Professional Documents
Culture Documents
Gush Dan Metro Applicability Report
Gush Dan Metro Applicability Report
MEMBERS OF THE STEERING COMMITTEE 4 4.5 STEP 3: MULTICRITERIA ANALYSIS - RESULTS 108
4.6 STEP 4: FINAL NETWORK CONFIGURATION 121
NOTE FROM THE CEO 5
5. PHASES 5 AND 6: FEASIBILITY STUDIES 128
1. INTRODUCTION 6
5.1 PROCESS 128
1.1 BACKGROUND: TEL AVIV MASS TRANSIT STRATEGIC PLAN 6
5.2 EXCLUSIONS 128
1.2 STRATEGIC GOALS 7
5.3 FINAL TRAFFIC FORECASTS 130
1.3 PURPOSE OF THE METRO FEASIBILITY STUDIES 7
5.4 ALIGNMENT STUDIES 133
1.4 FEASIBILITY STUDIES PHASES 8
5.5 RIGHT-OF-WAY REQUIREMENTS AND LAND ACQUISITION SUMMARY139
2. PHASE 1: DATA COLLECTION 10 5.6 STATIONS CONTEXT PLANNING 141
2.1 COLLECTION OF INPUTS DATA 10 5.7 TYPICAL STATIONS 148
2.2 MEETINGS WITH MUNICIPALITIES 15 5.8 OPERATION 160
2.3 CONCLUSION 17 5.9 PRELIMINARY MAINTENANCE PLAN 174
3. PHASES 2 AND 3: DESIGN GUIDELINES AND DETAILING OF DESIGN PARAMETERS 18 5.10 DEPOTS STUDIES 176
3.1 OVERVIEW 18 5.11 BALANCE OF POWER HV/LV OF THE METRO NETWORK 191
3.6 STATIONS 28 5.16 MASS TRANSIT NETWORK EXPANSION BEYOND 2040 202
2 3
Members of the Steering Committee
Member of NTA
Yehuda Bar-On
Nir Kugel Yehuda Bar-On
4 5
1. Introduction
1.1 Background: Tel Aviv Mass Transit Strategic Plan public transportation network:
The Metro Feasibility Study was undertaken on the basis of the Tel Aviv Mass Transit Line M1: North/South backbone passing through Tel Aviv and with 4 branches serving
Strategic Plan, finalized in 2016 and defining the shape of the future Tel Aviv Metropolitan Hertzliya/Raanana, Ramat Hasharon, Holon, Rishon Letzion, Rehovot, Ramle, etc.
Area (TAM) public transportation network for the horizon 2040, which is planned to be Line M2: East/West radial line linking the centre of Tel Aviv to Givatayim, Ramat Gan,
structured around a core of 3 Metro lines, as shown below. Petah Tikva and Rosh Hayin.
Line M3: semi-circular service of secondary development areas in the inner ring (Glilot,
Atidim, Kiryat Arye, Tel Hashomer, east-west axis through Holon and Bat Yam), also
ensuring the required connectivity between lines of the network.
These corridors were the starting point of the Metro Feasibility Studies.
6 7
1. Introduction
Studies based on the selected configuration and covering: alignment, operation, rolling
stock/depots, power supply and systems, etc.
Phase 2 – Design Guidelines: Definition of the design guidelines of the Mass Transit
System as presented in the Tel Aviv Mass Transit Strategic Plan and to generate a
sweeping view of the network and its integration with major developments.
Phase 5 & 6: Feasibility: Refine the selected alignment for each of the metro lines.
The main technical characteristics were highlighted in order to prepare the next design
stages.
The process and outputs of these 6 phases are highlighted in the present document.
8
2. Phase 1: Data Collection
This phase was marked by the collection of inputs data (mapping, statistics, projects, • Population and employment forecasts for 2010, 2030 and 2040, essential for the study,
environment, etc.), meetings with relevant municipalities and site visits. definition and comparison of alignment alternatives in particular. The examples below
are:
2.1 Collection of inputs data Population density map for 2012 based on population figures and model zoning
2.1.1 Main data Population growth map based on 2012 figures and 2040 forecasts
• Existing/planned networks complementary to Metro: bus, rail, LRT, BRT. For example:
Israel Railways network in the TAM distinguishing existing lines (black) and future
projects (blue)
RT (Red, Green, Purple, Brown) and BRT (Blue, Pink, Yellow) lines as defined in
L
the initial Mass Transit Master Plan
Figure 1. Examples of base layers
• Physical context and environment. The examples below from left to right are:
Geotechnical profiles (Red Line project)
Mapping of sensitive environment area (Environment GIS data)
• Tel Aviv transport model data and initial Metro corridors from the Tel Aviv Mass Transit 2.1.2 Main findings
Strategic Plan for a first analysis of their relevancy 2.1.2.1 Transportation analysis
The work was based on the Tel Aviv Transport Model outputs for a first picture of the 2040
traffic forecasts of the complete mass transit network in the TAM area (Metro corridors,
LRT, Israel Railways).
The model data were supposed to take into account all the future urban developments
for 2040. This first run allowed to observe the predominance of M1 corridor, backbone of
the network, and to have a base of comparison for the further phases, particularly Phase
4 where the model was to be re-run for comparing the alternative alignments.
Morning peak
Lines
boardings
Metro M1 73 300
Metro M2 32 200
Metro M3 27 400
Figure 7. Load map for the entire mass transit network (2040)
12 13
2. Phase 1: Data Collection
2.1.2.2 Metro corridors vs. existing and future densities 2.2 Meetings with municipalities
Collection of the population/employment forecasts as well as urban projects data allowed A thorough program was undertaken to meet all municipalities potentially more or less
to estimate the matching of the Mass Transit Strategic Plan Metro corridors with the 2040 covered by the Metro corridors, thus potentially involved in the Metro projects. The
densities and projects mapping of the TAM. The superimposition, illustrated below, lead municipalities are listed in the table below.
to the following conclusions:
• All 3 Metro corridors consistent with the 2040 picture, in particular population and
employment densities, mega projects and housing plans, thus confirming the N˚ Municipality
relevancy of the conclusions of the Mass Transit Strategic Plan
1 Givat Shmuel 14 Kyriat Ono
• No major questioning of the M2 corridor, only local refinements to define in Phase 4
2 Ramle 15 Lod
• Potential alternatives routes for M3 in the North and South areas
3 Raanana 16 Holon
• Need for optimization of M1: not the corridor itself but the shape of the line, in order
to reduce the share of the branches (89% of the total length) and to have branches less 4 Ramat Gan 17 Drom Hasharon
close to each other
5 Rosh Hayin 18 Beer Yaakov
6 Kyriat Ekron 19 Kfar Saba
7 Tel Aviv 20 Rehovot
8 Hertzliya 21 Ramat Hasharon
9 Ness Tziona 22 Mikve Israel
10 Bat Yam 23 Azur
11 Hod Hasharon 24 Or Yehuda
12 Petah Tikva 25 Givatayim
13 Rishon Letzion 26 Kyriat Ono
Figure 8. Superimposition of Metro corridors and 2040 urban densities and projects
14 15
2. Phase 1: Data Collection
The purpose of these meetings which were held between July and August 2017 was to: In conclusion the meetings with municipalities allowed to collect more information and
• Collect thoughts and expectation of the municipalities regarding the Metro project data regarding the local contexts along the corridors, and therefore a useful material for
the definition of the alignment alternatives in Phase 4. However, there was some limits:
• Identify all current and future major urban developments and projects (comprehensive
local plans) to feed the data collection process • Most of the ideas and requests from the city engineers were based on a micro-scale
visions (alternative routes, stations) that were not necessarily compatible with the
• Discuss the initial corridors and municipalities wishes in terms of routes, potential needs and requirements at the macro-scale of a Metro Line/network (balanced service,
station locations, etc. performance, etc.),
In addition to the comprehensive local plans, the main outputs of this process were • Therefore, in preparation for the Phase 4, it was necessary to filtering: some ideas will
summary maps of each municipality, identifying the focal points for stations and potential influence the definition of alternatives only when relevant at the scale of each line.
alternative routes reflecting the ideas expressed by the city engineers.
2.3 Conclusion
The Phase 1 process was successful with the collection of all essential data for a feasibility
study, providing a good framework for the following phases.
It particularly allowed to confirm the relevancy of the 3 Metro corridors from the Mass
Transit Strategic Plan and to have all the necessary data and information (traffic forecasts,
urban densities, projects, ideas from municipalities) that would enable to refine them in
the Phase 4 for the definition of alignment alternatives.
Figure 10. Examples of maps summarizing projects and ideas from municipalities
(Rosh Hayin and Holon)
16 17
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
After the data collection and in parallel with the elaboration of the alternatives, the
Phase 2: Design Guidelines Phase 3: DTP
definition of the design criteria for the future Metro network was done in 2 steps.
Operation and Maintenance Design
Production of Design Guidelines (Phase 2) based on international standards but consistent Operation and Maintenance Design Criteria
Guidelines
with Israeli codes/standards. They covered all relevant disciplines (infrastructure/stations,
systems, operation, environment, etc.) and focused on aspects such as intermodality, Alignment Design Guidelines Alignment Design Criteria
sustainability, urban planning. Infrastructure Design Guidelines - Infrastructure - Underground Structures
Following the high-level vision, the basic technical parameters of the Metro network (Phase Underground Structures Design Criteria
3) were defined with a more detailed approach, and these DTP associated with the design Infrastructure Design Guidelines - Elevated Infrastructure - Elevated Structures Design
guidelines allowed to have a complete set of design criteria covering the key disciplines of Structures Criteria
the project, particularly: Stations Design Guidelines Stations Design Criteria
• Alignment/tracks Depot Design Criteria
• Civil works (options for tunnels and viaducts) MEP - Station and Linear Infrastructure
• Stations, power supply and other subsystems Design Criteria
Systems - Track Design Criteria Systems -
• Operation Track Design Guidelines
Track Laying Schematics Design Criteria
• Rolling stock Systems - Power Supply Design Criteria
Systems Design Guidelines - Power Supply
• Depots and maintenance Systems - Power Supply Single Line Diagram
and Traction Power
Design Criteria
• Park and ride, etc
Systems Design Guidelines - Rolling Stock Systems - Rolling Stock Design Criteria
Systems Design Guidelines - Signalling Systems - Signalling Design Criteria
3.1 Overview
The following table provides the list of the Design Guidelines and Technical Parameters Systems Design Guidelines - PSD Systems - PSD Design Criteria
(DTP) produced for each topics. Systems Design Guidelines -
Systems - Communication - Design Criteria
Communications Systems
Rail Systems - AFC Design Guidelines Systems - AFC - Design Criteria
RAMS/Fire Life Safety
Environmental and Sustainability Environmental and Sustainability - Design
Guidelines Criteria
Park and Ride Design Criteria (common Phases 2 and 3)
18 19
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
• Operation targets • Demand analysis and corresponding headway assumptions for the 3 lines, based on the
transport model outputs processed in Phase 1 (pphpd forecasts). It helped introducing
• Production and quality of service, including safety, commercial speed, comfort, the assumption of 3 minutes headway for all lines in 2040.
regularity, availability and continuity
• Rolling stock options
• Signalling system and automation, explaining the benefits of the CBTC systems for
signalling, and the highest grade of automation (GoA4) regarding the driving. lassic width of 2.8m or large trains of 3.2m, to be chosen in Phase 4 based on
C
updated traffic forecasts,
Trains length, considering options between 108 and 126m depending of the width,
meeting the capacity target of around 1030 passengers defined in line with the
pphpd.
Running time estimation based on the length of the corridors and assuming the
targeted average speed of 35km/h.
Rolling stock fleet estimation based on the running time estimation, as illustrated
below for a 3 minutes headway.
