PROCESSING CONTRACT
● Features of processing activity
1. Consumption rate
2. Ownership of the raw material inputs
3. Processing contract
4. Input material = Output material
5. Ownership of product label/trademark
6. Handling methods of excess materials/ supplies…
1) Sold in Vietnam
2) Re-exported to abroad
3) Used for another processing contract in Vietnam
4) Donated or given away in Vietnam
5) Destroyed in Vietnam
● Structure
1. Introduction
- Title
- Contract number (name)
- Place, date
- Parties’s information
+ Company name
+ Address
+ Fax, Email, Tel
+ Legal representative person, position
+ Willingness to sign the contract
2. Terms and conditions
3. Conclusion
● Content
Art. 1. Commodity
Art. 2. Quantity
Art. 3. Quality
➢ Sample (Master/Counter)
All technical details and designs as for master sample submitted by the Party B,
signed and sealed by both parties No 08/19 date April 1st 2019, each party keeps
one. The sample is a part not separate from this contract.
➢Technical stipulation
- Party A shall provide Party B with all technical conditions and appropriated
documents such as master samples, paper patterns, consumption rates, size
specifications and assortments, color cards…
- Party B undertakes to respect the quality required by Party A and to base the
production on the samples approved by both parties and according to the
technical know-how of Party A
- A representative of Party A will survey and control the production and
attempt to solve all technical problems arising from the execution of this
agreement.
- In the event quality production is below the quality level which was agreed
by both parties at the time of the agreement, and, if Party B remains in
default to remedy the default within 15 days of their noting, Party A shall
have the right to terminate the agreement all damages incurred in respect of
the default.
➢Inspection from Processee ‘s representative
- Party A shall inspect finished products at the Party B‘s warehouse and
issue the final inspection to accept exporting the above goods mentioned.
- Should there be any shortage in quantity, non-respect of the quality
required by Party A, or any other defects, Party A shall within 15 days
following the discovery of the default, and in any case not later than 30 days
following the reception of the product, notify Party B thereof in writing and
Party B undertakes to remedy the defects within 30 days upon receipt of the
written notice mentioned here above.
- Should Party B remain in default to remedy the defect, Party A shall be
entitled to the reparation of the prejudice caused by this default.
Art. 4. Price
➢ Unit price: USD…/MT CFR Cat Lai Port, HCMC, VN, Incoterms 2020.
➢ Total amount: USD…×…MT=USD…(chữ và số)
Say: US Dollars …
➢ This price shall be understood to be including...
➢ Processor’s obligation:
+ CM (cutting and making)
+ CMP (cutting, making and packaging)
+ CMT (cutting, making and trimming)
+ CMP+Q (cutting, making, packaging and quota fee)
+ CMA+Q (cutting, making, accessories and quota fee)
+ CMT+Th (Thread) + Q (cutting, making, trimming, thread and quota fee)
Art. 5. Shipment
Art. 6. Payment
Art. 7. Packing and marking
Art. 8. Material & Accessories
➢Supply method
➢ Kind
Party A will supply material and accessories to Party B after 15 days signing date this
contract.
Party A will advise to Party B via fax/email the details of material and accessories
shipment within a day of shipping date.
➢ Quantity, Quality
Upon unloading of material and accessories in Party B warehouse, representatives of
both parties will check the quantity and quality of all items delivered to Party B and
will jointly establish a control report which will be sent to Party A within 7 days
following the arrival of materials, accessories delivered by Party A.
➢ Value
➢ Shipment
- time
- place
- transshipment
- notice of shipment
- shipping docs
Shipping documents of fabric and accessories include:
- Signed Commercial Invoice in triplicate.
- Full set original clean on board Bill of lading marked “Freight prepaid”.
- Certificate of origin.
- Packing list in triplicate.
Shipping documents shall be sent to Party B within 3 days after shipping date.
➢ Consumption rate, wastage allowances rate
3% of material and 3% of accessories shall be added to consumption rate for
production wastage allowances.
➢ Method for solving wasted materials, extra raw materials after processing
contract liquidation: As for the extra material and accessories after liquidation of the
contract, both parties agree to transfer to the next contract upon request of Party A that
be returned to the place of origin, to bear all responsibilities for any tax, or, to carry
out of cancel of them in right of stipulation.
Art. 9. Machinery & Equipment
➢ Method of transfer: lend or lease
➢ Types of machinery and equipment
➢ Quantity
➢ Price, amount
➢ Quality
➢ Shipment
➢ Method for solving lent/borrowed machinery and equipment
➢ Obligation to install Machinery and Equipment
➢ Processee’s obligation to train Processor’s worker to operate Machinery and
Equipment
➢ Obligation to fix broken down Machinery and Equipment, supply replacing
spare
- In the implement of this contract, Party A agrees to lend to Party B some of
machines and equipment for processing products. Appendixes of machine and
equipment have to be agreed by both parties and which also keeps on the policies of
Vietnam Government.
- At the expiry day of the contract, all the machines & equipment will be taken over
to the next contract or other factories or Party B agrees to return all machines and
equipment to Party A result in failing to continue production.
- Party A supplies all replacing spare parts of machine in order to keep the
production line operation. The expenses of installing machine are in Party A
account.
Art. 10. Training
➢Quantity of employees
➢Training quality
➢Form/method, time, place of training (Form: face to face hoặc gửi tài liệu để đọc
online, …)
➢Training cost
The Transferor shall cover all expenses including return air ticket, transportation,
hotel accommodation, meals for 4 people of the Transferee for 4 days 3 nights
training in Korea. The exact schedule of training will be informed after the
agreement is signed.
Art. 11. Label/Trademark
➢ Owner is processee
➢ Processee authorizes processor to use
➢ Processee’s obligation to solve claims from 3rd party (if any)
Party A undertakes that Party A is the owner of the labels under this contract.
Party A authorizes Party B to use these labels for production of the order under this
contract. Party A guarantees that will take all responsibilities for all disputes, if
there are, arising for the labels under international and local law.
Art. 12. Penalty
Art. 13. Force majeure
Art. 14. Claim
Art. 15. Arbitration
Art. 16. Other terms and conditions
- Expiry of the contract to Dec 31, 2019
- By signing this contract previous correspondence and negotiation connected
herewith shall be null and void.
- This contract is made in Ho Chi Minh City- Viet Nam, in 06 English originals, 03
for each party of equal value. This contract comes into effect from signing date, any
amendment and additional clause to these conditions shall be valid only if made in
written form by telex or fax and confirmed by both parties.
II. COMPLETE EQUIPMENT IMPORT CONTRACT
Art. 1. Definitions
8 Quantity
Cert
9 Quality Cert
10 B/L
11 CI
12 PL
13 Custom
declaration
sheet
14 Bill of
exchange
1 Mate’s Receipt Captain of the ship After the cargo is cleared from the customs
examination and other formalities are over,
it is handed over to the shipping company
for loading.
8 Report on receipt Carrier This record has the effect of proving the
of cargoes – lack or excess between the actual quantity
ROROC of goods received at the port of destination
(Biên bản kết toán and the quantity of goods stated in the
nhận hàng với tàu) "manifest" of the ship, which is one of the
grounds for complaining to the carrier. and
is the basis for the port to deliver the goods
to the shipper