Professional Documents
Culture Documents
12 OFC Laying Technique - TOFCLAY001
12 OFC Laying Technique - TOFCLAY001
OF Cable Laying
1
Topics Covered
Necessity of Laying
Inspection & Survey
Estimates & Tender
Types of Pipes Used
Trenching
Laying
2
Necessity of OF Cable Laying
Network Expansion
Developments
Diversity Route
New Technology Introduction
Customers Demand
Re-engineering of Existing Routes
Forecast from Engg./ Traffic Units
Junction Network
Route Protection
3
Inspection
The route is inspected to decide that conditions for
smooth maintenance and operation (e.g. approach
road in good condition) are available.
Decision regarding the side of the road on which
trenching to be carried out is also to be taken into
consideration during inspection.
This decision is based on obstruction based on
route
Simultaneously route diagram is prepared showing
road crossing, railway crossing if any, rivers, bridges,
culverts etc with their lengths so that the exact
quantity of GI pipes RCC half/full round pipes etc
can be calculated
4
Survey of Routes
After selection of a route, survey is conducted
to know exactly
- Whether the route is feasible to take up the
work or not
Exact details of strata to carryout estimation so
that economical viability of route can be
ascertained
5
Selection of Route
Accommodation of other public utility services
Due regard should be given to the underground
properties of other departments like
Electricity
Water supply
Sewers
Drains
Gas
Other company telecom cables
6
Survey
Survey consists of two steps
a) Inspection
b) Strata Verification :
• Eye Survey
• Pit Survey
7
Pit Survey
It is time consuming, but is very accurate and
reliable
It gives correct details of strata up to full depth.
In this method, sample pits are got excavated
at every 200 meters on route of
- 165 cms deep,
- 45cms wide on top and
- 30 cms wide at bottom.
Length of pit is generally kept as 1 meter
If any rock is encountered after certain depth,
then further excavation is not done
8
Pit for Trench
If murram is encountered, then full depth is excavated
These pits are then inspected by surveyor who records
data of strata seeing actual type of soil and its correct
measurements
45 cm 45 cm
1M
165 cm
30 cm
30 cm
9
Trenching
Manual excavations
Thrust boring
Excavating with Machine tools
10
Trenching
Trench Dimensions
5 CMS 105CMS
30 – 40 CMS
11
Trenching
5 CMS
5CMS
30 – 40 CMS
12
Trenching
Warning bricks
5CMS
30 – 40 CMS
13
Trenching
Trench sloping
200 MTS
Paying of cables
14
Trenching
Cable bending
7.5 d
15
●
Permission
Permission :
-Permission from the appropriate authorities
such as R&B, Railways and Municipality is to be
obtained by paying re-instatement charges as
per rules
Award of work :
- After finalization of tender, work is awarded
to approved contractor after entering into
agreement as specified in the tender document
16
●
Procurement
Procurement of OFC Accessories:
-Certain accessories are required to be
procured locally which are essential for
trenching, laying of pipes & proper installation of
equipment. availability of these accessories must
be ensured before issue of work order
17
Supervision and Inspection of routes
This activity is started as soon as the work
order is issued.
It is essential to ensure that contractor initiates
action on the work in time so that it can be
completed on time
Continuous monitoring of the work is must to
maintain quality as per the standards
18
●
Estimates
Preparation of Estimates :
- Project Estimate is prepared once the survey
is completed & Strata report is made available
Floating of NIT :
- NIT for trenching, laying of HDPE pipes &
pulling of O.F. cable along with associated works
is floated after preparation and approval of
estimate by competent authority. Departmental
standard instructions are available on this
subject
19
Types of Pipes
HDPE (High Density Poly-Ethylene) Pipes
PLB HDPE Pipe (Permanently Lubricated High
Density Polyethylene pipe)
20
HDPE Pipes
HDPE (High Density Poly-Ethylene) Pipes :
- It is light, not very rigid, durable, available
easily, cheaper and easier for handling
- The OF cables will be laid in HDPE pipes
standardized 50mm outer diameter having strength
of 6 kg/cm2 for cross country and 10kg/cm2 pipes
for congested city
21
PLB HDPE PIPE
Two Layer Construction
Outer layer construction
The base HDPE resin used for the outer layer
of the PLB HDPE pipe shall conform to any
designation of IS-7328 standard.
