10. IN THE CASE OF SITES OR BUILDINGS INTENDED FOR HUMAN HABITATION, WHAT
ARE THE SAFE DISTANCE REQUIREMENTS MENTIONED IN SECTION 105?
13. WHAT IS THE ROLE OF THE "BUILDING OFFICIAL" ACCORDING TO THE DEFINITIONS
IN SECTION 106?
**Exam Questionnaire on General Provisions of the National Building Code of the Philippines
(P.D. 1096) IRR:**
**Overall Understanding:**
15. In what situations can existing buildings or structures without appropriate permits/certificates
be legalized, according to Section 103?
16. Explain the role of the Office of the Building Official (OBO) as mentioned in the Definitions
section.
**Questionnaire on the National Building Code of the Philippines and its Revised Implementing
Rules and Regulations (PD 1096):**
2. According to the introduction, what purpose does PD 1096, the National Building Code of the
Philippines, serve?
3. How were the original rules and regulations of the Code issued, and who compiled them?
5. Mention at least two factors mentioned in the text that justify the update of the IRR.
7. What is the significance of rearranging the rules and regulations following the same sequence
and numbering as those of the Chapters and Sections of the Code?
8. Besides updating, what other changes are mentioned in the revised IRR, and why are they
included?
**Publication Inclusions:**
9. According to the text, what additional elements are included in the revised IRR publication?
12. Name at least two bodies mentioned in the text that played a role in the development of the
revised IRR.
14. According to the text, how is the revised IRR intended to enhance the enforcement of the
Code?
15. Why is a uniform and clearer interpretation and understanding of the Code considered
essential?
These questions aim to assess understanding and awareness of the context, purpose, and
contents of the National Building Code of the Philippines and its Revised Implementing Rules
and Regulations.
CHAPTER 3
1. **Multiple Choice:**
What information must be included in every building permit application according to Section
302?
a. TCT and contract of lease
b. Description of the work, TCT, use or occupancy, estimated cost
c. Plans and specifications, environmental health assessment
d. Only a certified true copy of the TCT
2. **True/False:**
The Building Official has the authority to issue a permit for only a part or portion of a building
or structure if the submitted plans do not cover the entire project.
a. True
b. False
4. **Short Answer:**
List three grounds for which the Building Official may order the non-issuance, suspension, or
revocation of building permits, as stated in Section 306.
5. **Essay Question:**
Explain the role and responsibilities of the owner of a building, as outlined in Section 308.
Include the requirements for inspection and supervision of construction work, as well as the
submission of necessary documentation.
6. **Scenario Analysis:**
Suppose a building permit is issued based on approved plans and specifications, but defects
are later discovered. Discuss the actions the Building Official can take, as mentioned in Section
305.
7. **Short Answer:**
According to Section 309, when can a Certificate of Occupancy be issued, and what is the
required timeframe for its issuance after the final inspection and submission of the Certificate of
Completion?
8. **Multiple Choice:**
What is the final authority for an appeal related to the non-issuance, suspension, or revocation
of building permits, as per Section 307?
a. Building Official
b. Secretary
c. Office of the President
d. The owner of the building
Remember to review the provided text for accurate information while crafting your exam-like
questions.
9. **Matching:**
Match the following responsibilities with the appropriate professional mentioned in Section
308:
a. Full-time inspection and supervision
b. Designing architect or civil engineer
c. Logbook maintenance
1. Duly licensed architect or civil engineer
2. Building owner
10. **True/False:**
According to Section 304, the approved plans and specifications for a building project can be
changed, modified, or altered without the approval of the Building Official.
a. True
b. False
11. **Fill in the Blank:**
The Building Official may order or cause the non-issuance, suspension, or revocation of
building permits for errors found in the plans and specifications, incorrect or inaccurate
____________, or non-compliance with the provisions of the National Building Code.
1. **Multiple Choice:**
- Answer: b. Description of the work, TCT, use or occupancy, estimated cost
2. **True/False:**
- Answer: a. True
5. **Essay Question:**
- Answer: The owner is required to engage the services of a duly licensed architect or civil
engineer for full-time inspection and supervision of construction work. The architect or civil
engineer must maintain a logbook at the job site, recording progress, tests conducted, weather
conditions, and other relevant data. After completion, the architect or civil engineer submits the
logbook and a Certificate of Completion to the Building Official.
6. **Scenario Analysis:**
- Answer: The Building Official can require the permittee to correct the defective plans and
specifications. They can also order the stoppage of any building operations that violate the
National Building Code.
7. **Short Answer:**
- Answer: A Certificate of Occupancy can be issued within 30 days after final inspection and
submission of a Certificate of Completion.
8. **Multiple Choice:**
- Answer: c. Office of the President
9. **Matching:**
- Answer:
- a - 1 (Duly licensed architect or civil engineer)
- b - 2 (Building owner)
- c - 2 (Building owner)
10. **True/False:**
- Answer: b. False