ACTIVITY 2: MASONRY WALL TAKE-OFF

I. CHB
IN ALL THE COMPUTATION IN THIS SECTION TO ESTIMATE THE NUMBER OF
PIECES/BLOCKS USED THE VALUE WITH THE BREAKAGE FACTOR = 13.75/SQM.
GROUND FLOOR
EXTERIOR WALL PERIMETER
FRONT PERIMETER WALL
L=11.40 mm=11.40 mm=11.4 m
H=3200 m=3.20 m
2
A=11.4m ( 3.20 m )=36.48 m

Σ A 0=W 8+ W 1+ D 3
Σ A 0=(1 (2.5 )+ 1 ( 1 ) +2.1 ( 1.8 ) )m
2
A0 =7.28 m

2 2 2
A NET =38.48 m −7.28 m =29.20 m

N oCMU =29.20 m
2
( 13.75
m
2 )
pcs =402 pcs

LEFT PERIMETER WALL


L=8700 mm=8.7 m
H=3200 mm=3.2 m
2
A=8.7 m ( 3.2 m )=27.84 m

Σ A 0=W 8+ D1+W 8
Σ A 0=(2 [ 1 ( 2.5 ) ] +2.1 ( 1 ) )m
2
A0 =7.10 m

2 2 2
A NET =27.84 m −7.10 m =20.74 m

N oCMU =33 m
2
( 13.75
m )
pcs =286 pcs
2

REAR PERIMETER WALL


L=11.40 mm=11.40 mm=11.4 m
H=3200 mm=3.2 m
2
A=11.4m ( 3.20 m )=36.48 m
Σ A 0=W 6+ W 4+ W 1+ D1
Σ A 0=(1 ( 0.50 ) +1.5 ( 1 )+ 1 ( 1 ) +1 ( 2.1 ))m
2
A0 =7.10 m

2 2 2
A NET =36.48 m −7.10 m =29.38 m

N oCMU =29.38 m
2
( 13.75
m
2 )
pcs =404 pcs

RIGHT PERIMETER WALL


L=8.70 m
H=3200 mm=3.2 m
A=8.7 m ( 3.2 m )=27.84 m2

Σ A 0=W 8+ W 1
Σ A 0=(1 (2.5 )+ 1(1))m
2
A0 =3.5 m

2 2 2
A NET =27.84 m −3.5 m =24.34 m

N oCMU =24.34 m
2
( 13.75
m
2 )
pcs =335 pcs

INTERIOR PERIMETER WALLS EXCLUDING PERIMETER WALLS


GUEST ROOM
L=6.50 m
H=3.2 m
2
A=6.50 m ( 3.2 m )=20.8 m

COMMON T&B 1
L=1.85 m
H=3.2 m
2
A=1.85 m ( 3.2 m )=5.92 m

BEDROOM 1
L=7.13 m
H=3.2 m
A=7.13 m ( 3.2 m )=22.80613152 m2

Σ A 0=D 1+ D 2
Σ A 0=1 ( 2 ) +0.7( 2.1)
2
A0 =10.71 m

2 2 2
A NET =101.520 m −10.71 m =90.80973 m

N oCMU =90.80973 m
2
( 13.75
m
2 )
pcs =1249 pcs

SUB TOTAL GROUND FLOOR 2676.0000 pcs

SECOND FLOOR
EXTERIOR WALL PERIMETER
FRONT PERIMETER WALL
L=11.97500 m
H=3.30 m
2
A=11.97500m (3.30 m ) =39.51750 m

Σ A 0=D 4 +W 3+W 7
Σ A 0=(2.1 ( 0.7 ) +1 ( 2 )+ 1.25(3))m
2
A0 =7.22 m

2 2 2
A NET =39.51750 m −7.22 m =32.28750 m

N oCMU =32.28750 m
2
( 13.75
m
2 )
pcs =445 pcs

LEFT PERIMETER WALL


L=6.8 m
H=3.30 m
2
A=6.8 m ( 3.30 m )=22.44 m

Σ A 0=W 3+W 3
Σ A 0=2 ( 1 ( 2 ) ) m
2
A0 =4 m
2 2 2
A NET =22.44 m −4 m =18.44 m

N oCMU =18.44 m
2
( 13.75
m
2
pcs =254 pcs
)
REAR PERIMETER WALL
L=11.25 m
H=3.30 m
2
A=11.25m (3.30 m ) =37.125 m