Fleet
needed for Maintenance Reserve for
Line TOTAL
operation in (10%) operation
peak hour
M1
• Infrastructure and equipment: requirements for stations, platform screen doors,
degraded modes of service, evacuation, power supply, control center, communications, (Northeast – 30 3 1 34
depots Southeast)
• Maintenance, in particularly the 5 relevant levels. M1
(Northwest- 27 3 1 31
Southwest)
M2 26 3 1 30
M3 31 4 1 36
20 21
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
3.3.2 DTP
Following the basic requirements, the DTP completed the design criteria with the following Figure 11. Typical cross-section for twin tunnel single-track
aspects:
• Applicable codes and standards
• General design requirements:
Speed: 90km/h for design, 80km/h for operation
Curve radius: minimum in tunnel, viaduct and depot
Gradients: maximum values in line, stations, depot
Track gauge: standard 1435mm
• Alignment design requirements: detailed values for horizontal and vertical alignments.
22 23
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
3.4.2 DTP
Following the basic requirements, the DTP completed the design criteria with the following
aspects:
• Civil defense: functional and civil engineering requirements with appropriate values
• General values to take into account for the design, loads in particular
• Design criteria for materials: concrete, reinforcement steel, structural steel, etc.
• Additional design requirements for underground structures, completing chapters
initiated in Phase 2 with appropriate values and criteria Figure 13. Open Trench – typical cross-section
• Comparison of construction methods with advantages/disadvantages, e.g. between
bottom-up and top-down
24 25
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
• Fire protection
• Design loads
• General design methodology and typologies of viaducts, including comparative anlysis
Adaptability
Environment Urban
Durability to site Cost
impact impact
constrains
Prestressed
concrete beams ++ ++ + + 3
viaduct
Steel-concrete
++ +++ ++ ++ 3.5
composite viaduct
Box girder viaduct +++ +++ ++ +++ 3.5
“U-shape” viaduct
+++ +++ + + 4
– 2 types
26 27
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
28 29
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
• Advertising examples
• Maintenance requirements
CRITERIA
Track gauge 1435 mm
Trackform Ballastless
Design speed 90 km/h
Max. operating speed 80 km/h
4 % (mainline tracks)
Max. gradient running track
6 % (depot access)
536 m
Figure 20. Power collection principles Minimum horizontal curve radius main
line tracks Absolut minimum horizontal curve radius
is 150 m on viaduct and 250 m in tunnel
Train Power Supply 1500 volt DC
Third rail
Power conductor Return current through running rails or
eventually via 4th rail
Three rail system - from under
Power collection
Four rail system - side contact
Inclination of rail 1 in 20
Rail profile UIC: 54E1 or 60E1
Max +33°C
Figure 21. Example of functional dimensions of third rail equipment Climate Condition Air Temperature
Min +9°C
Max 73%
• Vehicle-arresting devices: buffer stops, wheel Climate Condition Ambient Humidity
Min 63%
stops.
Table 2. Track design parameters
32 33
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
• Design life: concrete slab 100 years, rails 35 years, fastening 30 years, etc. • Track structures for depots
• Requirements for mainline tracks in different tunnel configurations • Design requirements for rail profile, rail material
• Design requirements for continuous welded rail (CWR) and neutral rail temperature
• Design requirements for switches and crossings: crossing angle, type of rail, radius,
material and all other required parameters
• Comparative analysis confirming the recommended configuration for 3rd rail (on 1 side)
Figure 22. Single track in twin tunnels - Casted in situ slab track with DFF
Figure 23. Double track on U-shaped girder viaduct. Casted in situ plinth-track with DFF.
34 35
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
3.8 Power supply and traction power • Typologies of traction power collection: 3rd rail, 4th rail, catenary
3.8.1 Design Guidelines • Earthing and bonding principles and electromagnetic compatibility (EMC)
It first defined applicable codes and standards, specifying the priority given to Israeli
standards prior to foreign/international ones.
It then defined basic requirements regarding:
• MH/HV distribution system, considering 33kV for the MV and 162kV for the HV
• Examples of distribution patterns (antenna, loop)
Figure 26. Figure 4 Example for Earthing a typical bonding principle in bored tunnels
3.8.2 DTP
Following the basic requirements, the DTP completed the design criteria with the following
aspects:
Figure 24. Example of antenna and loop type patterns voltage level till 11, 20 or 33kV • Comparison of current collection types, confirming the recommendation of the third
rail over catenary solutions
Traction power substations: location, tension levels, rectifiers • Recommendation of 1500Vdc rather than 750Vdc for the line voltage
configuration • Power traction substations typology, to be determined during the simulation process
in next phase
• Interface to manage for the design: other systems, energy supplier requirements
• Design procedure
• Grounding system, particularly earthing and bondig, lighting protection
• Details about EMC
36 37
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
38 39
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
• Design Principles: main dimensions, aesthetic and environmental conditions, comfort • Recommendation from Operational point:
requirements • Fully automated
• Functional aspects: design and system, power (supply and collection, traction and • GoA level 4, UTO
braking)
• No driver on train attendant
• Safety and Emergency Systems, Fire Safety
• Degraded modes to cover: delocalization, temporary loss of communication, re-
• Operating modes and Control Management Systems
start on board or trackside ATC
• Performance and Maintainability
•
Degraded mode: system to cover restoration of automatic operation under
• Passenger Communication remote control of operators at OCC/BOCC
3.10.2 DTP • Distributed architecture recommended
In Phase 3, the Rolling Stock topics were completed with more detailed elements taking
into account the context of the project.
• Rolling stock options
Classic width of 2.8m or large trains of 3.2m, to be chosen in Phase 4 based on
updated traffic forecasts
Trains length, considering options between 108 and 126m depending of the width,
meeting the capacity target of around 1030 passengers defined in line with the
pphpd
• Bogies of two axels, designed for a speed of 90 Km/h and with a 30-year lifetime
warranty
• Best solution after comparing the options of: 3rd rail, 4th rail (superimposed rails) 4th
rail (rails in both sides)
Infrastructure: either 750V DC or 1500V DC from third rail Figure 27. CBTC system architecture
Power supply: 1500V DC from 4th rail (superimposed rails)
• Deployment of secondary detection
3.11 Signalling
• Use of UPS system recommended
3.11.1 Design Guidelines
It defined the basic requirements regarding:
• General performance and operation modes
• Functional aspects: ATP, ATO, ATS and depot
• Human-machine interface
• External interface: rolling stock, PSD, passenger communication, traction power, etc.
• Technical system aspects
40 41
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
3.12 PSD (Platform screen doors) 3.13 AFC (Automated Fare Collection)
3.12.1 Design Guidelines 3.13.1 Design Guidelines
It defined the basic requirements regarding: It defined the basic requirements regarding:
• General aspects • Operational aspects
• Functional: PSD sliding doors, emergency escape, platform end door, local control • Architectures
panel, control system • Technical aspects: design, ergonomics, flexibility, durability, communication,
• Technical aspects environmental, external interfaces
• Interfaces • Overall performance: management, processing, payment, ingress/egress, data
• Performance prcessing
3.12.2 DTP In Phase 3, the PSD topics were completed with more detailed elements taking into account
the context of the project.
In Phase 3, the PSD topics were completed with more detailed elements taking into account
the context of the project. • Recommended AFC technical architecture “Dedicated Level 3”
• Interfaces to consider with the following subsystems: Figure 30. Metro AFC system
42 43
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
Figure 31. Sore value card use A single Design Criteria document (common to Phases 2 and 3) was delivered for the Park
& Ride that were to be studied throughout the Metro network for attracting car users and
• Infrastructure Integration promote modal shift to the Metro. The main categories of criteria referred to the location,
the sizing and the design principles.
3.14.1 Location guidelines
The location guidelines were summarized as follows:
• P&R shall be located so as to catch trips from catchment areas,
• P&R shall be accessible from targeted catchment areas,
• P&R shall be located near major roads leading to the city centre and accommodating
a heavy traffic,
• It should be easy for users to access/egress the P&R from/to these roads,
• In case of road congestion, P&R shall be located just ahead of congestion,
Figure 32. Synthetic view of AFC equipment location in station • P&R shall be located on Metro lines that offer competitive travel times, headways,
times of operation etc. as compared to road,
• Performance criteria • P&R shall be located so as not to compete with other existing or planned P&R,
Sale Equipment: • P&R shall be located so as not to compete with local Public Transport feeder lines,
Automatic Ticketing Machines (TVM): minimum 2/station • P&R shall be located where land can be purchased/leased easily. Ideally, vacant land
Credit Loading Machines (CLM) with single-ownership should be favoured,
Point of service/sale (POS): minimum 2/station • Local plans: keeping the required distance from sensitive uses (residential, public
buildings),
Validation Equipment:
• In open spaces with low sensitivity / value adjacent to the land uses above (with priority
Automatic Fare Gate: allowance of passenger equivalent to 2 full trains to
to agricultural or open countryside land uses).
leave the station in less than 5 min
Control Equipment:
Inspector portable Unit (IPU)
Reliability, Availability, Maintainability (RAM)
44 45
3. Phases 2 and 3: Design
Guidelines and Detailing of
Design Parameters
46
4. Phase 4: Alternatives report
4.1 Process summary 4.2 Steps 1 and 2: refinement of corridors and definition of alternatives
The Phase 4 was the most strategic part of the Feasibility study as it aimed to define, As a first step, the refinement of the corridors was undertaken in order to transform each
analyse and compare robust alternative Metro alignments prior to selecting the best Mass Transit Strategic Plan corridor into a viable alignment, then called the reference
possible option for each line. alignment, taking into account of the followings:
It was generally developed in 4 steps: • Rational and efficient route serving most of the key urban centres and mega projects
• Refinement of the initial Mass Transit Strategic Plan corridors based on Phase 1 outputs identified in data collection and during meetings with municipalities,
(data, some ideas from the municipalities), • Technically feasible alignment considering the contract requirements (commercial
• Definition of technically viable alternative alignments (according to Phases 2/3 design speed, key stations locations) and the design criteria defined in Phases 2 and 3 for
criteria) for each line and model run for each alternative for comparison purpose, alignment and stations among others. The main criteria were:
• Multicriteria analysis (MCA) of the alternatives line per line and recommendations, Large curves (minimum 250m radius) in order to ensure good commercial speed
(minimum 55km/h in curve) and being suitable for both underground and elevated
• Steering Committee arbitration and choice of a final alignment for each line prior to options,
start the design in Phase 5.
Alignment as much as possible along existing roads and through public lands for
The process is summarized in the scheme below. easy accommodation of Metro stations and minimizing land takes,
Stations in straight alignment sections only.
Once the reference alignment was defined, the second step was to:
• Split it into relevant sectors, taking into account the geography, urban fabric, projects,
etc.
• Define for each sector up to 2 more alternatives routes serving various areas and
points of interest, which was mostly based on ideas expressed by the municipalities at
data collection stage, and investigations by the project team taking into account urban
densities, projects and arterial roads.
• Transformation of the alternative routes into viable Metro alignments following the
same criteria described for the reference alignment. Including the latter, there was in
average 3 alternative alignment for each geographic sector of a line.
Figure 35. Tunnelling method – mechanized with EPB TBM
The next subchapters illustrate the process and the outputs for each line.
48 49
4. Phase 4: Alternatives report
step 1 step 2
4.2.1 M1 corridor and alternatives
The refinement of the corridor of M1 took into account the drawbacks of the Mass Transit
Strategic Plan corridor identified in Phase 1 regarding the excessive share of the branches,
which accounted for 90% of the length of the line and were often too close to each other.
This configuration potentially involved:
• High length (80km) and corresponding investment cost,
• Low quality of service with no more than a train every 6 minutes on the branches
instead of 3 minutes for the central section.
