PPC-POWERCHINA-CDEC CONSORTIUM

SAN MATEO-RODRIGUEZ SEWAGE TREATMENT PLAN PROJECT


Yumol Compound, Brgy. Sta. Ana, San Mateo, Rizal
Lifting Plan - Single Crane Lift
1. Project Details
Contractor: Powerchina Philippines Corporation
Contractor Contact Name: Armando Aballe Phone Number: 9811979226
Crane make/model: XCMG XGC85 Crane ID: NCC-15R

Communication method: ⃝ (Hand Signals) ⃝ (Radio) ⃝ (Whistle)


Location of Lift: STP Date and Time: Dec. 28, 2023
All lifting work or ordinary lifting
Lift Description:

2. Pre-Lift Checklist

indicate OK and Checked. indicates furthur controls are reuired. Please use "N/A" for hazard that is not applicable.
On-site Hazards explained ⃝________ Traffic managed ⃝________
Crane Hazards explained ⃝________ First aid, muster point location known ⃝________
JSA completion including lift plan discussion ⃝________ Radio’s Checked ⃝________
Hazard notification required ⃝________ RCI configured and working ⃝________
Crane daily check ⃝________ Electrical hazards identified ⃝________
CraneSafe current ⃝________ Spotters appropriately positioned ⃝________
Crane Operator licenced ⃝________ Crane is earthed ⃝________
Rigger licenced ⃝________ Ground conditions checked ⃝________
Fatigue management ⃝________ Underground services are clear ⃝________
Vision condition checked ⃝________ Obstruction checked ⃝________
Weather conditions checked ⃝________ Rigging methodology discussed ⃝________
PPE correct ⃝________ Load support checked ⃝________
Lifting equip certs correct ⃝________ The lift will use a tag line ⃝________
Rating charts correct ⃝________ Loose objects removed from load ⃝________
Counterweight correct ⃝________ No simultaneous operations ⃝________
Reeving correct ⃝________ Man-cage checked ⃝________
Outriggers Ext/ Pinned ⃝________ Confined Space checked ⃝________
Crane set-up as per lift plan ⃝________ Aiport's notified ⃝________
3. Lift Details
Lift #______ Lift #______ Lift #______ Lift #______
Weight of load kg kg kg kg
Weight of rigging kg kg kg kg
Weight of hooks kg kg kg kg
Additional weight kg kg kg kg
Total* 0 kg 0 kg 0 kg 0 kg
Boom Length m m m m
Boom Sequence
Line pull T T T T
Parts of Line No. No. No. No.
Hook block WLL T T T T
Pick up radius m m m m
Set-down radius m m m m
Max radius m m m m
SWL at max radius kg kg kg kg

Communication method* ⃝ ⃝ ⃝ ⃝ ⃝ ⃝ ⃝ ⃝ ⃝ ⃝ ⃝ ⃝

Rigger initial*
* Operator to calculate, rigger must initial below when checked

Lifting Plan Revision A December 28, 2023


PPC-POWERCHINA-CDEC CONSORTIUM

SAN MATEO-RODRIGUEZ SEWAGE TREATMENT PLAN PROJECT


Yumol Compound, Brgy. Sta. Ana, San Mateo, Rizal

4. Lift Sketch
Sketch the load and show the following:
1. Crane standing position
2. Outrigger location
3. Load location
4. Show distances and load movement-direction

5. Sign off
Position Name Signature Date

Engineer's Representative
Sign to show you have read and understood the lift plan and all hazard checks

Hazard Control Responsible


Unbalanced load, sharp edges, pinch points Crane operators shall be properly licensed or certified Safety Officer
Tripping hazards, excessive point loading Appropriate work permit shall be issued for crane operations Construction Supervisor
Shifting or dropping of load Crane operator shall have final decesion on crane lift affect the safety
Operator
of the crane
Improper set-up and operation Crane must be inspected 3rd party and daily checklist Rigger
Operation of crane Crane cabs shall provide maximum visibility, obstruction not allowed
All lifting crew/team
Improper rigged loads and load movement Must have a competent riggers
General working involving cranes Must have tag lines in all loads
Un-inspected rigging Crane lift area must be barricaded and secured
Uncontrolled motionof loads Crane operator shall not leave the controls while load is attached
Severe weather condition Pre-lift safety meeting
Swinging uncontrolled loads
Controls: E– Eliminate Hazard, S–Substitute, I– Isolate, E-Engineering controls, A– Administrative controls, PPE
If further controls are added, such as in the collision example above, ensure those with responsibilities, who are not the crane operator, rigger, or Engineer representative, initial
to acknowledge that they agree with the chosen control method. Crane operators must keep a copy of the completed lift plan.
ARMANDO ABALLE
Prepared By
HSE Manager
WENJU ZHENG
Approved By
Site Manager

Lifting Plan Revision A December 28, 2023