Σ A 0=D 4 +W 3+W 6+ W 1+W 8


Σ A 0=(2.1 ( 0.7 ) +1 ( 2 )+ 0.5 ( 1 )+ 1 ( 1 ) +1(2.5))m
2
A0 =7.4700 m

2 2 2
A NET =37.125 m −7.47 m =29.6550 m

N oCMU =28. 7975 m


2
( 13.75
m
2 )
pcs =408 pcs

RIGHT PERIMETER WALL


L=8.925 m
H=3.3 m
2
A=8.925 m ( 3.3 m )=29.45250 m

Σ A 0=D 4 +W 3+W 5+W 2


Σ A 0=(2.1 ( 0.7 ) +1 ( 2 )+ 1.25 (3 )+ 1 ( 2.8 ))m
2
A0 =10.02 m

2 2 2
A NET =29.45250 m −10.02 m =19.43250 m

N oCMU =19.43250 m
2
( 13.75
m
2 )
pcs =268 pcs

INTERIOR PERIMETER WALLS EXCLUDING EXTERIOR WALLS

BEDROOM 3
L=3.17500 m
H=3.30 m
2
A=3.17500 m ( 3.3 m )=10.47750 m
COMMON T&B 2
L=5.27500 m
H=3.30 m
2
A=5.27500 m ( 3.3 m )=17.40750 m

STORAGE ROOM
L=9.25000 m
H=3.30 m
2
A=9.25000 m ( 3.3 m )=30.52500 m

BEDROOM 2
L=4.54816 m
H=3.30 m
2
A=4.54816 m ( 3.3 m )=15.00894 m

BEDROOM 4
L=7.35 m
H=3.3 m
2
A=7.35 m ( 3.3 m )=30.525 m

Σ A 0=D 1+ D 2
Σ A 0=(1 (2.1 )+ 0.7 ( 2.1 ))m
2
A0 =9.87 m

2 2 2
A NET =97.67394 m −9.87 m =87.80394 m

N oCMU =87.80394 m
2
( 13.75
m
2 )
pcs =1208 pcs

SUB TOTAL 2ND FLOOR = 2583 pcs

PARAPET WALL
FRONT AND REAR
L=12.85 m
H=850 mm=0.850 m
2
A=12.85 m ( 0.850 m ) 2=21.84500 m

2
A NET =21.84500 m

N oCMU =21.84500 m
2
( 13.75
m
2 )
pcs =301 pcs

LEFT AND RIGHT


L=9.85 m
H=850 mm=0.850 m
2
A=9.85 m ( 0.850 m ) (2)=16.7450 m

2
A NET =16.7450 m

N oCMU =16.7450 m
2
( 13.75
m
2 )
pcs =231 pcs

SUBTOTAL PARAPET WALLS = 532 pcs


TOTAL NO. OF CMU = 5791.0000 pcs

II. CEMENT FILLER

Use 1:3 Mixture


Mixture Class B
Use 4” CMU
Using 40kg of Cement
bags
For Cement = 0.468 2
m
3
0.052 m sand
For Sand = 2
m

