):

S/N DOCUMENT NUMBER REV DOCUMENT TITLE COPY Remark

NSCR-GCR-N03-ZWD- N-03; Site Daily Activity Report


1
TRL-DC-000709 040424

For:

☐Approval ☐Action ☒Information/Record


☐Revision/Resubmission ☐Other (Specify)

NOTE:

Please acknowledge receipt by signing and returning a copy of this transmittal sheet;
Issued By:
Signature:
Name:
Position:
Date:

GCR Consortium Office: 20th and 21st Floor, Greenfield Tower, Mayflower Street, Greenfield District, Mandaluyong City, 1550 Metro
(Main Office) Manila, Philippines
Tel: +63-2-5322-3700
Oriental Consultants Global Unit 38C, 38th Floor, Rufino Pacific Tower Bldg., 6784 Ayala Avenue, Makati City 1223, Philippines
Philippine Branch Office Tel: +63-2-856-9747~9750 | Fax: +63-2-856-9751
North-South Commuter Railway Extension
(NSCR-EX) Project
General Consultant Services

This is to acknowledge that I received the abovementioned documents;

Received By: DOTR


Signature :____________________________
Name :____________________________
Position :____________________________
Date :____________________________

GCR Consortium Office: 20th and 21st Floor, Greenfield Tower, Mayflower Street, Greenfield District, Mandaluyong City, 1550 Metro
(Main Office) Manila, Philippines
Tel: +63-2-5322-3700
Oriental Consultants Global Unit 38C, 38th Floor, Rufino Pacific Tower Bldg., 6784 Ayala Avenue, Makati City 1223, Philippines
Philippine Branch Office Tel: +63-2-856-9747~9750 | Fax: +63-2-856-9751
North – South Commuter Railway Extension (NSCR-EX) Project
General Consultant
Package CP N-03: Civil Works

Site Daily Activity Report

Date: April 04, 2024 (Thursday)


Weather: Sunny

A. Manpower:

Main Sub-
Item Description Remarks
Contractor Contractor
1 Supervisors 79 14
2 Skilled Workers 144 105
3 Unskilled Workers 40 27

B. Equipment:

Main Sub-
Item Description Remarks
Contractor Contractor
1 Drilling Rig 2 1-idle, 1-working
2 Crawler Crane 3
3 Mobile Crane 5
4 Gantry Crane 10
5 Rough Terrain Crane 8
6 Excavator / Backhoe 3
7 Motor Grader 1
8 Loader 1
9 Roller Compactor 2 1-1T, 1-10T
10 Dump Truck 4
11 Boom Truck 3
12 Water Truck 2
13 Telehandler 4T 2
14 Telescopic Forklift 1
15 Desanding Machine
16 Koden Machine 1
17 Vibro Machine/Hammer 2
18 Jack Hammer 3

C. Activities:

C1. Precast Yard Area (Brgy Baliti)


• Post-concrete survey inspection for SBGs S-839/13(T1-1), S-984NB/03(T3-1), S-983NB/10(T3), S-
840/09(T1), S-835/04(T1-1).
• Pre-concrete survey inspection for SBGs S-834/02(T1M), S-1110/04(T1), S-840/08(T1), S-1112SB/01
(A3) & S-839/12(T1-2).
• Maintenance, repair & cleaning works of segments’ molds.
• Inspection of rebar cages & repair works of casted segments.
• Rebar cage assembly & fabrication for casting segments.
• Casting of segments S-834/02(T1M), S-1110/04(T1), S-840/08(T1), S-839/12(T1-2), S-1112SB/01(A3),
S-983NB/09(T3) & S-984NB/02(T3S).
C2. San Fernando Mainline / Sapang Balen Area (Area 01)
• Survey inspection of temporary casing for bored piles P900-01 & P900-04.
• Bored piling works.
• Site clearing & cutting of trees.
• Excavation for river diversion works.
• Bored pile rebar cage assembly & fabrication at fabrication area.
• Concrete pouring for bored piles P903-04 & P900-04.

C3. Angeles Station Area / Area L Sub-Camp Area (Area 02)


• Survey inspection on pier column (1st lift) at P986.
• Excavation works for PDA pile at P992.
• Rebar installation works for pile cap at P989L.
• Cutting of CSL pipes for testing at P987.
• Formworks & rebars fixing for pier column (1st lift) at P986.
• LG#1: Duct pressure test & grouting caps removal at installed segments.
• Rebar fabrication works at fabrication area.
• Concrete pouring for pier column (1st lift) at P986.

