Septic Tank Detail:

Plan Size: 11′-0″ X 7′-6″


Depth: – 6′-9″
Septic Tank Items:
 Earth Work Excavation
 Filling Quantity of Septic Tank
 P.C.C
 Reinforced Concrete Work

 Reinforcement
 Brick Work – 230mm:
 Plastering Septic Tank Calculator

 Manhole

How To Prepare Cost Estimate of Septic Tank:


Description:
Reinforced Concrete Work:
R.C.C 1:1.5:3 mix using 20 mm stone jelly for roof slab, lintel, roof slab, lintel and
sunshade excluding fabrication of RCC items and including cost and conveyance of all
materials labor, etc., Septic Tank Calculator
Septic tank cost installation
Larger tanks are generally more expensive than smaller ones due to the

Pause
Unmute
Loaded: 34.75%

Remaining Time -4:44


Fullscreen

Septic tank cost installation


Reinforcement:
Reinforcement for R.C.C work including straightening, cutting, bending, placing in
position & binding all TMT bars Septic Tank Estimate Excel

Centering and Shuttering work:


Centering and shuttering including strutting, propping, etc. and removal o formwork for
Cut lintel & roof Concrete Septic Tank Cost

Earthwork:
Earthwork in excavation including disposal of the earth; disposed earth to be leveled and
neatly dressed. Excavation of Septic Tank
How To Prepare Cost Estimate of Septic Tank:
P.C.C:
P.C.C work: Providing and laying plain cement concrete of 1:5:10 (1cement: 5 coarse
sand: 10 graded stone aggregate) including the cost of centering and shuttering.

Sand Filling:
Supplying and filling with river sand including watering, ramming, consolidating, and
dressing. Excavation
How to Prepare Cost Estimate of Septic Tank
1. Excavation:
Volume of excavation

= [length × breadth × depth]

Here, the length & breadth of excavation is the same as that of PCC.

= [ 11ft. × 7.5ft. × 6.75ft.]

= 556.88 cu ft.

2. PCC:
Given data:
The extra length of PCC on all 4 sides of the septic tank is 6″ (0.5ft.)

Length = 11ft.

Breadth = 7.5ft.

Thickness= 5″ = 0.416 ft.

(As 1ft. = 12 inches)

Brickwork in Septic Tank

Volume of PCC:
= [length × breadth × thickness]

= [ 11ft. × 7.5ft. × 0.416ft.]

= 34.32 cu ft.
3. Brick masonry:
a. 9″ thick outer wall:
Given data:
Length = 10ft.

Width = 9″ = 0.75 ft.

(As 1ft. = 12 inches)

Height = 6ft.

Let us find the vol. of brick masonry by the longwall short wall method.

The volume of the longwall:

= [2nos.×( length × width × height)]

= [2nos. × ( 10 ft. × 0.75 ft. × 6 ft.)]

= [ 2nos. × 45 cu ft.]

= 90 cu ft.

The volume of the short wall:


= 2nos. × [{ length} × width × height]

= 2nos. × [{6.5 ft.- (2nos.× 0.75 ft.)} × 0.75 ft. × 6 ft.]

= 2nos. × [{5 ft.} × 0.75 ft. × 6 ft.]

= 2nos. × [ 22.5 cu ft.]

= 45 cu ft.

The total volume of 9″ thk. brick wall


= the volume of { longwall + short wall}

= {90 cu ft. + 45 cu ft.}


= 135 cu ft.

b. 4″ thick inner partition walls:


Baffle wall-1
The volume of the baffle wall-1

= [ {length} × width × (height)]

= [{ 6.5 ft.- (2nos.× 0.75 ft.)} × 0.33 ft. × (6 ft. – 1.5 ft.)]

= [{5 ft.} × 0.33 ft. × (4.5 ft.)]

= 7.425 cu ft.

The volume of wall-2

= [ {length} × width × height]

= [{6.5 ft.- (2nos.× 0.75 ft.)} × 0.33 ft. × 6 ft.]

= [{5 ft.} × 0.33 ft. × 6 ft.]

= 9.90 cu ft.

The total volume of 4″ thk. brick wall


= the volume of { wall-1+ wall-2}

= {7.425 cu ft. + 9.9 cu ft.}

= 17.33 cu ft.