Step 2: The following step was to divide the new reference alignment into 4 geographical
sectors and design alternative alignments for each sector, 12 in total with reference
alignment, as shown in the map below.
step 3
Therefore the corridor was rationalized following the following principles figure39:
• Pushing North and South splits as further as possible in order to maximize the length
of the central section, avoid duplication in the South and reduce the total length of the
line,
• Ensuring more distance between branches for improving the coverage of the line,
particularly in the North
The outputs of this work (before and after) are illustrated in the map below, with the
initial Strategic Plan corridor (length 80km) in blue colour and the optimized reference
alignment (length 72km) in black colour.
50 51
4. Phase 4: Alternatives report
Figure 41. Tel Aviv CBD and South Tel Aviv alternatives
Figure 39. North-West alternatives
52 53
4. Phase 4: Alternatives report
step 2
The reference alignment was longer than the initial corridor (24.5km instead of 20.5km)
mostly due to its extension towards Shlavim in Tel Aviv CBD, as per a request from the Tel
Aviv municipality. The route was splitted into 3 geographical sectors from West to East,
and 10 alternatives were defined in total, including the reference alignment.
Figure 42. South-West/South-East alternatives step 3
4.2.2 M2 corridor and alternatives
The same process was undertaken for M2, besides rationalization which was not necessary
for this corridor. The outputs are shown in the maps below
step 1
54 55
4. Phase 4: Alternatives report
Figure 47. Ramat Gan/Petah Tikva alternatives The new reference alignment was 25.5 km and the route was splitted into 5 geographical
sectors from North to South, and 15 alternatives were defined in total, including the
reference alignment.
56 57
4. Phase 4: Alternatives report
step 3
The maps below show the alternatives for each sector.
Table 11. Summary table of M2 alternatives Figure 53. Holon/Bat Yam alternatives
58 59
4. Phase 4: Alternatives report
60 61
4. Phase 4: Alternatives report
4.3.2 Methodology
The first step was to score evaluate all of the 37 abovementioned criteria, which were
given scores between 1 (lowest) and 5 (best).
Scale
meaning
scoring
5 best
4
3
2
1 worst
The second step was to harmonize the subtotals for each of the 7 categories at the same
for a consistent ranking.
In the third step, sensitivity tests were undertaken in order to check how the ranking
changed when applying different combinations of weights between categories.
The subtotals were different due to the numbers of criteria in each category (eg. up to 7
for Urban Context and Network Performance vs. only 2 for Costs/Economic Performance).
For consistency, these subtotals were brought back to a common scale of 100 taking into
account of the number of criteria and allowing to compare all alternatives on the same
basis.
The aggregation of the 7 subtotals gave the Grand total score for each alternative, which
was also brought back to a scale of 100. The outputs were displayed in two steps:
1. Aggregated score for each alternative calculated with a specific weighting giving
more importance to some categories of criteria such as urban context, network
performance, costs and technical issues over environmental criteria which are not
critical for metro infrastructures likely to run mostly underground. Since there can
be numerous weights combinations between key categories, it has been decided
to consider an average between combinations elaborated by all members of the
project team, as shown in the table below.
62 63
4. Phase 4: Alternatives report
Table 12. Calculation of the average weights used for the MCA grand totals
A1 A2
Section length (km) 10.5 9.7
Section number of stations 7 7
2. Sensitivity tests applying a very high weight of 40% to one of the 5 key categories,
Total line 778,000 758,000
with a parallel reduction of the weight of all other categories proportionally to the Population coverage
Section 83,000 60,000
average weights shown in the above table. The performed sensitivity tests are
detailed below. Employment Total line 546,000 539,000
coverage Section 29,000 20,000
Focus on Focus on
Focus on M3, Rail, BRT Pink
Focus on Service/ Costs/ Focus on Section interconnections M3, BRT Pink line
Urban and Yellow lines
Social/ network economic Technical
context and
societal performance performance issues
planning Table 1. Main alternatives characteristics for North-West sector
and operation
Open areas and nature values 4% 4% 4% 4% 4% North-East (Kfar Saba branch)
Population and human
4% 4% 5% 4% 4%
environment
Urban context and planning 40% 11% 12% 11% 11%
Social/societal 13% 40% 14% 13% 12%
Service/network performance 16% 17% 40% 17% 16%
Costs/economic performance 13% 14% 15% 40% 13%
Technical issues 10% 10% 10% 10% 40%
Total 100% 100% 100% 100% 100%
64 65
4. Phase 4: Alternatives report
Table 2. Main alternatives characteristics for North-East sector Table 4. Main alternatives characteristics for the Tel Aviv CBD sector
C1 C2 C3 B1 B2 B3 B4
Section length (km) 7.2 7.2 9.3 Section length (km) 9,550 9,550 9,800 12,750
Section number of stations 7 7 8 Section number of stations 9 9 9 12
Population Total line 778,000 778,000 861,000 Population Total line 445,000 470,000 481,000 462,000
coverage Section 122,000 126,000 205,000 coverage Section 214,000 236,000 236,000 231,000
Employment Total line 546,000 506,000 602,000 Employment Total line 290,000 321,000 328,000 300,000
coverage Section 227,000 189,000 283,000 coverage Section 50,000 82,000 84,000 60,000
Rail, M2, LRT Rail, M2, LRT M3, LRT M3, LRT
Rail, M2, LRT M3, BRT M3, BRT
Green, Purple Green, Purple Section interconnections Purple, BRT Purple, BRT
Section interconnections Green, Purple Yellow Yellow
and Red, BRT and Red, BRT Yellow Yellow
and Red
Yellow and Blue Yellow and Blue
Table 5. Main alternatives characteristics for the central sector
Table 3. Alternatives main characteristics for Tel Aviv Center sector
66 67
4. Phase 4: Alternatives report
C1 C2 C3 B1 B2 B3 B4
Section length (km) 8,300 9,400 7,500 Section length (km) 3,200 3,200 4,500 12,750
Section number of stations 7 8 7 Section number of stations 4 4 5 12
Population Total line 445,000 444,000 417,000 Population Total line 345,000 345,000 352,000 462,000
coverage Section 68,000 67,000 46,000 coverage Section 24,000 24,000 33,000 231,000
Employment Total line 290,000 295,000 282,000 Employment Total line 169,000 170,000 189,000 300,000
coverage Section 15,000 20,000 9,000 coverage Section 25,000 25,000 44,000 60,000
Section interconnections None Israel Railways None M3, LRT
LRT Green, LRT Green, LRT Green,
Section interconnections Purple, BRT
Table 6. Alternatives main characteristics for the East sector BRT Yellow BRT Yellow BRT Yellow
Yellow
C1 C2 C3
A1 A2 A3
Section length (km) 7,850 8,800 10,900
Section length (km) 4,000 5,950 3,450
Section number of stations 6 7 8
Section number of stations 3 5 2
Population Total line 345,000 300,000 358,000
Population Total line 345,000 344,000 357,000
coverage Section 114,000 69,000 127,000
coverage Section 22,000 20,000 33,000
Employment Total line 169,000 189,000 173,000
Employment Total line 169,000 202,000 168,000
coverage Section 63,000 82,000 68,000
coverage Section 12,000 44,000 10,000
Rail, Metro M2,
Railways, M1, Metro M1, LRT Railway, Metro Metro M2, LRT Metro M2, LRT
Section interconnections LRT Red and
Section interconnections LRT Green, BRT Green, BRT M1, LRT Green, Red and Purple Red and Purple
Purple
Yellow Yellow and Pink BRT Yellow
Table 9. Alternatives main characteristics for East 1 sector
Table 7. Main alternatives characteristics for Hertzliya sector
68 69
4. Phase 4: Alternatives report
Table 12. Generated daily trips per mode for all alternatives
70 71
4. Phase 4: Alternatives report
Modal split This table display the model outputs for the North-West alternatives.
The global modal share. It does not vary significantly in the different M1 alternatives. The A1 A2
majority of the trips are done with private cars but the public transport trips account for
more than 40 % of all trips, mostly mass transit modes and bus. Morning peak max 17,900 17,800
M1 load Center: 80,600 Center: 82,300
Daily mean
Branches: 24,600 Branches: 25,600
8.9 Average trip All modes 8.6 min 8.5 min
Bus duration Metro 7.1 min 7.0 min
12.8 Transfer rate
PT 1.86 1.86
Rail MT 1.89 1.9
Car (total) 80,937,000 80,961,000
58.4 Daily veh.km Metro (studied
19.9 Car
section)
100 100
MT
Bus 13,976,000 13,969,000
BRT 9,702,000 9,753,000
Passenger*km
MT 4,618,000 4,603,000
(daily)
Rail 21,828,000 21,806,000
Car 90,114,000 90,141,000
Traffic forecasts Table 13. Traffic forecast comparison for the North-West sector
The map below shows the loads for the reference alignment and all the indicators necessary
This table display the model outputs for the North-West alternatives.
to the multicriteria analysis are then presented and compared for the alternatives of each
sector. B1 B2 B3 B4
Morning peak
17,900 17,900 25,800 25,800
max
M1 load Center: 80,600 Center: 86,900 Center: 96,200 Center: 96,100
Daily mean Branches: Branches: Branches: Branches:
24,600 25,700 31,900 32,200
Average trip All modes 8.6 min 8.5 min 8.3 min 8.4 min
duration Metro 7.1 min 7.1 min 6.8 min 6.8 min
PT 1.86 1.86 1.89 1.89
Transfer rate
MT 1.89 1.89 1.96 1.97
Car (total) 80,937,000 80,941,000 80,830,000 80,946,000
Daily veh.km Metro (studied
230 230 200 180
section)
Bus 13,976,000 13,965,000 13,883,000 13,931,000
BRT 9,702,000 9,776,000 9,986,000 9,791,000
Passenger*km
MT 4,618,000 4,593,000 4,578,000 4,564,000
(daily)
Rail 21,828,000 21,815,000 21,632,000 21,670,000
Figure 56. M1 loads and passenger movements for the reference alignment Car 90,114,000 90,122,000 90,018,000 90,140,000
Table 14. Traffic forecast comparison for North Kfar Saba sector
72 73
4. Phase 4: Alternatives report
This table display the model outputs for the Tel Aviv CBD alternatives. This table display the model outputs for the southern alternatives.
C1 C2 C3 F1 F2 F3 F4
Morning Morning peak
17,900 17,700 19,800 17,900 17,800 18,100 18,000
peak max max
M1 load Center: 80,600 Center: 80,900 Center: 78,300 M1 load Center: 80,600 Center: 80,100 Center: 81,800 Center: 81,300
Daily mean Branches: Branches: Branches: Daily mean Branches: Branches: Branches: Branches:
24,600 24,600 24,400
24,600 24,800 25,300 27,400
Average trip All modes 8.6 min 8.5 8.5
Average trip All modes 8.6 min 8.5 min 8.5 min 8.5 min
duration Metro 7.1 min 7.0 7.1
duration Metro 7.1 min 7.1 min 7.0 min 7.0 min
PT 1.86 1.86 1.87
Transfer rate PT 1.86 1.85 1.87 1.86
MT 1.89 1.90 1.91 Transfer rate
MT 1.89 1.89 1.91 1.90
Car (total) 80,937,000 80,918,000 80,939,000
Car (total) 80,937,000 80,938,000 80,859,000 80,888,000
Daily veh.km Metro
(studied 140 140 190 Daily veh.km Metro (studied
90 100 110 110
section) section)
Bus 13,976,000 13,957,000 13,927,000 Bus 13,976,000 13,985,000 13,888,000 13,948,000
BRT 9,702,000 9,662,000 10,127,000 BRT 9,702,000 9,732,000 9,936,000 10,112,000
Passenger*km Passenger*km
MT 4,618,000 4,640,000 4,531,000 MT 4,618,000 4,535,000 4,540,000 4,420,000
(daily) (daily)
Rail 21,828,000 21,816,000 21,750,000 Rail 21,828,000 21,861,000 21,794,000 21,827,000
Car 90,114,000 90,089,000 90,117,000 Car 90,114,000 90,114,000 90,031,000 90,057,000
Table 15. Traffic forecast comparison for the North-West sector Table 17. Traffic forecast comparison for South of TAM sector
This table display the model outputs for the South Tel Aviv alternatives.
