ID Task Task Name Duration Start Finish 08 Apr '24 15 Apr '24 22 Apr '24 29 Apr '24 06 May

9;24 15 Apr '24 22 Apr '24 29 Apr '24 06 May '24 13 May '24 20 May '24
Mode M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1 Project kick-off meeting, review of 1 wk Tue Sat 13/04/24
technical specifications, and 09/04/24
finalization of material selection
2 Procurement and expediting of 3 wks Mon Wed
anchoring equipment. 15/04/24 01/05/24
3 Mobilization to the work site. 1 wk Thu 02/05/24Tue 07/05/24
4 Installation of the anchoring 1 wk Wed Mon
system. 08/05/24 13/05/24
5 System verification, testing, and 1 wk Tue Sat 18/05/24
documentation. 14/05/24
6 Demobilization from the work site 1 wk Mon Fri 24/05/24
and project handover 20/05/24

Task Project Summary Manual Task Start-only Deadline

Project: SCHEDULE FOR THE PR Split Inactive Task Duration-only Finish-only Progress
Date: Wed 03/04/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone