Subject: Estimation
Detailed estimate
of MajorofBridge
Approaches road for Major Bridge Bridge - 6
Item
Description Unit No L B D Quantity Rate Amount
No.
1 Construction of embankment with
approved material obtained from
approved borrow areas complete with
all leads and lifts as per Technical
Specification Clause 305.
Approach ramp Cu.m. 1 Volume = 22670.8 22671
Straight Portion Cu.m. 1 Volume = 627.0 627
Total Quantity = 23298 200 4659565
2 Construction of Sub grade & earthen /
un paved shoulders satisfying the
requirements of minimum 10% CBR
value as indicated in the drawings and
specification with approved material
with all leads & lifts all complete as per
Technical Specification Clause No 305.
Subgrade layer
Approach ramp Cum 1 383.40 Area = 6.96 2668
Straight Portion Cum 2 50.00 Area = 6.96 696
Between pavement layers
Approach ramp Cum 2 383.40 Area = 0.8 613
Straight Portion Cum 4 50.00 Area = 0.8 160
Total Quantity = 4137 250 1034355
3 Providing and laying coarse graded
granular sub-base (GSB) Grading-I
complete as per MoRT&H Technical
Specification Clause 401.
Approach ramp Cum 1 383.40 Area = 2.085 799
Straight Portion Cum 2 50.00 Area = 2.085 209
Total Quantity = 1008 1400 1411045
4 Providing and laying wet mix macadam
(WMM) base complete as per MoRT&H
Technical Specification Clause 406.
Subject: Estimation
Detailed estimate
of MajorofBridge
Approaches road for Major Bridge Bridge - 6
Item
Description Unit No L B D Quantity Rate Amount
No.
Approach ramp Cum 1 383.40 7.50 0.04 115
Straight Portion Cum 2 50.00 7.50 0.04 30
Total Quantity = 145 6800 986136
7 Providing Grouted Revetment with
rough stone (HBG) of not less than 300
mm size grouted with 0.20 cum of CC
(1:4:8) including cost, seigniorage
charges and conveyance of materials to
site and including labour charges for
packing the stones for revetment etc.,
complete for finished item of work as
per MoRT&H specification 2504 ( 4th
revision ) for Embankment Revetment
& Toe walls (600x600mm)
a) For Embankment Revetment Cum 2 383.40 Area = 2.344 1797
b) For Toe walls along Embankment Cum 2 383.40 0.6 0.6 276
Total Quantity = 2073 1060 2197833
8 Providing and laying filter material with
Gravel underneath pitching in slopes
including cost, seigniorage charges and
conveyance of materials to site including
labour charges etc., complete for
finished item of work as per MoRT&H
Specification 2504 (4th Revision) for
Cum 2 383.40 Area = 1.172 899
Embankment.
Total Quantity = 899 1390 1249179
9 Construction of Earthen drain as per
drawing and Technical specifications
Cum 2 383.40 Area = 1.125 863
Total Quantity = 863 150 129398
10 Provision of Highmast Lightening as per
drawing and technical specifications
Cum 9 9
Total Quantity = 9 50000 450000