North-South Commuter Railway Extension

(NSCR-EX) Project
General Consultant Services

Reference No.: NSCR-GCR-N03-ZWD-TRL-DC-000705


01 April 2024

DOCUMENT TRANSMITTAL FORM


GCR Consortium

Usec. Jeremy S. Regino


Undersecretary for Railways
Department of Transportation (DOTr)
12th Floor Primex Tower, EDSA Corner,
Connecticut Street, San Juan City,
1503 Metro Manila

We transmit herewith the following document/(s):

S/N DOCUMENT NUMBER REV DOCUMENT TITLE COPY Remark

NSCR-GCR-N03-ZWD- N-03; Site Daily Activity Report


1
TRL-DC-000705 270324

For:

☐Approval ☐Action ☒Information/Record


☐Revision/Resubmission ☐Other (Specify)

NOTE:

Please acknowledge receipt by signing and returning a copy of this transmittal sheet;
Issued By:
Signature:
Name:
Position:
Date:

GCR Consortium Office: 20th and 21st Floor, Greenfield Tower, Mayflower Street, Greenfield District, Mandaluyong City, 1550 Metro
(Main Office) Manila, Philippines
Tel: +63-2-5322-3700
Oriental Consultants Global Unit 38C, 38th Floor, Rufino Pacific Tower Bldg., 6784 Ayala Avenue, Makati City 1223, Philippines
Philippine Branch Office Tel: +63-2-856-9747~9750 | Fax: +63-2-856-9751
North-South Commuter Railway Extension
(NSCR-EX) Project
General Consultant Services

This is to acknowledge that I received the abovementioned documents;

Received By: DOTR


Signature :____________________________
Name :____________________________
Position :____________________________
Date :____________________________

GCR Consortium Office: 20th and 21st Floor, Greenfield Tower, Mayflower Street, Greenfield District, Mandaluyong City, 1550 Metro
(Main Office) Manila, Philippines
Tel: +63-2-5322-3700
Oriental Consultants Global Unit 38C, 38th Floor, Rufino Pacific Tower Bldg., 6784 Ayala Avenue, Makati City 1223, Philippines
Philippine Branch Office Tel: +63-2-856-9747~9750 | Fax: +63-2-856-9751
North – South Commuter Railway Extension (NSCR-EX) Project
General Consultant
Package CP N-03: Civil Works

Site Daily Activity Report

Date: March 27, 2024 (Wednesday)


Weather: Sunny

A. Manpower:

Main Sub-
Item Description Remarks
Contractor Contractor
1 Supervisors 79 13
2 Skilled Workers 144 105
3 Unskilled Workers 40 26

B. Equipment:

Main Sub-
Item Description Remarks
Contractor Contractor
1 Drilling Rig 2 1-idle, 1-working
2 Crawler Crane 3
3 Mobile Crane 5
4 Gantry Crane 10
5 Rough Terrain Crane 8
6 Excavator / Backhoe 3
7 Motor Grader 1
8 Loader 1
9 Roller Compactor 2 1-1T, 1-10T
10 Dump Truck 4
11 Boom Truck 3
12 Water Truck 2
13 Telehandler 4T 2
14 Telescopic Forklift 1
15 Desanding Machine
16 Koden Machine 1
17 Vibro Machine/Hammer 2
18 Jack Hammer 3

C. Activities:

C1. Precast Yard Area (Brgy Baliti)


• Post-concrete survey inspection for SBGs S-837/14(T1M-2), S-1109/02(T1M), S-834/04(T1-1), S-
840/11(T1-3), S-985NB/04(T3-2), S-983NB/13(T3-2), S-984NB/05(T3-3) & S-835/06(T1-3).
• Maintenance, repair & cleaning works of segments’ molds.
• Inspection of rebar cages & repair works of casted segments.
• Rebar cage assembly & fabrication for casting segments.
C2. San Fernando Mainline / Sapang Balen Area (Area 01)
• Survey inspection of temporary casing for bored pile P903-03-06 & P900-05.
• Survey inspection of excavation for river diversion.
• Bored piling works.
• Rebar cage assembly & fabrication at fabrication area.
• Concrete pouring for bored piles P900-05 & P903-06.

C3. Angeles Station Area / Area L Sub-Camp Area (Area 02)


• Formworks installation for pile cap at P989L.
• LG#1: Duct pressure test & grouting at installed segments.
• Rebar fabrication works at fabrication area.

C4. Old Angeles Station Area (Area-03)


• No activity.