GROUND FLOOR
EXTERIOR WALL PERIMETER
FRONT PERIMETER WALL
2
A NET =29.20 m

No. of Bags of Cement

NoCEMENT =( 29.20 m ) 0.468


2
( bags
m
2 )
NoCEMENT =13.6656=14 bags

Volume of Sand

( )
3
2 0.052 m sand
Volume=( 29.20 m ) 2
m
3
Volume=1.5184 m sand

LEFT PERIMETER WALL


2
A NET =20.74 m

No. of Bags of Cement

NoCEMENT =( 20.74 m ) 0.468


2
( bags
m
2 )
NoCEMENT =9.7063=10 bags

Volume of Sand

( )
3
2 0.052 m sand
Volume=( 20.74 m ) 2
m
3
Volume=1.0785 m sand

REAR PERIMETER WALL


2
A NET =29.38 m
No. of Bags of Cement

(
NoCEMENT =( 29.38 m ) 0.468
2 bags
m
2 )
NoCEMENT =13.7498=14 bags

Volume of Sand

( )
3
2 0.052 m sand
(
Volume= 29.38 m ) 2
m
3
Volume=1.5278 m sand

RIGHT PERIMETER WALL


2
A NET =24.34 m

No. of Bags of Cement

(
NoCEMENT =( 24.34 m ) 0.468
2 bags
m
2 )
NoCEMENT =11.3911=12 bags

Volume of Sand

( )
3
2 0.052 m sand
Volume=( 24.34 m ) 2
m
3
Volume=1.2657 m sand

INTERIOR WALLS
2
A NET =90.8097 m
No. of Bags of Cement

(
NoCEMENT =( 90.8097 m ) 0.468
2 bags
m
2 )
NoCEMENT =42.4990=43 bags

Volume of Sand

( )
3
2 0.052 m sand
Volume=( 90.8097 m ) 2
m
3
Volume=4.7221 m sand

SECOND FLOOR

EXTERIOR WALL PERIMETER

FRONT PERIMETER WALL


2
A NET =32.2975 m

No. of Bags of Cement

(
NoCEMENT =( 32.2975 m ) 0.468
2 bags
m
2 )
NoCEMENT =15.1152=16 bags

Volume of Sand

( )
3
2 0.052 m sand
Volume=( 32.2975 m ) 2
m
3
Volume=1.6795 m sand

LEFT PERIMETER WALL


2
A NET =18.44 m
No. of Bags of Cement

(
NoCEMENT =( 18.44 m ) 0.468
2 bags
m
2 )
NoCEMENT =8.6299=9 bags

Volume of Sand

( )
3
2 0.052 m sand
(
Volume= 18.44 m ) 2
m
3
Volume=0.9589 m sand

REAR PERIMETER WALL


2
A NET =29.655 m

No. of Bags of Cement

NoCEMENT =( 29.655 m ) 0.468


2
( bags
m
2 )
NoCEMENT =13.8785=14 bags

Volume of Sand

( )
3
2 0.052 m sand
Volume=( 29.655 m ) 2
m
3
Volume=1.5421 m sand

RIGHT PERIMETER WALL


2
A NET =19.4325 m
No. of Bags of Cement

(
NoCEMENT =( 19.4325 m ) 0.468
2 bags
m
2 )
NoCEMENT =9.0944=10 bags

Volume of Sand

( )
3
2 0.052 m sand
Volume=( 19.4325 m ) 2
m
3
Volume=1.0105 m sand

INTERIOR PERIMETER WALLS


2
A NET =87.8039 m

No. of Bags of Cement

(
NoCEMENT =( 87.8039 m ) 0.468
2 bags
m
2 )
NoCEMENT =41.0923=42bags

Volume of Sand

( )
3
2 0.052 m sand
Volume=( 87.8039 m ) 2
m
3
Volume=4.5658 m sand

PARAPET WALL

FRONT AND REAR


2
A NET =21.8450 m
No. of Bags of Cement

(
NoCEMENT =( 21.8450 m ) 0.624
2 bags
m
2 )
NoCEMENT =10.2235=11bags

Volume of Sand

