Professional Documents
Culture Documents
RP Wme ST TWR1 B2 100 00
RP Wme ST TWR1 B2 100 00
T1-01T1-02 T1-03 T1-04 T1-05 T1-06 T1-07 T1-08 T1-09 T1-10 T1-11 T1-12T1-13T1-14T1-15 T1-16T1-17T1-18 T1-19 T1-20T1-21 T1-22 T1-23T1-24 T1-25 T1-26 T1-27 T1-28 T1-29 T1-30T1-31T1-32 T1-33T1-34 T1-35T1-37 T2-01T2-02
565 4680 50 1615 2925 1145 1130 3290 1840 3300 315 1415 445 2830 640 1825 640 2830 445 1415 135 3300 1840 3340 1080 2060 1695 295 1590 710 1410 1335 75 1330 1600
135 320
T1 T2
NT-1A NT-2A 375 THK RETAINING WALL NT-3A NT-4A NT-5A NT-6A NT-7A
7900 7900 7900 7900 7900 7900 T3
SSL +36.175
1950
1525
1525
1810
A1 A1 A1 850 THK. RAFT A1 A1 A1 SSL +34.975 A1 495 A1
100
1360
A1 A1 A1 A1 A1 A1 A1 A1 A1
01
01
01
01
01
01
01
F01 F01
PC
PC
PC
PC
PC
PC
PC
F01 1. THIS DRAWING IS THE COPYRIGHT OF WME CONSULTANTS, AND
01
F01 F01 F01 F02
2900
PC
NT-A1 MUST NOT BE RETAINED, COPIED OR USED WITHOUT THE ABOVE
CONSULTANT'S AUTHORITY.
6
1350
1450
1450
SSL +36.175 2. DO NOT SCALE FROM THE DRAWINGS.
1150
1320 1750 300 RP-WME-ST-TWR1-00-300-01
RP-WME-ST-TWR1-00-301-01 3. ALL DIMENSIONS ARE IN MILLIMETRES AND LEVELS IN METRES
TYP. 450 THK. RAFT SSL +36.175 UNLESS NOTED OTHERWISE. ALL DIMENSIONS TO BE VERIFIED ON
1340 SITE AND APPROVED BY THE ENGINEER.
A1 450 THK. RAFT 1255
TYP.
4. ALL DRAWINGS SHOULD BE READ IN CONJUNCTION WITH OTHER
300
2700 A1 A1 A1 A1 A1 A1 A1 A1 3825 A1 RELEVANT ARCHITECTURAL, STRUCTURAL, MECHANICAL AND
A1 A1 A1 A1 A1 A1
850 THK. RAFT
SSL +34.975
10 9 ELECTRICAL DRAWINGS AND ALL RELEVANT SECTIONS OF THE
SPECIFICATIONS. ANY DISCREPANCIES ARE TO BE BROUGHT TO
RP-WME-ST-TWR1-00-300-01 RP-WME-ST-TWR1-00-300-01 THE ATTENTION OF THE ENGINEER AND RESOLVED BEFORE
COMMENCEMENT OF ANY WORK.