D1 D2 D3
Morning 17,900 16,700 25,600
peak max
M1 load Center: 80,600 Center: 76,700 Center: 91,900
Daily mean Branches: Branches: Branches:
24,600 25,300 23,800
Average trip 8.6 min 8.6 min 8.6 min 8.5
duration 7.1 min 7.2 min 7.1 min 7.1
1.86 1.85 1.87 1.87
Transfer rate
1.89 1.89 1.91 1.91
80,937,000 80,971,000 80,908,000 80,939,000
Daily veh.km
260 230 300 190
13,976,000 13,990,000 13,976,000 13,927,000
9,702,000 9,407,000 10,515,000 10,127,000
Passenger*km 4,618,000 4,806,000 4,528,000 4,531,000
(daily)
21,828,000 21,927,000 21,533,000 21,750,000
90,114,000 90,149,000 90,092,000 90,117,000
Table 16. Traffic forecast comparison for North Kfar Saba sector
74 75
4. Phase 4: Alternatives report
Table 18. Generated daily trips per mode for all alternatives
Modal split
Figure 56. M1 loads and passenger movements for the reference alignment
76 77
4. Phase 4: Alternatives report
This table display the model outputs for the Tel Aviv CBD alternatives. This table display the model outputs for the Sirkin/Rosh Hayin alternatives.
For all alternatives, average trip durations and transfer rates do not vary significantly.
A1 A2 A3
The other figures have small variations among the alternatives: C3 has the lowest load
Morning (both maximum and mean), the lowest mass transit patronage and the highest car veh.
14,500 12,800 12,500
M2 load peak max km, while C1 and C2 has slightly better figures.
Daily mean 37,600 33,700 33,800
Average trip All modes 19.0 min 19.1 min 19.1 min
duration C1 C2 C3
Metro 13.3 min 13.5 min 13.5 min
PT 1.86 1.88 1.88 Morning
Transfer rate 14,500 14,400 14,200
M2 load peak max
MT 1.91 1.95 1.95
Daily mean 37,600 38,000 36,700
Car (total) 80,888,000 80,893,000 80,888,000
Average trip All modes 19.0 min 19.0 min 19.0
Metro
Daily veh.km duration Metro 13.3 min 13.3 min 13.2
(studied 110 120 120
section) PT 1.86 1.86 1.86
Transfer rate
Bus 13,927,000 13,951,000 13,948,000 MT 1.91 1.90 1.9
BRT 10,200,000 10,265,000 10,286,000 Car (total) 80,888,000 80,893,000 80,913,000
Passenger*km Metro
MT 4,518,000 4,684,000 4,690,000 Daily veh.km
(daily) (studied 170 190 150
Rail 21,866,000 21,688,000 21,679,000
section)
Car 90,054,000 90,053,000 90,054,000
Bus 13,927,000 13,911,000 13,951,000
Table 20. Traffic forecast comparison for the Tel Aviv CBD sector BRT 10,200,000 10,272,000 10,048,000
Passenger*km
This table display the model outputs for the Ramat Gan/Petah Tikva alternatives. MT 4,518,000 4,497,000 4,491,000
(daily)
Rail 21,866,000 21,861,000 21,889,000
B1 B2 B3 B4 Car 90,054,000 90,052,000 90,077,000
Morning peak
14,500 13,600 14,100 14,800 Table 22. Traffic forecast comparison for Eastern sector
M2 load max
Daily mean 37,600 38,400 39,000 40,000
Average trip All modes 19.0 min 19.1 min 19.2 min 19.0 min
duration Metro 13.3 min 13.4 min 13.4 min 13.4 min
PT 1.86 1.87 1.87 1.85
Transfer rate
MT 1.91 1.92 1.92 1.89
Car (total) 80,888,000 80,914,000 80,959,000 80,889,000
Daily veh.km Metro (studied
200 200 200 260
section)
Bus 13,927,000 13,922,000 13,930,000 13,858,000
BRT 10,200,000 10,270,000 10,340,000 10,492,000
Passenger*km
MT 4,518,000 4,465,000 4,413,000 4,400,000
(daily)
Rail 21,866,000 21,852,000 21,851,000 21,909,000
Car 90,054,000 90,061,000 90,114,000 90,050,000
78 79
4. Phase 4: Alternatives report
Modal split
Ramat Gan /
Tel Aviv / Sirkin / Rosh
Sector Global Petah Tikva
Givatayim sector Hayin sector
sector
All
Zones
zones
80 81
4. Phase 4: Alternatives report
This table display the model outputs for the Hertzliya sector alternatives. The highest mean This table display the model outputs for the North Tel Aviv sector alternatives. The size
daily load is reached with the reference alignment, which also has the lowest number of of the sector makes the general traffic characteristics of the alternatives similar. B1 and
car veh.km and car passenger.km. In terms of average trip duration, it is also the best B2 only differ by 1 station. For B3, the additional station and the better coverage induce
alternative. This alignment however has a slightly higher mean transfer rate than A2 and A3. a small load increase. However, the length increase induces more veh.km and a larger
average trip duration for passengers.
A1 A2 A3 B1 B2 B3
Morning Morning peak
10,100 10,000 10,100 10,100 10,100 10,100
M3 load peak max M3 load max
Daily mean 36,600 33,000 31,700 Daily mean 36,600 36,900 37,200
Average trip All modes 19.3 min 19.3 min 19.4 min Average trip All modes 19.3 19.2 19.3
duration Metro 13.3 min 13.4 min 13.5 min duration Metro 13.3 13.3 13.4
PT 1.91 1.91 1.90 PT 1.91 1.91 1.91
Transfer rate Transfer rate
MT 2.0 1.99 1.97 MT 2.0 2.0 2.0
Car (total) 81,039,000 81,054,000 81,118,000 Car (total) 81,039,000 81,051,000 81,041,000
Daily veh.km Metro Daily veh.km Metro (studied
(studied 90 120 60 80 80 110
section)
section) Bus 14,080,000 14,087,000 14,068,000
Bus 14,080,000 14,126,000 14,131,000 BRT 10,042,000 10,044,000 10,194,000
BRT 10,042,000 10,061,000 9,871,000 Passenger*km
Passenger*km MT 4,428,000 4,429,000 4,414,000
MT 4,428,000 4,430,000 4,520,000 (daily)
(daily) Rail 21,856,000 21,853,000 21,850,000
Rail 21,856,000 21,894,000 21,934,000 Car 90,196,000 90,211,000 90,205,000
Car 90,196,000 90,212,000 90,276,000
Table 26. Traffic forecast comparison for North Tel Aviv sector
Table 25. Traffic forecast comparison for Hertzliya sector
82 83
4. Phase 4: Alternatives report
This table display the model outputs for the East 1 sector alternatives. C2 is better with a This table display the model outputs for the East 2 sector alternatives. The 3 alternatives
higher morning peak maximum and higher daily mean, and also the lowest average trip have close figures. For passenger.km, although D1 has more MT passenger.km, its number
duration. C3 has lower metro load figures but is the best in terms of transfer rate and car of car passenger.km is also higher due to a lower usage of the BRT. D2 and D3 are close.
usage.
C1 C2 C3 D1 D2 D3
Morning Morning peak
10,100 11,100 8,000 10,100 10,800 11.000
M3 load peak max M3 load max
Daily mean 36,600 37,700 31,800 Daily mean 36,600 36,900 34,600
Average trip All modes 19.3 19.1 19.2 Average trip All modes 19.3 19.0 19.0
duration Metro 13.3 13.3 13.4 duration Metro 13.3 13.2 13.3
PT 2.0 2.01 1.93 PT 2.0 2.01 2.01
Transfer rate Transfer rate
MT 1.91 1.91 1.87 MT 1.91 1.92 1.91
Car (total) 81,039,000 80,946,000 80,893,000 Car (total) 81,039,000 80,945,000 80,925,000
Metro Daily veh.km Metro (studied
Daily veh.km 80 120 170
(studied 160 180 220 section)
section) Bus 14,080,000 13,993,000 13,933,000
Bus 14,080,000 13,987,000 13,896,000 BRT 10,042,000 10,557,000 10,694,000
BRT 10,042,000 10,215,000 10,518,000 Passenger*km
MT 4,428,000 4,174,000 4,194,000
Passenger*km (daily)
MT 4,428,000 4,374,000 4,413,000 Rail 21,856,000 21,842,000 21,858,000
(daily)
Rail 21,856,000 21,834,000 21,823,000 Car 90,196,000 90,099,000 90,076,000
Car 90,196,000 90,113,000 90,047,000
Table 28. Traffic forecast comparison for East 2 sector
Table 27. Traffic forecast comparison for East 1 sector
84 85
4. Phase 4: Alternatives report
This table display the model outputs for the South sector alternatives. 4.4.3 Urban development and land use
In this sector, the reference alignment has better traffic figures than the 2 other alternatives: Based on the numerous data collected in Phase 1 and on the expertise of the team, a
although it has the shortest length, its daily mean load in M3 is significantly higher than the thorough urban analysis of the 2040 horizon was provided for all alternatives of each line,
load of E2 and E3. It also allows a shorter commute in average, as its mean trip durations particularly focusing on:
are slightly lower. • Land use in the areas potentially served by the Metro, particularly in the comprehensive
The observation of the southern part of the line for the 3 alternatives shows that the load local outline plans collected from the municipalities.
is the highest in the reference alignment, in both directions. • Development areas, mega projects and points of interests located within the 800m
catchment area of each alternative.
For these 2 items feeding the MCA, the work is here summarized with a mapping.
E1 E2 E3
4.4.3.1 M1 alternatives
Morning
10,100 10,000 9,900 Land use and statutory aspects
M3 load peak max
Daily mean 36,600 33,800 30,800 The 4 maps below give an overview of the expected land status in 2040 according to the
All modes 19.3 19.3 19.4 comprehensive local outline plans for each of the sectors covered by the alternatives of
Average trip
M1.
duration Metro 13.3 13.5 13.6
PT 2.0 1.99 1.97
Transfer rate
MT 1.91 1.9 1.89
Car (total) 81,039,000 81,090,000 81,041,000
Daily veh.km Metro
(studied 80 120 130
section)
Bus 14,080,000 14,100,000 14,087,000
BRT 10,042,000 10,019,000 9,819,000
Passenger*km
MT 4,428,000 4,505,000 4,684,000
(daily)
Rail 21,856,000 21,861,000 21,868,000
Car 90,196,000 90,248,000 90,193,000
86 87
4. Phase 4: Alternatives report
Figure 61. Comprehensive Local Outline Plans for the Tel Aviv South sector
Figure 60. Comprehensive Local Outline Plans for the Tel Aviv CBD sector
Figure 62. Comprehensive Local Outline Plans for the South of TAM sector
88 89
4. Phase 4: Alternatives report
Figure 65. Points of Interest and new developments in Tel Aviv CBD and South Tel Aviv sectors
Figure 64. Points of Interest and new development areas in the North area of M1
90 Figure 66. Points of Interest and new developments in South-West and South-East sectors
91
4. Phase 4: Alternatives report
Figure 70. Points of Interest and new developments in the Tel Aviv CBD sector
Figure 71. Points of Interest and new developments in the Ramat Gan/Petah Tikva sector
Figure 68. Sirkin/Rosh Hayin sector Land Use Map (in black)
92 93
4. Phase 4: Alternatives report
Figure 72. Points of Interest and new developments in the Sirkin/Rosh Hayin sector
94 95
4. Phase 4: Alternatives report
Figure 79. Points of Interest and new developments in North Tel Aviv sector
96 97
4. Phase 4: Alternatives report
Figure 83. Potential land take in built Figure 84. Potential land take in built
areas - C1 areas - C2
98 99
4. Phase 4: Alternatives report
Figure 88. M1 North-West branch on the map of rivers and streams from TAMA 34/B/3
Figure 89. M2 Tel Aviv CBD on the map of overflowing area and streams from TAMA 34/B/3
100 101
4. Phase 4: Alternatives report
Figure 90. M2 Ramat Gan/Petah Tikva sector on the map of suspected soil and
groundwater pollution
Figure 92. M1 South of Tel Aviv sector on the map of heritage and archaeological sites
Figure 91. M1 North-East alternatives on the map of suspected soil and groundwater pollution
102 103
4. Phase 4: Alternatives report
Figure 93. M1-All Alternatives on geological map Figure 95. M3-All Alternatives on geological map
104 105
4. Phase 4: Alternatives report
M3 mapping
106 107
4. Phase 4: Alternatives report
108 109
4. Phase 4: Alternatives report
4.5.1.3 Tel Aviv CBD alternatives 4.5.1.4 South of Tel Aviv alternatives
The re-scaled grand totals and aggregated scores calculated with a similar weight for The re-scaled grand totals and aggregated scores calculated with a similar weight for
each category are displayed in the table below. Although C1 performs better regarding each category are displayed in the table below. It show that D1 performs better in most
implementation constraints, C2 would have more benefits in terms of network efficiency of the key aspects, particularly in terms of service of strategic urban areas (H500 in Holon,
and operation (outputs of the transport model) and would be less costly due to its passage etc.), network efficiency and relatively low engineering constraints compared with the 2
to the east of the Ayalon corridor. alternatives. D2 only performs better regarding costs.
The following table shows the variation of the aggregated scores and ranking resulting
The following table shows the variation of the aggregated scores and ranking resulting
from 5 sensitivity tests.
from 5 sensitivity tests.
Weights combinations C1 C2 C3
Weights combinations D1 D2 D3
Focus on costs and technical 68 72 63
Focus on costs and technical 66 63 63
Focus on urban, social and network performance 67 69 65
Focus on urban, social and network performance 64 59 63
Focus on network performance 66 69 64
Focus on network performance 63 58 65
MT Strategic Plan weights 66 71 61
MT Strategic Plan weights 64 63 66
Average of all weights 67 70 63
Average of all weights 64 61 64
C1 was initially recommended as it provided a better access to the CBD despite lower
scores. Further Steering Committee arbitration led to select C2 and the east of the D1 selected as the best alignment.
Ayalon corridor, shifting the interchange M1/M2 at Hashalom East (Yigal Alon boulevard).
110 111
4. Phase 4: Alternatives report
Taking into account the scores and traffic forecasts, the selected option was eventually to
combine sections F1 and F4 alignments and having an alignment ending in Lod.
112 113
4. Phase 4: Alternatives report
Categories of criteria B1 B2 B3 B4
Categories of criteria C1 C2 C3
1. Open areas and nature values 88 88 84 84
1. Open areas and nature values 68 56 76
2. Human environment 93 87 77 90
2. Human environment 80 77 77
3. Urban context and planning 57 60 53 53
3. Urban context and planning 66 71 63
4. Social/societal 67 73 70 73
4. Social/societal 77 80 60
5. Service/network performance and operation 77 69 60 69
5. Service/network performance and operation 71 80 66
6. Costs/economic performance 70 80 80 20
6. Costs/economic performance 70 60 100
7. Technical issues 80 64 60 68
7. Technical issues 64 64 60
Aggregated score 73 72 67 60
Aggregated score 71 71 71
The following table shows the variation of the aggregated scores and ranking resulting
from the 5 sensitivity tests. The following table shows the variation of the aggregated scores and ranking resulting
from 5 sensitivity tests.
Sensitivity Tests B1 B2 B3 B4
40% Urban context and planning 68 68 63 58 Sensitivity Tests C1 C2 C3
40% Social/societal 71 72 68 63 40% Urban context and planning 69 71 69
40% Service/network performance and operation 74 71 65 62 40% Social/societal 72 74 68
40% Costs/economic performance 72 74 70 50 40% Service/network performance and operation 71 73 70
40% Technical issues 75 69 65 62 40% Costs/economic performance 70 68 79
The poor scores of alternative F2 lead to assume that scores of F4 would be higher in case 40% Technical issues 69 69 68
it would not share the same alignment with D2 towards Ramle center.
C2 was selected as the preferred alignment in the East sector, particularly for
Figure 99. Combination B1/B2
the connection with Israel Railways and the service of the employment area of
Better scoring for B1 but the arbitration lead to introduce a combination between B1 for North Rosh Hayin.
the west part and B2 for the east part in Petah Tikva.
114 115
4. Phase 4: Alternatives report
4.5.3 MCA outputs for M3 A1 is the best alignment, but arbitration in favour of the service of Hertzliya Marina
4.5.3.1 North sector alternatives and connection with Israel railways in Hertzliya, leading to develop and select a
readjusted version of A2.
The re-scaled subtotals and the aggregated scores including the average weights for all categories
are displayed in the table below. While A3 performed poorly in terms of urban potential and 4.5.3.2 North Tel Aviv sector alternatives
traffic forecasts and other model outputs, A1 generally had best scores than A2 in many aspects: The re-scaled subtotals and the aggregated scores including the average weights for
urban planning and traffic in particular, as well as cost (shorter route than A2 initially).
all categories are displayed in the table below. B2 made a major difference with the
technical issues (largely less narrow roads and insertion constraints than B2 and B3) and
Categories of criteria A1 A2 A3
corresponding cost estimates.
1. Open areas and nature values 84 72 84
2. Human environment 73 67 77
3. Urban context and planning 73 57 70 Categories of criteria B1 B2 B3
4. Social/societal 47 60 50 1. Open areas and nature values 96 96 84
5. Service/network performance and operation 77 60 51 2. Human environment 87 83 73
6. Costs/economic performance 70 40 90 3. Urban context and planning 53 53 67
7. Technical issues 76 80 64 4. Social/societal 53 50 67
Overall scores 70 60 60 5. Service/network performance and operation 66 63 60
The following table shows the variation of the aggregated scores and ranking resulting 6. Costs/economic performance 70 90 50
from 5 sensitivity tests. 7. Technical issues 88 100 84
Overall scores 68 72 66
Sensitivity tests A1 A2 A3
40% Urban context and planning 71 59 67 The following table shows the variation of the aggregated scores and ranking resulting
40% Social/societal 64 60 62 from 5 sensitivity tests.
40% Service/network performance and operation 71 60 63
Sensitivity tests B1 B2 B3
40% Costs/economic performance 70 54 72
40% Urban context and planning 64 67 66
40% Technical issues 72 66 66
40% Social/societal 64 66 66
40% Service/network performance and operation 68 70 65
40% Costs/economic performance 69 77 62
40% Technical issues 74 81 71
A1 is the best alignment, but arbitration in favour of the service of Hertzliya Marina and
connection with Israel railways in Raanana, leading to develop and select a readjusted
version of A2.
B2 is the best alignment.
116 117
4. Phase 4: Alternatives report
Advantage C1 but due to uncertain technical feasibility along the Road 4 corridor and
absence of direct connection with the Petah Tikva branch of the Red Line, this alternative
was discarded and C2 was eventually selected with adjustments such as the service of
Beilinson Hospital.
Sensitivity tests E1 E2 E3 This modification followed a request from the Tel Aviv District to serve the Interdisciplinary
College of Hertzliya, despite it being away from the chosen alignment serving the city
40% Urban context and planning 66 61 57
centers of Hertzliya and Raanana.
40% Social/societal 66 59 54
40% Service/network performance and operation 71 58 54
40% Costs/economic performance 70 62 51
40% Technical issues 74 59 59
120 121
4. Phase 4: Alternatives report
4.6.2.2 M1: shift from Glilot to Kiryat Shaul The characteristics of this extension are:
The background was the request from the Tel Aviv District to shift the M1 alignment away from • Additional length: 3.3km (final M2 length 29km)
Glilot (initial decision based on urban planning and interchange potential with M3) and consider a • 2 additional stations: Nes Lagoyim and Wolfson Hospital
straighter route through Kiryat Shaul cemetery, where the connection with M3 would move as well.
• Wolfson Hospital station on the East side of the Ayalon expressway, adjacent to Edith
Wolfson Medical Centre.
4.6.2.4 M3: service of Beilinson Hospital
While the initially selected alignment for M3 had a relatively straight route between Kiryat
Arye and Bar Ilan University, the Steering Committee decided to make a detour to the East
in order to serve Beilinson Hospital.
Figure 102. Initial M1 alignment and requested modification through Kiryat Shaul
122 123
4. Phase 4: Alternatives report
4.6.2.5M3: Bar Ilan/Kiryat Ono areas The principles considered and discussed for this Airport link are as follows:
The Steering Committee decision was to move the M3 alignment to provide service to • Length around 4km (to be confirmed precisely according to necessary inputs data such
Kiryat Ono and the west of Petah Tikva, instead of Bar Ilan University which is already as land availability for Airport station and various constraints),
served by M2. • Shuttle service between Bikat Ono and Airport Terminal 3, no intermediate stop,
allowing a very attractive commercial speed,
• Independent from M3 with an optimal connection in Bikat Ono for very short transfer
(side by side or superimposed platforms, as seen in such as Singapore Green line, Paris-
Orly Airport shuttle).
4.6.2.7 Final network configuration for Phase 5
The figure below shows the network configuration taking into account the changes depicted
above.
Figure 105. Initial M3 alignment and requested modification through Kiryat Ono
124 125
4. Phase 4: Alternatives report
The 2 plans below summarizes all the work undertaken in Phase 4, from the definition of
numerous alternatives for each Metro line towards the preferred 3 alignments selected at
the end of the process for further study in Phase 5.
In the background, the initial corridors from the Mass Transit Strategic Plan are visible in
dotted lines.
Figure 108. From Strategic Plans and alignment alternatives to the final configuration
126
5. Phases 5 and 6:
Feasibility Studies
5.1 Process • Relocation of the maintenance depot of M2 from the initially selected site in North-East
Based on the network configuration selected at the end of the Phase 4, as well as the Petah Tikva to Rosh Hayin, following a request from the Centre District.
design criteria issued in Phase 3, detailed studies were undertaken in Phases 5 and 6 for
completing the Metro feasibility. These studies covered the following areas:
• Detailed alignment of the 3 lines: horizontal and vertical alignments, cross sections
• Stations studies: urban context planning, sizing principles and examples, design of 3
typical stations (elevated, underground, interchange)
• Depots studies: choice of sites, sizing and functional layouts for each line
• Preliminary Operation Plan for defining all the service characteristics such as headway,
commercial speed, fleet sizing, etc.
• Preliminary Maintenance Plan
• Sizing of the needs for power supply
• Cost estimates for investment (CAPEX) and operation (OPEX)
• Initial Park and Ride study: sites selection, basic sizing, design principles
• Analysis of the option to incorporate exterior utilities in Metro tunnels
• Implementation schedule for the whole Metro project
• Scenarios for expansion of the Mass Transit network beyond 2040 with new
infrastructures. Figure 110. Locations of current (1) and future (3) depots sites of M2
5.2 Exclusions
• Feasibility study of the Airport link connecting M3 in Or Yehuda and the Terminal 3 of
All aspects of the Feasibility Studies are covered here, except the following 3 tasks:
Ben Gourion Airport, recent addition to the scope of the study.
• Final update of M1 in order to reflect configuration changes requested at the end of the
Phase 5, which shall include route changes in Hod Hasharon (North-West branch) and
Beer Yaakov/Ramle area (South-East branch) involving new alignment and different
stations locations.