Density :0.94 to 0.958 gm/cc at 270 C temp
Melt flow rate :0.2 to 1.1 gm/10min at 1900 C
temp & 5 Kg load
22
HDPE DUCT Pipes and Fittings
23
PLB HDPE PIPE
24
HDPE DUCT
25
Accessories Required to lay PLB HDPE duct
Plastic Coupler: To couple Two ducts
End Plug: Sealing the ends of empty ducts
prior to installation of O.F cable.
Cable Sealing Plug: Used after laying of O.F
cable to prevent entry of dirt, water, and
moisture, Rodent.
End Cap: Fitted into both ends of duct coil after
manufacturing the duct
26
Double E-LOC Electro Fusion
Coupling Coupler
27
28
Continued
Replacement of faulty cable is less time
consuming
Couplers are better fitted therefore no
problems of choking
Damage to cables during pulling is less
Blowing methods is used
29
Trenching and Pipe Laying
Major specifications for trenching are :
Depth should be 165 cm in soft soil with a min.
of 1m depth in rocky areas
Top and bottom width of the trenches should
be a min. of 45 cm and 30 cm respectively.
Trenching should be as far as possible straight
Whenever curves or deviations are
encountered it should be very smooth curve
where the radius of curvature should be more
than 60 cm at least
30
In Built Up Areas
On Ducted Routes: Optical Fiber cable may be
laid through the existing ducts wherever new
pipes for this purpose are to be laid in the duct
PVC pipes of 100 mm inner diameter with 2.5
mm thickness in case of cement encased duct
and 4 mm in case of sand filled duct may be
used as per standard practice being followed by
the Department
It is preferable to lay optical fiber cable through
sub-pipes. 3 PVC sub pipes of 30 mm diameter
each may be fixed in main duct pipe
31
Non-Ducted Routes
Optical Fiber cable may be laid through HDPE
pipe of 75 mm outer diameter having strength of
6 kg/cm2
It is directly buried in the ground at about 1.65
m depth with stone/CC slab of about 35 mm
thick, 300 mm wide and 0.6-1 meter long at
about 20 cm. above the pipe.
In case the CC slab is expensive, metal or
equivalent RCC may be used.
The top of the stone/CC slab is sign-written as
ITD “Optical Fiber Cable” in indelible yellow
paints
32
Congested City Limits : 10 kg/cm2 pipes are
laid in congested city limits to ensure better
protection.
In Cross Country :
-The Optical Fiber cable shall be directly
buried at 1.65 m depth with stone/CC slab as
per specification mentioned above. The pipe
used in 950 mm outer diameter, 6 kg/cm2
HDPE
33
Special Types of Terrain
Undulating Terrain
34
Type of Man-holes
Since the cable lengths are very large, it is difficult
to pull the whole cable length (1-2 km) in one stretch,
therefore, DOT has prescribed temporary
intermediate manholes at every 200 m. The normal
manholes may be of different shapes and sizes as per
the requirement. The manholes on the straight
stretches may be either square or rectangular. The
man-holes at the corner are normally L-type. The size
of the manholes should be such that the
installation/maintenance personnel can stand inside
and perform the work conveniently. Typically, the
manhole size is 12’ x 6’
35
Precautions while Laying
Avoid sharp bends
Overlap duct ends by 1 m from each side. Both
ends must be sealed with end plugs
Do not hang ducts on fences barriers etc
Pump out water if any
Lay pipe under tree routes
36
Continued
Lay pipe under tree routes
Tightly close the end of the ducts
Use forklift for lifting duct
Do not wrap chain etc to lift
Roll down on planks or drop on sand
Ensure sealing during storage
37
Contd..
The Optical fiber cable may be lubricated for
easy pulling of cable through the duct by means
of pulling rope attached to pulling eye at the
cable end
38
The previously laid pipe and manholes,
portion of bends etc. on the cable route as per
records maintained a the time of laying pipes
may be cleaned thoroughly before pulling of
Optical fiber cable is started
39
The wire brush to clean the duct with
rags is shown in Fig.
40
Sufficient overlap of cable may be kept at
splicing location so that the ends may be taken in
the van placed near by and splicing can be done
by testing instruments in a dust free atmosphere.
The extra length of 5-10m each on both ends
may be required for overlap
41
–Laying operation has to be done to have
mechanical/protection against stretching, bending,
twisting, vibration and crushing beyond specified
limit
–It is essential to take all precautions so that cable is
laid with minimum tension and should lie in the
trench with no tension.
–This would help in achieving the desired life of 40
years
42
General Precautions
Special precautions required are :
–Shocks due to drops from higher points should be
avoided
–The drums should not be laid flat
–Drums should not be rolled for transportation
purposes except for short movement at installation
sites
–The drums should always be rolled in direction
indicated by arrow mark
43
Contd..
–Drums should be kept to remain battened until
the cable laying work is actually started.
–Batterns on the cable drums should be removed
carefully to prevent any physical damage to cable
–The Optical Fiber Cable drums should be
handled with utmost care
–The cable pulling speed should be determined
considering the site condition
44
Preparation for Cable laying
The pulling of the cable can be done in 3 ways
in the Indian conditions.
–By cable winch (machine pulling)
–By cable winch assisted by manual pulling at
intermediate stations
–Manually with intermediate assistance
45
Setting Position of Cable Drum
46
Each cable drum is given a number indicating
its relative position along the cable route.
Therefore, cable drums should be arranged
so that each cable piece is laid in its relative
predetermined position, without replacement of
cable piece unless otherwise specially
instructed by the persons concerned
47
Machine Pulling
48
Machine Pulling
For this purpose cable winch and pulling
machines are to be used.
First 12 mm cable pulling rope is installed through
the pipeline in two kms length of section with the
help of 4 mm rope.
The pulling machine is so adjusted that maximum
pulling tension of cable, as specified by
manufacturer, is not exceeded
The anti–twist device is attached between 12 mm
pulling rope and optical fiber cable with the help of
pulling grip to avoid twist in the cable during pulling
49
The typical arrangement of cable connection
in manhole is shown in Fig. During machine
pulling monitor the pulling tension and slow
down the pulling speed whenever required.
Again, there are two methods for using pulling
machine
50
Straight Pulling
51
Straight Pulling
This method is applicable for straight length of
2 km. with even surfaces
Two pulling machines are used, one at
intermediate point at 1 km from cable rear and
other at 2 km pulling end
Speed of machine is so set that machine "B"
pulls slightly faster than "A"
52
Centre Pulling
–This method is adopted for typical section having
uneven surface, 90 degree turns or curves in
pipelines. The steps to be followed are as under :
–)Place the cable drum at middle point of 2 km.
section.
–)Install pulling machine at 600 to 800 meters from
cable drum to both sides (Fig.)
–)First pull 1000 meters feeding from cable drum
using machine and manual pull, in one direction
53
000M 200M 400M 600M 800M 1000M 1200M 1400M 1600M 1800M 2000M
Cable drum
Fig.of Eight
54
Make figure of eight (refer Fig) of the
remaining cable of the drum
55
Pull remaining cable, i.e. 1000 meter to
other direction using other pulling machine
and manual pulls.
Manual pulling assistance in the
intermediate pits is necessary to reduce the
tail load to nearly zero
56
Manual Pulling
–For the route having :
•Uneven surfaces,
•90 degree turns and
•Hilly terrain
The manual pulling method is easy and
progress of work is also better than machine
pulling.
In case of manual pulling, monitoring of tension
is not required.
It is always better to use centre pull-method in
case of manual pulling
57
Records of Cable during Pulling
– During pulling of cable always maintain following
records which will be helpful for route index diagram
and for future fault localization by OTDR during
installation of cable drum
58
Contd..
–Manufacturer’s packing details of cable drum
–Cable drum number of repeater section
–Physical length of cable on drum
–Both ends meter marks of cable
–Date of pulling of cable drum
–Meter marks at each pit location after
pulling of cable
–Permanent landmarks and km stones of road
for references
–Cable drum location/Figure of eight
locations
59
Methods of U/G Cable Laying
Laying direct in the ground
Drawing through ducts
Laying solid
60
Laying Direct in the Ground
Advantages
– Simple & cheap
– Widely used
– Initial cost of laying is very less
Disadvantages
– Vulnerable to damage
– Repeated trenches
– Delayed installation
– Delayed maintenance
– Faulty cable not easily identifiable
– Armoured cables are costly
– Costly pavement surfaces are
– To be dug & reinstated
– Prone to electrolytic & chemical corrosion
61
Safety Precautions
Proper protection
Bridges over open trenches
Danger from falling material
Jumping in trench to be avoided
Glass bits corroded wires sharp
Objects to be removed
Excavated material to be properly
Stored to avoid accidents
Extra care while excavating near foundations
Excavation in presence of the owner of bldg.
