SITE MANIFEST
Chemical for Bonding Slurry for 3" Slab: Supply & Provision of BS Smartbond 100, to
be applied diluted with water at 1:4 and admixed with OPC cement provided by
1.1 Kg 100.00
client at site and applied by manual spreading using suitable tools , just before
star ng of the concrete pour.
Dowel Plates: Providng and Instala on of Dowel Plates with a gap of 600mm on the
5 panel joints. Dowel Plate size of 6mm thickness and width of 110mm by 110mm in Each 600.00
an ABS housing
Applica on of Dry Shake Floor Hardener - 5kg /sqm: Using mechanical spreader
applica on of first layer of hardener at 3 kg per sqm and the panning the surface
6 with power floater, applying second layer of dryshake floor hardener at 2Kg per Sqm Sqm 6,500.00
finishing the surface with power trowel and power floater along with ride on trowel
to finally finish the surface
Finishing Aid Cum PreDensifica on: Providng and Applying BS BluTop, by Spray, at
6.1 the me of dryshake hardener applica on using fine mist aerosol sprayer at 10 Sqm Sqm 6,500.00
per Litre. To be used in between layers of Hardener Dryshake Applica on
Green Densifica on : Providing and Applica on of Hard NS, a Nano Silica based
6.2 patented technology from Concria Finland at the me of final Ride on Trowel L 450.00
Finishing Opera ons, to be sprayed by Electrical Sprayer at 15 Sqm Per Litre.
Cu ng Contrac on or Saw Cut Joints : - Cu ng of contrac on joint 5mm wide to a
7 Rmtr 3,000.00
depth of upto 45mm mm dept using high speed Diamond Cu ng Machine.
Sealing of the Saw Cut Joints: A er clearing and cleaning out loose material, with
grinder wheel and with high speed blower, installing backer rod of 6mm in the joint,
8 filling the joint with high performance, abrasion resistant, Semi Rigid Solvent Free Rmtr 3,000.00
Epoxy System including cost of materal, primer if as needed, masking tape
applica on and cleanup.
Curing Sheets: Supply and Installa on of Transparent Curing Sheets for curing
9 management. Water Tanker or Water Supply or required pipe line to be supplied by Sqm 3,000.00
client free of cost at site for curing works. Curing 7 Days only