128 129
5. Phases 5 and 6:
Feasibility Studies
5.3.2 M1
Based on the outputs of the Tel Aviv transport model run of the full Metro + LRT + rail
network, the maximum traffic in the morning peak hour for the M1 is 23,350 passengers
per hour and direction, as illustrated in the diagram below. This figure was then used for
defining the headway, length of trains and size of fleet as part of the Preliminary Operation
Plan.
This figure of 23,350 is used for defining the headway, length of trains and size of fleet as
part of the Preliminary Operation Plan.
130 131
5. Phases 5 and 6:
Feasibility Studies
Characteristics
5.3.4 M3
• Length: 74.1 km
Based on the outputs of the Tel Aviv transport model run of the full Metro + LRT + rail
• 100%
network, the maximum traffic in the morning peak hour for the M2 is 12,300 passengers
undeground
per hour and direction, as illustrated in the diagram below.
• Total stations: 55
132 133
5. Phases 5 and 6:
Feasibility Studies
134 135
5. Phases 5 and 6:
Feasibility Studies
Characteristics
• Length: 29 km
• Length underground: 24.9 km
• Length elevated: 4.1 km
• Total stations: 26 Characteristics
• Underground stations: 23 • Length: 36 km
• Elevated stations: 3 • 100%
underground
• Total stations: 27
Figure 114. Overall view M2
136 137
5. Phases 5 and 6:
Feasibility Studies
138 139
5. Phases 5 and 6:
Feasibility Studies
• Land acquisitions in green and other open areas. 5.6 Stations context planning
All the stations were studied from an urban point of view in order to provide a basis for
the detailed station planning (urban insertion, location of entrances/exits, etc.) to be
developed in the Preliminary Design.
The synthetic presentation of each station was developed as follows:
• Key map
• Location and intermodality
• Population density
• Population and employment forecasts
• Points of interest
• Principles for urban insertion
Figure 119. Example land acquisition in green area
• Mapping (urban context within 800m radius, land use) and aerial picture
• Presumed land acquisitions in zones where the future status of the lands (property,
availability) is unclear.
The next tables summarizes all the potential land acquisitions identified along M1,
M2 and M3.
140 141
5. Phases 5 and 6:
Feasibility Studies
142 143
5. Phases 5 and 6:
Feasibility Studies
144 145
5. Phases 5 and 6:
Feasibility Studies
146 147
5. Phases 5 and 6:
Feasibility Studies
• Rail level: +12m; This typical station shall be adapted for each of the particular rail levels
indicated on the vertical alignment;
• Side platforms: typically 3.5 m minimum width (exclusive of vertical circulation);
• Entrance provided from either side of the road;
• No public space at street level, except entrances and possibly a limited number of
technical rooms underground in traffic island zone (access hatch located between Figure 122. Elevated Station –Concourse Level plan
viaduct piers);
• Vertical circulations are integrated so that passenger flows are clear, easy to understand
and comfortable during normal operation, and so that a safe exit is provide in case of
emergency;
• For step-free access for all in the stations, two elevators provided at each entrance
(linking street and concourse levels), and from concourse to each platform. The double
elevator ensures service continuity, even if one of the elevators is out of service/ being
maintained.
• The underside of any part of the concourse which is above a carriageway is to respect
the minimum clearance (typically 5.50m).
148 149
5. Phases 5 and 6:
Feasibility Studies
150 151
5. Phases 5 and 6:
Feasibility Studies
• Indicative rail level for typical station: -20 m; This typical station shall be adapted for
each of the particular rail levels indicated on the vertical alignment.
• Island platform - typically 12,6 m minimum width (due to construction constraints
surrounding the minimum distance between the twin tunnels);
• Two single track tunnels;
• Vertical circulations are integrated so that passenger flows are clear, easy to understand
and comfortable during normal operation, and so that a safe exit is provide in case of
emergency;
• In order to provide step-free access for all in the stations, two elevators are provided at
each entrance (linking street and concourse levels), and from concourse to platform.
The double elevator ensures the continuity of service even if one of the elevators is out
of service/ being maintained.
Figure 128. Underground Station – Concourse Level Plan
• At each level change, the vertical circulation is mechanized with, as a minimum, an
escalator in both up and down directions.
152 153
5. Phases 5 and 6:
Feasibility Studies
A transfer corridor linking both station boxes at a level approximately equidistant between
the two rail levels, is provided on mezzanine level 2. The width of this corridor is to be sized
to reflect the number of transfer passengers passing through the station.
As the station box of M1 is an adaptation of the standard typical underground station, only
the deepest box (M3) is represented, with four underground levels:
• Concourse level;
• Mezzanine 1 level;
• Mezzanine 2 (Transfer) level;
• Platform level.
The characteristics of this station box are similar to those of the typical underground
station, but with a rail level of -37,23 m.
154 155
5. Phases 5 and 6:
Feasibility Studies
156 157
5. Phases 5 and 6:
Feasibility Studies
5.7.2.2 Pre-sizing for normal operations Example: Meir Hospital (underground station, central platform)
Level of service requirements: Direction A
• Platform Waiting zone LOS C = 0.7 to 0.9m²/pax Max Boarding Max Alighting Explanation
• Platform Walking zone LOS C = 1.4 to 2.3m²/pax 305 PAX/H 2100 PAX/H
• Stairs LOS C = 1.0m²/pax 549 PAX Peak 3780 PAX Peak Multiply by peak factors (1.2 x 1.5)
27 PAX/ 189 PAX/
Data/assumptions Divide by 60, Multiply by Headway (3 min)
headway headway
Multiply by LoS densities 0.8 (boarding) and 1.85 (alighting)
21 m² 350 m²
Description value units to give required area
0.16 m 2.70 m Divide by platform length (130m) to give required width.
Passenger forecasts figures unreliability
1.2 2.86m (2.50 m) Total net circulation width required (absolute minimum)
factor
Net half platform net width (island) once minimum width
Surge Factor 1.5 3.86m
for circulation zone (2.50m) is applied.
158 159
5. Phases 5 and 6:
Feasibility Studies
160 161
5. Phases 5 and 6:
Feasibility Studies
5.8.2.1 Turn back time Therefore, for a 180s s headway, the fleet size is:
Turnback studies have been performed for a 360s operational headway on the branches.
FLEET SIZE – M1 EAST
The first train arriving at the terminal goes through security checks. However, the second Theoretical fleet for operation 25,46
train will use the turn-back before the station and will be checked at the opposite terminus. Practical fleet for operation 26
Reserve for operation 1
Reserve for maintenance (10%) 3
TOTAL 30
Considering the practical fleet for operation, the layover time is 196 s.
162 163
5. Phases 5 and 6:
Feasibility Studies
M1 EAST TIME The operational staff estimation for the OCC is presented in the table below:
Raanana - Rehovot 01:06:12
JOB NUMBER
Rehovot – Raanana 01:07:09
OCC Director 1 (office hour)
Raanana North terminal station 00:03:19
OCC Supervisor 4 (1 staff per shift onto 3 shifts)
Rehovot Kaplan Hospital terminal station 00:03:19
Traffic-line Controller 8 (2 staff per shift onto 3 shifts)
ROUND-TRIP TIME 2:19:59
Traffic-depot Controller 4 (1 staff per shift onto 3 shifts)
Table 63. Round-trip time – M1 West (h = 180s) Station Controller 4 (1 staff per shift onto 3 shifts)
Therefore, for a 180s s headway, the fleet size is: Security Controller 4 (1 staff per shift onto 3 shifts)
The following figure shows the train distribution during the peak hour:
164 165
5. Phases 5 and 6:
Feasibility Studies
166 167
5. Phases 5 and 6:
Feasibility Studies
Figure 138. Turnback movement for a 180s operational headway Table 74. OCC staff size estimation
Considering the practical fleet for operation, the layover time is 207 s.
168 169
5. Phases 5 and 6:
Feasibility Studies
170 171
5. Phases 5 and 6:
Feasibility Studies
172 173
5. Phases 5 and 6:
Feasibility Studies
174 175
5. Phases 5 and 6:
Feasibility Studies
(1) Level 2 operations are usually carried out on site. They often lead to change a complete • Local plans: keeping the required distance from sensitive uses (residential, public
subassembly which will then be repaired in the workshop. buildings, etc.) in accordance with approved plans and according to environmental
(2) Level 3 operations are usually carried out on site. They often lead to change one or guidelines.
more elements of a subset. These elements are then repaired in the workshop. 5.10.1.3 Depot integration with needs of development
(3) Level 4 operations often involve repairing removed subsets on site. Research of the Depots could be planned in a multi-story structure with mixed uses – mainly industrial &
failure and the change of the failed component require very specific ways and level of employment, and any other use whose activity in the plot does not impair the operation of
qualification. the railway system.
(4) Level 5 operations often involve renovation facilities or carrying out a major enhancement. 5.10.2 Sites selection process
In order to maximize the chance to find appropriate site(s), numerous options were defined
5.10 Depots studies and compared for each line. The process was as follows:
5.10.1 Sites selection parameters • Identification of potentially available plots meeting the physical and land use criteria
described above
5.10.1.1 Physical criteria
• Multicriteria analysis ( for comparing the sites sector per sector and line per line
Assuming no mutualization, the depots experts of the team estimated that each Metro line
would require a depot of approximately 200 Dunams, except M1 which is twice longer and
would require 2 sites in the same range of size. Additional physical criteria:
• Plot dimensions: Minimum width ~150 m
• Plot shape: as regular as possible (rectangular)
• Maximum distance from the end of the line: 800-1,000 m
The location of the depots should take into account the implementation stages if any, and
could be at an edge or along a line.
5.10.1.2 Land use criteria
According to planning policy depot should be located within the urban fabric: Figure 141. Example of comparison and choice (Raanana vs. Kfar Saba for M1)
1. N.O.P.35 (national outline plan for Integrated construction, development and
conservation (land use priorities: • Shortlisting of sites and arbitration with the relevant planning authorities of Tel Aviv
District and Central District
• Urban Fabric
This process lead to confirm and sometimes refine options for M1 (2 depots) and M3 (1
• Adjacent to Urban fabric, in integrated conservation fabric
depot), and to reconsider the location of the site for M2 depot between Petah Tikva and
• Integrated conservation fabric adjacent to approved construction area Rosh Hayin.
2. All of the above is subject to compliance with the N.O.P.s dealing with the sensitivity
of open spaces (NOP.8 – natural reserves and national parks; NOP.22 – forests and
forestry; NOP.13 – the coastal area and others).
3. DOP (district outline plan of the ‘Central’ and ‘Tel Aviv’ districts) land use priorities:
• Transportation centers, Operational areas and other utilities
• Industrial areas
• Employment areas
• In open spaces with low sensitivity / value adjacent to the land uses above (with priority
to agricultural or open countryside land uses) Figure 142. Selected sites for the Metro network, including 2 depots for M1
176 177
5. Phases 5 and 6:
Feasibility Studies
Located in the South of Rishon Letzion in the South-West branch (Rishonim), the M1 Depot
2 should be fitted with the following facilities:
Figure 143. Location and site of M1 depot 1
• Stabling area;
Located in the North (Raanana), M1 Depot 1 should be fitted with the following facilities: • Washing machine building;
• Stabling area; • Light and heavy maintenance building;
• Washing machine building; • Test track;
• Light maintenance building; • Back-up OCC building.
• Wheel machining facilities;
• Storage area for infrastructure maintenance;
• Infrastructure maintenance vehicles stabling area;
• Test track;
• OCC building.