Heavy equipment not to be allowed near trench to
avoid cave in
62
Safety Precautions
Excavations should be protected by barriers
Openings must be indicated by red flags
During night red lamps to be displayed
Excavation in consultation with electrical auth.
Wooden handled handtool
Handles of tool should be dry
Disconnection of power in the area is good
Slight damage to electric cable be reported
Warning bricks be replaced before refilling
Workman not allowed to work singally
Even during power shutoff power cable treated live
63
Safety Precautions
Determine the location of underground pipes,
electrical, gas, sewage, or fuel lines before
digging
Trench depth: If the trench is 5 feet deep or
more, it must be shored or sloped. If there is a
possibility of soil movement, even shallower
trenches have to be shored. If you have any
doubt about it -- shore or slope the trench
64
Safety Precautions
Running Soils: The more liquid the soil, the
more you need to use additional types of shoring
Changing Weather Conditions: Hard packed
soil can become soupy and unstable after rain.
Trenches, which are safely sloped or shored in
dry weather, can be very dangerous in wet
weather
65
Safety Precautions
Heavy loads in the area: Don't park heavy
equipment next to a trench. Nearby structures
such as buildings, curbs, trees, and utility poles
will exert stress on trench shoring.
66
Safety Precautions
Bration: If you are digging a trench near a roadway or
where other operations create vibration, make the
shoring strong enough to withstand the added stress.
If a trench is 5 feet deep or more, work should be
supervised by an individual knowledgeable about trench
safety.
Always shore from the top down, and take it out from
the bottom up. Vi
67
Safety Precautions
Place soil removed from the traench at least 2 feet from
the trench rim.
Always wear hard hats and other necessary protective
equipment.
Notify your supervisor when you are working in a
trench.
For easy, safe and quick exit, set exit ladders every 25
feet for trenches greater than 4 feet deep.
Post warning signs and rope off the areas that may be
dangerous to the public and other
68
Laying of Pipes on Bridges, Culverts
In small bridges and culverts across canals,
different methods as given below could be
followed, depending upon the situations
If the bridge/culvert is broad and having
sufficient cushioning, the pipes can be buried
under the cushioning
69
Laying of Pipes on Bridges, Culverts
If the bridge/culvert is provided with raised and
hollow footpath or wheel guard, the pipe can be
buried inside the hollow footpath or can be laid
over the wheel guard and chambered
If the supporting pillars are having projections
and the distance between the pillars is small,
then the pipes (HDPE and G.I.) could be laid
over the pillar projections
70
Laying of Pipes on Bridges, Culverts
If none of the above solutions is possible then
outside the parapet wall, G.I. troughs can be
fitted with suitable clamps
For smaller bridges, the HDPE pipes can be
laid inside the trough
However, for long bridges, HDPE pipes need
not be laid inside the troughs
While laying the cable, glass-wool or other
cushioning items may be used to reduce
vibrations. At expansion joints ‘S’ type troughs
may be used to reduce tension
71
Laying of Pipes on Bridges, Culverts
It may be appreciated that all these works can
be completed in advance before the receipt of
the cable
When the cable is received it can be
straightway pulled through the pipes which have
already been laid
In such cases the cable can be pulled at a
much faster speed, when compared to direct
burial after the cable is received
72
Cable Laying
Cable laying in railway properties
Cable laying at road crossing
73
Solid Laying Process
This method involves laying a cable in trough
made in the excavated trench
74
Solid Laying Precautions
Wooden pieces spaced at such intervals that
will prevent undue sag
This ensures that cable gets completely
surrounded by the compound
75
Laying Solid
Advantages :
76
Laying Solid
Disadvantages
High cost
Greater skill required by labour
Greater time required for installation
Difficulties encountered in filling the troughs
when the cable run is not horizontal
Inability to lay in wet weather
Unsuitable where subsidence of soil is severe
Recovery of cable is extremely difficult
77
Summary
Session covered in details of Route Survey,
Trenching, and Laying, Pulling of OFC.
Estimate and Tender procedures covered.
Different methods of laying discussed.
Important of Planning studied.
78