Professional Documents
Culture Documents
Method Statement CMC Hotakena
Method Statement CMC Hotakena
Method Statement CMC Hotakena
INTRODUCTION
Colombo municipal council has called for a proposal for Rectification of Slope Failure
at CMC play ground – hotakena.
The restoration of this slope failure and its enhanced stability are of utmost priority
according to the field observations, Soil Tech (Pvt Ltd) has observed that the slope is
composed of debris and loose soil. The area prone to sliding is about 200m 2.It was
learnt that, the area was used to crush the boulders with explosives about 20-30
years ago. After that, the area was used to dump the garbage of the surrounding
area. When we dig at the toe of the slope using excavator, there have being decaying
garbage and forming peat layer. Further, height of the retaining wall from the toe
more than 5m. thus, there is a possibilities to settlement. Due to that, the retaining
wall/ gabion wall could have been settled or tilted by unfavorably large vertical
pressure exerted on the base of the retaining wall/gabion wall
According to site and geotechnical conditions of the location, the slope should be protected
by suitable earth retention system without compromising the slope stability and the
surrounding operations further. A number of different techniques including Soil nailing, Self
Drilling anchors and Shotcreting are envisaged in the restoration design.
The potential for further slope stability, cost effective and access to the site determines that
soil nailing rather than soil nailing.
2.0 METHODOLOGY
The proposed solution for preventing further slope failure & erosion entails the use of
soil nailing to supplement the protection of the existing slopes around the site. Finally
Plantation of Grass to beneficial for aesthetic appearance soil conservation
Soil anailing technology can be utilized to restore unstable slopes and rectify
landslides, stabilise permanent and temporary excavation related construction and to
restore weak structures or those on the verge of collapse. The methodology involves
installation and grouting of soil nails (Steel reinforcing bars) over a designed regular
pattern to create a soil that acts as a coherent mass with improved shear strength.
Soil nailing System is today’s solution for a fast and efficient stabilisation method of
slopes into virtually any type of soil.
Due to the potential stability of the slope, the construction of outer surface of the face
is divided into three stages. Only one section is engaged in construction at a given
time.
The first stage is the clearing, trimming and excavation of the cut from the top down
with given trimming angle.usually to remove the loosened materials and trimmed
150mm of layer of top soil. Next, the soil nails, for carrying tension, are drilled and
grouted into the slope surface at the designed vertical and horizontal spacing to
ensure that the soil and soil nails act as a coherent mass. Before Shotcreting the
surface of the slope, the collapsed retaining wall segments should be cleared from the
site. If any cavities or large boulders encounter during the construction, The EPS
blocks would be used to replace/fill the cavities or boulders with light weight and
durable fill.
Soil nail holes are drilled at predetermined locations to a specified length and
inclination using a drilling method appropriate for the ground conditions. The
system has historically been known as a “self-drilling anchoring” because the
hollow fully-threaded anchor bar serves as both the drill string and the grouted
anchor, thus installation is performed in a single operation. The sacrificial drill bit is
threaded onto the end of the Geo-Drill bar and left in place following drilling. The
drilling fluid (air, water, or grout) is introduced through the hollow bar and allows
the spoils to flush from the borehole.
2.3Shotcreting
Firstly collapsed old retaining wall and its debris(soil or other materials from the
surface) are removed. Then the recessed beam (grid) facing is constructed by
shotcrete to connect the nails, and then Coir net is securely laid on the slope surface,
and shotcrete up to the required thickness, as per specifications.
Figure 5.Shotcreting
2.3.2 Materials
Installation of parallel horizontal drains is often used when access follows a linear
alignment such as a cutting for a road way.
Short Drains are 40 mm external diameter and 2 m long, PVC (Type 1000) slotted
pipes. Long drains are of 90 mm external diameter PVC (1000) pipes. These drains are
perforated on the upper half (perforated diameter 5 mm with 125 mm centres) and
wrapped with an approved type of geotextile. Inner end of the PVC pipe is closed with
an end cap.
2.5Pullout Test
The primary objective of field pullout test for soil nails or anchors is to verify design
assumptions about the bond strength at the interface between the ground and the
cement grout sleeve. Figure 6 shows schematic apparatus for conducting a pullout
test. The anchors are normally tested with pull test only, if there any need.
During the manual trimming, the personals are concerned and trained to be
with all aspects of safety precautions including safety belts, safety helmets,
gloves and goggles, proper communication systems between the crew and
the Site-In-charge to inform the probability of risk for them as well as the
public, and they communicate without hesitation whenever it is necessary.
4 Site Photos