7990
1500
DELAYED POUR STRIP
500
BASEMENT-02 EXCAVATION
750
1250
1000
02
07
06
03
05
04
RP-WME-ST-TWR1-00-300-01 FOUNDATION GA SECTION
-C
-C
-C
-C
1700
-C
A1 A1
-C
T1
T1
T1
T1
A1
1275
08
T1
1325
1585
T1
-C
1000 RP-WME-ST-COMM-00-000-03 STANDARD DETAILS GENERAL NOTES - 01
01
1000 1275
350
T1
-C
T2CW01
T1-A
SSL +36.175
A1 A1 1000 BASEMENT-02 COLUMN AND WALL
1380
1325
A1 RP-WME-ST-TWR1-B2-450-00
SETTING OUT LAYOUT
750 5 SSL +36.175
600
T1-B
1000
1880
1300
1000 1000
1465
RP-WME-ST-TWR1-B2-202-00
09
DETAILS
-C
675
10
675
11
12
915
600
T1
-C
-C
-C
T1-E
1650 THK. RAFT
T1
T1
T1
T2CW03
250
1600
1125 485 1060 50 1180
T1-G
ARCH. REFERENCE DRAWING
T1-H 155 RECEIVE MAIL ON -23RD MARCH 2023
1 SSL +33.675
13
-C
T1-J RP-WME-ST-TWR1-00-300-01
RP-WME-ST-TWR1-00-301-01 1650 1650 THK. RAFT
T1
T1-N
-C
RP-WME-ST-TWR1-00-301-01
200
WME-MD-DWG-B1-097-00
T1
600x600x600 600x600x600
1650
T1-P 200THK. NON STRUCTURAL SUMP IN FILLING SUMP IN FILLING 7
4150 THK. RAFT FOLD
T1-Q WALL UPTO GROUND FLOOR RP-WME-ST-TWR1-00-300-01
1150
T1-R
T1-S 16
17
18
250 1180
600x600x600 1000
-C
-C
-C
15
1000
SSL +34.275
T1
T1
T1
1000
-C
3 SUMP IN FILLING
T1
T1-T RP-WME-ST-TWR1-00-300-01
1000 1000
600
600
600
T2CW13
1235
2
2055
360 800
850
225
545
225
SSL +36.175
T1-W
900
900
900
900
F04 450 THK. RAFT F04
19
1695
A1 A1
-C
1265
A1 A1 F04
1000
1000
F04
T1
T1-X
20
21
600
1275
-C
-C
105
T1
T1
24
25
22
-C
-C
-C
510
A1 A1 11 360 800
1265
T1-Y A1
1140
T1
T1
T1
23
26
1000
-C
-C
750
T2CW15
595
595
900 RP-WME-ST-TWR1-00-300-01 900
T1
T1
900 900 900 900
6850
SSL +36.175
A1 A1
A1 A1
2760
02
02
02
02
02
02
02
02
PC
PC
PC
PC
PC
PC
PC
02
PC
02
02
02
PC
03
NT-A
PC
PC
PC
PC
1625
R0 06.04.2023 ISSUED FOR CONSTRUCTION RK
800
800
800
800
800
800
800
800
REV NO. DATE DESCRIPTION BY.
STATUS:
2300 ISSUED FOR CONSTRUCTION
1000
1000
CONSTRUCTION
850 THK. RAFT
PROJECT:
JOINT
1500
DELAYED POUR STRIP
RIVALI PARK, PHASE III
Mumbai, India
5275 5735 6260 5610 3405 1950 3405 5610 6260 5635 3380
CLIENT:
NT-01 NT-02 NT-03 NT-04 NT-05 NT-06 NT-07 NT-08 NT-09 NT-10 NT-11 NT-12
NOTES :-
1. CONCRETE GRADE : TOWER M50 & PODIUM M40 U.N.O
2. SBC ASSUMED -250T/SQM TOWER AREA, PODIUM 50T/SQM TOWER-01 BASEMENT-02 GENERAL ARRANGEMENT PLAN
3. GRADE OF STEEL Fe 550 D 1 : 100 ARCHITECT:
4. AS PER GEOTECHNICAL CONSULTANT RECOMMENDATION
WATER TABLE IS CONSIDERED AT 1m. BELOW GROUND FLOOR
LEVEL FOR UPLIFT STABILITY PURPOSE
5. WHEN EXCAVATING TO FOUNDATION LEVEL, CARE SHOULD
BETAKEN NOT TO DISTURB STRATA UNDERLYING FORMATION TOWER COLUMN SIZE (B02 TO U/S GR)
LEVEL IF ANY DISTURBANCE DOES, OCCUR , OR IF ANY SOFT LEGEND
29 Bank Street, Fort, Mumbai 400 023 Tel : 2266 1920
SPOTS OR GYPSIFEROUS MATERIALS ARE ENCOUNTERED, MARK SIZE REMARK
THEN THE MATERIAL SHOULD BE REMOVED AND REPLACED COLOR CODE RAFT THK. NOTES- 1. SBC CONSIDERED BASED ON GEOTECHNICAL REPORT RECEIVED STRUCTURAL / MEP CONSULTANT:
APPROVED GRANULAR ENGINEERED FILL, WHICH SHOULD BE T1-C01 575X2175 - ON DATED 31st JANUARY 2022, KINDLY RECONFIRMED SBC BASED
1650 THK RAFT ON ACTUAL SITE CONDITION PRIOR TO COMMENCEMENT OF
COMPACTED AS SPECIFIED BEFORE THE FOUNDATIONS ARE
T1-C02,T1-C03, 500X2250 - CONSTRUCTION WORK
PODIUM COLUMN SIZE (B02 TO U/S GR)
CONSTRUCTED.