M1 depot 2
178 179
5. Phases 5 and 6:
Feasibility Studies
180 181
5. Phases 5 and 6:
Feasibility Studies
182 183
5. Phases 5 and 6:
Feasibility Studies
184 185
5. Phases 5 and 6:
Feasibility Studies
5.10.4.2 Depot sizing and layout Requirements Requirements Difference with the
Building Name
The calculations were performed on the basis of the fleet defined in the Preliminary headway 3 min headway 90 s drawings
Operation Plan (upcoming update). The sizing is based on the 180 seconds headway and a • Road, track • Road, track
No difference
comparison was made assuming a 90 seconds for the long term to check the margin. The connection, connection,
Other between the sizing
conclusions are summarized below. delivery areas, delivery areas,
and the drawings.
security check, etc security check, etc
Requirements Requirements Difference with the • 1 outside track • 1 outside track No difference between
Building Name
headway 3 min headway 90 s drawings Delivery track on slab of 130m on slab of 130m the sizing and the
32 stabling positions 32 stabling positions length (track 7) length (track 7) drawings.
Stabling area 32 stabling positions
of 65m RS of 130m RS • 2 tracks for 30m • 2 tracks for 30m
• Train wash slab • Train wash slab Auxiliary vehicles vehicles vehicles No difference between
and technical room and technical room maintenance the sizing and the
No difference between building • Workshops and • Workshops and drawings.
Train washing • Free track at each • Free track at each the sizing and the offices offices
machine side of the plant side of the plant drawings. • Workshops, • Workshops,
shall be provided shall be provided Fixed installations No difference between
offices, etc. offices, etc.
(for trains of 130m) (for trains of 130m) maintenance the sizing and the
• 4 tracks for 130m • 4 tracks for 130m building • 1 loading platform • 1 loading platform drawings.
trains (3 elevated trains (3 elevated of 150m length of 150m length
tracks, one flat tracks and one flat No difference between • 2 tracks of 100m • 2 tracks of 100m
Light maintenance track) track) for infrastructure for infrastructure
the sizing and the
building
• Workshop, storage, • Workshop, storage, drawings. maintenance maintenance
technical rooms, technical rooms, vehicles storage vehicles storage
offices offices and convoy and convoy
• 3 tracks for 130m • 3 tracks for 130m forming forming
trains: 3 flat tracks. trains: 3 flat tracks. No difference between • Outside area • Outside area
Heavy maintenance Vehicles storage No difference between
building • Workshop, storage, • Workshop, storage, the sizing and the area (infrastructure for loading and for loading and the sizing and the
technical rooms, technical rooms, drawings. maintenance) unloading of trucks unloading of trucks drawings.
offices offices and rail service and rail service
• 1 track • 1 track vehicles vehicles
accommodating accommodating
• Service cars and • Service cars and
the plant the plant No difference between truck parking truck parking
Bogie drop system • Free track at each • Free track at each the sizing and the
drawings. • Outside storage for • Outside storage for
side of the plant side of the plant
shall be provided shall be provided heavy components heavy components
(for trains of 130m) (for trains of 130m) No difference between
Test track • 1 test track • 1 test track Not a dedicated track Main store • Storage building • Storage building the sizing and the
drawings.
• 1 track for 130m • 1 track for 130m
trains (double trains (double
No difference between Table 74. M2 Depot requirements summary
units): units):
Inspection track the sizing and the
• Workshop, storage, • Workshop, storage, drawings.
office and workers office and workers
premises premises
186 187
5. Phases 5 and 6:
Feasibility Studies
The designed functional layout of the M2 depot in Givat Hashlosha is shown below. 5.10.5.2 Depot sizing and layout
The calculations were performed on the basis of the fleet defined in the Preliminary
Operation Plan. The sizing is based on the 180 seconds operational headway required for
2040, and a comparison was made assuming a 90 seconds headway for the long term, in
order to check the margin. The conclusions are summarized in the table below.
188 189
5. Phases 5 and 6:
Feasibility Studies
Requirements Requirements Difference with the The designed functional layout for the M3 depot in Or Yehuda is shown in the next page.
Building Name
headway 3 min headway 90 s drawings
1 outside track on 1 outside track on No difference between
Delivery track slab of 100m length slab of 100m length the sizing and the
(min.) (min.) drawings.
• 2 tracks for 30m • 2 tracks for 30m
Auxiliary vehicles vehicles vehicles No difference between
maintenance the sizing and the
building • Workshops and • Workshops and drawings.
offices offices
• Workshops, • Workshops,
Fixed installations offices, etc. offices, etc. No difference between
maintenance the sizing and the
building • 1 loading platform • 1 loading platform drawings.
of 150m length of 150m length Figure 150. M3 depot layout
• 2 tracks of 100m • 2 tracks of 100m
for infrastructure for infrastructure 5.11 Balance of power HV/LV of the Metro network
maintenance maintenance 5.11.1 Traction power substations
vehicles storage vehicles storage
The total power needed for power traction supply and its auxiliary were calculated through
and convoy and convoy
power simulations performed with the software MARCADET.
forming forming
M1
Vehicles storage • Outside area • Outside area No difference between
area (infrastructure for loading and for loading and the sizing and the • Traction power supply for 24 TSS (3 MW) on line and 2 TSS in depot (4,5 MW) is 81 MW;
maintenance) unloading of trucks unloading of trucks drawings. • Auxiliary power for 24 TSS (0,1 MW) on line and 2 TSS in depots (0,5 MW) is 3,4 MW.
and rail service and rail service
vehicles vehicles M2
• Service cars and • Service cars and • Traction power supply for 13 TSS (4,5 MW) on line and 1 TSS in depot (4,5 MW) is 63 MW;
truck parking truck parking • Auxiliary power for 13 TSS (0,1 MW) on line and 1 TSS in depot (0,5 MW) is 1,8 MW.
• Outside storage for • Outside storage for M3
heavy components heavy components
• Traction power supply for 13 TSS (3 MW) on line and 2 TSS in depot (4,5 MW) is 43,5 MW;
No difference between
Main store • Storage building • Storage building the sizing and the • Auxiliary power for 13 TSS (0,1 MW) on line and 1 TSS in depot (0,5 MW) is 1,8 MW.
drawings.
• Road, track • Road, track No difference between 5.11.2 Lighting and power substations
Others connection, connection, the sizing and the
delivery areas, etc. delivery areas, etc. drawings. The total power needed for lighting and power substations was estimated as part of the
MEP study in Phase 6.
Table 75. M3 Depot requirements summary M1: lighting & power substation for 5 LPS (0,8 MW) on elevated stations and 50 LPS (2,5
MW) in underground stations and 2 LPS in depots 2,5 MW), is 134 MW.
M2: lighting & power substation for 3 LPS (0,8 MW) on elevated station and 23 LPS (2,5
MW) in underground station and 1 LPS in depot 2,5 MW), is 62,4 MW.
M3: lighting & power substation for 27 LPS (2,5 MW) in underground station and 1 LPS in
depot 2,5 MW), is 70 MW.
190 191
5. Phases 5 and 6:
Feasibility Studies
5.11.3 Diversity factor and balance power results 5.12 Park & Ride
In order to have a real balance of power, we apply a coefficient of use for all the power The Park & Ride study was conducted based on the design criteria defined in Phases 2/3
systems. for location, sizing and design, summarized in the corresponding chapter of the present
This coefficient reduces the theorical global power and the values are given in the table document.
below: 5.12.1 Initial sites selection
The study selected numerous potential P&R sites in the area served by the 3 Metro lines,
Theorical Diversity taking into account:
Line System Result
power factor
• Major roads,
TSS 81 MW 0,8 64,8 MW
• Traffic,
M1 AUX 3,4 MW 0,6 2,04 MW
LPS 134 MW 0,65 87,1 MW • Potential catchment areas,
TSS 63 MW 0,8 50,4 MW • Local existing and designated land use, etc.
M2 AUX 1,8 MW 0,6 1,08 MW During the process, 12 sites were examined, among which 7 were eventually selected.
LPS 62,4 MW 0,65 40,56 MW
For each of the 8 sites, sizing calculation and analysis of options for design was made. The
TSS 43,5 MW 0,8 34,8 MW
sizing and design principles were based upon NTA demand calculation for the selected
M3 AUX 1,8 MW 0,6 1,08 MW sites. The basic assumptions assumed that 40% of the traffic volumes entering the site in
LPS 70 MW 0,65 45,5 MW three AM peak hours would enter the facility during one AM peak hour. The calculation for
327,36 MW the whole three hours is:
Total power for 22 kV
(~330 MW)
Demand for AM peak hour X 2.2 = Demand for 3 peak hours.
Table 76. Balance of Power results table The P&R facility size estimation was calculated as follows:
For power generators, we take the result of each line power LPS. 1. Calculation of the parking demand as shown above.
Then we have for: 2. Multiplying the number of parking spaces by 30m² for at-grade P&R, or by 40m² for
• M1: 9 10 kV power generators of 10 MW; superstructure P&R.
• M2: 4 10 kV power generators of 10 MW; and The decision regarding the parking facility characteristics and geometry would be based
upon the availability of the land taken for this purpose.
• M3: 4 10 kV power generators of 10 MW.
• If the lot would be large enough and matching the estimated demand, at-grade
These power generators could be displayed in 7 DSS, located along the 3 lines. configuration is possible,
As shown in the table above, we obtain for the 22 kV, a balance of power of approximately • If the lot would be a smaller one, multi-level superstructure would be needed.
330 MW. This value should be taken into account for the balance of power for the Distribution
Substation (DSS). The 12 considered sites are summarized in the next table and located in the next page:
192 193
5. Phases 5 and 6:
Feasibility Studies
Figure 153. Ramle Neve David Station Park And Ride detail location
194 Figure 154. Ramle Neve David Station Park And Ride Layout general design 195
5. Phases 5 and 6:
Feasibility Studies
• Group 4: utilities needed for emergency purpose: emergency lights, ventilation fans,
Minor impact Utility incorporation doesn’t impact the functional tunnel section
water supply for fire hydrant.
Moderated impact Utility incorporation may impact the functional tunnel section
Major impact Utility incorporation impacts the functional tunnel section
In overall, the issues raised by additional utilities from concessionaires were listed as
follows:
• Increase of the tunnel diameter and corresponding constructions costs,
• Connection issues (entrances/exits to tunnel), impact in stations and absence of route
flexibility,
• Geometry incompatibilities, for example power supply cables requiring specific bending
radius impacting the linear or station infrastructure,
• Incompatibility issues such as minimum distance to observe between power supply
cables and other utilities,
• Operation and legal/responsibility issues, in particular for granting access to
Figure 154. Example of tunnel cross section with Metro utilities
concessionaires for maintenance).
Therefore, and as illustrated with the above cross section, the tunnel gauge is strongly
constrained by these Metro utilities, which is an issue for incorporating additional utilities
5.14.3 Conclusions of the analysis
or equipment.
As a conclusion of this analysis, it was confirmed that from benchmarks:
• There are no significant cases of incorporation of exterior utilities in any Metro tunnel
worldwide,
• The only exception can be optical fibre communication networks, which can be easy
to accommodate (no impact on the tunnel diameter, no significant maintenance issue)
and can even be a source of revenue for the Metro infrastructure owner.
Therefore, additional utilities in the tunnel, besides optical fibre, are not a relevant option
for the Metro project.