( )
3
2 0.052 m sand
Volume=( 21.8450 m ) 2
m
3
Volume=1.1359 m sand

LEFT AND RIGHT


2
A NET =16.7450 m

No. of Bags of Cement

(
NoCEMENT =( 16.7450 m ) 0.624
2 bags
m
2 )
NoCEMENT =7.8367=8 bags

Volume of Sand

( )
3
2 0.052 m sand
Volume=( 16.7450 m ) 2
m
3
Volume=0.8707 m sand

TOTAL NUMBER OF CEMENT = 197 BAGS

TOTAL VOLUME OF SAND = 22 m3


III. PLASTERING

Use 1:2 Mixture


Thickness of Plaster = 25 mm
Mixture Class A
For Cement = 0.450
For Sand = 0.025

GROUND FLOOR
EXTERIOR WALL PERIMETER
FRONT PERIMETER WALL
2
A NET =35.62 m

Number of Cement

NoCEMENT =( 35.62 m2 ) ( 0.450 )

NoCEMENT =16.029=17 bags

Quantity of Sand

Volume=( 35.62 m2 ) ( 0.025 )


3
Volume=0.8905 m

LEFT PERIMETER WALL


2
A NET =25.9 m

Number of Cement

NoCEMENT =( 25.9 m2 ) ( 0.450 )

NoCEMENT =11.655=12 bags


Quantity of Sand

Volume=( 25.9 m2 ) ( 0.025 )


3
Volume=0.6475 m

REAR PERIMETER WALL


2
A NET =37.9 m

Number of Cement

NoCEMENT =( 37.9 m2 ) ( 0.450 )

NoCEMENT =17.055=18 bags

Quantity of Sand

Volume=( 37.9 m2 ) ( 0.025 )


3
Volume=0.9475 m

RIGHT PERIMETER WALL


2
A NET =25.5 m

Number of Cement

NoCEMENT =( 25.5 m2 ) ( 0.450 )

NoCEMENT =11.475=12 bags

Quantity of Sand

Volume=( 25.5 m2 ) ( 0.025 )


3
Volume=0.6375 m
INTERIOR PERIMETER WALLS
GUEST ROOM
2
A NET =10.3575 m

Number of Cement

NoCEMENT =( 10.3575 m2 ) ( 0.450 )

NoCEMENT =4.6609=5 bags

Quantity of Sand

Volume=( 10.3575 m2 ) ( 0.025 )


3
Volume=0.2589 m

COMMON T&B 1
2
A NET =4.635 m

Number of Cement

NoCEMENT =( 4.635 m2 ) ( 0.450 )

NoCEMENT =2.0858=3 bags

Quantity of Sand

Volume=( 4.635 m2 ) ( 0.025 )


3
Volume=0.1159 m

MASTER’S BEDROOM
2
A NET =38.345 m

Number of Cement

NoCEMENT =( 38.345 m2 ) ( 0.450 )

NoCEMENT =17.2553=18 bags

Quantity of Sand

Volume=( 38.345 m2 ) ( 0.025 )


3
Volume=0.9586 m

MASTER’S T&B
2
A NET =6.0375 m

Number of Cement

NoCEMENT =( 6.0375 m2 ) ( 0.450 )

NoCEMENT =2.7169=3 bags

Quantity of Sand

Volume=( 6.0375 m2 ) ( 0.025 )


3
Volume=0.1509 m

WALK-IN CLOSET
2
A NET =7.5075 m

Number of Cement
NoCEMENT =( 7.5075 m2 ) ( 0.450 )

NoCEMENT =3.3784=4 bags

Quantity of Sand

Volume=( 7.5075 m2 ) ( 0.025 )


3
Volume=0.1877 m

KITCHEN
2
A NET =11.3025m

Number of Cement

NoCEMENT =( 11.3025 m2 ) ( 0.450 )

NoCEMENT =5.0861=6 bags

Quantity of Sand

Volume=( 11.3025m2 ) ( 0.025 )


3
Volume=0.2826 m

BEDROOM 1
2
A NET =23.5575 m

Number of Cement

NoCEMENT =( 23.5575 m2 ) ( 0.450 )

