SCHEDULE -H
See Clauses10.1 (iv) and 19.3
Contract Price Weightages
1.1 The Contract Price for this Agreement is Rs. 30.00 Crore
Proportions of the Contract Price for different stages of Construction of the Project Highway
shall be as specified below:

SCHEDULE -H Weightage in Stage for payment Percentage weightage to


percentage to the Particular Item
See Clauses10.1
Original contract
(iv) and 19.3 price
Contract
1 Price 2 3 4
A) New 4-lane realignment/bypass
Road works 1. Earthwork up to top of the subgrade 22.376 %
including culverts,
minor bridges, 2. Granular Sub-base(GSB) 11.999 %
underpasses,
3. Base Course(WMM, Shoulders) 16.658 %
Overpasses,
Reinforced Earth
DBM(Shoulders) 19.088 %
walls, approaches
4. Bituminous work
to ROB/RUB/Major BC(Shoulders) 14.228 %
Bridges/Structur es
76.900 % B- New culverts, minor bridges, underpasses, overpasses on existing road,
including (but
excluding service realignment, bypasses
roads) 1) (i) Box Culvert (New) 6.715 %

2) Minor Bridge

i) Foundation 2.221 %
ii) Sub-structure 1.224 %
iii) Super-structure 5.491 %
A) VUP

i) Foundation 21.210%
Structure (VUP) 2.240% ii) Sub-structure 12.530%

iii) Super-structure (including crash barrier, wearing coat, etc. complete in all 66.260%
respect)
A)- Fly over

i) Foundation 54.550 %
Fly over 5.400 % ii) Sub-structure 20.450 %

iii) Super-structure (including crash barrier, wearing coat, etc. complete in all 25.000 %
respect)

i) Service Road 55.565 %

ii) Roadside drain(RCC Drain) 17.242 %

iii) Road signs, markings, km stone, boundary stone, safety devices etc. 17.416 %
Other works 15.460 % iv) Roadside and median plantation, 0.733 %

v) Safety and traffic management during construction 3.211 %

(vi) Miscellaneous items (Major and Minor road junctions, traffic management 5.833 %
during execution, EMP laying tiles on kerbs, etc.)

Procedure of estimating the value of work done.


1.3.1 Road works
Procedure for estimating the value of road work done shall be as follows:
Stage for payment Percentage Payment procedure
weightage
A) New 4-lane realignment/bypass
1. Earthwork up to top of the subgrade 22.376 %

2. Granular Sub-base(GSB) 11.999 %


Unit of measurement is linear length .
Payment of each stage shall be made on
3. Base Course(WMM, Shoulders) 16.658 % prorata basis on completion of a stage
in aminimum length of 0.500 Km in Full
width.
4. Bituminous work DBM 19.088 %

BC 14.228 %
B) New culverts, minor bridges, underpasses, overpasses on existing road, realignments, bypasses:
Cost of each culvert shall be determined on
pro – rata basis with respect to total
number of culverts. Payment shall be made
on completion of two culverts in full width.for
80% cost of eachculvert, pendingminor
(1) (i) Culverts(New) 6.715 % protection work.Out of 20% balance,15%
shall be eligible on completion of
Retaining wall/ parapet wall etc. Balance
5% shall be eligible on completion of slope
pitching etc, complete in all respect.

(2) Minor bridges


i) Foundation 2.221 % Payment shall be eligible on completion of
pile cap.

ii) Sub-structure 1.224 % Payment shall be eligible on completion of


each pier / abutment

iii) Super-structure 5.491 % Payment shall be eligible on completion


of the super-structure in all respects
including hand rails,/crash barriers, wing
walls, return walls, road furniture works,
tests on completion etc., complete in all
respects

C) VUP works
(1) Foundation: On completion of 21.210%
the foundation work in all respect.

(2) Substructure: On completion of 12.530%


abutment up to abutment cap,
including wing wall and return
walls complete all respect. Payment shall be eligible on completion of
each stage of a structure as per weightage
given in the table.
(3) Superstructure: On completion of
the superstructure in all respects
including handrails /crash barrier,
wing walls, return walls, road furniture 66.260%
works, tests on completion etc. complete
in all respects

D) Flyover Work
(1) Foundation: On completion of 54.55%
the foundation work in all respect.

(2) Substructure: On completion of 19.45%


abutment up to abutment cap,
including wing wall and return
walls complete all respect. Payment shall be eligible on completion of
each stage of a structure as per weightage
(3) Superstructure: On completion of given in the table.
the superstructure in all respects
including Approaches handrails
/crash barrier, wing walls, return
25%
walls, road furniture works, tests on
completion etc. complete in all respects
Other works
i) Service Road Unit of measurement shall be linear length in
km. Payment shall be made on completion of
55.565 %
a stage in a length of not less than 2.5% of
the total scope length.
ii) Roadside drain Unit of measurement shall be linear length in
km. Payment shall be made on pro-rata
17.242 % basis on completion of a stage in a length
not less than 2.5% of the total scope length.
iiiii) Road signs, markings, km Unit of measurement shall be linear length in
stone, boundary stone, safety devices km. Payment shall be made on pro-rata
etc. 17.416 % basis on completion of a stage in a length
not less than 5% of the total scope length.
iv) Roadside plantation 0.733 % Unit of measurement shall be linear length in
km. Payment shall be made on pro-rata
basis on completion of a stage in
a length not less than 5% of the total scope
length.
v) Safety and traffic management 3.211 %
during
construction
(vi) Miscellaneous items (Major and 5.833 % Payment shall be made on pro-rata basis
Minor road junctions, traffic every three months.
management during
execution, EMP laying tiles on kerbs,
etc.)