C4. Old Angeles Station Area (Area-03)


• No activity.

C5. Clark Area / Mabalacat (Area-04)


• Survey inspection on blinding concrete for pile cap at Main Station.
• Rebars installation for pier head at P1113NB.
• Bottom rebar installation for pile cap at P1115NB.
• Rebars installation for portal beam at P1120 L-R.
• LG#2: Excess epoxy clearing at installed segments.
• PT strand installation for cast-in-situ span at P1130 to P1131.
• LG#3: PT strand installation for segment at span P1133 to P1132.
• Rebar installation works for Substation SS21 tie beams.
• Temporary drainage works at East Perimeter area.
• Rebar installation, sheet pile driving & gravel bedding at Main Station footings/pile caps.

C6. Pulung Bulu, Angeles Area (Area-05)


• Lateral ties installation for pier column (2nd lift) at P964 & P967.
• Bored pile hacking at MT03 Pier 1.

D. Production & Progress:


Item Description Total 04-Apr-24 Cumulative % Complete
1 Bored Piles 1034
1.1 Area-01 (P825 - P931, Mainline) 574 2 49 8.54%
1.2 Area-02 (P973 - P992, Mainline) 216 0 216 100.00%
1.3 Area-03 (P1001 – P1035, Mainline) 210 0 100 47.62%
1.4 Area-04 (P1105 – P1142, Mainline) 278 0 278 100.00%
1.5 Area-05 (P932 – P972, Mainline) 242 0 72 29.75%
1.6 Angeles Station 86 0 86 100.00%
1.7 Angeles SigCom 45 0 45 100.00%
1.8 Angeles GenSet 4 0 4 100.00%
1.9 Clark Station 101 0 101 100.00%
1.10 Clark SigCom 27 0 27 100.00%
1.11 Clark GenSet 4 0 4 100.00%
1.12 Sub Station 19 22 0 22 100.00%
1.13 Sub Station 21 18 0 18 100.00%
1.14 Maintenance Ramp 12 0 12 100.00%
2 Pile Caps 102
2.1 Area-01 (P825 - P931, Mainline) 105 0 0 0.00%
2.2 Area-02 (P973 - P992, Mainline) 46 0 35 76.09%
2.3 Area-03 (P1001 – P1035, Mainline) 35 0 5 14.29%
2.4 Area-04 (P1105 – P1142, Mainline) 63 0 50 79.37%
2.5 Area-05 (P932 – P972, Mainline) 42 0 11 26.19%
2.6 Maintenance Ramp 3 0 1 33.33%
3 Pier Columns 88
3.1 Area-01 (P825 - P931, Mainline) 105 0 0 0.00%
3.2 Area-02 (P973 - P992, Mainline) 46 0 32 69.57%
3.3 Area-03 (P1001 – P1035, Mainline) 35 0 0 0.00%
3.4 Area-04 (P1105 – P1142, Mainline) 63 0 48 76.19%
3.5 Area-05 (P932 – P972, Mainline) 42 0 8 19.05%
3.6 Maintenance Ramp 3 0 0 0.00%
4 Pier Heads 63
4.1 Area-01 (P825 - P931, Mainline) 105 0 0 0.00%
4.2 Area-02 (P973 - P992, Mainline) 46 0 19 41.30%
4.3 Area-03 (P1001 – P1035, Mainline) 35 0 0 0.00%
4.4 Area-04 (P1105 – P1142, Mainline) 63 0 41 65.08%
4.5 Area-05 (P932 – P972, Mainline) 42 0 3 7.14%
4.6 Maintenance Ramp 3 0 0 0.00%
5 SBGs Casted 1104
5.1 SBG (10.30 m) 4,420 4 824 18.64%
5.2 SBG (6.30 m) 314 0 88 28.03%
5.3 SBG (5.10 m) 408 3 192 47.06%
6 SBGs Delivered to Site 390 25 Spans
6.1 SBG (10.30 m) 4,420 0 390 8.82%
6.2 SBG (6.30 m) 314 0 0 0.00%
6.3 SBG (5.10 m) 408 0 0 0.00%
7 SBGs Erected / Installed 376 24 Spans
7.1 SBG (10.30 m) 4,420 0 376 8.51%
7.2 SBG (6.30 m) 314 0 0 0.00%
7.3 SBG (5.10 m) 408 0 0 0.00%
• Only those areas with progress are listed here.