Status
Sr no Points Remarks
PES
1 Cable tags are missing Planned on next visit
6 There must be a proper drawing in every DB as accordingly their termination. Planned on next visit
7 In every drawing must mention the spare IO's of plc. Planned on next visit
8 There must be spare terminal blocks as per spare IO's of plc. Done
12 Ethernet cables are not properly dressed in DB's due to their size. Done
14 Their must be a file of all meters addresses and baud rate for communication area wise. Done
15 Add mimic for solar power plant FP2 & FP7 after PGP. Done
22 Fiber patch cords core must be highlighted as sender & reciever with tags. Planned on next visit
24 Add generator breaker status and running hours at cfpp, pgp, Whrp1 & whrp2 Done
BFW 2 kwh are not matched there is difference of 6 units, waiting for pump startup than it will be Kindly confirm status
25
checked. after pump startup
Discussed cant be
27 G1 PLC should be CFPP and G2 PGP. Done
changed.
29 Generator breaker status needs connection with generator symbol at CFPP SLD. Done
31 Cable tags for Gen breaker status required. Planned on next visit