NoCEMENT =10.6009=11bags

Quantity of Sand
Volume=( 23.5575 m2 ) ( 0.025 )
3
Volume=0.5889 m

SECOND FLOOR
EXTERIOR WALL PERIMETER
FRONT PERIMETER WALL
2
A NET =30.48 m

Number of Cement

NoCEMENT =( 30.48 m2 ) ( 0.450 )

NoCEMENT =13.716=14 bags

Quantity of Sand

Volume=( 30.48 m2 ) ( 0.025 )


3
Volume=0.762 m

LEFT PERIMETER WALL


2
A NET =18.04 m

Number of Cement

NoCEMENT =( 18.04 m2 ) ( 0.450 )

NoCEMENT =8.118=9 bags


Quantity of Sand

Volume=( 18.04 m2 ) ( 0.025 )


3
Volume=0.451 m

REAR PERIMETER WALL


2
A NET =27.5475 m

Number of Cement

NoCEMENT =( 27.5475 m2 ) ( 0.450 )

NoCEMENT =12.3964=13 bags

Quantity of Sand

Volume=( 27.5475 m2 ) ( 0.025 )


3
Volume=0.6887 m

RIGHT PERIMETER WALL


2
A NET =18.78 m

Number of Cement

NoCEMENT =( 18.78 m2 ) ( 0.450 )

NoCEMENT =8.451=9 bags

Quantity of Sand

Volume=( 18.78 m2 ) ( 0.025 )


3
Volume=0.4695 m
INTERIOR PERIMETER WALLS
BALCONY
2
A NET =2.8275 m

Number of Cement

NoCEMENT =( 2.8275 m2 ) ( 0.450 )

NoCEMENT =1.2724=2 bags

Quantity of Sand

Volume=( 2.8275 m2 ) ( 0.025 )


3
Volume=0.0707 m

BEDROOM 3
2
A NET =20.5925 m

Number of Cement

N oCEMENT =( 20.5925 m2) ( 0.450 )

N oCEMENT =9.2666=10 bags

Quantity of Sand

Volume=( 20.5925 m2 ) ( 0.025 )


3
Volume=0.5148 m

COMMON T&B 2
2
A NET =3.895 m
Number of Cement

NoCEMENT =( 3.895 m2 ) ( 0.450 )

NoCEMENT =1.7528=2bags

Quantity of Sand

Volume=( 3.895 m2 ) ( 0.025 )


3
Volume=0.0974 m

STORAGE ROOM
2
A NET =15.6625 m

Number of Cement

NoCEMENT =( 15.6625 m2 ) ( 0.450 )

NoCEMENT =7.0481=8 bags

Quantity of Sand

Volume=( 15.6625 m2 ) ( 0.025 )


3
Volume=0.3916 m

BEDROOM 2
2
A NET =9.065 m

Number of Cement

NoCEMENT =( 9.065 m2 ) ( 0.450 )

NoCEMENT =4.0793=5 bags


Quantity of Sand

Volume=( 9.065 m2 ) ( 0.025 )


3
Volume=0.2266 m

BEDROOM 4
2
A NET =10.4425 m

Number of Cement

NoCEMENT =( 10.4425 m2 ) ( 0.450 )

NoCEMENT =4.6991=5 bags

Quantity of Sand

Volume=( 10.4425 m2 ) ( 0.025 )


3
Volume=0.2611m

PARAPET WALL
FRONT AND REAR
2
A NET =11.05m

Number of Cement

NoCEMENT =( 11.05 m2 ) ( 0.450 )

NoCEMENT =4.9725=5 bags

Quantity of Sand

Volume=( 11.05m2 ) ( 0.025 )


3
Volume=0.2763 m
LEFT AND RIGHT
2
A NET =8.5 m

Number of Cement

NoCEMENT =( 8.5 m2 ) ( 0.450 )

NoCEMENT =3.825=4 bags

Quantity of Sand

Volume=( 8.5 m2 ) ( 0.025 )


3
Volume=0.2125 m

TOTAL NUMBER OF CEMENT = 195 bags

TOTAL VOLUME OF SAND = 10.0887 m3