196 197
5. Phases 5 and 6:
Feasibility Studies
198 199
5. Phases 5 and 6:
Feasibility Studies
Item Measurement Rate NIS Units CAPEX NIS Item Measurement Rate NIS Units CAPEX NIS
units units
Length of the line km 29 Length of the line km 36
Underground km 29 Underground km 36
Underground stations Unit 26 Underground stations Unit 27
Rolling stock Cars 304 Rolling stock Cars 164
Utilities relocation 1,216,800,000 Utilities relocation 1,263,600,000
Infrastructure NIS/km 5,274,360,840 Infrastructure 6,502,244,280
Underground sections 5,274,360,840 Underground sections 6,502,244,280
Stations 9,360,000,000 Stations 9,720,000,000
Underground stations NIS/unit 360,000,000 26 9,360,000,000 Underground stations NIS/unit 360,000,000 27 9,720,000,000
Systems 2,426,159,400 Systems 2,746,129,050
Tracks 398,832,000 Tracks 488,720,400
Power supply system 388,143,000 Power supply system 502,558,350
Signalling system 603,489,600 Signalling system 649,059,600
Communications / Telecoms Communications / Telecoms
274,638,000 313,427,100
and passenger information and passenger information
NIS/ NIS/
Environmental Control Environmental Control
underground 16,800,000 26 436,800,000 underground 16,800,000 27 453,600,000
System (ECS) System (ECS)
station station
Platform Screen Doors (PSD) NIS/station 10,920,000 26 283,920,000 Platform Screen Doors (PSD) NIS/station 10,920,000 27 294,840,000
Fare collection system (AFC) 40,336,800 Fare collection system (AFC) 43,923,600
Equipment and Rolling Stock 2,037,703,500 Equipment and Rolling Stock 1,224,153,000
Depot 326,959,500 Depot 295,449,000
Control centre building NIS/unit 12,600,000 12,600,000 Control centre building NIS/unit 12,600,000 12,600,000
Rolling stock NIS/car 1,698,144,000 Rolling stock NIS/car 916,104,000
Grand Total NIS 20,315,023,740 Grand Total NIS 21,456,126,330
Design 1,015,751,187 Design 1,072,806,317
PMC 711,025,831 PMC 750,964,422
QA 1,015,751,187 QA 1,072,806,317
Percentage of Percentage of
Contingencies 40% 9,223,020,778 Contingencies 40% 9,741,081,354
Grand Total Grand Total
Outturn Total NIS 32,280,572,723 Outturn Total NIS 34,093,784,738
Outturn Total Inc. VAT 37,768,270,086 Outturn Total Inc. VAT 39,889,728,144
200 201
5. Phases 5 and 6:
Feasibility Studies
Central corridor
A first main demand corridor can be observed on the eastern part of the central area.
Following a North-South axis, it is composed of three major demand flows that do not
match with any planned infrastructure to efficiently address them.
• A northern flow, seeking to reach Bnei Brak and the central-eastern area from the
northern sector and especially from Raanana.
• A central-eastern flow, in the North-South axis, located between M1 and M3 but not
caught by these metro lines.
• A southern flow, in-between the southern and eastern sectors.
Figure 156. Demand matrix assignment and superimposition with the mass transit Coastal corridor
network
This second corridor follows the coastline between Bat Yam and Tel Aviv CBD and then joins
According to the level of demand, the identified corridors were splitted between: the northern part of the central main corridor through Bnei Brak. Its main characteristics
• Key demand corridors, suitable for heavy modes such as Metro are:
• Secondary demand corridors, suitable for lighter modes such as LRT and BRT • It goes through areas out of reach of M1. Although LRT Green and Red lines are on the
outer edges of this corridor, a complimentary infrastructure allowing a faster commute
These corridors served then as the basis for construction of the network expansion through the centre could be suggested.
scenarios.
• Between the coast and Bnei Brak, it is parallel to a Red line section with a high load
(around 8,000 passengers toward the centre in peak hour) that might exceed its capacity.
The corridor then joins the northern part of the central corridor.
202 203
5. Phases 5 and 6:
Feasibility Studies
5.16.1.3 Conclusion
The map below gives an overview of the identified demand corridors, main in Red and
secondary in orange. The following step of the study was to propose infrastructures
covering these corridors prior to building scenarios based on them.
Northern sector
In this sector, 2 corridors were identified:
• One connecting Kfar Saba to Petah Tikva and the north-east of Tel Aviv. High inter-sectors
flows were observed and the corridor currently do not meet any public transport offer.
• One connecting Kfar Saba and Raanana branches of M1, and the northern ends of M3
and Green Line. While allowing a better intra-sector transport offer in the northern
area, this corridor would also increase the connectivity of the network in the North. The
BRT Pink line was initially planned within this corridor.
• A southern flow, in-between the southern and eastern sectors.
Eastern sector
Figure 159 Summary of demand corridors
In this sector, one secondary transport demand corridor can be observed a few kilometres
to the East of M3 along a North-South axis. The modelled demand in this area is lower
than the one closer to M3 but can be consistent as a secondary transport corridor (not as
a metro) and is currently not served.
Southern sector 5.16.2 Suggested infrastructures
In the southern part of Tel Aviv, two secondary demand corridors can be identified and Based on the expected demand shown on the desire lines, on the length of the corridors,
mostly meet a strong intra-sector transport demand, currently not catered: and by analysing the trip production and attraction densities along the corridors, several
• One in the southern end of the sector, connecting Rehovot to Lod. The two areas are public transport infrastructures were suggested and discussed.
well connected to Tel Aviv CBD, but don’t have efficient public transportation linking
them together. This corridor continues in the North to reach the Purple line and the
southern part of the eastern sector.
• The second one is shorter and connects Assaf Harofe Hospital to the southern ends of
LRT lines Green and Red. The BRT Brown line was initially planned within this corridor.
204 205
5. Phases 5 and 6:
Feasibility Studies
M1 south-east extension in Lod M4 in the east of Tel Aviv M4 through Tel Aviv CBD Additional BRT corridors
5.16.3 Scenarios
In total 5 scenarios combining the infrastructures listed above were defined and compared
through the model.
206 207
5. Phases 5 and 6:
Feasibility Studies
LRT 121 119 119 150 140 119 Figure 160. Infrastructure length and coverage comparison
BRT 21 73 73 88 88 73
LRT 192 188 188 230 221 188 kilometres, and a length of new metro alignment ranging from 26 to 47 km.
BRT 45 53 53 75 75 53
Total 342 381 368 427 418 382 5.16.3.2 Example Scenarios 1 and 4
Metro 30 38 35 34 34 38 Below are shown examples of scenarios 1 and 4, with corresponding maps and
coverage (%)
Population
characteristics.
Metro / 44 48 46 47 47 49
LRT
Metro/LRT 45 51 50 52 51 51
BRT
Metro 41 48 46 47 47 49
Employment e
coverage (%)
Metro / 55 60 59 60 60 60
LRT
Metro/LRT 56 62 61 62 62 62
BRT
208 209
5. Phases 5 and 6:
Feasibility Studies
Central corridor
• The central corridor is covered by M4 in scenarios 1, 2 and 5,
• The maximal load observed is in Ramat Gan/Bnei Brak area (10,200 pphpd) and is
significantly lower than the coastal option,
• Despite a relatively low demand, it was noted that having M4 along this corridor
improved connectivity and resilience of the overall network.
Coastal corridor
• The North section of this corridor, which all of the scenarios,
• Depending on the scenarios, the South section is served either by M4 or by the south
extension of M2,
Figure 161. Maps of network scenarios 1 and 4 • In scenarios 3 and 4 where the M4 follows the coastal corridor, the traffic forecasts
reach 22,000 pphpd, strongly justifying a Metro,
Scenario 1 focuses on 2 major metro developments: • In parallel, it was noted there is a potentially strong impact of M4 on LRT Red and Green
in the south of Tel Aviv (traffic decrease),
In this sector, 2 corridors were identified:
• The minimal priority in terms of connectivity and network resilience, whatever the
• The extension of M2 taking over the South-Eastern branch of M1 ;
corridor choice for M4, would be the extension of M2 towards M3 in Bat Yam, regarding
• The central alternative of metro line M4, combined with a northern alignment taking the short distance between the 2 lines and the interest of an additional connection.
over the M1 branch to Raanana, and a southern alignment crossing M1 and M2.A
southern flow, in-between the southern and eastern sectors.
5.16.4.2 Secondary corridors: Brown line and Yellow line
• According to the traffic forecasts from the model, this corridor is still relevant,
In addition to these new infrastructures, the LRT Grey (only northern part) and Brown lines
allow the coverage of secondary demand corridors, alongside with BRT Black and Pink • Recommendation: length reduction in the east by ending the line in Asaf Harofe Hospital
lines. (Beer Yaakov) instead of Lod in order to reduce the investment and mainly to promote
complementary with M1 until Ramle/Lod rather than duplication and competition.
Scenario 4 has M4 following the coastal demand corridor and serving the CBD of Tel Aviv,
while the central corridor is followed by a LRT Orange line between Rishon Letzion and
Ramat Hachayal.
Brown line
210 211
5. Phases 5 and 6:
Feasibility Studies
• A very low demand, not exceeding 500 pphpd in Scenarios 3 and 4, was ovserved in
scenarios 3 and 4 which covered the Yellow line corridor with a BRT. Therefore, a bus-
In conclusion, this strategic goal can be considered as fulfilled.
type service is not relevant.
• Due to the good results of LRT scenarios in the same area and to the high population/
employment densities, this corridor could be to reconsider in the future as part of a 5.17.1.2 Service supply
larger mass transit corridor. The target was set to 100 yearly public transport vehicle.km per capita.
According to the evaluation, the network would reach 72.5 yearly public transport vehicle.
km per capita including all modes in inner and outer rings.
The plan focused on the metro system. The target will be achieved when BRT and bus
systems will be planned for 2040.
212 213
5. Phases 5 and 6:
Feasibility Studies
5.17.1.3 Accessibility In conclusion, this strategic goal can be considered as largely fulfilled.
The target was set to an average of 60% of the population with a travel time not exceeding 5.17.2.2 Modal split
45-60 minutes. The results of the evaluation are summarized in the table below: The target was a public transport share reaching 40% of total daily motorized trips.
The results of the evaluation were as follows:
Trip duration Total with outer ring
In conclusion, this strategic goal can be considered as largely fulfilled. Core and inner 64.6% 44.1% 25.6%
5.17.1.4 Coverage
Middle 58.3% 39.4% 26.3%
The target was set to an average 60% of the population and employments within a
distance of 600m from the mass transit stations/stops. The results of the evaluation
are summarized per geographical sectors (rings) in the table below:
Outer 44.9% 25.2% 20.8%
Average
Inner ring + Total with In conclusion, this strategic goal can be considered as largely fulfilled.
Middle ring inner Outer ring
core outer ring
core-middle
5.17.3 Investment
5.17.3.1 Mass transit infrastructure length
Outputs 1 74% 53% 64% 6% 45% The target was set to 150 meters of dedicated public transport right-of-way per 1,000
habitants. The estimation was made considering 3.26M habitants in core, inner and middle
rings in 2040, considering the following modes:
In conclusion, this strategic goal can be considered as fulfilled when accounting the
first 3 rings. The figures are unsurprisingly lower in the outer ring where urban densities
are much lower and spread, and the coverage of the network reduced. The plan focused on • Metro: 138.5km = 43m/1,000 habitants
the metro system. The target will be achieved when BRT and bus systems will be planned • LRT: 115km = 36m/1,000 habitants
for 2040
With a total of around 80 meters of right-of-way per 1,000 habitants, the target
5.17.2 Usage is not met. However this calculation did not consider the length of the Israel Railways
5.17.2.1 Annual boardings network within the TAM
The target was set to at least 250 annual boardings per capita.
According to the evaluation, the annual boardings within the network (all modes and all trips
including inner and outer rings) would reach 350 annual boardings per capita in 2040.
214 215
5. Phases 5 and 6:
Feasibility Studies
area, so the figure could be significantly higher. Similarly, bus dedicated lanes
were not included in the calculation because the plan is not completed yet.
5.17.4 Conclusion
In conclusion, at least 6 of the 8 strategic goals of the Mass Transit Strategic Plan are met
with the 2040 configuration of the public transport network, which illustrates the very
strong weight and influence of the 3 Metro lines over the whole network.
216
METRO NETWORK
FEASIBILITY STUDY REPORT