Professional Documents
Culture Documents
Chapter 02 - Pipeline FeaturesOCR OK
Chapter 02 - Pipeline FeaturesOCR OK
Chapter 02 - Pipeline FeaturesOCR OK
2
Pipeline Features
2.1 Overview
This chapter lists the main types of subsea and land pipelines and the different
types of construction materials and terminations. The figures in this chapter
illustrate and identify the various components of pipelines.
The usual parts for export and infield pipelines and flowlines are listed below:
Figure 2.3-Flowline
Figure 2.4-Bundle
• Subsea risers
• Subsea pipeline
Figures 2.1 through 2.4 show compo- Table 2.2-Components of Subsea Pipelines
nent locations of a subsea trunkline, (Corresponding to Figures 2.1 to 2.4)
an infield pipeline, a flowline, and a A Topside riser, pig trap, and connecting pipework
bundle. Components are listed in B Topside riser to subsea riser tie-in joint
Table 2.2. C Subsea riser
D Subsea riser
After components are pressure tested
by the construction contractor, they E Subsea valve spool piece
may be tested again by both the F Subsea pipeline
prime contractor and the pipeline G Subsea tee
owner. For example, spool pieces are H Subsea pipeline to shore approach tie-in joint
tested on the vessel before installa- J Shore approach
tion and are then subjected to at least K Shore approach to land pipeline section tie-in joint
one additional test after installation. L Land pipeline section
The pipeline section is often tested
M Land pipeline to pig trap tie-in piece
before and after trenching. To save
N Terminal pig trap and connecting pipework
time at a later stage in the project, the
pipeline owner can arrange for the 0 Pipeline bundle
contractor's tests to be combined P Flexible pipeline
strength and leak tests. Q Subsea manifold
R Subsea export pipeline tee
S Wellhead connection
• All component parts of the pipeline have been previously strength tested
for a 24-hour period.
• The joining flanges that have not been leak tested are on the platform or
in the terminal and are visible.
• Terminal facilities
• Flowline
• Wellhead manifold
Either the pipeline owner or the contractor usually awards the pipeline construc-
tion contract according to parts. Different contractors or subcontractors may be
responsible for testing each part.
A
c
D -
B
c
Figure 2.5-Typical Land Trunkline Configuration
D
F
The tee water problem is more difficult to resolve during air, nitrogen, or
vacuum drying. The reduced surface area of the water contained in the tee
extends the time required to dry the pipeline. Consider surface area when
calculating the total drying time. Refer to Chapter 8 for more information on air,
nitrogen, or vacuum drying.
Many older pipelines have tees without sleeves or sphere bars. Carefully select
the type of pig to use in these pipelines.
2.4.4 Valves
When a check valve is fitted in the pipeline, make sure the valve allows pigs to
pass through the valve in either direction. When planning to pig in the opposite
direction to flow, make sure the distance between the front and rear discs is
sufficient to allow the front discs to pass through the valve before the first rear
disc enters the valve.
As with subsea tees, consider water that remains trapped in valve body cavities
when planning drying operations.
For emergency shutdown (ESD) and other valves, ensure that the valve bore is
the same diameter as the pipeline bore.