Approach Ramp - Bridge-4-F
Approach Ramp - Bridge-4-F
Subject: Estimation
Detailed estimate
of MajorofBridge
Approaches road for Major Bridge Bridge - 4
Item
Description Unit No L B D Quantity Rate Amount
No.
1 Construction of embankment with
approved material obtained from
approved borrow areas complete with
all leads and lifts as per Technical
Specification Clause 305.
Approach ramp Cu.m. 1 Volume = 232307.9 232308
Straight Portion Cu.m. 1 Volume = 580.0 580
Total Quantity = 232888 200 46577574
2 Construction of Sub grade & earthen /
un paved shoulders satisfying the
requirements of minimum 10% CBR
value as indicated in the drawings and
specification with approved material
with all leads & lifts all complete as per
Technical Specification Clause No 305.
Subgrade layer
Approach ramp Cum 1 1660.00 Area = 6.20 10292
Straight Portion Cum 2 50.00 Area = 6.20 620
Between pavement layers
Approach ramp Cum 2 1660.00 Area = 1 3320
Straight Portion Cum 4 50.00 Area = 1 200
Total Quantity = 14432 250 3608000
3 Providing and laying coarse graded
granular sub-base (GSB) Grading-I
complete as per MoRT&H Technical
Specification Clause 401.
Approach ramp Cum 1 1660.00 Area = 1.935 3212
Straight Portion Cum 2 50.00 Area = 1.935 194
Total Quantity = 3406 1400 4767840
4 Providing and laying wet mix macadam
(WMM) base complete as per MoRT&H
Technical Specification Clause 406.
Subject: Estimation
Detailed estimate
of MajorofBridge
Approaches road for Major Bridge Bridge - 4
Item
Description Unit No L B D Quantity Rate Amount
No.
Approach ramp Cum 1 1660.00 7.50 0.04 498
Straight Portion Cum 2 50.00 7.50 0.04 30
Total Quantity = 528 6800 3590400
7 Providing Grouted Revetment with
rough stone (HBG) of not less than 300
mm size grouted with 0.20 cum of CC
(1:4:8) including cost, seigniorage
charges and conveyance of materials to
site and including labour charges for
packing the stones for revetment etc.,
complete for finished item of work as
per MoRT&H specification 2504 ( 4th
revision ) for Embankment Revetment
& Toe walls (600x600mm)
a) For Embankment Revetment Cum 2 1660.00 Area = 3.744 12430
b) For Toe walls along Embankment Cum 2 1660.00 0.6 0.6 1195
Total Quantity = 13625 1060 14442797
8 Providing and laying filter material with
Gravel underneath pitching in slopes
including cost, seigniorage charges and
conveyance of materials to site including
labour charges etc., complete for
finished item of work as per MoRT&H
Specification 2504 (4th Revision) for
Cum 2 1660.00 Area = 1.872 6215
Embankment.
Total Quantity = 6215 1390 8638906
9 Construction of Earthen drain as per
drawing and Technical specifications
Cum 2 1660.00 Area = 1.125 3735
Total Quantity = 3735 150 560250
10 Provision of Highmast Lightening as per
drawing and technical specifications
Cum 37 37
Total Quantity = 37 50000 1850000