T1-C06,T1-C07 2000 THK RAFT FOOTING SCHEDULE 2. PODIUM FOOTINGS CAN BE REVISITED IF HIGHER SBC
6. REFER STRUCTURAL DRAWING ALONG WITH ARCHITECTURAL MARK SIZE REMARK
DRAWING. T1-C04,T1-C05,T1-C08, 500X1550 - RECOMMENDED BY GEOTECHNICAL CONSULTANT POST HIS .
T1-C22 3550 THK RAFT STRATA VERIFICATION VISIT.
7. PRESSURE RELEASE PIPES TO BE PROVIDED & KEPT OPEN TILL MARK SIZE REMARK PC01 400X600 -
ALL PODIUM LEVELS ARE CONCRETED AND CURED COMPLETELY T1-C09,T1-C15 580X1705 - LEGEND OF CONCRETE GRADE FOR VERTICAL ELEMENTS
1350 THK RAFT PC02 450X1200 -
WITH FINISHES OR CONTINUOUS DEWATERING TO BE CARRIED L B D DRAWING TITLE:
OUT DURING CONSTRUCTION TO MAINTAIN THE WATER LEVEL - CONCRETE GRADE CONCRETE GRADE
T1-C13,T1-C14 500X1705 4150 THK RAFT LEVEL REMARK PC03 525X1200 -
BELOW RAFT BOTTOM LEVEL TILL THE BALANCED DEAD WEIGHT mm mm mm FOR COLUMNS FOR WALL TOWER-01
OCCURS. T1-C10,T1-C11,T1-C12, 550X750 - FOUNDATION TO L05 M60 M50
T1-C16,T1-C17,T1-C18 850 THK RAFT F01 2900 2700 850 SBC 50T/M2 BASEMENT-02 (FOUNDATION) GENERAL
8. FOR OTHER RELEVANT REFERENCE ARCHITECTURAL NECESSARY L05 TO L10 M60 M50 LEGEND OF ROCK ANCHORS
DETAILS TO BE REFERRED FROM ARCHITECTURAL DRAWINGS. T1-C19 575X2775 - 1400 THK RAFT F02 3825 2900 850 SBC 50T/M2 L10 TO L16 M50 M40
ARRANGEMENT PLAN
9. SHORE PILES REMOVED AS INSTRUCTED AND CONFIRMED
T1-C20,T1-C21 F03 4100 2350 1350 SBC 250T/M2 L16 TO L22 M50 M40 MARK TYPE OF ROCK ANCHORS ROCK ANCHOR CAPACITY
BY CLIENT. 500X2565 - DATE: SCALE @ A1: DRN BY: CHKD BY: APP BY: REVISION
450 THK RAFT
10.NON STRUCTURAL WALL TO BE REFERRED FROM ARCH L22 TO L28 M40 M40
DRAWING & REBAR TO PLACED AS PER NON STRUCTURAL WALL
T1-C23,T1-C26 500X2885 - F04 6850 2300 1400 SBC 250T/M2
A1 100T
06-04-2023 As indicated RK SP NR R0
L28 TO L34 M40 M40
PROJECT No: DRAWING No:
TYPICAL DETAILS FROM STRUCTURAL DRAWING T1-C24,T1-C25 500X3900 - DELAYED POUR STRIP (450 THK) TOWER RAFT REFER PLAN 1650 SBC 250T/M2 L34 TO ROOF M40 M40
P550012 RP-WME-ST-TWR1-B2-100-00