4. Plastering:
a. For 9″ brick wall:
Area of plastering

= 2nos. × [ (area of a longwall) + (area of a short wall)]


= 2nos. × [ (10ft. × 6ft.) + (5ft. × 6ft.)]

= 2nos. × [ 60 sq ft. + 30 sq ft.]

= 180 sq ft.

Note: Length & height of the longwall & short walls are taken for area calculation.

b. For 4″ inner wall


Area of plastering

= 2 sides. × [ (area of wall-1) + (area of wall-2)]

= 2 sides × [ ( 5ft. × 4.5ft.) + ( 5ft. × 6ft.)]

= 2 sides × [ 22.5 sq ft. + 30 sq ft.]

= 105 sq ft.

c. For floor base


Floor area plastering

= [ {length} × { breadth.}]

= [{10 ft. – (2nos. × 0.75ft.)} × {6.5ft. – (2nos. × 0.75ft.)}]

= [ {10ft. – 1.5 ft.} × { 6.5ft. – 1.5ft.}]

= [8.5ft. × 5ft.]

= 42.5 sq ft.

Total plastering area


= plastering area of [ 9″ wall + 4″ wall + floor]

= [180 sq ft. + 105sq ft. + 42.5 sq ft.]

= 327.5 sq ft.
5. RCC slab:
The area of the RCC slab

= [length × breadth ]

= [ 10ft. × 6.5 ft.]

= 65.0 sq ft.

6. Miscellaneous:
Inlet & outlet pipe of 4″ dia = 2 nos.

Manhole cover with frame = 1no.

Vent pipe = 1no.

Let us calculate the cost of a brick masonry septic tank as shown below.

Estimation and Rate Analysis of a Septic Tank:


Here, we will estimate the septic tank in sheet format as given below.

Total
Sl. Length in Breadth in Depth i Qty. in c
No. Description Nos. ft. ft. n ft. Qty. ft/sq ft.
Earthwork
1. Excavation 1 11 7.5 6.75 556.88 556.88
2. M20 grade PCC 1 11 7.5 0.416 34.32 34.32
3. 9″ brick masonry in 1:6 CM.
3a. Long wall 2 10 0.75 6.0 45 90
3b. Short wall 2 5 0.75 6.0 22.5 45
Total volume of 9″ brick masonry 135.0
4. 4″ brick masonry in 1:5 CM.
4a. Baffle wall-1 1 5 0.33 4.5 7.425 7.425
4b. Wall-2 1 5 0.33 6.0 9.90 9.90
Total volume of 4″ brick masonry 17.33
5. 12mm thick Plastering in 1:4CM
5a. 9″ long wall 2 10 —— 6.0 60 120
5b. 9″ short wall 2 5 —— 6.0 30 60
4″ baffle wall-1
5c. (on 2 sides) 2 5 —— 4.5 22.5 45
4″ wall-2 (on 2
5d. sides) 2 5 —— 6.0 30.0 60
5e. Floor area. 1 8.5 5.0 —– 42.5 42.5
Total area of plastering 327.50
RCC slab in
M25 grade
6. concrete 1 10 6.5 —– 65 65
7. Manhole cover & frame of 2ft × 2ft size. 1 no.
8. Vent. pipe 1 no.
9. 4″ dia. inlet & outlet pipe 2 nos.

Now, the cost of a septic tank is calculated in table format.

Sl. Rate. in Cost in


no. Item. Qty. INR. Unit. INR.
1. Excavation 556.99 11/- Cu ft. 6,126.89
2. PCC 34.32 207.15/- Cu ft. 7,109.39
9″ brick
3. masonry. 135 159.52/- Cu ft. 21,535.20
4″ brick
4. masonry. 17.33 174.17/- Cu ft. 3,018.37
5. Plastering. 327.5 18.10/- Sq ft. 5,927.75
6. RCC slab 65 210/- Sq ft. 13,650.00
7. Man hole. 1 1800/- No 1,800.00
8. Vent pipe. 1 450/- No 450.00
Inlet & outlet
9. pipe. 2 350/- No 700.00
6. The cost of septic tank = 60,317.40

7. Add 12% for contractors profit = 7,238.09


10. The total cost of septic tank = 67,555.49