C5. Clark Area / Mabalacat (Area-04)


• Survey as-built on pier column (2nd lift) at P1109SB.
• Survey inspection on pile cap at P1108L.
• Formworks & top rebars installation for pile cap at P1108L.
• Rebar works for PDA pile at P1110SB.
• Working platform installation for pier head at P1113NB.
• Scaffolding installation for pier column at P1114NB.
• LG#2: Oil injection and excess epoxy removal at installed segments.
• Formworks installation for portal beam at P1121 L-R.
• Dolly testing & formworks dismantling for cast-in-situ span at P1130 to P1131.
• LG#3: Segment erection at span P1133 to P1132.
• Concrete blinding & rebar works for Substation SS21 footings & tie beam.
• Temporary drainage works at East Perimeter area.
• Pile excavation, soil compaction & rebar works for PDA pile at Main Station footings/pile caps.
• Concrete pouring for pile cap at P1108L.

C6. Pulung Bulu, Angeles Area (Area-05)


• No activity.

D. Production & Progress:


Item Description Total 27-Mar-24 Cumulative % Complete
1 Bored Piles 1026
1.1 Area-01 (P825 - P931, Mainline) 574 2 41 7.14%
1.2 Area-02 (P973 - P992, Mainline) 216 0 216 100.00%
1.3 Area-03 (P1001 – P1035, Mainline) 210 0 100 47.62%
1.4 Area-04 (P1105 – P1142, Mainline) 278 0 278 100.00%
1.5 Area-05 (P932 – P972, Mainline) 242 0 72 29.75%
1.6 Angeles Station 86 0 86 100.00%
1.7 Angeles SigCom 45 0 45 100.00%
1.8 Angeles GenSet 4 0 4 100.00%
1.9 Clark Station 101 0 101 100.00%
1.10 Clark SigCom 27 0 27 100.00%
1.11 Clark GenSet 4 0 4 100.00%
1.12 Sub Station 19 22 0 22 100.00%
1.13 Sub Station 21 18 0 18 100.00%
1.14 Maintenance Ramp 12 0 12 100.00%
2 Pile Caps 102
2.1 Area-01 (P825 - P931, Mainline) 105 0 0 0.00%
2.2 Area-02 (P973 - P992, Mainline) 46 0 35 76.09%
2.3 Area-03 (P1001 – P1035, Mainline) 35 0 5 14.29%
2.4 Area-04 (P1105 – P1142, Mainline) 63 1 50 79.37%
2.5 Area-05 (P932 – P972, Mainline) 42 0 11 26.19%
2.6 Maintenance Ramp 3 0 1 33.33%
3 Pier Columns 88
3.1 Area-01 (P825 - P931, Mainline) 105 0 0 0.00%
3.2 Area-02 (P973 - P992, Mainline) 46 0 32 69.57%
3.3 Area-03 (P1001 – P1035, Mainline) 35 0 0 0.00%
3.4 Area-04 (P1105 – P1142, Mainline) 63 0 48 76.19%
3.5 Area-05 (P932 – P972, Mainline) 42 0 8 19.05%
3.6 Maintenance Ramp 3 0 0 0.00%
4 Pier Heads 61
4.1 Area-01 (P825 - P931, Mainline) 105 0 0 0.00%
4.2 Area-02 (P973 - P992, Mainline) 46 0 19 41.30%
4.3 Area-03 (P1001 – P1035, Mainline) 35 0 0 0.00%
4.4 Area-04 (P1105 – P1142, Mainline) 63 0 39 61.90%
4.5 Area-05 (P932 – P972, Mainline) 42 0 3 7.14%
4.6 Maintenance Ramp 3 0 0 0.00%
5 SBGs Casted 1080
5.1 SBG (10.30 m) 4,420 0 810 18.33%
5.2 SBG (6.30 m) 314 0 88 28.03%
5.3 SBG (5.10 m) 408 0 182 44.61%
6 SBGs Delivered to Site 390 25 Spans
6.1 SBG (10.30 m) 4,420 7 390 8.82%
6.2 SBG (6.30 m) 314 0 0 0.00%
6.3 SBG (5.10 m) 408 0 0 0.00%
7 SBGs Erected / Installed 376 24 Spans
7.1 SBG (10.30 m) 4,420 0 376 8.51%
7.2 SBG (6.30 m) 314 0 0 0.00%
7.3 SBG (5.10 m) 408 0 0 0.00%
• Only those areas with progress are listed here.